ANNEXURE-D |
Quarter Wise Action Plan For 2020-21 Road works under NESIDS. |
Sl |
Name of Division |
Name of work |
Source of Funding |
Date of W.O issued |
Stipulated date of completion |
Remarks |
CIRCLE-III |
1 |
Amarpur |
Improvement of Tourist spot connectivity from Amarpur (fatiksagar) leading to Chabimura and having access toeco-Tourist Centre. Agency: Debasish Das. |
NESIDES |
24-01-2020 |
08-08-2021 |
Work in progress. |
CIRCLE-V |
2 |
Ambassa |
Improvement of road from Gandacherra - Raishyabari road at Ch.18.30 Km to Narikel Kunja (L -8.00km) for easy access for the Tourists from Dhalai, North & Unakoti Districts to Narikel Kunja island surrounded by Dumbur Lake Water. |
NESIDES |
31-12-2019 |
30-06-2021 |
Work in progress. |
ANNEXURE-E |
Quarter Wise Action Plan For RIDF Road Works During 2020-21 |
Sl |
Name of Division |
Name of work |
Source of Funding |
Date of W.O issued |
Stipulated date of completion |
Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
CIRCLE-I |
1 |
Kailasahar |
Strengthening of Kailashahar - Fatikroy road/ Patch metalling,grouting, re-carpeting, seal coating including CD and road side pucca drain ch. 0.00 to 7.10 km.Job.No TP/COM/53/2018-19 (General) |
RIDF-XXIV |
02-09-2019 |
28-02-2020 |
completed |
2 |
Dharmanagar |
Strengthening of road D.A. Road to NH-08 via Baraithal/ SH:- re-carpeting,grouting, portion from ch. 1.50 km to ch. 4.00 km.Job No. TP/COM/48 /2018-19.(RIDF) (general) |
RIDF-XXIV |
28-08-2019 |
11-12-2019 |
completed |
3 |
Dharmanagar |
Improvement of Bagbassa – Dharmanagar road from intermediate lane to double lane (Job No.TP/COM/107/2016-17) (RIDF) General |
RIDF-XXII |
06-08-2019 |
20-02-2020 |
completed |
4 |
Dharmanagar |
Improvement of road from Nutanbazar to Gobindapur road via Pretyekroy H.S. School road (L-4.00 km) (Job No.TP/COM/112/2016-17) Agency: S.N Bhattacharjee. |
RIDF-XXII |
17-06-2019 |
31-12-2019 |
Work in progress |
5 |
Kumarghat |
Up-gradation of Machmara to Krishnatilla Road (Total Length=7.00 Km). |
RIDF-XXIII |
06.12.19 |
31.07.21 |
Work in progress |
6 |
Kumarghat |
Sthrengthening oif road from 82 mile to bhati Dhudpur during the year 2018-19 /SH: Carpeting, Grouting etc. |
RIDF-XXIV |
01.08.19 |
30.06.20 |
work completed |
CIRCLE-II |
7 |
Khowai |
Strengthening of PWD Bituminus road from Tulasikhar Block to Tulasikhar Bazar under Tulasikhar Block ( L= 7.00km) / SH: WBM-II, WBM-III and re-carpeting work |
RIDF-XXIV |
06-12-2019 |
21-10-2020 |
Work completd |
8 |
Khowai |
Strengthening of PWD Bituminus road from Dhalabil to Ramchandra Ghat under Khowai Block ( L= 6.50km) / SH: WBM-II, WBM-III and re-carpeting work |
RIDF-XXIV |
18-12-2019 |
03-10-2020 |
Completed |
9 |
Khowai |
Imp of road from T.K. road from Baramaidan to Porkhalong (L=11.00 km) via Worento bar to Hazaribari under Padmabil Block /SH: Re- Carpeting, WBM-II,Tack Coat carpeting, Seal Coat, Surface drain ,Soling, CD. JOB NO. TP/COM/23/2018-19 |
RIDF-XXIII |
15.06.2019 |
30.06.2021 |
Completed |
10 |
Teliamura |
Up-gradation of road from Rajkumar para to Dhaniram para (L = 3.50 km)under Mungiakami Block / Sh:- Metalling, carpeting,box culvert, pucca drain and protection work etc. |
RIDF-XXV |
|
|
Tender accepted |
11 |
Teliamura |
Improvement of road from AA road near Tuichindrai bazar to Hrankhal bazar (Ch..00 km to 2.50 Km)SH: Widening metalling,carpeting,retaining wall, cd etc (TP/COM/22/2018-19) |
RIDF-XXIII |
14.02.2019 |
01.06.2020 |
Completed |
CIRCLE-III |
12 |
shantirbazar |
Strengthening of the road from Santi Colony to Paikhola via Rail Station. L= 4.50km. Agency (Ratan Sarkar) SCSP |
RIDF-XXIV |
07-06-2019 |
22-06-2020 |
completed |
13 |
shantirbazar |
Improvement of road from Bagafa to Gobindabari / Sh:- Widening of road, re-grading, soling,retaining wall, toe wall, metalling, carpeting and road side pucca drain etc. ch. 4.00 km to 9.50 Km. (Job No.TP/COM/126/2016-17) (TSP)Name of agency:- N.G. Bhattacharjee |
RIDF-XXII |
09/092016 |
24-03-2018 |
Work in progress |
14 |
shantirbazar |
Upgradation of of road from Shillong Mog Para to Lowgang Bazar (L = 1.648 km) and Lowgang Bazar (Ganga Mandir) to Gardhang via Chaigharia School and Das Para (L = 3.176 km)/ Sh:- Soling, metalling, carpeting, protection wall and road side pucca drain etc.(Total length 4.824 km).SCSP |
RIDF-XXV |
|
|
Work in progrss. |
15 |
Santir bazar |
Imp. of road from Bagafa to Akama (L= 12.00 km)/ Sh:- Widening of road, re-grading, soling,retaining wall, toe wall, metalling, carpeting and road side pucca drain etc. ch. 0.00 km to 10.50 km.(Job No.TP/COM/127/2016-17) Name of agency:-Sri Bhanu Patari(Gr.No.II ch 5.50 to 12.00 km) |
RIDF-XXII |
31-07-2017 |
15-02-2019 |
Tender accepted |
16 |
Santir bazar |
Improvement of road from NH-44 (Jolaibari)to Ailmara via Kowaifung (L = 21.25 Km)(Job No.TP/COM/128/2016-17).Agency: Jahar lal Sarkar(TSP) |
RIDF-XXII |
17-01-2018 |
01-08-2019 |
Work in progress |
17 |
Shantirbazar |
Improvement of road from Santirbazar to Kasko (Amarpur)via Debipur (L = 33.50 Km).Agency: Kishore Roy.(Job No.TP/COM/120/2016-17) |
RIDF-XXII |
|
|
Proposal sent for dropping the work vide letter No.F.3(23)/PC(RDQP)/2015-16/4897-903 dated 7th January 2021. |
18 |
Santir bazar |
Improvement of road from Jolaibari to Hrishyamukhvia Ramraibari (L=16.96 km)/ widening, regrading,C.D. , Side drain, Toe wall , etc. ch. 0.00 Km to 16.96 km.Agency: Kishore Roy |
RIDF-XXIII |
30-09-2019 |
14-06-2021 |
Out of Total Length=16.96 K.M only 6.25k.m is under Santirbazar PWD (R&B) Division. 6.25 Kmformation completed. |
19 |
Santir bazar |
Improvement of road from TNV Colony(Aloy Cherra Market, NH44) to B.B. road viaKhas Tilla & NBCC Road (L094) (L= 7.80 Km)(Job No.TP/COM/129/2016-17) |
RIDF-XXII |
14-01-2020 |
29-07-2021 |
Work completed. |
20 |
Belonia |
Improvement of road from Satmura Chowmuhani to Belonia Railway Station (L-2.40 km)/ SH: Widening, Flat & edge Soling, Metalling,Carpeting, Construction of C.D., Toe wall,Road side pucca drain & other allied works.Agency: Sankar Saha. |
RIDF-XXIII |
13.12.19 |
20.06.21 |
Work in progress |
21 |
Belonia |
Strengthening of road from Ratanpur to Monirambari via Shibpur ADCV Village under Hrishyamukh RD Block / Sh:- Patch repairing and re-carpeting.etc. L= 6.00km.Name of Agency: Gopi Deb Roy.Job No. TP/COM/44 /2018-19. |
RIDF-XXIV |
30.05.19 |
13.06.20 |
Work completed |
22 |
Belonia |
Strengthening of road from Belonia - Rajnagar road near Sonapur Girls School to Monaipathar via Hetalia under Rajnagar RD Block / Sh:- Patch repairing and re-carpeting etc. L= 4.00km.Job No. TP/COM/45/2018-19 .Agency: Jiban Krishna Sen. |
RIDF-XXIV |
06.08.19 |
18.08.20 |
Work in progress |
23 |
Belonia |
Improvement and widening (both side) of road from Kashari Trijunction to Gourangabazar to make it intermediate width (total length - 30.00 km)/ Sh:- Flat brick soling, edge soling, metalling, carpeting, seal coat, protection wall and other allied works etc. |
RIDF-XXIII |
|
|
Work in progress. |
24 |
Udaipur |
Strengthening of road from Agartala - Udaipur (Police Line) road to Khupilong / SH:- Re-carpeting & seal coat.L= 5.00km Job No. TP/COM/40 /2018-19. Name of Agency: Chitta Rn Saha. |
RIDF-XXIV |
07.03.2019 |
22.09.2019 |
Work completed |
25 |
Amarpur |
Strengthening of road from Dalak to Gamako via Paschim Malbassa/ SH;- Re-carpeting, sand seal coat. L= 4.00km |
RIDF-XXIV |
01/08/209 |
16-08-2020. |
Work in progrss. |
26 |
Amarpur |
Improvement of road from Tuidu-Lungfung via Palku ( L=10.50 Km)/ SH: Brick Soling, WBM, Carpeting, Sand seal coat, CD etc. Agency: Ajit Bhattacharjee. SCSP |
RIDF-XXIII |
22-08-2019 |
09-12-2020. |
Work in progrss. |
27 |
Sabroom |
Improvement of road from Jalefa Petrol Pump to Sabroom Railway Station. L=2.00km. Job No.TP/COM/47/2018-19. Agency: Jiban lal Sarkar.(General) |
RIDF-XXIV |
21.10.2019 |
04.02.2021 |
Work completed |
28 |
Sabroom |
Improvement of road from Kalacherra to Manirambari via Gardhang (L = 9.50 Km) (Job No.TP/COM/125/2016-17). Agency:- Bimalendu Chakraborty. |
RIDF-XXII |
07.08.2019 |
06.01.2021 |
Work completed |
CIRCLE-V |
29 |
Ambassa |
Improvement of road from NH-08 (ch. 381 km) to Sikaribari tower/ Re-carpeting, metalling and seal coating, retaining wall, traffic signages etc. |
RIDF-XXV |
|
|
4th call tender invited on 01.03.21 |
30 |
Ambassa |
Improvement of Gandacherra-Raishyabari road (L=32.00KM) /SH:-Widening, strengthening, retaining wall, toe wall, CDs etc. portion from 0.00 Km to 28.50Km. Job No.TP/COM/49/2015-16 Agency:- M/S.N.G Bhattacharjee .co |
RIDF-XXI |
20-01-2017 |
04-03-2019 |
Work in progress |
31 |
Ambassa |
Strengthening of road from Gandacherra to Amarpur ch. 0.00 km to ch. 17.50 km/ re-carpeting, metalling and seal coating. L=17.50km Job No. TP/COM/46 /2018-19. |
RIDF-XXIV |
|
|
Work in progress |
32 |
Kamalpur |
Improvement and upgradation of Lamboo-Garden road to Mayacherri of length 4.625 km/ SH;- Widening, carpeting, CD etc. |
RIDF-XXV |
|
|
Tender accepted |
33 |
Kamalpur |
Improvement and upgradation of Kamalpur to Manikbhander Road to Double Lane/ SH: Widening,BM, carpeting, CD etc. portion from 0.00 Km to 5.00 Km. |
RIDF-XXIII |
|
|
Work order issued on 02.02.2021 |
34 |
LTV |
Improvement of road from Karamcherra market (at NH44) to Ramani Reang Para (L= 3.00 km)/ SH:- Metalling, carpeting, road side drain and retaining wall wall etc. Portion from 1.00 km to 3.00 km. |
RIDF-XXV |
|
|
Work order issued. |
35 |
LTV |
Improvement of road from Chailengta Buddha Mandir to NH-44(A) Lalcherra road (L = 0.75 km)/ SH:- Metalling, carpeting, road side drain and toe wall etc. |
RIDF-XXV |
05/05/2020. |
19/11/2020. |
Work order issued. |
36 |
LTV |
Strengthening of road from Santi Para to Berimura (L = 4.87 km) during the year 2018-19/ SH:-patch soling, patch metalling, re-carpeting, grouting in/c side drain etc. |
RIDF-XXII |
16/11/2017. |
30.11.2018. |
Work in progress. |
CIRCLE-IV |
|
|
|
|
|
37 |
Mohanpur |
Strengthening of road from Santi Para to Berimura (L = 4.87 km) during the year 2018-19 / SH:-patch soling, patch metalling, re-carpeting,grouting in/c side drain etc.
|
RIDF-XXIV |
|
|
0.8 Km PMC completed on May,20. |
38 |
Mohanpur |
Improvement of road from Lembucherra to Kalkalia via Noagaon-Bazalghat / SH:- Patch soling, metalling,carpeting, side drain in/c 2 nos CD portion from Noagaon up to Bamutia-Fatikcherra road (L = 2.15 km) |
RIDF-XXV |
|
|
W.O issued.Expected to complete 1.15 Km in Dwc,20 and rest 1.00 Km in Jan,21. |
39 |
Mohanpur |
Improvement of road from Agt - Simna road at ch. 33.00 km to Khowai Chowmuhani via Hezamara (L = 5.50 km) / SH:- Patch soling, metalling,carpeting, side drain including 2 nos CD etc. Portion from Ch. 1.70 km to 3.60 km (Haticherra to Barshanpara). |
RIDF-XXV |
|
|
Work in progress. |
40 |
Mohanpur |
Improvement of road from Khowai to Radhanagar via Sankhola Industry (L = 10.00 km)/ Patch soling, metalling, carpeting,side drain, CD etc./ Portion from ch. 0.00 km to 6.00 km starting from Radhanagar |
RIDF-XXIV |
|
|
Work order issued.site |
41 |
Jirania |
Improvement of road from TTAADC H/Q to Jampaijala SDM Office via Gurupada Colony and Firm Chowmuhani (L = 10.90 km) under Belbari RD Block/ SH:- Widening by GSB,metalling, carpeting & construction of retaining wall,toe wall & CD etc. |
RIDF-XXV |
|
|
Work order to be issued. |
42 |
Jirania |
Improvement of road from NH-44 (now NH-08) (Champak Nagar) to TTAADC H/Q via Balaram Thakur Para and Bikram Molsom (L = 14.00 km) under Belbari R D Block / SH:- Widening by GSB, metalling,carpeting, sand seal coating & construction of retaining wall,toe wall & CD etc. |
RIDF-XXV |
|
|
Tender received |
43 |
Jirania |
Strenthening of ring road of NIT from NIT North gate to sankar Bazar PWD road via Badramiship para(L=2.64Km) during the year 2018-19/ SH: re-sectioning, DBm,carpeting, seal coating, masonry toe wall and pucca drain etc. |
RIDF-XXIV |
29.02.20 |
15.09.20 |
Work completed |
44 |
Jirania |
Improvement of road from Old Mandai to Madhabpara (L = 12.50 Km) / Sh:- Construction of retaining wall and road side pucca drain including metalling, carpeting, sand seal coat etc. portion from 1.00 km to 12.50 km (Job No.TP/COM/117/2016-17) Name of agency:-Sri. Prafulla Das |
RIDF-XXII |
06.01.17 |
16.09.17 |
Completed |
45 |
Jirania |
Imp. of road from NH08 (Karaiban) to Tolakona via Noagaon Keprampara Landless Colony (L = 5.00 km).Name of Agency : Dilip Kar. |
RIDF-XXIII |
|
02.10.20 |
completed |
46 |
Sonamura |
Strengthening of road from Durlavnarayan to Kalirbazar via Kash Chowmuhani (L = 6.10 km) during the year 2018-19 / SH:- Widening, GSB,WBM,carpeting, CD,toe wall, pucca drain etc. (Job No:-TP/COM/63/2018-19) |
RIDF-XXIV |
8.0619 |
21.08.20 |
Work in progress |
47 |
Sonamura |
Construction of road from Ghoshpara to Barmura Panchayet Office via Ghoshpara School under Paharmura Panchayet L= 0.50km |
RIDF-XXIV |
08.0.3.19 |
22.01.20 |
Work in progress. |
48 |
Sonamura |
Improvement of road from Kathalia Microsapara road (at Ledrabari) to Manaipathar (L=7.50Km) /SH: Widening,Formation, GSB, WBM,BM,PMC with seal coat, CD,Protection wall and Road side drain/Kathalia Block/TSP area.Agency:-Sri Tapesh Debnath.Agrement No-138/CE/SE-IV/EE/SNM/2017-18 |
RIDF-XXII |
17.06.2017 |
01.01.2019 |
Work completed |
49 |
Sonamura |
Strengtheing of road from Mayarani to Kalirbazar via Rabigopal School (L = 3.50 km) and road from Kunaban Chowmuhani to Durlavnarayan (L = 2.00 km) during the year 2018-19 / SH:- Widening, GSB, WBM,carpeting, CD, toe wall, pucca drain etc. |
RIDF-XXIV |
03.08.19 |
23.03.20 |
Wok completed |
50 |
Bishalgarh |
Strengthening of road from Sarkar Tilla Champamura (L 4.00 km) during the year 2018-19/ SH:- re-sectioning,carpeting, sand seal coating & CD. |
RIDF-XXIV |
3.0619 |
17.02.20 |
Completed |
51 |
Bishalgarh |
Strengtheing and widening road from Bye Pass (near Railway Station over Bridge) To 400 kv Sub-Station Surjyamaninagar via Kathaltali G.P. Madhuban G.P. At Dukli Industrial Block to Ranirkhamar (L=5.00km)/SH:- GSB, metalling and carpeting etc.(Job No:-TP/COM/61/2018-19) |
RIDF-XXIV |
|
|
6th call tender received and tender under scrutiny. |
52 |
Bishramganj |
Improvement of road from Golaghati - Nabasantiganj Bazar to Birchandrapara under Jampaijala R D Block (L = 3.60 km)during the year 2018-19/ SH:- Formation,GSB, WBM-II & III, carpeting, sand seal coating.(Job No:-TP/COM/56/2018-19). |
RIDF-XXIV |
9.1019 |
24.04.19 |
1.02 Km completed in MaY'20. Work is almost completed as per availibility. Balance length of 0.480 Km is being taken up shortly against the sanctioned amount and length of 3.60 Km |
ANNEXURE-F |
Quarter Wise Action Plan For OTPMGSY Road works During 2020-21 |
Sl |
Name of Division |
Name of work |
Source of fund |
Date of W.O issued |
Stipulated date of completion |
Present status |
CIRCLE-I |
1 |
Kumarghat |
Improvement of Road from |
RIDF-Gap Fund |
10.01.2018 |
31.12.2020 |
Completed |
|
|
|
|
|
|
|
|
|
Nadiyapur bazaar to P-F-H-C road via Saidacherra village (length-6.0 Km) during the year 2014-15 Under Kumarghat Block(3.50 Km) .Otpmgsy |
|
|
|
|
CIRCLE-II |
2 |
Teliamura |
Improvement of road from A.A. road to Kuishartilla under Paschim Teliamura GP (L-1.50 Km)/ SH: Formation,soling, metalling, carpeting,Toe wall, drain in/c. CD. |
RIDF-Gap Fund |
14-09-2017 |
30-11-2019 |
Work suspended |
CIRCLE-V |
3 |
Ambasa |
Improvement of road from Chowkidar para road near Kulakbashi Sutradhar house to Goutam Saha house (L=0.205 km) portion from 0.00 km to 0.205 km /SH:- Formation, GSB, WBM,Carpeting, RCC Box cell (Size 6.00 x 6.00 mtr. Triple cell)etc. under Gandacherra Sub-division,PWD (R&B), Gandacherra,Dhalai Tripura during the year 2015-16.TP/COM/23/2016-17 |
RIDF-Gap Fund |
|
|
Completed |
4 |
Ambasa |
Construction of colony road adjacent to newly constructed ChandraiparaH/S School From NH-8 to slab culvert |
RIDF-Gap Fund |
|
|
Completed |
CIRCLE-IV |
5 |
Sonamura |
Improvement Of road from Uttar Thalibari to Gamaicherra market(L=3.00 KM) /SH:- Formation ,re-soling, metalling,carpeting and seal coat in/c. protection wall,pucca drain and CD structure etc./Kathalia Block/TSP area.Agreement No :-30/CE/SE-IV/EE/SNM/PWD/2018-19.under OTPMGSY. |
RIDF-Gap Fund |
27.06.2017 |
11.10.2018 |
Work in progress |
CIRCLE-III |
6 |
Amarpur |
Imp. of road from Amarpur -Gandacherra road to Chandukcherra (L= 3.50 km)/SH: Missing Soling,WBM, carpeting and sand seal coat.(Job No-TP/COM/50/2016-17) |
RIDF-Gap Fund |
24-10-2019 |
08-05-2020. |
Work in progress |
ANNEXURE-G |
Quarter Wise Action Plan For SDS & SPA Road Works During 2020-21 |
Sl No |
Name of Division |
Name of work |
Source of Fund |
Date of W.O issued |
Stipulated time of completion |
Presnt status |
CIRCLE-IV |
SDS |
|
|
|
|
1 |
Sonamura |
Imp. of road from Barpathar School to Kirtania Bari, Indoria Road via Madhucharan Para, Banker Bari under Mohanbhog RD Block(L-4.10 Km)/ SH: Formation, soling, WBM,carpeting, CD structure, protection wall and road side pucca drain. |
RIDF(Gap Fund) |
21-09-2017 |
12-06-2018 |
(a) 600 mtr. Formation work & other work as per contract wil be started in 1st Qtr. b) 1.00 Km land not available. |
2 |
Sonamura |
Imp. of road from Santi Kali Ashram to Subash Colony via Kani Pathar (L-3.50 Km) under Mohanbhog RD Block/ SH: Formation, soling,metalling, carpeting, CD structure in/c protection wall and road side pucca drain. |
RIDF(Gap Fund) |
08-09-2017 |
24-05-2018 |
120 m paddy land not available.a) Gr. I, II, III, of Ch. 0.00 Km to Ch. 2.625 Km completed. b) Formation work of Gr-IV Ch. 2.625 Km to Ch. 3.50Km on availability of land will be started soon |
3 |
Sonamura |
Improvement of road from Harihar Noatia house to Chandul ADC village to Taisakandal PWD road via Baman Kumar Para (L=4.250km)/ SH: Formation, soling, WBM,carpeting, CD, Protection wall,road side drain etc. Under SDS. |
RIDF(Gap Fund) |
01-02-2018 |
17-01-2019 |
(a) PMC completed 1.00 Km in Gr-I b) Soling, Drain, R/W & drain completed in Gr-II & III (C )4 m wide CD to be converted into 30mtr. Bailey bridge preparing separate estimate (d) 1.20Km soling road has depressed in different stratches in Gr-II & III,re- sectioning by sand filling selected soil will be started by may,2020 & then WBM work will be started. |
SPA |
1 |
Sonamura |
Improvement of road from Kathalia to Kirtaniabari via Naldhepa, Barkhala, Indoria (L=11.713 Km) under SPA |
|
27.11.2015 |
10.06.2017 |
(a) Formation= 7.640Km,GSB= 7.640Km,WBM II= 3.20Km,WBM III =7.00Km and PMC = 4.800km has already been completed. Balance PMC = 2.200Km will be done after approved of tentative deviation from the higher authority. |