Annexure-B |
ACTION PLAN FOR RCC BRIDGE TO BE SPILLED OVER TO NEXT YEAR |
Sl No |
Name of work |
Source of fund |
Date of W.O issued |
Stipulated date of completion |
Present status |
1 |
Replacement of Bailey by RCC bridge on the road from Dasda Bazar to Adibasighta at ch. 1.20 km over Deo river. 2-span. |
RIDF-XXIII |
|
|
Tendering stage |
2 |
Replacement of Bailey by RCC bridge on the road from Kanchanpur to Dasda at Ch. 3.00 Km. |
RIDF-XXIII |
|
|
do |
3 |
Replacement of Bailey by RCC bridge on the road from Damcherra to Jalabassa over piplacherra |
RIDF-XXIII |
|
|
work in progress for sinking of piles |
4 |
Replacement of Bailey by RCC bridge over Waimbookcherra on the road from Damcherra to Khedacherra |
RIDF-XXIII |
|
|
do |
5 |
Replacement of SPT bridge no-2 ch-3.00 km by RCC bridge on Nadiapurbazar- Old NEC road via Saidacherra Agency:-Sri. Bhanu Bhusan Deb. |
RIDF-XX |
16-08-2019 |
30-09-2021 |
Piles completed |
6 |
Construction of RCC Bridge over river Manu on Sonaimuri-Telia road(RIDF-XIV) Agency:- Sri.Ashes Deb |
RIDF-IV |
06.01.17 |
20.01.19 |
tender under process |
7 |
Replacement of SPT bridge no-1 ch-0.250 km by RCC bridge on Nadiapurbazar- Old NEC road via Saidacherra. Span-2 |
RIDF-XX |
21-11-2017 |
|
W/Oissued |
8 |
Construction of RCC Bridge over Manu at Chaintail ferrighat on Paiturbazar – Sunamara road(Ch.2035 Km.)(General) |
RIDF-XXIII |
29/05/2020 |
|
Pile work in progress |
9 |
Replacement of Bailey by RCC bridge over Halai cherra on Kailashahar Golakpur –N.C Para road(Ch.-6.90Km) |
RIDF-XXIII |
|
|
Tender accepted. W/O to be issued on receipt of BG |
10 |
Replacement of of Cable Suspension Bridge by RCC Steel truss Bridge over river Manu at Jalai Village near Jalai bazaar |
RIDF-XXIII |
|
|
Tender received |
11 |
Construction of RCC Bridge of over river Khowai at Ch:0.75Km. on the road from Seoratali to Paharmura (L=6.10Km) Agency:-Simplex Projects Ltd |
RIDF-XIV |
09-10-2010 |
09-10-2012 |
Work rescinded. Tender to be invited for balance work |
12 |
Replacement of Bailey Bridge by RCC bridge over Kalsi Cherra on Bagafa to Gobinbari via Akhangama at Ch:- 14.00 Km. Agency:- Tripura Development Corporation Ltd. (TSP) |
RIDF-XX |
24-03-2020 |
08-04-2022 |
Piles of one abutment complete, work in progress |
13 |
Replacement of Bailey Bridge by RCC Bridge over Muhuri river on the road from Kowaifung to Panjirai at Ch.-22.25Km. Agency: Jahar lal Sarkar. 2-span(TSP) |
RIDF-XXVIII |
10-10-2019 |
25-10-2021 |
Diversion work in progress |
14 |
Replacement of Bailey Bridge by RCC Bridge over Thakur Cherra on the road from Jolaibari-Hrishyamukh road at ch.-2.70 Km. Agency:-Sri.Jayanta Chakraborty. |
RIDF-XX |
|
|
Diversion of bridge work started |
15 |
Replacement of Bailey Bridge by RCC Bridge over Borpatirai Cherra on the road from Panjirai at Ch-3.25 Km. 2-span(TSP) |
RIDF-XX |
|
|
12 Nos. pile completed out of 20 |
16 |
Constn. Of RCC bridge (Span = 25.00 mtr) over local cherra near Hrishyamuka Block Office on the road from Belonia – Nalua Road to Hrishyamuka Block |
RIDF-XXIII |
|
|
Tender accepted. W/O to be issued on receipt of BG |
17 |
Replacement of Bailey Bridge by RCC Bridge over Dewan Cherra on Pitra to Nityabazar road at Ch. 0.180 Km.(Job No.TP/COM/28/2013-14) 2-span (TSP). Agency : Prhallad Saha |
RIDF-XX |
10-06-2020 |
|
Pile work in progress |
18 |
Replacement of Bailey bridge by RCC Bridge over Gangachera at Ch.3.110 Km. Of Dataram to Maidabari road. .(Job No.TP/COM/32/ 2013-14). 2-span(TSP) Agency: Sankar Kanti Saha. |
RIDF-XX |
|
|
Pile work completed |
19 |
Replaicement of bailey bridge by RCC bridge over chellagang kurma cherra on the road barmatilla road to chellagang at ch 2.00km. Agency:-Sri.Shambhu Pau. 2-span (TSP) |
RIDF-XX |
21-11-2017 |
06-06-2019. |
Abutments completed, pier work in progress |
20 |
Replacement of SPT Bridge by RCC Bridge (Length=50.00meter) over Mailak Cherra on the road Mailak Panchayet office to East Malabassa at Ch:1.50Km,(Job No.TP/COM/33/2014-15. Agency: TDC Ltd. (SCSP) |
RIDF-XX |
|
|
piles completed |
21 |
Replacement of Baily Bridge by RCC Bridge (Length=50.00meter) over local Cherra on Jatanbari to Lambacherra road at Ch.18.60Km. (TSP) |
RIDF-XVII |
|
|
Dropped vide Letter No. F. 3(23)/PC(RDQP)/2015-16/694-700, dated 16 June, 2020. |
22 |
Replacement of Baily Bridge by RCC/Steel girder Bridge over river Gomati at Mailak from Amarpur-Mailak road at Ch.-00.30Km. Name of agency: Tapesh Debnath. 2-span (General) |
RIDF-XXIII |
30-07-2019 |
14-08-2021 |
Piles of 2 abutmentsanf 2 piers completed. |
23 |
Replacement of Bailey Bridge by RCC bridge over local cherra on Jatanbari to Lambacherra road at Ch: 9.70 km. [Job No-TP/COM/38/2011-12] . Agency: TDC Ltd, (TSP0 |
RIDF-XVII |
|
|
pile work in progress. |
24 |
Replacement of Bailey Bridge by RCC bridge over local cherra on Jatanbari to Lambacherra road at ch:10.00km. [Job No-TP/COM/39/2011-12] (TSP) |
RIDF-XVII |
|
|
pile work in progress. |
25 |
Replacement of of existing Bailley bridge by RCC bridge over Betaga cherra on the road from Manubazar to Srinagar at ch.3.50 km. Agency: Bimalendu Chakraborty (TSP) |
RIDF-XX |
|
|
Pile work in progress |
26 |
Replacement of Baily Bridge by RCC Bridge over local Cherra on Jatanbari to Lambacherra road at Ch.14.80Km. (TSP) |
RIDF-XVII |
|
|
Tendering stage |
27 |
Replacement of bailey bridge by RCC bridge over sarma river at 30(Thirty) Card on Gandacherra-Amarpur road.(Ch.1.50 Km) Agency:-Sri.Asesh Deb. (TSP) |
RIDF-XX |
|
|
tender invited |
28 |
Replaicement of bailey bridge by RCC bridge over sarma river at Bankarghat on Bankarghat road(Ch.1.00 Km) . |
RIDF-XX |
|
|
tender invited |
29 |
Replacement of bailey bridge by RCC bridge over Thaura Cherra on Gandacherra-Raishyabari road.(Ch.3.50 Km). Agency:-Sri Sunit Das |
RIDF-XX |
25-10-2017 |
10-05-2019 |
pile work completed. pile cap work in progress |
30 |
Replacement of bailey bridge by RCC bridge over Thakura Cherra on Gandacherra-Raishyabari road.(Ch.7.50 Km) |
RIDF-XX |
|
|
tendering stage |
31 |
Construction of RCC Bridge over Raima river on Ganacherr-Raishyabari road(Ch.-19.320 Km.) under PWD(R&B) Gandacherra Sub-Division (TSP) |
RIDF-XXVIII |
|
|
tendering stage |
32 |
Replacement of Baily Bridge by RCC Bridge over Baiboon cherra on Bankumari to Manikpur road at Ch.-6.20Km. Single span (TSP). Agency : Bhanu Bhusan Deb. |
RIDF-XXVIII |
29-05-2020 |
24 months |
pile work in progress |
33 |
Const. of RCC Bridge on Chailengta- Chowmanu road.(RIDF-XIV) 3-span(TSP) ii] Over Guri Cherra at Ch: 8.35 km (Span-40.00m) |
RIDF-XIV |
29/02/ 2020. |
14-09-2021. |
pile cap work in progress |
34 |
iii)Malidhar Cherra on the road from Kacharicherra TSR camp to Kacharicherra regrouping centre road at Ch:0.21Km(Length=60.00m) |
RIDF-XVIII |
|
18 Months |
pile cap work in progress |
35 |
Replacement od bailey bridge by RCC bridge over Ghoramara cherra at Ranirbazar (Balance work) |
RIDF-Gap fund |
|
|
Tender accepted. |