ANNEXURE-C
Quarter Wise Action Plan For RCC Box Culvert to be completed During 2020-21
Sl Name of work Source of Fund Date of W.O issued Sipulated date of completion. Present status
1 Re-Construction of RCC double Cell Box culvert (2x 5.00x 5.00) on Dharmanagar - Khedacherra Road at Ch. 5.90km during the year 2017-18.(General) RIDF-XXIV 17-06-2019 02-01-2020 Open for traffic 
2 Replacement  of  baiiley bridge by RCC  Box culvert (Span  =3x 6.00  mtr  Height 4.00 m ) over Ragnacherra  near Ragna LCS  during the year 2017-18 RIDF-XXIV 28-08-2019 January,20 Work could not be started due to non-availability of clear site. Matter has been communicated with BSF authority and SDM, Dharmanagar.
3 Construction of  RCC  Box culvert (Span  =3x 6.00  mtr  Height 5.00 m ) over local  cherra  on Bhagyapur PWD road to  NH 208 A near Sonarbassa   during the year 2017-18.  (General)                     RIDF-XXIV 28-08-2019 March,20 Work in progree
4 Replacement of bailey bridge by Triple Box Cell Culvert at North Waimbukcherra on Damcherra to Khedacherra road(3 x7.00 x 7.00 mtrs) (At ch. 44.10 km). (TSP) RIDF-XXIV 26-02-2020 Aug, 2020 Work in progress
5 Construction of R.C.C box cell culvert  (L=3X8.00m=24.00m, height-5.60m) over Ichalicherra on the road from Ratanpur bazaar tilla to Padmabil  under padmabil block  ( TSP)  RIDF-XXIV 06-06-2019 20-12-2019 Work of approach is in progress.
6 Construction of R.C.C box cell culvert  (L=3X6.00m=18.00m, height-5.00m) over sonaraicherra on the road from Iswarsardar para to Dulalia bari under padmbil block (TSP) RIDF-XXIV 22-02-2019 07-09-2019 Work of approach is in progress.
7 Construction of R.C.C box cell culvert  (L=3X4.00m=12.00m, height-3.00m) over local cherra on the road from Baijalbari to Donbosco school under padmabil block ( TSP) .Job No. TP/COM/70/2018-19                                       RIDF-XXIV 22-02-2019 09-09-2019 Work of approach is in progress.
8 Construction of RCC box cell of span (3x5.00m) and 5.00m clear height and carriage width 6.00m on the road from NH-08(Harina)to Babugram at ch 1.70km on Rupaicherra. (general) RIDF-XXIV 31.05.2019 30.11.2020 Work  in progress
9 Construction of RCC Box-Cell Culvert ( 3x8.00mtr) over Local Cherra on the road from Karbook-Silachari road (Nabajoy Para) to Chellagang  at Ch. 10.80km. RIDF-XXIV     Work  in progress
10 Construction of RCC Box-Cell Culvert ( 3x6.00mtr) over Local Cherra on the road from Karbook-Silachari road (Nabajoy Para) to Chellagang  at Ch. 10.00km. RIDF-XXIV     Open for trffic.
11 Construction of RCC Box-Cell Culvert ( 2x6.00mtr) over Local Cherra on the road from Karbook-Silachari road (Nabajoy Para) to Chellagang  at Ch. 0.70km. RIDF-XXIV     Work in progress.
12 Replacement of spun pipe culvert by Box-cell 5.00 x 5.00mtr at ch.7.9km of garjee tainani road. (TSP) RIDF-XXIV 09.09.2019 24.12.2019 Open for trffic.
13 Construction of four cell RCC Box structure 5.5 m x 7.80 m (with earth cushion) over local cherra across the approach road towards Santirbazar end of the RCC Bridge over river Muhuri from Shillong Mog Para - Bhagyamani Chakma Para (PMGSY road) to Betaga via Lowgang at ch. 1.70 km.(General) RIDF-XXIV 26-06-2019 11-07-2020 Work in progress.
4. Approach RIDF-XXIV
14 Construction of RCC Box-cell Culvert  on bridge approach of Shilong Mog para - Bhagyamuni Chakma Para (PMGSY road) to Betaga via Lowgang at ch. 2.069 Km. (General) RIDF-XXIV 18-06-2019 03-01-2020 Open for traffic
15 Replacement of bailey bridge by construction of RCC Box culvert (3m x 8m) at Madhyapara on the road from  Belonia-UBC Nagar road to UBC nagar-Barpathari road during the year 2018-19. (General) RIDF-XXIV 30.05.19 10.12.19 Work in progress.
16 Replacement of bailey bridge by construction of RCC Box culvert (3m x 8m) at Muzaffar para on the road from Bishnupur AWC to Bagachetal bazar during the year 2018-19. (Genral) RIDF-XXIV 30.05.19 10.12.19 Work in progress.
17 Construction of RCC Box culvert ( Length = 2 x 8.00 m = 16.00 m, Height =7m, Carriageway width 7.5 m without footpath) over Localcherra on the road from Chailengta to Chawmanu via Chalitacherra under Manu R.D. Block during the year 2018-19/ SH: Earth work, P.C.C Work, R.C.C. work, C.C. blockpitching, Brick work, soling etc. Job No. TP/COM/78/2018-19                               RIDF-XXIV 18-06-2019. 02-10-2019. Openfor traffic
18 Construction of RCC Box culvert ( Length = 2 x 8.00 m = 16.00 m, Height =7m, Carriageway width 7.5 m without footpath) over Localcherra on the road from Lalcherra to Gejacherra via Twichak Twisa High School under Manu R.D. Block during the year 2018-19/ SH: Earth work, P.C.C Work, R.C.C. work, C.C. blockpitching, Brick work, soling etc. Job.No /COM/79/2018-19 RIDF-XXIV 19-10-2019. 03-01-2020. Openfor traffic
19 Replacement of existing Bailey Bridge at Khasiapunji on K-A Road to Ashapurna Roaja Para by construction of Box Cell during the year 2016-17/ SH :- Construction of 1 (One) no. Box-cell (3 x 8.00 mtr) . Sri Sujit Ghosh RIDF-XXIII 11-12-2018 24-12-2019 Work in progress.
20 Construction of  RCC Box-cell   at Ch. 2.60 Km over local cherra on K-M-A road to Kachucherra Police Station via Kakariatila  / SH :-1(one) no RCC Box Cell (3x8.00) mtr. RIDF-XXIV 04-09-2019 17-09-2020 Top slab reinforcement work in progress.
21 RCC Boxcell 2 x 6.00 Mtr at Radhanagar over local Cherra Road from Kalinjoy to Battala under Hezamara R.D. Block. RIDF-XXIV 30/02/2019 29-08-2019 Agency has surrended the work. Tender invited.
22 Construction of RCC box cell near Amarendranagar bazar on the road from Takarjala to Bishramganj at ch. 8.00 km (3 x 8.00 m) RIDF-XXIV 30-05-2019 15-06-2020 Open for traffic.
23 Replacement of Baily bridge by construction of RCC box cell (2 x 8.00 m) on the road starting from NH-44 to Bikram Molsom para via Balaram thakur Kashidas at Ch.1.20 km. RIDF-XXIII 15-12-2018 06-01-2019 Open for traffic.
24 Replacement of bailey bridge by construction of RCC box cell (2x8.00m) on the road from Korbong to Radha Charan para at Ch: 0.60Km. under Belbari block.  RIDF-XXIV 18-03-2020 10-01-2020 Work in progress
25 Replacement of Bailey Bridge on the road from Anandanagar to Muchrai Para via 9 no. Para ch. Km 0.80 RIDF-XXIV 03.06.19 17.12.19 Open for traffic.

 

 