ANNEXURE-C |
Quarter Wise Action Plan For RCC Box Culvert to be completed During 2020-21 |
Sl |
Name of work |
Source of Fund |
Date of W.O issued |
Sipulated date of completion. |
Present status |
1 |
Re-Construction of RCC double Cell Box culvert (2x 5.00x 5.00) on Dharmanagar - Khedacherra Road at Ch. 5.90km during the year 2017-18.(General) |
RIDF-XXIV |
17-06-2019 |
02-01-2020 |
Open for traffic |
2 |
Replacement of baiiley bridge by RCC Box culvert (Span =3x 6.00 mtr Height 4.00 m ) over Ragnacherra near Ragna LCS during the year 2017-18 |
RIDF-XXIV |
28-08-2019 |
January,20 |
Work could not be started due to non-availability of clear site. Matter has been communicated with BSF authority and SDM, Dharmanagar. |
3 |
Construction of RCC Box culvert (Span =3x 6.00 mtr Height 5.00 m ) over local cherra on Bhagyapur PWD road to NH 208 A near Sonarbassa during the year 2017-18. (General) |
RIDF-XXIV |
28-08-2019 |
March,20 |
Work in progree |
4 |
Replacement of bailey bridge by Triple Box Cell Culvert at North Waimbukcherra on Damcherra to Khedacherra road(3 x7.00 x 7.00 mtrs) (At ch. 44.10 km). (TSP) |
RIDF-XXIV |
26-02-2020 |
Aug, 2020 |
Work in progress |
5 |
Construction of R.C.C box cell culvert (L=3X8.00m=24.00m, height-5.60m) over Ichalicherra on the road from Ratanpur bazaar tilla to Padmabil under padmabil block ( TSP) |
RIDF-XXIV |
06-06-2019 |
20-12-2019 |
Work of approach is in progress. |
6 |
Construction of R.C.C box cell culvert (L=3X6.00m=18.00m, height-5.00m) over sonaraicherra on the road from Iswarsardar para to Dulalia bari under padmbil block (TSP) |
RIDF-XXIV |
22-02-2019 |
07-09-2019 |
Work of approach is in progress. |
7 |
Construction of R.C.C box cell culvert (L=3X4.00m=12.00m, height-3.00m) over local cherra on the road from Baijalbari to Donbosco school under padmabil block ( TSP) .Job No. TP/COM/70/2018-19 |
RIDF-XXIV |
22-02-2019 |
09-09-2019 |
Work of approach is in progress. |
8 |
Construction of RCC box cell of span (3x5.00m) and 5.00m clear height and carriage width 6.00m on the road from NH-08(Harina)to Babugram at ch 1.70km on Rupaicherra. (general) |
RIDF-XXIV |
31.05.2019 |
30.11.2020 |
Work in progress |
9 |
Construction of RCC Box-Cell Culvert ( 3x8.00mtr) over Local Cherra on the road from Karbook-Silachari road (Nabajoy Para) to Chellagang at Ch. 10.80km. |
RIDF-XXIV |
|
|
Work in progress |
10 |
Construction of RCC Box-Cell Culvert ( 3x6.00mtr) over Local Cherra on the road from Karbook-Silachari road (Nabajoy Para) to Chellagang at Ch. 10.00km. |
RIDF-XXIV |
|
|
Open for trffic. |
11 |
Construction of RCC Box-Cell Culvert ( 2x6.00mtr) over Local Cherra on the road from Karbook-Silachari road (Nabajoy Para) to Chellagang at Ch. 0.70km. |
RIDF-XXIV |
|
|
Work in progress. |
12 |
Replacement of spun pipe culvert by Box-cell 5.00 x 5.00mtr at ch.7.9km of garjee tainani road. (TSP) |
RIDF-XXIV |
09.09.2019 |
24.12.2019 |
Open for trffic. |
13 |
Construction of four cell RCC Box structure 5.5 m x 7.80 m (with earth cushion) over local cherra across the approach road towards Santirbazar end of the RCC Bridge over river Muhuri from Shillong Mog Para - Bhagyamani Chakma Para (PMGSY road) to Betaga via Lowgang at ch. 1.70 km.(General) |
RIDF-XXIV |
26-06-2019 |
11-07-2020 |
Work in progress. |
4. Approach |
RIDF-XXIV |
14 |
Construction of RCC Box-cell Culvert on bridge approach of Shilong Mog para - Bhagyamuni Chakma Para (PMGSY road) to Betaga via Lowgang at ch. 2.069 Km. (General) |
RIDF-XXIV |
18-06-2019 |
03-01-2020 |
Open for traffic |
15 |
Replacement of bailey bridge by construction of RCC Box culvert (3m x 8m) at Madhyapara on the road from Belonia-UBC Nagar road to UBC nagar-Barpathari road during the year 2018-19. (General) |
RIDF-XXIV |
30.05.19 |
10.12.19 |
Work in progress. |
16 |
Replacement of bailey bridge by construction of RCC Box culvert (3m x 8m) at Muzaffar para on the road from Bishnupur AWC to Bagachetal bazar during the year 2018-19. (Genral) |
RIDF-XXIV |
30.05.19 |
10.12.19 |
Work in progress. |
17 |
Construction of RCC Box culvert ( Length = 2 x 8.00 m = 16.00 m, Height =7m, Carriageway width 7.5 m without footpath) over Localcherra on the road from Chailengta to Chawmanu via Chalitacherra under Manu R.D. Block during the year 2018-19/ SH: Earth work, P.C.C Work, R.C.C. work, C.C. blockpitching, Brick work, soling etc. Job No. TP/COM/78/2018-19 |
RIDF-XXIV |
18-06-2019. |
02-10-2019. |
Openfor traffic |
18 |
Construction of RCC Box culvert ( Length = 2 x 8.00 m = 16.00 m, Height =7m, Carriageway width 7.5 m without footpath) over Localcherra on the road from Lalcherra to Gejacherra via Twichak Twisa High School under Manu R.D. Block during the year 2018-19/ SH: Earth work, P.C.C Work, R.C.C. work, C.C. blockpitching, Brick work, soling etc. Job.No /COM/79/2018-19 |
RIDF-XXIV |
19-10-2019. |
03-01-2020. |
Openfor traffic |
19 |
Replacement of existing Bailey Bridge at Khasiapunji on K-A Road to Ashapurna Roaja Para by construction of Box Cell during the year 2016-17/ SH :- Construction of 1 (One) no. Box-cell (3 x 8.00 mtr) . Sri Sujit Ghosh |
RIDF-XXIII |
11-12-2018 |
24-12-2019 |
Work in progress. |
20 |
Construction of RCC Box-cell at Ch. 2.60 Km over local cherra on K-M-A road to Kachucherra Police Station via Kakariatila / SH :-1(one) no RCC Box Cell (3x8.00) mtr. |
RIDF-XXIV |
04-09-2019 |
17-09-2020 |
Top slab reinforcement work in progress. |
21 |
RCC Boxcell 2 x 6.00 Mtr at Radhanagar over local Cherra Road from Kalinjoy to Battala under Hezamara R.D. Block. |
RIDF-XXIV |
30/02/2019 |
29-08-2019 |
Agency has surrended the work. Tender invited. |
22 |
Construction of RCC box cell near Amarendranagar bazar on the road from Takarjala to Bishramganj at ch. 8.00 km (3 x 8.00 m) |
RIDF-XXIV |
30-05-2019 |
15-06-2020 |
Open for traffic. |
23 |
Replacement of Baily bridge by construction of RCC box cell (2 x 8.00 m) on the road starting from NH-44 to Bikram Molsom para via Balaram thakur Kashidas at Ch.1.20 km. |
RIDF-XXIII |
15-12-2018 |
06-01-2019 |
Open for traffic. |
24 |
Replacement of bailey bridge by construction of RCC box cell (2x8.00m) on the road from Korbong to Radha Charan para at Ch: 0.60Km. under Belbari block. |
RIDF-XXIV |
18-03-2020 |
10-01-2020 |
Work in progress |
25 |
Replacement of Bailey Bridge on the road from Anandanagar to Muchrai Para via 9 no. Para ch. Km 0.80 |
RIDF-XXIV |
03.06.19 |
17.12.19 |
Open for traffic. |