ANNEXURE-D
Quarter Wise Action Plan For 2020-21  Road works under NESIDS.
Sl Name of Division Name of work Source of Funding Date of W.O issued Stipulated date of completion Remarks
CIRCLE-III
1 Amarpur Improvement of Tourist spot connectivity from Amarpur (fatiksagar) leading to Chabimura and having access toeco-Tourist Centre. Agency: Debasish Das. NESIDES 24-01-2020 08-08-2021 Work in progress.
CIRCLE-V
2 Ambassa Improvement of  road from Gandacherra - Raishyabari road at Ch.18.30 Km to Narikel Kunja (L -8.00km) for easy access for the Tourists from Dhalai, North & Unakoti Districts to Narikel Kunja island surrounded by Dumbur Lake Water. NESIDES 31-12-2019 30-06-2021 Work in progress.
ANNEXURE-E
Quarter Wise Action Plan For RIDF Road Works During 2020-21
Sl Name of Division Name of work Source of Funding Date of W.O issued Stipulated date of completion Remarks
1 2 3 4 5 6 7
CIRCLE-I
1 Kailasahar Strengthening of Kailashahar - Fatikroy road/ Patch metalling,grouting, re-carpeting, seal coating including CD and road side pucca drain ch. 0.00 to 7.10 km.Job.No TP/COM/53/2018-19 (General) RIDF-XXIV 02-09-2019 28-02-2020 completed
2 Dharmanagar Strengthening of road D.A. Road to NH-08 via Baraithal/ SH:- re-carpeting,grouting, portion from ch. 1.50 km to ch. 4.00 km.Job No. TP/COM/48 /2018-19.(RIDF) (general) RIDF-XXIV 28-08-2019 11-12-2019 completed
3 Dharmanagar Improvement of Bagbassa – Dharmanagar road from intermediate lane to double lane (Job No.TP/COM/107/2016-17) (RIDF) General RIDF-XXII 06-08-2019 20-02-2020 completed
4 Dharmanagar Improvement of road from Nutanbazar to Gobindapur road via Pretyekroy H.S. School road (L-4.00 km)  (Job No.TP/COM/112/2016-17) Agency: S.N Bhattacharjee. RIDF-XXII 17-06-2019 31-12-2019 Work in progress
5 Kumarghat Up-gradation of Machmara to Krishnatilla Road (Total Length=7.00 Km). RIDF-XXIII 06.12.19 31.07.21 Work in progress
6 Kumarghat Sthrengthening oif road from 82 mile to bhati Dhudpur during the year 2018-19 /SH: Carpeting, Grouting etc. RIDF-XXIV 01.08.19 30.06.20 work completed
CIRCLE-II
7 Khowai Strengthening of PWD Bituminus road from Tulasikhar Block to Tulasikhar Bazar under Tulasikhar Block ( L= 7.00km) / SH: WBM-II, WBM-III and re-carpeting work  RIDF-XXIV 06-12-2019 21-10-2020 Work completd
8 Khowai Strengthening of PWD Bituminus road from  Dhalabil to Ramchandra Ghat under Khowai Block ( L= 6.50km) / SH: WBM-II, WBM-III and re-carpeting work  RIDF-XXIV 18-12-2019 03-10-2020 Completed
9 Khowai Imp of road from T.K. road  from Baramaidan to Porkhalong (L=11.00 km) via Worento bar to Hazaribari under Padmabil Block /SH: Re- Carpeting, WBM-II,Tack Coat carpeting, Seal Coat, Surface drain ,Soling, CD. JOB NO. TP/COM/23/2018-19 RIDF-XXIII 15.06.2019 30.06.2021 Completed
10 Teliamura Up-gradation of road from Rajkumar para to Dhaniram para (L = 3.50 km)under Mungiakami Block / Sh:- Metalling, carpeting,box culvert, pucca drain and protection work etc. RIDF-XXV     Tender accepted
11 Teliamura Improvement of road from AA road near Tuichindrai bazar to Hrankhal bazar (Ch..00 km to 2.50 Km)SH: Widening metalling,carpeting,retaining wall, cd etc (TP/COM/22/2018-19) RIDF-XXIII 14.02.2019 01.06.2020 Completed
CIRCLE-III
12 shantirbazar Strengthening of the road from Santi Colony to Paikhola via Rail Station. L= 4.50km. Agency (Ratan Sarkar) SCSP RIDF-XXIV 07-06-2019 22-06-2020 completed
13 shantirbazar Improvement of road from Bagafa to Gobindabari / Sh:- Widening of road, re-grading, soling,retaining wall, toe wall, metalling, carpeting and road side pucca drain etc. ch. 4.00 km to 9.50 Km. (Job No.TP/COM/126/2016-17) (TSP)Name of agency:- N.G. Bhattacharjee RIDF-XXII 09/092016 24-03-2018 Work in progress
14 shantirbazar Upgradation of of road from Shillong Mog Para to Lowgang Bazar (L = 1.648 km) and Lowgang Bazar (Ganga Mandir) to Gardhang via Chaigharia School and Das Para (L = 3.176 km)/ Sh:- Soling, metalling, carpeting, protection wall and road side pucca drain etc.(Total length 4.824 km).SCSP RIDF-XXV     Work in progrss.
15 Santir bazar Imp. of road from Bagafa to Akama (L= 12.00 km)/ Sh:- Widening of road, re-grading, soling,retaining wall, toe wall, metalling, carpeting and road side pucca drain etc. ch. 0.00 km to 10.50 km.(Job No.TP/COM/127/2016-17) Name of agency:-Sri Bhanu Patari(Gr.No.II ch 5.50 to 12.00 km) RIDF-XXII 31-07-2017 15-02-2019 Tender accepted
16 Santir bazar Improvement of road from NH-44 (Jolaibari)to Ailmara via Kowaifung (L = 21.25 Km)(Job No.TP/COM/128/2016-17).Agency: Jahar lal Sarkar(TSP) RIDF-XXII 17-01-2018 01-08-2019 Work in progress
17 Shantirbazar Improvement of road from Santirbazar to Kasko (Amarpur)via Debipur (L = 33.50 Km).Agency: Kishore Roy.(Job No.TP/COM/120/2016-17) RIDF-XXII     Proposal sent for dropping the work vide letter No.F.3(23)/PC(RDQP)/2015-16/4897-903 dated 7th January 2021.
18 Santir bazar Improvement of road from Jolaibari to Hrishyamukhvia Ramraibari (L=16.96 km)/ widening, regrading,C.D. , Side drain, Toe wall , etc. ch. 0.00 Km to 16.96 km.Agency: Kishore Roy RIDF-XXIII 30-09-2019 14-06-2021 Out of Total Length=16.96 K.M only 6.25k.m is under Santirbazar PWD (R&B) Division. 6.25 Kmformation completed.
19 Santir bazar Improvement of road from TNV Colony(Aloy Cherra Market, NH44) to B.B. road viaKhas Tilla & NBCC Road (L094) (L= 7.80 Km)(Job No.TP/COM/129/2016-17)  RIDF-XXII 14-01-2020 29-07-2021 Work completed.
20 Belonia Improvement of road from Satmura Chowmuhani to Belonia Railway Station (L-2.40 km)/ SH: Widening, Flat & edge Soling, Metalling,Carpeting, Construction of C.D., Toe wall,Road side pucca drain & other allied works.Agency: Sankar Saha. RIDF-XXIII 13.12.19 20.06.21 Work in progress
21 Belonia Strengthening of road from Ratanpur to Monirambari via Shibpur ADCV Village under Hrishyamukh RD Block / Sh:- Patch repairing and re-carpeting.etc. L= 6.00km.Name of Agency: Gopi Deb Roy.Job No. TP/COM/44 /2018-19. RIDF-XXIV 30.05.19 13.06.20 Work completed
22 Belonia Strengthening of road  from Belonia - Rajnagar road near Sonapur Girls School to Monaipathar via Hetalia under Rajnagar RD Block / Sh:- Patch repairing and re-carpeting etc. L= 4.00km.Job No. TP/COM/45/2018-19 .Agency: Jiban Krishna Sen. RIDF-XXIV 06.08.19 18.08.20 Work in progress
23 Belonia Improvement and widening (both side) of road from Kashari Trijunction to Gourangabazar to make it intermediate width (total length - 30.00 km)/ Sh:- Flat brick soling, edge soling, metalling, carpeting, seal coat, protection wall and other allied works etc. RIDF-XXIII     Work in progress.
24 Udaipur Strengthening of road from Agartala - Udaipur (Police Line) road to Khupilong / SH:- Re-carpeting & seal coat.L= 5.00km Job No. TP/COM/40 /2018-19. Name of Agency: Chitta Rn Saha. RIDF-XXIV 07.03.2019 22.09.2019 Work completed
25 Amarpur Strengthening of road from Dalak to Gamako via Paschim Malbassa/ SH;- Re-carpeting, sand seal coat. L= 4.00km RIDF-XXIV 01/08/209 16-08-2020. Work in progrss.
26 Amarpur Improvement of  road  from Tuidu-Lungfung via Palku ( L=10.50 Km)/ SH: Brick Soling, WBM, Carpeting, Sand seal coat, CD etc. Agency: Ajit Bhattacharjee. SCSP RIDF-XXIII 22-08-2019 09-12-2020. Work in progrss.
27 Sabroom Improvement of road from Jalefa Petrol Pump to Sabroom Railway Station. L=2.00km. Job No.TP/COM/47/2018-19. Agency: Jiban lal Sarkar.(General) RIDF-XXIV 21.10.2019 04.02.2021 Work completed
28 Sabroom Improvement of road from Kalacherra to Manirambari via Gardhang (L = 9.50 Km) (Job No.TP/COM/125/2016-17). Agency:- Bimalendu Chakraborty. RIDF-XXII 07.08.2019 06.01.2021 Work completed
CIRCLE-V
29 Ambassa Improvement of road from NH-08 (ch. 381 km) to Sikaribari tower/ Re-carpeting, metalling and seal coating, retaining wall, traffic signages etc. RIDF-XXV     4th call tender invited on 01.03.21
30 Ambassa Improvement of Gandacherra-Raishyabari  road (L=32.00KM) /SH:-Widening, strengthening, retaining wall, toe wall, CDs etc. portion from 0.00 Km to 28.50Km. Job No.TP/COM/49/2015-16 Agency:- M/S.N.G Bhattacharjee .co RIDF-XXI 20-01-2017 04-03-2019 Work in progress
31 Ambassa Strengthening of road from Gandacherra to Amarpur ch. 0.00 km to ch. 17.50 km/ re-carpeting, metalling and seal coating. L=17.50km Job No. TP/COM/46 /2018-19. RIDF-XXIV     Work in progress
32 Kamalpur Improvement and upgradation of Lamboo-Garden road to Mayacherri of length 4.625 km/ SH;- Widening, carpeting, CD etc. RIDF-XXV     Tender accepted
33 Kamalpur Improvement and upgradation of Kamalpur to Manikbhander Road to Double Lane/ SH: Widening,BM, carpeting, CD etc. portion from 0.00 Km to 5.00 Km. RIDF-XXIII     Work order issued on 02.02.2021
34 LTV Improvement of road from  Karamcherra market (at NH44) to Ramani Reang Para (L= 3.00 km)/ SH:- Metalling, carpeting, road side drain and retaining wall wall etc. Portion from  1.00 km to 3.00 km. RIDF-XXV     Work order issued.
35 LTV Improvement of road from Chailengta Buddha Mandir to NH-44(A) Lalcherra road (L = 0.75 km)/ SH:- Metalling, carpeting, road side drain and toe wall etc. RIDF-XXV 05/05/2020. 19/11/2020. Work order issued.
36 LTV Strengthening of road from Santi Para to Berimura (L = 4.87 km) during the year 2018-19/ SH:-patch soling, patch metalling, re-carpeting, grouting in/c side drain etc.  RIDF-XXII 16/11/2017. 30.11.2018. Work in progress.
CIRCLE-IV          
37 Mohanpur

Strengthening of road from Santi Para to Berimura (L = 4.87 km) during the year 2018-19 / SH:-patch soling, patch metalling, re-carpeting,grouting in/c side drain etc. 

 

RIDF-XXIV     0.8 Km PMC completed on May,20.
38 Mohanpur Improvement of road from Lembucherra to Kalkalia via Noagaon-Bazalghat / SH:- Patch soling, metalling,carpeting, side drain in/c 2 nos CD portion from Noagaon up to Bamutia-Fatikcherra road (L = 2.15 km) RIDF-XXV     W.O issued.Expected to complete 1.15 Km in Dwc,20 and rest 1.00 Km in Jan,21.
39 Mohanpur Improvement of road from Agt - Simna road at ch. 33.00 km to Khowai Chowmuhani via Hezamara (L = 5.50 km) / SH:- Patch soling, metalling,carpeting, side drain including 2 nos CD etc. Portion from Ch. 1.70 km to 3.60 km (Haticherra to Barshanpara). RIDF-XXV     Work in progress.
40 Mohanpur Improvement of road from Khowai to Radhanagar via Sankhola Industry (L = 10.00 km)/ Patch soling, metalling, carpeting,side drain, CD etc./ Portion from ch. 0.00 km to 6.00 km starting from Radhanagar  RIDF-XXIV     Work order issued.site 
41 Jirania Improvement of road from TTAADC H/Q to Jampaijala SDM Office via Gurupada Colony and Firm Chowmuhani (L = 10.90 km) under Belbari RD Block/ SH:- Widening by GSB,metalling, carpeting & construction of retaining wall,toe wall & CD etc. RIDF-XXV     Work order to be issued.
42 Jirania Improvement of road from NH-44 (now NH-08) (Champak Nagar) to TTAADC H/Q via Balaram Thakur Para and Bikram Molsom (L = 14.00 km) under Belbari R D Block / SH:- Widening by GSB, metalling,carpeting, sand seal coating & construction of retaining wall,toe wall & CD etc. RIDF-XXV     Tender received
43 Jirania Strenthening of ring road of NIT from NIT North gate to sankar Bazar PWD road via Badramiship para(L=2.64Km) during the year 2018-19/ SH: re-sectioning, DBm,carpeting, seal coating, masonry toe wall and pucca drain etc. RIDF-XXIV 29.02.20 15.09.20 Work completed
44 Jirania Improvement of road from Old Mandai to Madhabpara (L = 12.50 Km) / Sh:- Construction of retaining wall and road side pucca drain including metalling, carpeting, sand seal coat etc. portion from 1.00 km to 12.50 km (Job No.TP/COM/117/2016-17) Name of agency:-Sri. Prafulla Das RIDF-XXII 06.01.17 16.09.17 Completed
45 Jirania Imp. of road from NH08 (Karaiban) to Tolakona via Noagaon Keprampara Landless Colony (L = 5.00 km).Name of Agency : Dilip Kar. RIDF-XXIII   02.10.20 completed
46 Sonamura Strengthening of road from Durlavnarayan to Kalirbazar via Kash Chowmuhani (L = 6.10 km) during the year 2018-19 / SH:- Widening, GSB,WBM,carpeting, CD,toe wall, pucca drain etc. (Job No:-TP/COM/63/2018-19)  RIDF-XXIV 8.0619 21.08.20 Work in progress
47 Sonamura Construction of road from Ghoshpara to Barmura Panchayet Office via Ghoshpara School under Paharmura Panchayet L= 0.50km RIDF-XXIV 08.0.3.19 22.01.20 Work in progress.
48 Sonamura Improvement of road from Kathalia Microsapara road (at Ledrabari) to Manaipathar (L=7.50Km) /SH: Widening,Formation, GSB, WBM,BM,PMC with seal coat, CD,Protection wall and Road side drain/Kathalia Block/TSP area.Agency:-Sri Tapesh Debnath.Agrement No-138/CE/SE-IV/EE/SNM/2017-18 RIDF-XXII 17.06.2017     01.01.2019 Work completed
49 Sonamura Strengtheing of road from Mayarani to Kalirbazar via Rabigopal School (L = 3.50 km) and road from Kunaban Chowmuhani to Durlavnarayan (L = 2.00 km) during the year 2018-19 / SH:- Widening, GSB, WBM,carpeting, CD, toe wall, pucca drain etc.  RIDF-XXIV 03.08.19 23.03.20 Wok completed
50 Bishalgarh Strengthening of road from Sarkar Tilla Champamura (L 4.00 km) during the year 2018-19/ SH:- re-sectioning,carpeting, sand seal coating & CD.  RIDF-XXIV 3.0619 17.02.20 Completed
51 Bishalgarh Strengtheing and widening road from Bye Pass (near Railway Station over Bridge) To 400 kv Sub-Station Surjyamaninagar via Kathaltali G.P. Madhuban G.P. At Dukli Industrial Block to Ranirkhamar (L=5.00km)/SH:- GSB, metalling and carpeting etc.(Job No:-TP/COM/61/2018-19)  RIDF-XXIV     6th call tender received and tender under scrutiny.
52 Bishramganj Improvement of road from Golaghati - Nabasantiganj Bazar to Birchandrapara under Jampaijala R D Block (L = 3.60 km)during the year 2018-19/ SH:- Formation,GSB, WBM-II & III, carpeting, sand seal coating.(Job No:-TP/COM/56/2018-19).  RIDF-XXIV 9.1019 24.04.19 1.02 Km completed in MaY'20. Work is almost completed as per availibility. Balance length of 0.480 Km is being taken up shortly against the sanctioned  amount and length of 3.60 Km
ANNEXURE-F
Quarter Wise Action Plan For OTPMGSY Road works During 2020-21
Sl Name of Division Name of work Source of fund Date of W.O issued Stipulated date of completion Present status
CIRCLE-I
1 Kumarghat Improvement of Road from RIDF-Gap Fund 10.01.2018 31.12.2020 Completed
             
    Nadiyapur bazaar to P-F-H-C road via Saidacherra village (length-6.0 Km) during the year 2014-15 Under Kumarghat Block(3.50 Km) .Otpmgsy        
CIRCLE-II
2 Teliamura Improvement of road from A.A. road to Kuishartilla under Paschim Teliamura GP (L-1.50 Km)/ SH: Formation,soling, metalling, carpeting,Toe wall, drain in/c. CD. RIDF-Gap Fund 14-09-2017 30-11-2019 Work suspended
CIRCLE-V
3 Ambasa Improvement of road from Chowkidar para road near Kulakbashi Sutradhar house to Goutam Saha house (L=0.205 km) portion from 0.00 km to 0.205 km /SH:- Formation, GSB, WBM,Carpeting, RCC Box cell (Size 6.00 x 6.00 mtr. Triple cell)etc. under Gandacherra Sub-division,PWD (R&B), Gandacherra,Dhalai Tripura during the year 2015-16.TP/COM/23/2016-17 RIDF-Gap Fund     Completed
4 Ambasa Construction of colony road adjacent to newly constructed ChandraiparaH/S School From NH-8 to slab culvert  RIDF-Gap Fund     Completed
CIRCLE-IV
5 Sonamura Improvement Of road from  Uttar Thalibari to Gamaicherra market(L=3.00 KM) /SH:- Formation ,re-soling, metalling,carpeting and seal coat in/c. protection wall,pucca drain and CD structure etc./Kathalia Block/TSP area.Agreement No :-30/CE/SE-IV/EE/SNM/PWD/2018-19.under OTPMGSY. RIDF-Gap Fund 27.06.2017 11.10.2018 Work in progress
CIRCLE-III
6 Amarpur Imp. of road from Amarpur -Gandacherra road to Chandukcherra (L= 3.50 km)/SH: Missing Soling,WBM, carpeting and sand seal coat.(Job No-TP/COM/50/2016-17) RIDF-Gap Fund 24-10-2019 08-05-2020. Work in progress
ANNEXURE-G
Quarter Wise Action Plan For SDS & SPA Road Works During 2020-21
Sl No Name of Division Name of work Source of Fund Date of W.O issued Stipulated time of completion Presnt status
CIRCLE-IV
SDS        
1 Sonamura Imp. of road from Barpathar School to Kirtania Bari, Indoria Road via Madhucharan Para, Banker Bari under Mohanbhog RD Block(L-4.10 Km)/ SH: Formation, soling, WBM,carpeting, CD structure, protection wall and road side pucca drain. RIDF(Gap Fund) 21-09-2017 12-06-2018 (a) 600 mtr. Formation work & other work  as per contract  wil be started in 1st Qtr. b) 1.00 Km land not available.
2 Sonamura Imp. of road from Santi Kali Ashram to Subash Colony via Kani Pathar (L-3.50 Km) under Mohanbhog RD Block/ SH: Formation, soling,metalling, carpeting, CD structure in/c protection wall and road side pucca drain. RIDF(Gap Fund) 08-09-2017 24-05-2018 120 m paddy land not available.a) Gr. I, II, III, of Ch. 0.00 Km to Ch. 2.625 Km completed.  b) Formation work of Gr-IV Ch. 2.625 Km to Ch. 3.50Km on availability of land will be started soon 
3 Sonamura Improvement of road from Harihar Noatia house to Chandul ADC village to Taisakandal PWD road via Baman Kumar Para (L=4.250km)/ SH: Formation, soling, WBM,carpeting, CD, Protection wall,road side drain etc.  Under SDS. RIDF(Gap Fund) 01-02-2018 17-01-2019 (a) PMC completed 1.00 Km in Gr-I   b) Soling, Drain, R/W & drain completed in Gr-II & III (C )4 m wide CD  to be converted into 30mtr. Bailey bridge preparing separate estimate (d) 1.20Km soling road has depressed in different stratches in Gr-II & III,re- sectioning by sand filling selected soil will be started by may,2020 & then WBM work will be started.
SPA
1 Sonamura Improvement of road from Kathalia to Kirtaniabari via Naldhepa, Barkhala, Indoria (L=11.713 Km) under SPA   27.11.2015 10.06.2017 (a) Formation= 7.640Km,GSB= 7.640Km,WBM II= 3.20Km,WBM III =7.00Km and PMC = 4.800km has already been completed. Balance PMC = 2.200Km will be done after approved of tentative deviation from the higher authority.

 