Projects Status
Building Projects Status

Building Projects Status

Published: August 03, 2023
                                                                                                                             Status of Works of various departments entrusted to PWD(Buildings) as on 30-06-2023
Project Details Tendering Details                                          Physical Progress Details                                        Financial Progress Details Project Completion  Remarks                            Additional Informations    
Sl.
No.
Division Circle Client Department Name of Work Scheme Sanctioned Project Cost
(Rs.in Lac)
Ref of Sanction in/c name of authority & Amount. Sanction year Dt. Of NIeT/
(Details if not finalished)
Dt. Of Work order Awarded Value
(Rs.)
Name of Contractor & Contact No Dt. Of Commencement as per W/Order Actual Dt. Of Commencement Reason for delay in commencement & action taken/initiated (If any) Stipulated Period & Date of Completion as per agreement Brief Physical Progress and approx. Value of work done as on reporting date  Progress of IE works in percentage Progress of Mechanical works in percentage Overall Progress  in Percentage  Target date/Month  of Completion Fund received
(Upto Date)
(In Lac upto 3 Decimal)
Expenditure incurred
(Upto Date)
(In Lac upto 3 Decimal)
Balance in Hand
(In Lac upto 3 Decimal)
U.C Submitted (Upto date),
(In Lac upto 3 Decimal) 
Fund required (Upto date),
(In Lac upto 3 Decimal) 
 Date of actual Completion and reason for delay/, if any.   Whether Time extn  required (No of days)/Levy /LD realised during execution (With ref.)   (Detailed overall observation and information to include not covered in rest columns)   Approx Value of work done   Remaining value of work done  Ref Of Work order Other informations Status
( Column for Filtering the status)
For use of CE office only
   
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4      
1 Dharmanagar First
Circle
ARDD Veterinary Dispensary  at Panisangar  Special
Assistance
81.82 Memo No.F. 5(672)/ARDD/PLAN/2015/9641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 24-02-2022 03-08-2022 ₹ 77,45,201 Sri Raju Roy
9774915677
17-08-2022 08-11-2022 Initially delayed due to site problem 14-05-2023
270 days
Foundation workplinth beam  beam complete . Value of work done Rs 20.00 lakhs     20% Dec-23 90.730 56.000 34.730 56.000 190.910       ₹ 20,00,000 ₹ 57,45,201   Rs. 34.73 Lac lapsed during March 2023. In progress    
2 First
Circle
ARDD Veterinary Dispensary  at Uptakhali  Special
Assistance
81.82 Memo No.F. 5(672)/ARDD/PLAN/2015/9641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 24-02-2022 03-08-2022 ₹ 77,45,201 Sri Raju Roy
9774915677
17-08-2022 25-09-2022 Initially delayed due to site problem 14-05-2023
270 days
Shuttering and reinforcement work under progress for roof casting.
Value of work done Rs. 50.00 Lac approx.
  Not reqd. 55% Oct-23       ₹ 55,00,000 ₹ 22,45,201     In progress    
3 First
Circle
ARDD Veterinary Hospital   at Dharmanagar  Special
Assistance
118.00 Memo No.F. 5(672)/ARDD/PLAN/2015/9641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 04-08-2022 29-12-2022 ₹ 91,52,052 M/S S.N Bhattacharjee & Sons
9612705733
12-01-2023 12-01-2023 No delay 11-01-2024
365 Days
Brick work completed upto roof level. Shuttering and reinforcement work for ground floor roof is in progress. Value of work done Rs 55 lakhs   Not reqd. 55% Jan-24       ₹ 55,00,000 ₹ 36,52,052     In progress    
4 Kanchanpur First
Circle
ARDD Veterinary Dispensary
Strengthening of Veterinary Health Care Infrustructure through construction of Veterinary Dispensary at Dasda 
Special
Assistance
81.82 Memo No.F. 5(672)/ARDD/PLAN/2015/9641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 10-03-2021 09-11-2022 ₹ 77,45,000 Fountain Head
9435565557
24-11-2022 08-03-2023 Clear site was not available and the concerned dept. has cleared the site on 07.03.2023  July, 2023
240 Days
Upto Plinth beam completed. Work is in progress.
Value of work done Rs. 20.00 Lakh
    22% Nov-23 12.590 12.590 0.000         Work in progress. ₹ 20,00,000 ₹ 57,45,000     In progress    
5 Kumarghat First
Circle
ARDD Veterinary Dispensary
Strengthening of Veterinary Health Care Infrustructure through construction of Veterinary Dispensary at 
at Kanchanbari 
Special
Assistance
81.82 Memo No.F. 5(672)/ARDD/PLAN/2015/9641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 54/SE(I)/Kgt/2021-22 23-02-2022 15-06-2022 ₹ 77,45,000 Jayanta Das
70056 61542
30-06-2022 05-07-2022 Initially delayed due to site problem 10-06-2023
11 Months
Approximate 70% of the total work completed
 Rs. 56.00 Lac        
0.00% N.A. 80% Sept-23 48.000 48.000 0.000 0.000 33.820   3(Three) months For internal electrification work,     letter issued to  IE, IED ₹ 40,00,000 ₹ 37,45,000   Fund is required for making Payment  In progress    
6 First
Circle
ARDD Construction of Modern Abatitoir for Pig cum pork processing plant at Pecharthal, Unakoti District NEC 344.00 No.F.8(92)/E-Cell/ARDD/CONSTN/14/1281301 dt13/08/21 2021-22 21-12-2021 12-04-2022 ₹ 2,66,29,000 Sushen Ch. Das
98623 18088
27-04-2022 27-09-2022 Initial delay due to no accessibility to work site for 6 months 26-03-2023
11 Moths
Work is in progress and completed upto roof level , boundary wall & S-tank in progress
Rs. 200.00 Lac
20% 0% 70% Dec-23 10.000 50.000 0.000 10.000 334.000   3 (Three) months internal electrification  work in progress ₹ 2,00,00,000 ₹ 66,29,000     In progress    
7 Khowai Second
Circle
ARDD Veterinary Hospital at Khowai Special
Assistance
118.00 No. F. 5(672)/ARDD/PLAN/2015/9691-29, Dated 16-09-2021 2021-22 05-09-2022 29-12-2022 ₹ 1,02,20,945 Sujan Dey
(9436513028)
13-01-2023 15-06-2023 The concerned department could not yet handed over clear site to PWD, so work could not started yet. 180 Days
(12-07-2023)
Work just started. Nil Nil Nil Dec'23 125.450 0.000 125.450 0.000 0.000         ₹ 1,02,20,945   1) The EE, KHW has surrendered fund for Rs. 125.45 Lac and communicated to the Addl. Secretary, Directorate of ADD vide letter No.F>7(29)/EE/PWD/KHW/11566-570 Dated 24/02/23
2) EE, Khowai requested the Dy Director, ARDD vide his letter No.F.10(27)/EE/PWD/KHW/12058-12062 Dt. 15-3-23 for handing over the work site.
Not yet started    
8 Teliamura Second
Circle
ARDD Veterinary Dispensary
Strengthening of Veterinary Health Care Infrustructure through construction of Veterinary Dispensary at  Kalyanpur 
Special
Assistance
81.82 Memo No.F. 5(672)/ARDD/PLAN/2015/9641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 25-04-2022 29-07-2022 ₹ 79,66,486 Sri Sajal Datta
9436512491
13-08-2022 05-01-2023 initial delay in handing over over of clear site from the  concern department 12-05-2023
(9 months)
Finishing work is in progress. Total value of work done Rs.60.00 Lac     70% Aug,23 18.440 18.440 0.000 18.440 63.500       ₹ 60,00,000 ₹ 19,66,486     In progress    
9 Teliamura Second
Circle
ARDD Veterinary Dispensary at Teliamura  Special
Assistance
81.82 Memo No.F. 5(672)/ARDD/PLAN/2015/9641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 01-04-2022 12-08-2022 ₹ 80,03,368 Sri Haran Ch. Das
9436168447
27-08-2022 02-11-2022 Delay in handing over over of clear site from the concern department 26-05-2023
(9 months)
Finishing work is in progress.
Total value of work done Rs.75.00 Lac
    90% Aug,23 48.000 48.000 0.000 48.000 33.700       ₹ 70,00,000 ₹ 10,03,368     In progress    
10 Udaipur Third
Circle
ARDD Veterinary Hospital at Udaipur  Special
Assistance
118.00 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 16.08.2022 28.11.2022 ₹ 1,09,80,000 Sri Samar Ranjan Sarkar. M-7005461138 13.12.2022 24.05.2023 The client department changed the work site. Hance delayed 12.08.2023
8 Month
Demolition of old existing structure completed.  Earthwork for  foundation is to be started. But now suspended due to again indecision of site selection by ARD authority.       Dec'23     0.000   0.000     The requiring department changed the work site. Hence delayed( Letter No. F.4(37)/DDARD (G)/Store/2022/2847-48 Dt.21/03/2023 of the Deputy Director, ARDD.Accordingly, EE, UDP has furnished sueveryed site plan for proposed site.   ₹ 1,09,80,000     In progress    
11 Amarpur Third
Circle
ARDD  Veterinary Sub-Centre at West Malbasha under Amarpur Block  Special
Assistance
17.82 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 06-04-22 18-06-2022 ₹ 14,20,146 Sri Prantosh Saha,Contact No.9436189750 03-07-2022 10-12-2022 Initially delayed due to tland problem 180 days                02-01-2023 Foundation work  completed and column up to lintel level completed. Work in progress.
Value of work done Rs. 8.00 Lac        
0 0 50% Nov' 23 0.000 0.000 0.000 0.000 0.000       ₹ 8,00,000 ₹ 6,20,146     In progress    
12 Third
Circle
ARDD Veterinary Sub-Centre at Ekjancharra under Ompi Block  Special
Assistance
17.82 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 04-06-2022 28-07-2022 ₹ 13,03,207 Sri Prabal Das,Contact No.9366074685. 12-08-2022 07-01-2023 Initially delayed due to tland problem 180 days                          31-02-2023 Foundation work  in progress.
Value of work done Rs. 2.50  Lac        
_ _ 40% Aug'23 0.000 0.000 0.000 0.000 0.000       ₹ 2,00,000 ₹ 11,03,207   1) The EE, KHW has surrendered fund for Rs. 125.45 Lac and communicated to the Addl. Secretary, Directorate of ADD vide letter No.F>7(29)/EE/PWD/KHW/11566-570 Dated 24/02/23
2) EE, Khowai requested the Dy Director, ARDD vide his letter No.F.10(27)/EE/PWD/KHW/12058-12062 Dt. 15-3-23 for handing over the work site.
In progress    
13 Third
Circle
ARDD Veterinary Dispensary at Nutanbazar  Special
Assistance
81.82 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 13/4/2022 29-08-2022 ₹ 65,22,933 Sri Ratan Paul,Contact No.9436472211 13-09-2022 20-10-2022 Initially delayed due to tland problem 270 days                          31-06-2023 First floor roof Slab Work completed. And other ancillary work is in progress.
Value of work done Rs. 47.00 Lac        
_ _ 70% Mar'24 34.53 34.00 0.53 34.00 31.23     Fund revalidation submitted on 15/6/2023 for an amount of Rs. 0.53 lakhs ₹ 47,00,000 ₹ 18,22,933 Memo No.F. F.TC/5/EE/PWD/AMP/6295-309 dt '29-08-2022,   In progress    
14 Santirbazar Third
Circle
ARDD Veterinary Dispensary at Betaga  Special
Assistance
81.82 NO.F.F.5(672)/ARDD/PLAN/2015/9691-29 dated 16/09/2021 of the Jt Secretary Decondary Education.  2021-22 PNIeT- No:- 16/EE/PWD(R&B)/STB/2022-23 dated, 04-07-2022 20-10-2022 ₹ 80,03,523 Gathan Datta
9862453230
04-11-2022 04-11-2022 Work started in due time 270 days
01-08-2023
Roof casting completed. Work in progress.
Value of work done= Rs. 45.00 Lakh
Yet to start Not Required 40% Oct' 23 0.000 0.000 0.000 0.000 10.000       ₹ 45,00,000 ₹ 35,03,523 No.F. 9(3)/EE/PWD/STB/7256-68   In progress    
15 Third
Circle
Veterinary Dispensary  at Jolaibari  Special
Assistance
81.82 NO.F.F.5(672)/ARDD/PLAN/2015/9691-29 dated 16/09/2021 of the Jt Secretary Decondary Education.  2021-22 PNIeT- No:- 21/EE/PWD(R&B)/STB/2021-22 dated, 22-02-2022 17-06-2022 ₹ 80,33,029 Bikram Mitra
7005852266
02-07-2022 14-10-2022 Conerened deprtment was delayed for handing over the clear site. 270 days
10-04-2023
Roof custing completed. Work in progress.
Value of work done= Rs. 46.00 Lakh
Yet to start Not Required 35% Oct' 23 0.000 0.000 0.000 0.000 10.000       ₹ 46,00,000 ₹ 34,33,029 No.F. 9(3)/EE/PWD/STB/2650-62   In progress    
16 Belonia Third
Circle
Veterinary Hospital  at Belonia  Special
Assistance
118.00 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 12/EE(PWD)/BLN/2022-23                                     Dt 13-07-2022 26.10.2022 ₹ 91,89,451 Sankar Kanti Saha
9436124030
10.11.2022 10.11.2022 Work commenced in time 09.11.2023
365 days
Finishing work is in progress.
Rs.70.00 lakh
Not yet NA 90% Nov.23 45.927 45.927 0.000 45.927 72.080     -----     ₹ 70,00,000 ₹ 21,89,451 No.F.7(20 )Pt-I/EE(PW D)/BLN/DIV N/5103-12 Dt.26.10.22   In progress    
17 Sabroom Third
Circle
 Veterinary Dispensary
Strengthening of Veterinary Health Care Infrustructure through construction of Veterinary Dispensary at Sabroom ( G+1 Storied)/ Phase-I , Ground Floor only
Special
Assistance
118.00 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 25-07-2022 23-09-2022 ₹ 90,61,261 Shri Ratan Paul
(Mob# 9436472211)
28-10-2022 28-10-2022   365 Days
27-10-2023
Brick work completed, Plastering work is in progress.
Value of work done: Rs. 60.00 Lakh(Approx)
    60% Oct-23 52.180 33.600 18.580 0.000 30.000       ₹ 60,00,000 ₹ 30,61,261     In progress    
18 Jirania Fourth
Circle
ARDD Vertical extension of Veterinary College under NABARD RIDF 446.34 A/A and E/S: No. Board F.5(672)/ARD/PLAN/2015/1239-45 Dt. 30/04/2021 of the D.S , ARDD for 1) Vertical extension Vetenary College 2) Internal raod 3)Internal road 4) Boundrary wall & Guard room For Rs,446.34 Lac 2021-22 Combine Tender Veterinary College and Veterinary  Science , Animal  husbandary College               Recommended by the DPC for acceptasnce of the tender and sent to the Administrative Department for approval.         Rs.50.00 lakhs but surrendered             (Reporting of project:
Physical status, Tendering etc combine and Separate for Financial status.)
Technical bid sent to the SE, 4th Circle, PWD(R&B) on dated 13/02/2023. Est Cost  Rs.13,42,45,934/-
  ₹ 0     Tendering Stage    
19 Jirania Fourth
Circle
ARDD  Vertical extension of Veterinary  Science & Animal  husbandary College/ 1) Admn Block (First floor), 2) Academic Block (part of 3rd floor,lift block 4th floor, Lift Machine room 5th Floor3)  Boy's Hostel' (2nd Floor)4) Girls' Hostel (2nd Floor)
5) 2 Nos Lift
Special
Assistance
1500.00 A/A: No.F.8(132)/E-Cell/ARDD/CONStr/22/1616-1625 dated 12/09/22 of the Director ARDD.
1) Admn Block (First floor), Rs. 604.12 Lac
2) Academic Block (part of 3rd floor,lift block 4th floor, Lift Machine room 5th Floor Rs. 340.69 Lac
3)  Boy's Hostel (2nd Floor)Rs. 253.72 Lac 4) Girls' Hostel (2nd Floor) Rs. 253.72 Lac
5) 2 Nos Lift Rs. 47.76 Lac. (Total: Rs. 1500.00 Lac).
E/S: No.8(133)/E-Cell/ARDD/CONSTN/2022/895-905 Dt. 8/7/22 of the Director , ARDD for Rs, 1500.00 Lac
2022-23                 ₹ 0     Tendering Stage    
20 Mohanpur Fourth
Circle
ARDD Veterinary Sub-Centre at Barkathal under Hezamara Block  Special
Assistance
17.82 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 Project Dropped Project Dropped Project Dropped Project Dropped Project Dropped Project Dropped Project Dropped Project Dropped Project Dropped                           #VALUE!     Cancelled    
21 Veterinary Dispensary
Strengthening of Veterinary Health Care Infrustructure through construction of Veterinary Dispensary at Hezamara / Construction of building for Vety. Dispensaries including Doctor/staff room with lavatory, Dispensing room, medicine store, small laboratory, animal shed including water supply facility & electification
Special
Assistance
81.82 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22   20-10-2022 ₹ 76,58,000 Tamal sur Chowdury 05-11-2022   Demolishing work in progress by the ARDD. Work will be started soon July' 2023
Period?
Work not yet started           0.000 0.000 0.000 0.000         ₹ 76,58,000     Not yet started    
22  Modernization of State Poultry farm with Automated layer Unit at Gandhigram, West Tripura NEC 444.00 No.F.8(92)/E-Cell/ARDD/CONSTN/08/1095-1104 dt29/07/21 2021-22   16-03-2022 ₹ 3,59,00,000 Tapesh Ch Debnath 04.01.2022 29.04.2022 Initial delay for clear site 15.03.2023
Period?
All structural work completed in Hatchery,Layer and Brooder house building. In Grower House building structural work completed upto slab level.     60% Dec-23 10.000 10.000 0.000 10.000 433.440         ₹ 3,59,00,000     In progress    
23 Bishramganj Fourth
Circle
ARDD Veterinary Sub-Centre at Brajapur (replaced by Lalsinmura) under Charalim Block Special
Assistance
17.82 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 19-11-2022 17-04-2023 ₹ 17,96,713 Basu Ranjan Shil, 7005581944 02.05.2023   Delay due to Location modified by client dept and non handing over of clear site  Date:
270 days
Work order issued. Clear site yet to be handed over by client Dept. 0.00 NA 0.00   15.710   15.710         Delayed due to Location modified by client dept.     ₹ 17,96,713     Not yet started    
24 Bishramganj Fourth
Circle
ARDD Veterinary Sub-Centre at Sutarmura (replaced by Ramnagar)  under Charalim Block Special
Assistance
17.82 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 19-11-2022           Delay due to Location modified by client dept and non handing over of clear site  Date:?
270 days
Clear site not yet handed over by client de[pt. 0.00 NA 0.00     0.000         Delayed due to Location modified by client dept.
LOA issued. 
  ₹ 0     Not yet started    
25 Bishramganj Fourth
Circle
ARDD Veterinary Sub-Centr at South Charilam under Charalim Block /4th Call Special
Assistance
17.82 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 17-12-2022
'06-03-2023 (Fourth Call)
23-05-2012 ₹ 15,01,231 Kausik Das
7085736503
23-05-2001 Not started Delay due to Location modified by client dept and non handing over of clear site  270 days
Date?
Clear site not yet handed over by client deptt..LoA issued 0.00 NA 0.00     0.000         In 3rd call no tender received.
Tender invited in 4th Call.
  ₹ 15,01,231     Not yet started    
26 Sonamura Fourth
Circle
ARDD Veterinary Sub-Centre at Veluarchar under Boxonagar Block  Special
Assistance
17.82 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 DNIT No. 88/EE/SNM/PWD/2021-22.
Dt………….
28-04-2022 ₹ 16,13,131 Najrul Islam
8974367745
12-05-2022 17-05-2022   12-11-2022
Period?
GCI sheet roofing work in progress.
Approx value of work done Rs 11.53
    65% June-23 58.590 11.530 21.560         Recept of fund together for SL No 26,27,32 ₹ 11,53,000 ₹ 4,60,131 Vide No.F.10(30)/EE/SNM/PWD/461-76 dt.28-04-2022   In progress    
27 Veterinary Sub-Centre at Putia under Boxonagar Block  Special
Assistance
17.82 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 DNIT No. 87/EE/SNM/PWD/2021-22.
Dt……..
28-04-2022 ₹ 16,13,131 Basar Miah
9863266448
12-05-2022 28-09-2022   12-11-2022
Period?
Work Completed on 22-03-2023     100%     6.500       22-03-2023   Work Completed on 22-03-2023 ₹ 15,93,000 ₹ 20,131 Vide No.F.10(30)/EE/SNM/PWD/445-60 dt.28-04-2022   Completed in all respect    
28 Veterinary Dispensary at Kathalia  Special
Assistance
81.82 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 24/B/DNIeT/SE-IV/PWD(R&B)/
2021-22
Dt……...
06-07-2022 ₹ 78,92,722 Bishnu Pada Paul
9436519065
21-07-2022 11-11-2022   21-07-2023
Period?
first floor slab custing is completed. Value of work done Rs. 48.93 Lac     60% Dec.23   19.000             ₹ 48,93,000 ₹ 29,99,722 Vide No.F.10(30)/EE/SNM/PWD/2253-66 dt.06-07-2022   In progress    
29 ARDD Veterinary Dispensary at Melaghar  Special
Assistance
81.82 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 23/B/DNIeT/SE-IV/
PWD(R&B)/2021-22.
Dt………..
              Clear site is not handed over by the  authority till now.             0.000             ₹ 0     Not yet started    
30 LTV Veterinary Sub-Centre at Dhumacherra under Ganganagar  Block  Special
Assistance
17.82 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22                 Work order not issued due to non-availability of land.             0.000         Work order not issued due to non-available of Land   ₹ 0     Not yet started    
32 Gondatwisa Veterinary Dispensary at Raishyabari  Special
Assistance
81.82 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22   20-07-2022 ₹ 79,00,000 Rajib Prasad
8119003215
05-08-2022 20-02-2023 Delay due to Hand over of clear site  6 Month
'19-02-2023
Roof Slab casting completed.
Value of work done (approx): Rs. 40.00  Lac
    51% Sept'23 29.000 29.000 0.000           ₹ 40,00,000 ₹ 39,00,000     In progress    
33 Dharmanagar Fifth
Circle
Fishery Construction of Fish Farmer training Institute at Dharmanagar   100.00 F.4(2)-EE(FY)/CONSTN/2008-09/13461-64, DATED: 12-05-2016. 2016-17 10-03-2017 25-07-2017 ₹ 87,59,673 Sri Sajal Paul
9436132786
08-08-2017 08-08-2017 Work delayed due to non availibility of additional funds 24-11-2018
15 Months                                                   
Building Portion including plaster work completed. Flooring and Finishing work in progress.Value of work done Rs. 95.00 Lac     90% Dec-23 100.000 86.000 14.000 86.000 20.000     Additional fund required for additional works and internal electrification ₹ 95,00,000 ₹ -7,40,327     In progress    
34 Teliamura Second
Circle
FCS & CA Proposed Construction of single storied laboratory cum office building  of Legal Metrology at Teliamura   Strengthening Legal Metrology insfrastructure of state & Uts. 50.00 Rs. 50.00 Lakh
Memo No.F. 14(10)/LM/TLM/LAB/193-200 dt. 31/01/2022 of the Addl. Secretary to the Govt. of Tripura.
2021-22 06-06-2022 30-09-2022 ₹ 44,31,342 Sri Debashish Debnath
8014492537
15-10-2022 09-11-2022 initial delay in handing over over of clear site by the client department 14-04-2023
(6 months)
Work completed except Internal electrification.
Total value of work done Rs.44.31 Lac
Tender will be opened on 06-07-23   100% July,23 20.000 20.000 0.000 20.000 30.000       ₹ 44,31,000 ₹ 342     In progress    
35 Santirbazar Third
Circle
Forest Construction of Indian Bison conservation park at Patichari under North Takmacharra Mouja,Santirbazar,South Tripura. Special
assistance
252.00 NO.F.8(196)/WL/2008-2012/2781-95 dated 23/03/2021  2020-21 PNIeT- No:- 15/EE/PWD(R&B)/STB/2021-22 dated, 11-01-2022 26-04-2022 ₹ 2,55,94,718 Shri Sajal Bhattacharjee
(Mob: 9774910015)
11-05-2022 28-04-2022 Work started in due time. 365 Days
10-05-2023
50% work completed, Work in progress
Value of work done= Rs. 100.00 Lakh
Yet to start Not Required 50% July' 23 100.000 100.000 0.000 0.000 156.947       ₹ 1,00,00,000 ₹ 1,55,94,718 No.F. 9(3)/EE/ PWD/STB/620-32   In progress    
36 Belonia Third
Circle
Forest Construction of Type-V quarter for District Forest Officer, South Tripura near Sarasima under Belonia Sub-Division during the year 2022-2023 State Plan 91.00 No.F.5(672)/ARDD/PLAN/2015/9691-29 dt,.                                                                                                  16-09-2021 of  the Joint  Secretary to  the  Govt.                                                                                                      of Tripura 2021-22 24/EE(PWD)/BLN/2022-23                                     Dt 14-10-2022 09.01.2023 ₹ 77,15,000 Rajib Nandi
9436517634
24.01.2023 25.04.2023 Delayed by the agency 20.11.2023
270 Days
Work completed upto plinth level. Column work is in p rogress at Ground Floor
 Rs. 15.00 Lakh
Not yet NA   ----   Nov-23 91.000 0.000 91.000 0.000 0.000 Not yet completed     ₹ 15,00,000 ₹ 62,15,000 No.F.7(20) Pt-I/EE(PWD ) /BLN/DIVN /7443-51 Dt.09.01.2023   In progress    
37 Bishalgarh Fourth
Circle
Construction of Aviary at Sepahijala sanctuary Forest 150.00 F.8(127)/WL-2020-21/APO-CZA/Part/612-58, Dated-29/06/2022 2022-23 PNIeT No 12/EE-BSLD/PWD(R&B)/2022-23, Dated-08/07/2022, DNIeT-05/B/DNIeT/SE-IV/PWD(R&B)/22-23 09-09-2022 ₹ 1,18,29,255 Nikhil Rn. Chakraborty (8256939330) 24-09-2022 21-12-2022 Due to late receipt of structural drawing 180 Days                (22-03-2023) Foundation work is in progress. Fabrication of steel work is in progress. 48% Work Completed. Rs 56.80 Lakh  Nil Nil 48% July-23 100.000 35.000 65.000 0.000 0.000       ₹ 56,80,000 ₹ 61,49,255     In progress    
38 Construction of Reptile House at Sepahijala Zoological Park. Forest 103.00 F.8(127)/For-WL-2019-20/APO-CZA/Part/2277-87, Dated-13/02/2020 2019-20 PNIeT No 09/EE-BSLD/PWD(R&B)/2020-21, Dated-19/11/2020, DNIeT-04/B/DNIeT/SE-IV/PWD(R&B)/2020-21 18-01-2021 ₹ 1,02,89,419 Tapas Kumar Saha, (9862068690) 02-02-2021 10-08-2021   31-07-2021
Period?
Work completed in all respect except few Finishing work. 90% Work Completed. Rs 102.60  Lakh Nil Nil 90% July-23 79.774 79.774 0.000 0.000 34.000       ₹ 1,02,60,000 ₹ 29,419     In progress    
39 Kailashahar First
Circle
Home(Jail)  Constn of Kailashahar jail/Balance work (5th Call) SPA 1598.00 No.F.5(35)/PC/PD-II/2014 dt 22/03/2014  2013-14 31-05-2022 12-10-2022 ₹ 5,87,23,201 Tantia Construction Ltd
9903900530
26-10-2022 26-10-2022   25-07-2023
Period
9 Month
Plastering work is in progress. Tiles flooring at qtr building in progress.Approx value of work done Rs.50.00 Lac Preparing estimate 0% 8% Oct'23 0.000 0.000 0.000 0.000 100.000   Not required   ₹ 50,00,000 ₹ 5,37,23,201 F.23(01)EE/KLSD/6998-7023 dt 12-10-22   In progress    
40 Bishalgarh  Constn of 56 nos staff qtr at Bishalgarh jail /BALANCE WORK SPA 696.00 F.I-604/IGP/2020/663-70, Dated-18/02/2020    PNIeT No 26/EE-BSLD/PWD(R&B)/2021-22, Dated-09/02/2022, DNIeT-21/B/DNIeT/SE-IV/PWD(R&B)/2021-22 29-08-2022 ₹ 1,97,52,218 Tapas Kumar Saha, (9862068690) 12-09-2022 14-09-2022   180 Days                                (11-03-2023) Out of 36 nos quarter 24 Nos completed in all respect, rest work is in progress. 95% Work Completed. Rs 187.65 Lakh 100% Nil 95% Oct-23 133.950 133.950 0.000 Nil 0.000       ₹ 1,87,65,000 ₹ 9,87,218     In progress    
41 Construction of Unit Quarter guard in respect of 1st BN.TSR.at Gakulnagar,Sepahijala District,Tripura. No Scheme 273.00 No  AA & ES received                   Arch Drawing prepared & sent to the DIG,Police.After getting the A/A & E/S further process will be started.             0.000             ₹ 0     Not yet started    
42 Fourth
Circle
Home(Fire) Constn of Ananda nagar Fire station Major works capital (4059 462.00 No.F.5(7)-PD/2015/212 Dated 20/01/2022 of the DS, Home (Fire & Emergency Service) for Rs. 462.14 Lac (A/A) & Rs. 130.00 Lac (E/S) 2022-23 PNIeT No 23/EE-BSLD/PWD(R&B)/2021-22, Dated-16/12/2021. DNIeT-CE(Buildings)/PWD/DNIT/ACE/Project Unit/48/2021-22 18-03-2022 ₹ 3,04,58,107 Malay Lodh (8974947801) 01-04-2022 01-04-2022   15 Months               ('30-06-2023) Ground Floor work completed, First Floor finishinh work is in progress. 85% Work Completed. Rs 258.90 Lakh Ground Floor completed. 50% work completed Nil 85% Aug-23 300.000 148.250 151.750 0.000 0.000       ₹ 2,58,90,000 ₹ 45,68,107     In progress    
43 LTV Fifth
Circle
Home
(Police)
Constn of 8th BN TSR Head quarter at Lalcherra, L.T. Valley. TFC 1337.00 No.F.8(226)/PC(PD-I)/2006/S-I/S/9132 dated 11/12/2008 of the CE,PWD(R&B). 2008-09 Cost Plus Basis  24-01-2009. Cost Plus Basis  (TSR-2008 + 23.69% above) NPCC Ltd. 09-02-2009. '24-02-2009 Delay occurred due to non-available of clear site 24 months from the date of approval of DPR or handing over of site. 70.00% physical progress and 11.80 crore work done.Now, work suspended by the agency. 70% Not required 70%   1179.720 1179.720 0.000 1179.720     Initially 2(two) years delay occurred due to forest land diversion and thereafter delayed by the Agency. Recision proposal will be initiated. Rescision proposal to be initiated. ₹ 11,80,00,000 =     In progress    
44 Dharmanagar First
Circle
Health(DFWPM) Construction of 10 bedded PHC  with 10 nos. quarters at existing Uptakhali PHC NHM 645.00 No.F.19(109)-PLAN/DFWPM/ 4547-57)V-I0 dated 14/07/2021 2021-22 07-12-2021 23-03-2022 ₹ 4,91,79,788 M/S J.C Nath & Sons
9436132164
06-04-2022 06-04-2022 No Delay 02-07-2024
18 Months  
Finshing work for PHC  mainblock in progress. Type-I, Type-II quarter slab casting complete up to F-II level. Brick work in progrsss. Foundation work upto plinth level for Type-III quarter completed.   value of work done 240 lakhs Consealed pipeline installed Not reqd. 60% June-24 215.410 215.410 0.000 215.410 429.590       ₹ 2,40,00,000 ₹ 2,51,79,788     In progress    
45 Dharmanagar First
Circle
Health(DHS) Construction of single storied building for Trauma Care Centre (Level-III) in the North District Hospital at Dharmanagar, North Tripura. RIDF 390.00 F.3(2-396)-PLAN/DHS/2015/287-94/685, DATED: 29-05-2017. 2017-18 16-04-2018 11-10-2018 ₹ 3,53,68,858 M/S S.N Bhattacharjee & Sons
9612705733
25-10-2018 25-10-2018 Delayed due to demolition work of existing structures.   Finishing (painting) work is in progress.
Value of work done Rs. 340.00  Lac approx.
80.00%   95% Aug-23 230.000 230.000 0.000 230.000 160.000       ₹ 3,40,00,000 ₹ 13,68,858     In progress    
46 Vertical extension of Trauma Centre of District Hospital for constn. Of 50 seated Field Hospital at Dharmanagar under ECRP-II/ Building portion in/c internal electification ' Sanitary & Swerage NHM
(ECRP-II)
256.77 F.3(208)/DHFWS/CMO/N/ECRP-II/2022/5041-45 Dt. 12/04/2023 of the DM & Collector, North Tripura 2023-24
( Date of Notice inviting e-tender)
              Tender under scrutiny ( TEC meeting held 21/6/23)                       DNIT issued for Rs. 180.06 Lac on 18-04-2023. Tender under scrutiny at CE Office.         Tendering Stage    
47 Kanchanpur Health(NHM) Proposed construction of single storied 10(ten) bedded Primary Health Centre (PHC) building including 10(ten) Nos. Staff Quarters Kitchen, Morgue, Garage & Generator with Driver Room Building at existing Damcherra PHC under Kanchanpur Sub-division, North Tripura under NHM NHM 486.00 No.F.19(42)-PLAN/DFWPM/2000(S) dated 19/11/2018 2018-19 31-05-2019 17-10-2019 ₹ 4,34,57,000 Sri Arun Kanti Chanda
9436132072
01-11-2019 01-11-2019   Oct, 2021
24 Months
Finishing work of Main Building in progress. T-III qtr columns upto lintel level casting complted. T II Qtr 2nd floor slab casting completed. Brick and Plastering work in progress. T-I qtr clear site yet to be finalized.
Rs. 215.00 Lakh
    43% Nov.23 200.000 200.000 0.000 200.000 286.000     Work is in progress. ₹ 2,15,00,000 ₹ 2,19,57,000     In progress    
48 Kanchanpur First
Circle
Health(DHS)  Constn of 16 nos staff qtr Kanchanpur Hospital in Sub-Divisional Hospital Complex. SJTNY 598.00 1)Administrative approval only (No.F. 3(5-137)-PLAN/DHS/2022-23 Dt. 17/01/23 of the D.S, Health & Family Welfare Deptt)
2) E/S received vide memo No.F.(5-137)-PLAN/DHS/2022-23 Dt. 28/04/2023 of the D.S of Health & Family Welfare Deptt. for Rs. 598.00 Lac.
2022-23 24-05-2023               1st Call of tender received and under scrutiny.                           ₹ 0   DNIT issued on 20/05/23 ,  Not yet started    
49 Kailashahar Health(NHM) Construction of 10 nos quarter at Kanika Memorial PHC NHM 169.00 No.F19(42)=PLAN/DFWPM/2000(S)/3043-67 dt19/11/18 of the Under Secretary  Health and Family Welfare Department. 2018-19 09-12-2021 03-03-2022 ₹ 2,16,24,939 Mohan Lal Singha
9436120514
17-03-2022 17-03-2022   16-09-2023
(Period)
18 Month
Structural and brick work complted.Finishing work is in progress.Approx value of work done Rs.190.00 Lac 100% 0% 88% Sept.23 150.000 150.000 0.000 0.000 66.000   Not required   ₹ 1,90,00,000 ₹ 26,24,939 F.25(56)EE/KLSD/6711-26 dt 3/3/22   In progress    
50 Health(DFWPM) Proposed construction of District Training Centre at Kailashahar, Unakoti District, Tripura. IMR  597.00 No.F.5(35)/PC/PD-II/2015 dt 23-04-2016 2016-17 11-02-2016 28-10-2016 ₹ 3,61,61,952 Salil Acharjee
7308686797
11-11-2016 11-11-2016   10-11-2018
(Period)
24 Months
Tiles flooring, alluminium, sanitary, constn of water reservoir and boundary wall    work is in progress.Approx value of work done Rs.340.00 Lac 100% 0% 95% Aug-23 314.850 314.850 0.000 314.850 40.000   Not required   ₹ 3,40,00,000 ₹ 21,61,952 F.26(51)EE/KLSD/4407-25 dt 28/10/16 Fund surrendered Rs 32.90 Lakh In progress    
51 Kailashahar First
Circle
Health(DFWPM) Construction of 10 bedded PHC   at existing Irani PHC(6th Call) NHM 358.00 No.F.19(109)-PLAN/DFWPM/ 4547-57)V-I0 dated 14/07/2021 2021-22 03-05-2023(6th Call)                6th Call tender under scrutiny.( Letter issued to Bidder regarding shortfall of Documents)             0.000             ₹ 0     Tendering Stage    
52 Kailashahar First
Circle
Health(DHS)  Constn 48 nos staff qtr,Kailashahar Hospital under NLCPR NLCPR 1110.00 No.F.5(35)/PC/PD-II/2017 dt 22-12-2017 2017-18 28-06-2016 07-03-2018 ₹ 9,04,45,776 M/S J.C Nath & Sons
9436132164
21-03-18 21-03-2018   20-03-20
(Period)
24 Month
Completed & Just handed over (Date?). 100% 0% 100% Completed on 02/05/2022. 904.450 904.450 0.000 904.450 0.000 02-05-2022 Yes
773 days time extension required
Levy /LD ?
  ₹ 9,04,45,776 ₹ 0 F.25(1)EE/KLSD/5971-89 dt 7/3/18   Completed in all respect    
53 Kumarghat First
Circle
Health(NHM) Construction of 10 Bedded PHC at Pecharthal, Kumarghat NHM 210.00 No.F.19(610)-PLAN/DFWPM/2017/1258-85 (V-I)  dt.03/07/2017. 2017-18 09-03-2022 12-08-2022 ₹ 2,03,00,000 Sushen Ch. Das
98622 02500
27-08-2022 20-09-2022 Initially, delayed for 12 months due to site problem & Covid 19-06-2023
10 Moths
Work in progress. Above lintel level. Value of work done Rs. 160.00 Lac 50% 0% 55% Dec-23 150.000 150.000 0.000 150.000 65.000   6 (Six) months Work is in progress full swing. Project is delayed due to cancellation of First call of tender and finalisation of 2nd call of tender on 15-03-2022. ₹ 1,60,00,000 ₹ 43,00,000 No.F.34(14A)/EE/KD/2913-2927 dated,12/08/2022   In progress    
54 Kumarghat First
Circle
Health(NHM) Construction of 10 beded PHC with 10 (ten) Nos. staff quarters  at Kanchanbari under Kumarghat Subdivision NHM 458.00 F.19(219)-PLAN/DFWPM/2000  dt.04/01/2018. 2017-18 04-07-2018 02-03-2020 ₹ 4,46,84,000 Sanjib Kr. Prasad
94021 66076
17-03-2020 24-12-2020 Initially delayed fof Covid-19 & Site dispute. 01-03-2022
12 Months
Main building completed,
Finishing Work in progress, T-III Qtr Finishing work in progress. Work of T-I & T-II Qtr first flour at roof level. Value of wrok done (approx) Rs 350.00 Lac
100% N.A. 75% Jul 23 400.000 225.000 175.000 200.000 400.000 Delay in finalisation of tender and site dispute. 6 (Six) months   ₹ 3,50,00,000 ₹ 96,84,000     In progress    
55 Health(DHS) Proposed  1000 seated capacity town Hall at Kumarghat UDD 1180.00 F.16(15)-UDD/DUD/2014/8839-46  dt.31/10/14. 2014-15 19-05-2015 14-09-2016 ₹ 11,80,00,000 N.K. Dhar
94361 22664
29-09-2016 28-02-2017 Site dispute, Drawing, Non availability of required fund. 28-09-2018
12 Moths
All completed except chair. Value of work done Rs……..Lac 100% 100% 99% May-23 1180.000 1070.00 110.000 1070.000 0.000   2 Years requied Completed except auditorium chair   ₹ 11,80,00,000     In progress    
56 Khowai Second
Circle
Health(NHM) Constn of 10 bedded   PHC in/C  8 Nos Qtr( Ty-I: 4 Nos, Ty-II:2 Nos, Ty-III: 2 Nos. at Chebri PHC NHM 486.00 No.F.19(42)-PLAN/DFWPM/2000(S) dated 19/11/2018 2018-19 02-11-2020 14-06-2021 ₹ 4,44,53,888 Jasodalal Roy (9436137937) 29-06-2021 10-07-2021   24 Months
(13-06-2023)
Flooring and painting work in progress ( Rs. 400.00 Lac) 55% Nil 91% Aug'23 200.000 200.000 0.000 200.000 244.538       ₹ 4,00,00,000 ₹ 44,53,888   1) Demand of Rs. 100.00 lac placed by the EE, KHW to the State Prog Office vide letter No.F.7(29)/EE/PWD (R&B)/KHW/11614-617 dated 27/02/23 In progress    
57 Agt Div-V Health(NHM) Proposed construction of Urban Primary Health Centre(UPHC) at A.D.nagar, Agartala NHM 210.00 Memo No. F.19(637)-PLAN/DFWPM/2020 dated 15.06.2020.
Under Secretary , Govt. of Triura.
2020-21 12.07.2021 08.10.2021 1,69,50,518 Sri Satyabrata Roy  23.10.2021 04.02.2022 Initially  delayed due to change of site & layout plan. 9 Months/ 23.07.2022 Grond floor roof castng completed.Plastering completed. Approx. value of work done Rs 150.00Lac 20% N.A. 50% Sept-23 150.000 150.00 0 0 73.00     Work is in progress. Delayed due to selection of site . Clear site was not available. Architechtural/ Structural drawing modified. ₹ 1,50,00,000 Rs.73.00 (Including deviation & IE works) No.F.7(7)/EE-V/AGT/PWD/2020-21/3748-65 dated 08.10.2021 1) DNIT No. ACE/Project Unit/PWD/(Building)/DNIT/16/2021-22
PNIT No. 04/B/EE-V/AGT/PWD/(R&B)/2021-22. dated 12.07.2021
2) Tentative Deviation for an amount of 39.00 Lakh processed to the competent authority for approval.

 3) Completion of the project is August, 2023 subject to the approval of this Tentative deviation.

Mainly Deviation occurred due to site condition as part of the foundation of building raised from the ditch (low lying area), the resulting addtional tie , column, grade slab etc. matter earlier comunicated to the competent authority and Director, NHM before execution
In progress    
58 Amarpur Third
Circle
Health(NHM) Proposed construction of single storied 10(ten) bedded Primary Health Centre (PHC) building including 10(ten) Nos. Staff Quarters [  Kitchen, Morgue, Garage & Generator with Driver Room Building and Boundary wall at Silachari, Karbook Sub-division, Gomati District, Tripura  NHM 486.00 No.F.19(610)-PLAN/  DFWPM / 2017, Date,3-7-17 of the Under Secretary to the Govt of Tripura ,Health & Family Welfare Deptt. Rs.4.86 2017-18 11-06-2017 04-09-2018 ₹ 3,92,63,612 Sri Ashutosh Bandhopadhaya,Contact No.9436527307 23-04-2018 02-01-2019 Work  has been suspended by the agency in long time many show cuase  letter issued against agency. Now LD proposal sent to higher authority for approval. 24(Twenty four Month)                           22-04-2020 T-I Qtr= Completed upto Plinth level.
T-II Qtr= Completed upto roof level.
T-III Qtr= Structural work in progress,Work suspended by the agency. Work re-started. Value of work done 102.14 lakhs.
0.00 0.00 50% Dec-23 250.000 250.000 0.000 250.000 142.64     Notice issued under CL 54( Rescision of contract under risk & cost on 20/05/2023). Accordingly the liquidated damaged report submitted to SE-III circle Udaipur on 12-06-2023. ₹ 1,02,14,000 ₹ 2,90,49,612 04-09-2018,            Memo No.F. F.TC/5/EE/PWD/AMP/311-26   In progress    
59 Health(DHS) Constn of 16 nos staff qtr Amarpur Hospital at Amarpur Sub-Divisional Hospital Complex/Balance work SJTNY 553.00 Administrative approval only (No.F. 3(5-137)-PLAN/DHS/2022-23 Dt. 17/01/23 of the D.S, Health & Family Welfare Deptt).
E/S vide Memo No.F. 3(5-137)-PLAN/DHS/2022-23 Dt. 28/04/23 of the D.S, Health & Family Welfare Deptt) for Rs.552.77 Lac
2022-23 24/5/2022               DPC recommended for acceptance and sent to the administrative department for approval of the tender.         200.000   200.000         1) NIeT: 24-05-2022   07/NIT/EE/PWD/AMP/2022-23.   ₹ 0   1) Previously sanction Rs. 406.00 Lac vide A/A & E/S memo No.F. 3(1-560)-PLAN/DHS/2010/2462-69/10128(V-III) dated 15/11/2016 of the U.S , Health & Family Welfare Deptt. Head of A/C Central Assistance to State Plan.
2) SE, PU vide letter No.F.5(35)/PC(PD-II)/2022 (S)/380-83 Dt. 17/04/23 has requested to accord E/S for Rs. 552.00 lac to the Director of Health Services.
Tendering Stage    
60 Udaipur Health(NHM) Proposed construction of 50 ( fifty) bedded MCH Wing [ G+3 Storied ] building at Gomati District Hospital, Tepania, Udaipur, Gomati District, Tripura (2nd Call).  NHM 798.00 No.3(2-425)-PLAN/DHS/2016-17/3650-60, dt.06.03.2017. Amount  : 797.00 Lakh 2015-16 20.01.2021 31.08.2021 ₹ 6,49,54,000 Sri Jiban Kumar Saha. M-9436122376 12.09.2021 06.11.2021 1st structural drawing was received on 07.09.2021 but there was some discripency regarding location of ramp. Finaly 2nd and rectified drawing had been received on 09.12.2021 hance delay. 11.09.2023
24 Month
Structural work completed.Finishing work completed.
Value of work done  Rs.4,43,11,857.00
    82% Aug'23 595.000 503.000 92.000 503.000 190.000         ₹ 6,49,54,000     In progress    
61 Health
(DFWPM)
Proposed construction of 10 (ten) nos. staff quarters  at Tulamura Primary Health Centre (PHC) under Kakraban Block, Udaipur Sub-Division, Gomati District, Tripura. Special
Assistance
225.00 No.F.19(57)-PLAN/DFWPM/2000(SUB)/3387-3400(V-II), dated 07.08.2015. 2015-16 02.02.2021 29.05.2021 ₹ 2,13,99,000 Sri Nihar Chandra Debnath. M-9436131064 14.06.2021 01.11.2021 Lack of required drawing and design 12.02.2023
18 Month
Civil work completed on 29.04.23
Value of work done  Rs2,14,00,000.00
100%   100%   223.910 209.130 14.780 209.130 14.770 Due to Non-availability of drawing.       ₹ 2,13,99,000     Completed    
62 Construction of 10 bedded Primary Health Centre (PHC) including 10(ten) Nos. Staff Quarters  at Nityabazar under Killa Block, Gomati District, Tripura Under RIDF - XX.  RIDF-XX 540.00 No.F.19(554)/PLAN/DFWPM/2014, dated 19.03.2015 2014-15 07.05.2015 22.09.2015 ₹ 4,04,90,000 Sri Binode Bihari Datta. M- 9612807882 07.10.2015 01.07.2016 Delay for site Development 06.10.2017
24 Month
Finishing work in progress for PHC & Quarters.
Value of work done Rs. 3,32,00,000.00
  - 76% Dec' 23 509.360 416.490 92.870 416.690 0.000   Yes Initialy land problam was there & Slow Progress of work by the agency   ₹ 4,04,90,000   EE, Udp  requested to Director, Health & Family  Welfare to  revalid the balance unutilsed fund Rs. 92.874  vide letter No F/EE-PWD-DIVN/ACTT-UC-10/477-79 Dt. 01-05-2023. In progress    
63 Santirbazar Third
Circle
Proposed Construction of 20 (twenty) bedded Primary Health Centre (PHC) building [ double storied ]  including Kitchen, Morgue  and Garage & Generator with Driver room building at existing Muhuripur PHC Complex  under Jolaibari Block, Santirbazar, South Tripura. IMR -
13th FC
416.00 NO.F.19(83)-PLAN/DFWPM/2015(Sub)/1582-89(VII) dated 29-07-2017 of the Under Secretary to the Govt. of Tripura. ( Project Cost for Gap Fund: Rs. 340.02 Lac) 2017-18 PNIeT- No:- 09/EE/PWD(R&B)/STB/2021-22 dated, 16-08-2021 15-01-2022 ₹ 3,01,99,829 Pankaj Mallik
9436471344
31-01-2022 24-01-2022 Work started in due time. 12(twelve) months
 30-01-2023
Finishing work in progress. In addition Kitchen, Morgue  and Garage work in progress
Value of work done= 240.00 Lakh
50% Not Required 90% June'23 221.800 166.290 55.510 91.800 130.000 In progress,
Delay due to getting drawing of garrage & Kitchen in late. However, as per work volume, completion period is not sufficient.
    ₹ 2,40,00,000 ₹ 61,99,829 No.F. 9(3)/EE/PWD/STB/6748-60 The EE, STB has placed demand to the Director vide letter No.F.23(02)/EE/PWD/STB/15183-88 Dt. 0/2/2023 for placement of fund Rs. 130.00 Lac. In progress    
64 Construction of 10 bedded PHC at Durpabari with 10 nos. quarters under Santirbazar Sub-Division, Bagafa Block, South Tripura including Staff quarters. RIDF-XX 540.00 vide A/A & E/S memo No.F. 19(554)-PLAN/DFWPM/2014   dated06-12-2014  of the Health & Family Welfare Deptt.  2014-15 PNIeT- No:- 25/EE/PWD(R&B)/STB/2020-21 dated, 29-01-2021 06-07-2021 ₹ 4,89,23,754 Shri Sumanta Gupta
(9436457880)
21-07-2021 16-07-2021 Work started in due time. 24 Months
(20-07-23)
PHC building finishing work is in progress, Type-I work done upto foundation level; Type-II & Type-III completed upto roof casting.
Value of work Done= Rs. 260  Lakh
Work in progress Not Required 70% Oct' 23 451.970 451.940 0.030 151.330 37.300   Yes, required   ₹ 2,60,00,000 ₹ 2,29,23,754 No.F. 9(3)/EE/PWD/STB/1811-24   In progress    
65 Health(DHS)  Constn of 24 nos staff qtr for 100  bedded District Hospital at Santirbazar ( Type-I: 6, Type-II: 6 units, Type-III: 6 unit, Type-IV:6 Nos)  SPA 583.00 vide A/A & E/S memo No.F. 3(5-44)-PLAN/DHS/2013/2(Sub-II)/1735-43   dated 26/09/2016  of the U.S , Health & Family Welfare Deptt. Head of A/C Central Assistance to State Plan. 2016-17 PNIeT- No:- 22/EE/PWD(R&B)/STB/2017-18 dated, 29-12-2017 25-05-2018 ₹ 4,68,20,780 Jahar Sur Choudhury
9436133138
10-06-2018 13-06-2019 Initial delay because as clear site could not be handed over in time by the client Dept. 24 Months
09-06-2020
Ty-I, Ty-II, Ty-III: Completed and likes to be handed over by 15th July. Type-IV  second floor roof custing completed.
Value of Work done= Rs. 370.00 Lakh
85% Not Required 80% Oct' 23 568.000 440.000 128.000 407.525 0.000 Delay
Due to Fund
Yes, required   ₹ 3,70,00,000 ₹ 98,20,780 No.F. 9(3)/EE/PWD/STB/1556-69   In progress    
66 Belonia Health(NHM) Proposed Construction of new single storied  10(ten) bedded PHC building at existing Niharnagar PHC complex, Niharnagar under Rajnagar Block NHM 173.00 No.F.19(248)-PLAN/DFWPM/2001/4983-5004 (V-II) dated, 09.11.2015 2014-15 19/EE(PWD)/BLN/2015-16 Dt. 09.02.2016 18.05.2016 ₹ 1,44,06,000 Radh Raman Datta
8119953376
02.06.2016 20.08.2017 Initially, delayed by the agency.  02.06.2016
12 Month
Finishing work in progress.
Rs.115.00 lakh
70% NA 85% July-23 221.650 221.220 0.430 221.220 0.000 Work is in progress Yes Work delayed by the agency. ₹ 1,15,00,000 ₹ 29,06,000 No.F.7(20) Pt-I/EE(PWD ) /BLN/DIVN /3264-75 Dt.18.05.2016   In progress    
67 Health
(DFWPM)
Proposed construction of 10 (ten) nos. staff quarters [ Type -I quarter - 04 units (one block - twin double storey ), Type-II quarter - 04 units (one block - twin double storey ) and Type-III quarter - 02 units (one block - twin single storey ) ] at Chottakhola Primary Health Centre (PHC), Rajnagar, Belonia, South Tripura District, Tripura ./2nd call IMR 221.00 No.F.20(96)-BUDGET/ DFWPM/ 2013/7482(V-II) dated, 25.01.2014 2013-14 03/EE(PWD)/BLN/2014-15 Dt.23.05.14 11.11.2014 ₹ 1,78,11,000 Arun Kr. Dey
9436483072
25.06.2015 15.06.2015 Delayed by the agency. EE, BLN issued show casue notice to the agency under clause 54 ( FOR L.D) vide letter No.F.F.08(80)/EE (PWD)/BLN/DIVN/8599-8604 Dt. 22/3/23 and also for LD on 19-4-23 25.05.2016
12 Months
Type-III =Completed & Handed over.
Type-I & Type-II=Structure completed.
Rs.132.00 lakh
Not yet done in Type-I & Type-II Quarter NA 70% Oct-23 211.370 211.370 0.000 211.370       Agency has suspended the work for long time. Now work is in progress. ₹ 1,32,00,000 ₹ 46,11,000     In progress    
68 Health(DHS) Construction of Boundary wall at Ratanpur PHC IMR 28.00 No.F.19(56)-PLAN/DFWPM/2000/2558-65 (V-II) dated, 27.06.2017 2016-17 17/EE(PWD)/BLN/2017-18 Dt.04.11.2017 10-01-2018 ₹ 27,88,000 Sri Babul Saha
7085306543
25.01.2018 20.11.2018 Due to site dispute 24.07.2018
6 Month 
50% work completed.Land dispute . Rs.10.00 lakh NA NA 50%    -----   28.340 10.000 18.340 10.000       Due to land dispute balance work could not be completed for which letter has been issued addressed to the Director H&FWD vide this Office letter No.F.8(80)/EE(PWD)/BLN/DIVN/5947-52 Dt.22.11.22 ₹ 10,00,000 ₹ 17,88,000 No.F.7(20) Pt-I/EE(PWD ) /BLN/DIVN /6994-7002 Dt.10.01.2018   In progress    
69 Belonia Health(DHS) Construction of District Ware House at Belonia, South Tripura IMR 250.00 no.F.1991670-PLAN/DFWPM/2014 dated 28/12/2016 2016-17 PNIeT No. 02/EE/PWD/BLN/2022-23 Dt. 26-04-22 10.03.2023 ₹ 1,83,43,000 Biplab Choudhuri
9862970796
25.03.2023 25-04-2023 Due to tendering issue. 24.03.2024
365 days
Excavation for foundation trenches almost in completion stage. PCC work will be started shortly   NA 5% Mar-24 100.000 0.000 100.000 0.000       At the 1st time work order was issued but clear working site not handed over by the health authority to PWD. Hence work has been cancelled on 12.10.18. After that DNIT has been modified for e-tender where in the 1st call tender has been cancelled on 27.01.21 due to all participated bidders are found non-responsive. In the 2nd Call, the tender has been cancelled on 15.03.22 due to 1st lowest bidder has surrendered. After that the DNIeT has been changed as per SOR 2020. Now work order has been issued & work will be started very shortly   ₹ 1,83,43,000 No.F.7(20)/Pt-1/EE/PWD/BLN/DIVN/8346-56 Dt.10-03-23   In progress    
70 Sabroom Health(NHM) Construction of singled storied Integrated Ayush Hospital at paschim Jalefa under Sabroom Sub-Division. NHM & SAMT 900.00 No.F. 1(63)/SAMT/M5/AYUSH/2019 dated 22-01-2021 of the U/S to Govt of Tripura for Rs. 900.00 Lac 2021-22 13-05-2021 16-10-2021 ₹ 5,44,07,805 Shri Tapesh Ch Debnath
(Mob# 9436120787)
02-11-2021 01-12-2021 There was a verbal proposal for shifting of site at somewhere nearby NH-08 which lead one month delay in commencement of the work. 365 days
01-11-2022
Work Completed 80%   Civil Work 100% Completed Completed 342.260 342.260 0.000 342.260 202.000 05-06-2023
 There was a verbal proposal for shifting of site at somewhere nearby NH-08 which lead one month delay in commencement of the work.
    ₹ 5,00,00,000 ₹ 44,07,805   1) Fund requirement by EE, STB for Rs. 202.00 Alc vide letter No.F. AC(05)/EE/PWD/SBM/11239-41 Dt. 01/02/23 to the Mission Director. Completed     
71 Bishalgarh Fourth
Circle
Health(DHS) Construction of 8 ( Eight) nos staff quarters building  4 nosType-I , (one block twin double storey), , 2 nos Type -II Units (one block single storey), 2 Nos Type-III units(one block double storey) at Madhupur PHC under Bishalgarh Sub-Division. NHM 235.00 No.F.19(80)-PLAN/DFWPM/2000(S)/11015-21/(V-II), Dated-15/03/2017 2016-17 PNIeT No 09/EE-BSLD/PWD(R&B)/2022-23, Dated-04/06/2022, DNIeT-CE(Buildings)/PWD/DNIT/ACE/Project Unit/36/2021-22 30-12-2022 ₹ 2,13,35,925 Shri Jahar Sur
(9436133138)
14-01-23 27-02-2023 Due to late receipt of structural drawing 15 Months
(13-04-24)
Foundation, Sub-Structure work completed. Super structure work is in progress. 45% Work Completed. Rs 95.00 Lakh Not Started Nil 45% Mar-24 69.500 0.000 69.500 0.000 0.000       ₹ 85,00,000 ₹ 1,28,35,925 No.F. 21(1)/EE-BSLD/PWD(R&B)/9051-9065 Dated 30/12/22 of the EE, Bishalgarh   In progress    
72 Bishramganj Fourth
Circle
Health(NHM) Proposed construction of (i) New 30 (thirty) bedded Community Health Centre (CHC) building including Ramp [ GF + Part of FF ]  (ii) Kitchen  (iii) Morgue  and (iv) Garage & Generator with Driver room building at existing Takarjala CHC under Jampuijala Sub-Division, Sepahijala District, Tripura NHM 670.00 No.F.  19(263)-PLAN/DFWPM/2001(V-II)/94-99 dated 01/04/2017 of Under Secretary, Govt. of Tripura 2017-18 05-06-2017 17-01-2018 ₹ 5,86,70,414 Binode Bihari Datta, 9436131276 01-02-2018 04-09-2019 Initiall delayed due to Non availability of clear site, 24 months/
02-02-2020
Civil works of all component of CHC building under scope of present agreement is completed. IE work of morgue pending.
Value of work done Rs. 630,00,000.00
90% NA 90.00 June.23 500.000 500.000 0.000 500.000 170.000     Work is in progress. ₹ 6,30,00,000 ₹ -43,29,586     In progress    
73 Constructin of 50 bedded fieled hosptilal for COVID patient under emergency COVID response Plan -II at Bishramganj NHM 250.00 No. F. 2(63)/DHFWS/CMO/SPJ/ECRP-II/Accounts/2021-222/6729-38 dated 05/09/2022. of Joint Secretary, Govt. of Tripura 2022-23 a) 01.10.2022   b) 29.06.2022 a) 04-03-2023                   b) 13-10-2022 ₹ 2,15,57,256 a) Pradip Nag
8787752787
b) Ranjan Debnath
8956939330
a) 19-03-2023
b) 28-10-2022

b) 17/10/2022
A) Delayed, as the Site is not suitible to accommodate building. Accordingly CMO, SPJ has initiated  proposal sent  to the Mission Director , NHM to shift the proposed building at Bishalgarh vide letter No.2(63)/DHFWS/CMO/SP/ECRP-II/Account/2021-22/4374-78 Dated 29/05/2023..  a) 300 days   12/01/2024
 b) 180 days 26/04/2023
A) Not yet started. Site will be changed.
 B)  Finishing and tiles works in progress. (Approx. value of work: Rs. 6.00 Lac)
  NA a) 0.00

b) 30%
a)  Feb, 24

b) June, 24
250.000 19.75 230.250 0.000 0.000     A) Site is not suitible to accommodate building. Accordingly CMO, SPJ has initiated  proposal sent  to the Mission Director , NHM to shift the proposed building at Bishalgarh vide letter No.2(63)/DHFWS/CMO/SP/ECRP-II/Account/2021-22/4374-78 Dated 29/05/2023..
B)  Finishing and tiles works in progress.
₹ 6,00,000 ₹ 2,09,57,256     In progress    
74 Sonamura Health
(DFWPM)
Construction of 10 bedded PHC  with 10 nos. quarters at existing Kamalnagar PHC   645.00 No.F.19(109)-PLAN/DFWPM/ 4547-57)V-I0 dated 14/07/2021 2021-22 DNIT No : CE (Buildings)/PWD/ DNIT/ACE/
Project Unit/43/2021-22
Dt……….
28-04-2022 ₹ 5,29,51,364 Swapan Kr. Dey
9436121336
12-05-2022 02-12-2022   12-11-2023
18 Months
work is in progress up to 1st floor roof lavel type 1 and PHC block.  Value of work done Rs. 150 Lac       Dec.23 100.000 150.000   0.000 0.000       ₹ 1,50,00,000 ₹ 3,79,51,364 Vide No.F.10(30)/EE/SNM/PWD/421-37 dt.28-04-2022   In progress    
75 Health
(DFWPM)
Construction of 16 nos staff quarter building for Boxnagar CHC under Sepahijala District/ Type-I, 6 Units, Type-II: 6 Nos, Type-III: 4 Nos)    527.00 No.F.19(32)-PLAN/DFWPM/2000(Sub-1)/4203-10(V-i)dt 13/10/22 2022-23 CE(Buildings)/PWD/DNIT/ACE/Project Unit/89/2022-23, Dt. 19-12-2022
Dt………
              2nd call of tender invited on 12-04-2023 and to be opened on 11-05-2023             0.000         In the 1st call of tender no bids found and Tender documents sent to the Competent Athority for further necessary instruction.
2nd call of tender invited on 12-04-2023 and to be opened on 11-05-2023
  ₹ 0     Tendering Stage    
76 Health(DHS) Up- Gradation of Melaghar Sub- Divisional Hospital as First Referral Units (FRU) / Construction of new OPD Complex  and 10 (ten) Bedded Eye Ward with Eye OT building (G+1 storied) at Melaghar, Sonamura Sub-Division, Sepahijala District, Tripura under SPA (CASP) during the year 2016-17   196.00 No.F. 3(1-386)-PLAN/DHS/2010/1713-19/7967(v-III), Dt. 21-09-2016.
Rs. 6.15
2016-17 CE(Buildings)/PWD/DNIT
/ACE/Project Unit/59/2021-22.
Dt………..
13-07-2022. ₹ 2,03,59,836 Kanu Lal Saha
8575354399
28-07-2022 28-07-2022   25-02-2023
(Period?)
Finishing work is in progress. Value of work done Rs. 132.00 Lac     70% Oct-23 250.000 112.000 138.000 112.000         ₹ 1,32,00,000 ₹ 71,59,836 Vide No.F.10(30)/EE/SNM/PWD/2313-27 Dt.13-07-2022.   In progress    
77 LTV Fifth
Circle
Health(DHS) Proposed Expansion of Longtharai Valley (LTV) Sub-Divisional Hospital Building [ Ground Floor + Part of First Floor ] by 20 (twenty) beds at Chailengta under Dhalai District, Tripura under Special Central Assistance to Tribal Sub-Plan (SCA to TSP) CASP 808.00 No.F.3(2-410)-PLAN/DHS/2016/480-85 Dated.26-03-2018 for an amount of Rs.808.00 Lakh 2017-18 16-05-2018 13-09-2019. ₹ 6,98,62,467 Sri Gour Gobinda Saha  8787367268 28-09-2019. 28-04-2020. Delay for handing over of clear site 27-09-2021.
24(twenty four) months
Completed and inaugurated  0n 12/04/2023 &  808.00 lakh 100.00% Not required 100.00% Completed on 20.03.2023 808.000 739.000 69.000 739.000 0.000 20-03-2023 & delay occurred due to handing over of clear site & Covid. No & delay occurred due to Covid. Total value of work Rs.808.00 on completion (Civil-753.00 lakh & IE work-55.00 lakh)
Inaugurated on 12/04/2023 by the Hon'ble Chief Minister.
₹ 8,08,00,000 ₹ -1,09,37,533     Completed in all respect    
78 Ambassa Fifth
Circle
Health(NHM) Proposed construction of staff quarter [8 nos.] (Type-I=04 nos. & Type-II=04 nos.) for Ganganagar PHC, Jawharnagar Sub-division, Dhalai District, Tripura. IMR Incentive 170.00 19(254)-PLAN/DFWPM/   12001/6033/
Dt. 30/12/16
2016-17 PNIeT No: 09/EE/PWD(R&B)/AMB/2021-22  Dated:30-07-2021 19-01-2022 ₹ 72,45,371 Sajal Karmakar
[8731837723]
03.02.2022 08.02.2022 Due to willful delay of the agency 09 Months
'02-11-2022
Type-I= Painting work is in progress.
Type-II= Painting work is in progress.
Value of Work Done = Rs. 40.00 lac (approx)
In Progress 80% 0 80% July, 23 225.000 125.000 100.000 125.000 0.000   Yes
180 Days
Work is in progress ₹ 40,00,000 ₹ 32,45,371     In progress    
79 Fifth
Circle
Health(NHM) Construction of New 10 nos. staff quarters (Type-I-4, Type-II-4 & Type-III-2) at Ambassa under Ambassa block, Ambassa Sub-Division, Dhalai District, Tripura./

A) 10 nos. staff quarters (Type-I-4, Type-II-4 & Type-III-2)
B) Balance works
IMR Incentive 225.00 F.19(43)-PLAN/DFWPM/2000(S)/97-105
Under Secretary,H&FW Department
2016-17 08-05-2016 A) 03.01.2017
&
B) 05.04.2022
₹ 2,42,30,000 Shri Riot Narayan Ghosh
(Mob#) 8787305670
A) 18.01.2017
&
B) 20.04.2022
A) 18.04.2017
&
B) 20.04.2022
Due to willful delay of the agency A) 18.06.2018
&
B) 180 days
 15-11-2022
Work Completed
Value of Work Done = 259.00 lacs (approx)
Completed NIL 100%   225.000 225.000 0.000 223.550 34.000 Completed on 30th May,2023.
[ Not yet taken over by the Health Dept. water supply connection from DWS Deptt. Yet to be made ]
Yes
180 days (Aprox).
Plz provide information if Levy or LD imposed with reference.
The work which was awarded vide agreement No. T/17/SE(Project)/PWD(R&B)/EE/PWD(R&B)/AMB/2016-17 was not complete upto within agreement value plus 10% of the agreement amount . Therefore balance work agreement was awarded to the same agency vide agreement No.            T/01/SE-V/EE/PWD(R&B)/AMB/2022-23

Requisition of additional fund for an amounting Rs. 34.00 Lacs placed to the Health Deptt. but not yet received.
₹ 2,59,00,000 ₹ -16,70,000     Completed in all respect    
80 Fifth
Circle
Health(DHS) Construction of Dhalai District Hospital, Phase-II (Hospital Quarters ) at Kulai, Ambassa, Tripura under NLCPR Scheme / SH:- Construction of 48 Nos. Staff quarters
A) 36 Nos qtrs
B) 12 Nos Qtrs
NLCPR 1131.90 No. F. Arch /N/ 2(6)/ 567-572, Dated- 21/08/2018 and No. F. 3  (5-93)-Plan/ DHS/ 2017-18/ 1353-59, Dated- 01/08/2018, By the computent authority 2017-18  PNIeT.No: 21/EE/PWD(R&B)/AMB/2019-20 Dated:02-01-2020 A) 21-10-2020.
B) 17-12-2020.
₹ 10,17,31,442 A)  Shri Kashinath Bhattacherjee
B) Shri Ajit Bhattacherjee
A) 06.11.2020
&
B) 01.01.2021
A) 16.12.2020
&
B) 03.08.2022
The work was delayed because clear site was not available at Ambassa for type-III and Type-IV and at Kulai for Type-II and Type-IV. Concerned department didn’t provide land initially as there was some dispute regarding land for proposed medical college.   A) 15 Months [06.02.2022]
&

B) 12 Months
[03.01.2022]
Type - I(12 Nos) : - 95% Completed except Painting & Internal electrification.
Type II(12 Nos): - Upto 2nd & Final  Floor Slab casting Completed, Brick Masonry Work In progress.
Type III(12 Nos):-95% Completed except Painting & Internal
Type IV :-  Column completed upto 1st Floor Slab level
Approximate value of work done Rs.680 Lac
Type-I:- [Work order issued]
Type-II:-
Type-III:-[Tender Invited]
Type-IV:-
NIL 77% Dec, 2023 418.380 418.380 0.000 418.380 713.470   Yes

570 Days(Aprox)
  ₹ 6,80,00,000 ₹ 3,37,31,442     In progress    
81 Medical College Project
Unit
Health(DHS) Balance work for Construction of 750 Capacity Auditorium cum workshop & Cafeteria etc for of Tripura Medical college and Dr.BRAM Teaching Hospital at Hapania Deposite Work of TMC 845.00 NO.F.2(Acctts-89)SFTMC/11/Vol-1/2610-15 dated 16th December 2020 of CEO,TMC 2020-21   28-03-2022 ₹ 8,42,00,000 Swapan Chandra Dey 11-04-2022 30-09-2021 Due to Covid situation 365 days
12/04/2023
Roofing work completed, ceiling work and other finishing works in progress.
Approx. value of work done Rs 421.00 Lac
awaiting for approval of tentative deviation Work order issued on 21/3/23 for AC Rs.112.42 Lac 40% August -23 200.000 199.00 1.000 199.00 641.85   Time extension required,, no of days can be assessed on submission of final bill   ₹ 4,21,00,000 ₹ 4,21,00,000 7(72)/EE/MCD/PWD/20-21/9581-99, Dt-28/03/22 1) The CEO, Society for TMC has placed fund through Banker Ch No 031097 dated 9-3-23 for Rs. 200.00 Lac In progress    
82  Constn of 40 bedded Girls Hostel,(RIPSAT) in Regional Institute of Pharmaceutical Science and Technology Complex,Abhoynagar, Agartala, AICTE 260.00 No.F.12(1)-RIPSAT)/FUNDING/2018/198-205    RIPSAT 2018   27-09-2021 ₹ 2,00,89,000 Sri Krishna Gopal Saha 12-10-2021 12-10-2021   450 days
05-01-2022
Completed and Handed over on 04/07/23. Approx. value of work done Rs 200.89 Lac 100% not required 100%   150.000 150.000 0.000 0.000 50.890 Date of completion please.   Handed over on 04-07-2023 ₹ 2,00,89,000 ₹ 0 7(212)/EE/MCD/PWD/20-21/8284-8301 Dated 27-09-2021   Completed in all respect    
83 Upgradation/strengthening of ANM School at Durjoynagar,Agartala,Tripura/Construction of Administrative and Academic (G+2 ) storied building/Building portion including internal water supply and sanitary installation, sewege and drainage works CASP 843.00 No.F.3(2-403)-PLAN/DHS/2016(sub)/1822-33 dt 12-12-2017                          DHS 2017-18   18-10-2022 ₹ 8,12,42,000 Swapan Kumar Dey 11-10-2022 02-11-2022 Intially delayed due to existing old structure and felling of trees by forest deptt. 720 days
08-11-2024
Work completed upto FGL
Approx. value of work done Rs 121.86 Lac
Architectural drawing sent to EE,IE Architectural drawing sent to EE,Mech, lift block works in progress. 13% Oct 24 105.000 105.000 0.000 105.000 707.410       ₹ 1,21,86,300 ₹ 6,90,55,700 7(203)/EE/MCD/PWD/9729-40 Dated 18-10-2023   In progress    
84 Medical College Constn of proposed OPD building for Dr.BRAM &TMC at Hapania ,Agartala/SH:-Vertical extension OPD building from (G+3) to (G+4) level. NHM 415.00 No.F4(7)/ED/TMC/2009-2010/Vol-III/1342-46 dated 6-7-2020 of CEO,TMC 2020-21   04-09-2021 ₹ 4,15,13,890 Samir Lal Saha 19-09-2021 01-10-2022 Due to Covid situation 365 days
18-09-2022
Roof Castintg Completed.
value of work done Rs 290.60 
IE estimate  N/A 30% Nov 23 100.000 100.000 0.000 100.000 315.139     Due to Covid-19 TMC occupied this building till Nov.21. ₹ 2,90,59,723 ₹ 1,24,54,167 7(71)/EE/MCD/PWD/20-21/3864-81 Dated 04-09-2021 1) The EE, Med Collage submitted requistion to the CEO for placememnt of fund Rs.150.00 Lac vide letter No.F.7(13)/EE/MCD/PWD/22-23/14762-64 Dt. 24/2/23 In progress    
85(A) Project
Unit
Health(DHS) Establishment of Mechanised Laundry System at
A) Cancer Hospital  hospital, Agartala.
SJTNY 300.00 Administrative approval only (No.F. 3(5-137)-PLAN/DHS/2022-23 Dt. 17/01/23 of the D.S, Health & Family Welfare Deptt)
E/S received vide memo No.F.(5-137)-PLAN/DHS/2022-23 Dt. 28/04/2023 of the D.S of Health & Family Welfare Deptt. for Rs. 300.00 Lac.
2022-23     ₹ 78,09,646 Krishna Gopal Saha         Tender accepted on 06-05-23         150.000   150.000         7(243)/EE/MCD/PWD/(R&B)/721-24,Dt-11/05/2023.   ₹ 78,09,646   Approval under SJTNY Memo  No.1 (10)/PCD/ SJTNY/2022/28-52 Dated  04/01/2023 of the (P(P&C)D., S.C.GoT.

A/A received vide
Memo No.F.3 (5-137)-PLAN/DHS/2022-23/   Dated 17/01/2023  of the D.S., HFWD.
E/S received vide memo No.F.(5-137)-PLAN/DHS/2022-23 Dt. 28/04/2023 of the D.S of Health & Family Welfare Deptt. for Rs. 300.00 Lac.
Tendering Stage    
85(B) Health(DHS) B) IGM Hospital, Agartala SJTNY   31-05-2023 ₹ 1,19,32,010 Narayan Ch Saha                              
Tender accepted on 03-05-23
  ₹ 1,19,32,010 7(244)/EE/MCD/PWD/(R&B)/661-676,Dt-31/05/2023. Tendering Stage    
86 Dharmanagar First
Circle
Higher Education  Consruction of hostel at North Tripura District Polytechnic Dharmanagar AICTE 150.00 F.1(1)-NTDP/AICTE/CAFES/2021-22 dated: 18/07/22 2021-22                 Selected site is encroached by local inhabitants. Letter issued to higher Education for decision to resolve land issue.         0.000 0.000 0.000 0.000       Intervention of higher authority of the concerned department is rquired.   ₹ 0     Not yet started    
87 Agt Div-III Second
Circle
Construction of MBB Auditorium/1000 seated capacity NLCPR 919.00                     DPR is under scrutiny             0.000             #VALUE!     Not yet started    
88 Agt Div-V  Constn of Womens Polytechnic at Hapania Special
assistance
300.00 Memo No. 1(10)/PCD/PF/FIN/ 2021/Part/533563 dated 01.09.2022
 of the  Secretary P&C Department.
2021-22 DNIT No. CE(Building)PWD/DNIT/ACE/Project Unit/41/2021-22
PNIT No. 15/B/EE-V/AGT/PWD/(R&B)/2021-22. dated 15.12.2021
28.04.2022 2,70,24,486 Jasoda Lal roy 13.05.2022 28.05.2022 Non availibilty of drawing 18 months/'28.10.2023   Ground floor Roof ( Balance portion) in progress.Marble flooring in progress in other part of building. .Approx. value of work done Rs 180.00 Lac Tender invited Nil 50% Dec,23 150.00 140.19 9.81 140.19 150.00     Structure completed, work is in progress. ₹ 1,80,00,000 ₹ 90,24,486 F.No.6(337)/EE-V/AGT/PWD/2020-21/356-731 dated 28.04.2022 Balance part: Ground floor slab completed, 1st floor slab work is in progress.
Rest vertical extension part completed except IE works.
In progress    
89 Agt Div-III Second
Circle
Higher Education  Construction of Annexure block of Birchandra State Central library ( Balance work of Phase-I) NLCPR 975.00 9.75 vide F.No. DNER/NLCPR/TRI/104/2011 on 20.02.2014/ Higher Education  2013-14 24.03.2022  05-09-2022 5,18,76,772 Sri Tapan saha 19.09.2022   Initial delay as Clear site was not handed over by the Higher Education Deptt 28.02.2024
18 Months
Piling work in progress . Value of work done Rs 20.00 Lac  0 0 5% Feb-24 0.000 0.000 0.000 0.000 0.000       ₹ 20,00,000 ₹ 4,98,76,772     Not yet started    
91 Agt Div-V Construction of Ramthakur College Auditorium/Balance work   1207.00                     Revised Estimate amounting Rs. 1599.00 Lakhs, yet to be approved from Higher Education Department                        During Review meeting chaired by the Secretary, PWD, it was decided for a joint site visit along with officials of Higher Education.
Accordingly joint site visit have been conducted along with Dy. Director, Higher Education, Principal of Ramthakur College, where it was decided to prepare a fresh balance work estimate it present rate/ requirement including civil, electrical, mechanical scope of works to complete the project as a whole functional and to process the estimate to the Higher Education Deprtment through competent authority. The matter was also discussed with the C.E, PWD(Building). Accordingly estimate is under preparation from all wings of PWD.
  ₹ 0     Not yet started    
92 Agt Div-III Construction of  Science buildings(G+4) at MBB College( Construction of Ground floor only with provision of G+4 storied foundation)   1500.00 No.F5(415)-DHE/PLG/2022 dt 26/08/2022/Higher Education & Memo. No.F.5(415)-DHE/PLG/2022/3602(04) dated 30-11-2022 2022-23 16.01.2023               DPC recommended for acceptance of the tender on 03/06/2023         0.000 0.000 0.000 0.000 0.000     Estimated cost: Rs. 12,04,12,258/-   ₹ 0     Tendering Stage    
93 Jirania Fourth
Circle
Construction of Girls' hostel  for student /Researchers of TTADC Polytecnic Institute, Khumulwng under CAFES-NER Scheme of AICTE CAFES-NER  150.00 (AA Rs. 3.00 Crore and ES Rs. 1.50 Crore) vide No.F. 1(49)-TP/Estt/2021-22/AICTE-AQIS (CAFES-NER)/261 Dated 12/01/23 of the Addl. Secretary, Higher Education 2022-23                 Letter issued to higher Education for decision.DNIT to be issued for inviting tender             0.000         DNIT to be issued for inviting tender   #VALUE!     Not yet started    
94 Kamalpur Fifth
Circle
 Constn of Kamalpur Degree College/Vrtical extension Special
Assistance
234.00 No. F. 5(187)-DHE/PLG/ 09/2805(7) Dt. 28-12-2016 of the Under Secretary to the Govt. of Tripura. 2016-17   12-10-2017 ₹ 1,78,37,809 Sri Sukumar Ghosh & 9436499162  26-10-2017 17-10-2017   12 Month
/
25-10-2018
Superstructure almost completed and finishing work is going on.
Value of work done Rs. 60.50 lac.
Nil Nil 50% Sept.23   0.000 0.000 0.000 89.470 Progress of work is very slow by the Agency Yes Fund for 2022-23Rs. 89.47 Lac  has already been surrendered.
Progress of work is very slow by the Agency
₹ 60,50,000 ₹ 1,17,87,809     In progress    
95 Dharmanagar Industry Strengthening of ITI Dharmanagar Not assigned 147.00 F.DI/TRG/C-II/02/2015/ITI/DMN/PART-II/16556-59, DATED: 20-11-2017. 2018-19 15-03-2018 31-10-2018 ₹ 1,43,69,380 BBR (India) PVT. LTD.
9612164078
14-11-2018 14-11-2018 Work delayed due to non availibility of  funds, pandemic, and non availibility of specific materials for retrofitting and micro concrete of local market. 13-11-2019
12 Months
Structural and strengthing work completed. Flooring work completed.Finshing work is in progress.
Value of work done Rs. 143.00 Lac approx.
80% Not reqd. 98% June-23 147.000 147.000 0.000 147.000 0.000       ₹ 1,43,00,000 ₹ 69,380     In progress Toilet block and parking shed, work order issued  on 9/12/2022 for Rs. 24,27,000/-  
96 Law  Construction of residential quarters for Grade-II Judicial officers at Dharmanagar, North Tripura CSS 278.00 No.F.4(1)-LAW/ESTT(I)/2009(PART-1)/10302-308 dated 25/10/19 2019-20 05-11-2020 30-06-21 ₹ 2,10,32,418 M/S J.C Nath & Sons
9436132164
14-07-2021 14-07-2021 Delayed due to change in foundation and demolishing of existing structures 14-01-2023
18 Months
Finishing work of main building is in progress and sentry room, boundary wall work will start soon
Value of work done Rs. 180.00  Lac approx.
  Not reqd. 75% Oct-23 415.000 371.700 43.300 371.700 370.300       ₹ 1,80,00,000 ₹ 30,32,418   1) UC Submitted by the EE, DMR for Rs. 51.00 Lac vide letter No. F. 34-117/EE/DD 14/3/23.  In progress    
97 Construction of residential quarters for Grade-III Judicial officers at Dharmanagar, North Tripura CSS 236.00 No.F.4(1)-LAW/ESTT(I)/2009(PART-1)/12068-07 dated 21/10/19 2019-20 05-11-2020 30-06-21 ₹ 1,93,39,162 M/S Narmada Ranjan Das & Co.
9436132208
25-06-2021 25-06-2021 Delayed due to second time soil testing and demolishing of existing structures 24-12-2022
18 Months
First Floor Roof Casting completed. Brick work in progress
Value of work done Rs. 150.00 Lac approx.
  Not reqd. 60% July-23       ₹ 1,50,00,000 ₹ 43,39,162   In progress    
98 Proposed vertical extension of Court Building of      District & sessions Judge,North Tripura Judicial District, Dharmanagar, North Tripura CSS 228.00 No.F.4(1)/LAW/ESTT/2009(P-1)/9551-54 Dated 14/07/2022 2022-23 04-08-2022 09-12-2022 ₹ 1,21,86,410 Sri Saurajit Deb
8974360194
23-12-2022 23-12-2022 No delay 22-09-2023
270 Days
Column & Brickwork completed up to roof level. Tubulsr Truss work in progrss

Value of work done Rs. 115.00 Lac approx.
    70% Sept'23       ₹ 1,15,00,000 ₹ 6,86,410   In progress    
99 Kailashahar Constn.of  07 Numbers of new residential quarters for Judicial officers of various Grade at Kailashahar under Unakoti District Tripura CSS 884.00 No.F.4(9)/LAW/KLS/22/1225-29 dt 6/2/2023 2022-23 23-12-2022               DPC recommended  on 30-03-23 and accordingly, sent to the administrative department for acceptance of the tender.             0.000         Tender invited:
1st Call:
12/09/2022
2nd Call
06-12-2022
3rd Call
23-12-2022
  ₹ 0     Tendering Stage    
100 First
Circle
Construction of New Court Building for District & Sessions Judge at Kailashahar, Unakoti District,Tripura. CSS 1361.00 No.F.4(6)LAW/CONS/2013/8135-39 Dated 09/06/2022 2022-23 19-08-2022     Sri Pranab Paul         Tender accepted on 23/06/2023 (Rs. 9,87,71,770/- i.e 12% above on SoR 2021 ) and communicated to EE, KLS             0.000             ₹ 0     Tendering Stage    
101 Khowai Second
Circle
Law  Proposed construction of Judicial officer's quarters [Grade-I: 02 no's,Grade-II: 3 no's,Grade-III: 02 no's ]with sentry post & Boundary wall for District & sessions Judge's Court at Khowai, Khowai District,Tripura/ CSS 973.00 No.F.4(4)/LAW/CONS/KHW/2019/5770-73 Dt. 7/4/2021 of the DLC & Deputy Secretary, LAW 2021-22 30-12-2021 17-05-2022 ₹ 7,52,21,376 Dipak Nag
(9436123542)
02-06-2022 01-05-2023 'Delay in handing over of land. 'New land is handed over on 12-04-23 and work will be started. 18 Months
(01-12-2023)
Foundation work for grade 3 quarter building  has just started.   0% 0% 0% Dec'24 0.000 0.000 0.000 0.000 0.000     After demolishing of old structure it is found that the land is not adequate to set out the proposed buikding and thefore, alternative land to be handed over by the Law Deptt. ( Ref. Letter  No. F.11(10)/EE/PWD/KHW/11932-936 dt. 13/03/2023 of the EE, KHW)   ₹ 7,52,21,376     In progress    
102 Law  Vertical extension of New Multistoreyed Court building(G+2 to G+3) in the premises of Addl.District & Sessions Judge's Court Khowai Sub-Division,District Khowai Tripura/SH: Building portion in/c internal water supply,sanitary installations and 66.00 metre retaining wall. CSS 391.00 No.F4(7)-Law/Cons/2000/4121-27 dt06/05/2019 2019-20 10-01-2022 17-05-2022 ₹ 3,13,72,796 Dipak Nag
(9436123542)
02-06-2022 01-10-2023 Commencement of the work delayed for shifting of Solar Panel  on the roof of the existing structure.  12 Months
(16-05-2023)
Column work completed. Preparation for roof slab casting in progress.( Rs. 30.00 Lac) 0% 0% 35% Dec'23 0.000 0.00 0.00 0.00 100.000       ₹ 30,00,000 ₹ 2,83,72,796     In progress    
103 Teliamura Construction of Judicial officers Quarters at Teliamura   208.00 Awaited   14-09-2022               Tender under finalistion. A/A & E/S is awaited.              0.000         Tender under finalistion. A/A & E/S is awaited. The SE-II has persuaded for E/S vide letter No.F.14(4)/SE-II/3384-87 Dated 20/12/22.   #VALUE!     Tendering Stage    
104 Amarpur Third
Circle
Construction of 2 nos New Grade -III Judicial officers Quarters (G+2) storied at Amarpur, Gomati District,Tripura CSS 338.00 No.F.4(8)-LAW/ESTT(I)/2009(PART)/15307-13 dated 03/12/21 2021-22 08-03-2022 30-06-2022 ₹ 1,75,51,850 Sri Tapan Chakraborty,Contact No.9436472595 15-07-2022 01-11-2022 0.00 300 days                                                   30-09-2023 First floor slab reinforcement work ground floor & brick work  is in progress.
Rs.70.00 lakh
0.00 0.00 40% March-24 40.000 20.000 20.000 20.000 50.000     1) NIeT: 08-03-2022   20/NIT/EE/PWD/AMP/2021-22. ₹ 65,00,000 ₹ 1,10,51,850 '30-06-2022             Memo No.F. F.TC/5/EE/PWD/AMP/2967-80   In progress    
105 Udaipur Law Construction of Judicial officers Quqrters G+2 storied (02nos Grade -II quarters having parking facilities at GF in the Judicial Officers Quarter Complex situated at Koilar Math,Udaipur CSS 259.00 No.F.4(2)-Law/Estt(UDP)/2017/173-76dated 24th August2022 2022-23 02.11.2022 20.03.2023 ₹ 2,05,56,583 Sri Nihar Chandra Debnath. M-9436131064 24-03-23   Initial delay due to demolition  of existing structure for new construction. 23.092024
18 Month
Work is to be started soon       Dec'24     0.000   130.000     Work Order  Issued vide No.TC/03/EE/UDP-DIVN/UDP/10577-91 Dt.20/03/2023 of the EE, UDP   ₹ 2,05,56,583     not yet started    
106 Sabroom Construction of Judicialofficers Quarters at Subroom CSS 221.00 F.4(6)-LAW/ESTT/09(PART-I)/13819-23 dated 26/09/22 2022-23 12-0-2022 07-12-2022 ₹ 1,79,79,542 Shri Bishnu Pada Paul
(Mob# 6436519065)
10-01-2023 10-01-2023   450 Days
04-04-2024
1st floor slab casteing completed. Value of work done Rs. 50.00 Lakh     10% Mar'24 40.000 40.000 0.000 40.000 165.000       ₹ 50,00,000 ₹ 1,29,79,542     In progress    
107 Mohanpur Fourth
Circle
Construction of SDJM & Civil Judge (Jr.Div) court building (G+1) storied including 02(Two) nos Residential quarter for Grade-III Judiciary officer at mouja Taranagar under Mohanpur Sub-Division. CSS 2340.00 No.F.4(7)/LAW/CONS/MNP/2019/14628-34 Dated 12/11/2021 2021-22   16.03.2022 ₹ 11,89,00,000 Tapesh Ch Debnath 16.03.2022 19.03.2022   15.09.2023
Period ?
Roof casting upto 2nd floor completed. Brick work for superstructure in progress
Value of work done as on reporting date 
0 0 70% Nov' 23 1035.000 1035.000 0.000 1035.000 800.000         ₹ 11,89,00,000     In progress    
108 Fourth
Circle
Law Construction of National Law University(Ph-I)   2100.00                     Survey Site Plan submitted to authority. Drawing under preparation.                       Survey Site Plan submitted to authority. Drawing under preparation.   ₹ 0     not yet started    
109 Bishramganj Construction of 08 Numbers of New Residential Quarters for Judicial Officers of various Grade [ Grade-I: 03 nos, Grade-II: 03 nos, Grade-III: 02  Nos.] at Bishramganj under Sepahijala District, Tripura CSS 2208.00 No.F.4(7)/LAW/CONS/MNP/2019/14628-34 Dated 12/11/2021 2021-22 03-01-2023             720 days DPC recommended for acceptance of tender on 30/3/23 and processed to Admn deptt for acceptance             0.000             ₹ 0     Tendering stage    
110 Construction of New Court Building of District and Sessions Judge at Bishramganj  under Sepahijala District to accommodate all Civil & Criminal Courts under one Building  CSS 3529.00 No.F. 4(7)-LAW/ESTT (I)/2013/15497-500  Dt. 10-11-22  2021-22 19-11-2022             720 days DPC recommended for acceptance of tender on 30/3/23 and processed to Admn deptt for acceptance             0.000         DPC recommended for acceptance of tender on 30/3/23 and processed to Admn deptt for acceptance   ₹ 0     Tendering stage    
111 Kamalpur Fifth
Circle
Constn of Kamalpur Court/Balance work CSS 1640.00 F.4(7)-Law-Estt/09/7210-14 dt 04/08/17 Revised sanction F.45(24)-Hc/2021/19827-30 dated 07/09/21 2017-18   12-05-2022 ₹ 7,77,45,950 M/S L.K. Builders & 9436123268 26-05-2022 26-05-2022 Nil 15 Month
/
25-08-2023
i) Boundary wall completed.
ii) Superstructure work almost completed except dome portion.
iii) Finishing work is in progress.
Value of work done Rs. 534.24 lac.
Nil Nil 80% Aug.23 534.240 534.240 0.000 534.240 243.220 Nil N/A Work is in progress ₹ 4,14,24,000 ₹ 3,63,21,950     In progress    
112 Capital Complex Project
Unit
Constn of 1 no Bunglow for Hon'ble judge's of High court of Tripura/Balance work State Plan 300.00 4(1)Law/ESTT/CONS/JB/2020/1072   dtd 24.1.23  for Rs. 145 lakh 2022-23 27.06.2022               Tender under scrutiny. Revised estimate sent to LAW Deptt for revised A/A & E/S             0.000             #VALUE!     Tendering stage    
113 Construction of multistoried (G+4) building in High court premise at Agartala,West Tripura Special Assistance 858.00 4(3)Law/ESTT/4C/2001/6778-83   dtd 29.10.2016   A/A & E/S for Rs. 19.17 Crore 2016-17 15.10.2022 15.10.2022
(LOA issued)
₹ 8,58,00,000 Swapan Ch. Dey 23.11.2022 2.02.2023 At the initial stage work could not be started due to non availability of sufficient land. Thereafter, land made available. 24 months
22-11-2024
Building,:-Foundation work completed.
R/Wall: 32 mtr retaining wall is acompleted upto 80 %  of ht. Reinforcement for raft footing for balnce portion is going on.
Value of work done = 250 Lakh
    20% Oct'24 50.000 0.000 50.000 50.000 200.000       ₹ 2,50,00,000 ₹ 6,08,00,000     In progress    
114 Agt Div-III Second
Circle
Minority
Welfare
Construction of Nazrul Chatrabash-PH-II/Balance work Special Assistance 328.00                     Tender(4th call) under scrutiny and will be finalised on accord of sanction         0.000 0.000 0.000 0.000 0.000         ₹ 0     Tendering Stage    
115 Amarpur Third
Circle
Proposed construction of School Building at EK-Jatan Kr. H.S. School at Karbook RD Block, Gomati District, Tripura under PradhanMantri Jan VikasKrayakram (PMJVK) Scheme during the year 2019-20/ SH: Building portion including internal water supply, sanitary installation, sewage and drainage works. PMJVK 250.00 No.F. 3-2/MW/PMJVK/2018-19/1804-10                                                date, 26-07-2019 2021-22 11-08-2021 02-03-2022 ₹ 1,92,99,612 Sri Swapan Datta,Contact No.9436131286 16-03-2022 12-05-2022   12(Twelve Month) 
'15-03-2023
2nd floor both slab   completed, work in progress. Value of work done Rs.1.30 Cr. 0.00 0.00 85% Aug'23 112.50 6.98 105.52 6.98 80.50     fund revelidation submitted on 14-10-2022 but yet not received till date ₹ 1,30,00,000 ₹ 62,99,612 02-03-2022                               Memo No.F. F.TC/5/EE/PWD/AMP/11044-59   In progress    
116 Sonamura Fourth
Circle
Proposed constn of school Building at UNC School  under PMJVK PMJVK 250.00 No.F. 3-2/MW/PMJVK/2018-19/4127-36, Dated 16-12-2019 2019-20 DNIeT No. ACE/Project Unit/ PWD(Buildings)/DNIT/07/2021-22.
Dt……
30-09-2021. ₹ 2,17,46,553 Bishnu Pada Paul
9436519065
15-10-2022 15-10-2022   14-10-2023
Period ?
Work executed upto 1st floor  level. Total value of work done Rs.100.0 Lac     45% Sept-23 0.000 0.000 0.000 0.000 0.000       ₹ 1,00,00,000 ₹ 1,17,46,553 Vide No.F.10(30)/EE/SNM/PWD/9642-55 Dt.30-09-2021.   In progress    
117 Proposed constn of school Building at Sovapur  School  under PMJVK PMJVK 250.00 No.F. 3-2/MW/PMJVK/2018-19/4127-36, Dated 16-12-2019 2019-20 DNIeT No. ACE/Project Unit/ PWD(Buildings)/DNIT/06/2021-22.
Dt………
11-11-2021. ₹ 2,07,92,416 Tapash Datta
9612092053
26-11-2022     25-11-2023
12 Months
Clear site is not handed over by the school authority still now.         0.000 0.000 0.000 0.000 0.000     Clear site is not available.   ₹ 2,07,92,416 Vide No.F.10(30)/EE/SNM/PWD/10672-85 Dt.11-11-2021.   In progress    
118 Proposed constn of school Building at Baniacherra  School  under PMJVK PMJVK 250.00 No.F. 3-2/MW/PMJVK/2018-19/4127-36, Dated 16-12-2019 2019-20 DNIeT No. ACE/Project Unit/ PWD(Buildings)/DNIT/05/2021-22.
Dt…….
30-11-2021. ₹ 2,19,51,923 Kanu Lal Saha
8575354399
15-12-2022 19-01-2023   14-12-2023
12 Months
Foundation work is in progress. Work suspended by the agency.     1% Dec-23 0.000 0.000 0.000 0.000 0.000         ₹ 2,19,51,923 Vide No.F.10(30)/EE/SNM/PWD/11068-81 Dt.30-11-2021.   in progress    
119 LTV Fifth
Circle
Proposed constn of school Building at Annadhan School  under PMJVK PMJVK 250.00 No.F.3-2/MW/PMJVK/2018-19/4145-52 dated.1/12/2019 for an amount of 250.00 lakhs 2019-20. 24-06-2021 09-11-2021. ₹ 2,36,99,414 Avinash Kumar 7903703109 24-11-2021. 24-11-2021. No delay 23-11-2022.
12 months
Structutal work completed, now brick works in progress & 190.00 lakh Not required Not required 80% Sept-23 125.000 125.000 0.000 112.500 125.000 Delay occurred due to Covid. No & delay occurred due to Covid. Fund required ₹ 1,25,00,000 ₹ 1,11,99,414     In progress    
120 Kailashahar First
Circle
PWD Construction of building for Kailashahar, PWD(R&B) Division and Sub-Division office at Kailashahar,Unakoti District Special
Assistance
308.00   2017-18 10-03-2022 31-10-2022 ₹ 3,08,55,924 Salil Acharjee
7308686797
14-11-2022 14-11-2022   13-05-2024
Period ?
18 Months
Work suspended by the agency. Show cause notice issued on 16/05/2023. File to be processed for rescind the work  0% 0% 2% May-24 200.000 31.430 168.570 31.430 108.000         ₹ 3,08,55,924 F.29(16)EE/KLSD/7329-44 dt 31/10/22 Fund Surrendered Rs 100.00 Lakh In progress    
121 Agt Div-III Second
Circle
Construction of Community Hall at Madhya Bhubanban, Barjala under 4-Barjala Assembly Constituency, West Tripura SJTNY 234.00 A/A & E/S for Rs.234.00 Lac under SJTNY 2022-23 vide memo No.F.16(1)-PWD(W)/2018/ Dated 9/3/23 of the F.O to CE, PWD (R&B) for Rs. 234.00 Lac 2022-23 24-04-23               Tender under scrutiny                                 Tendering Stage    
122 Agt Div-I
&
Agt Div-V
Second
Circle
Improving Earth Quake resileny of Masonry lifeline building in Tripura
a) Retrofitting: 4 Buildings
b) Constn. Of TDU
CSS 205.00         ₹ 2,41,65,000           Work in progress.
a) Retrofitting: 4 Buildings (Progress) 90%
b) Constn. ff TDU: Will be taken up shortly
      May'23     0.000         LoA issued on 13/3/2023 for b.   ₹ 2,41,65,000     In progress    
123 Agt Div-III Second
Circle
Construction of Office building (B+G+14 storied) for accomodation of different State Government offices in a complex Special
assistance
12600.00 1(13)/CE(buildings)/2692-2724 dt.11.03.2022    Public Works Deptt 2021-22 20.01.2022 06.09.2022 ######### Engineering Projects (India) Ltd 27.09.2022 11.01.2023   915 days
24.03.2025
Preliminary Survey work & Soil testing are completed. Layout plan to be finalized.  The revised architectural drawing sent to the higher authority for scrutiny and the agency has been requested to submit detailed PERT network. 0 0   Mar-25 51.450 51.450 0.000 0.000 3000.000         ₹ 1,06,48,08,225   Fund Rs. 950.00 Lac has been surrendered by the EE, Div-III and communicated to the CE, PWD vide letter No.F. 8-16/EE-III/PWD(R&B)/10288-92 Dated 13-03-2023. Not yet started    
124 Udaipur Third
Circle
Proposed constructon of the SE (D.W.S) and SE(W.R.) including Conference Hall of PWD office Complex at Udaipur, Gomati District, Tripura. Special AssistanceCapital 1193.00 A/A & E/S: Vide Memo No.F.16(1)-PWD(W)/2018 dated 09/03/2023  of the F.O, PWD(R&B) for Rs. 1105.00 Lakh undder 4059-Special Assistance -Capital. 2022-23 04.08.2022 28-03-23 ₹ 10,19,35,279 Sri Jiban Kumar Saha. M-9436122376 02.04.2023   Delay due to Demolishing of old existing structure 24 Month
'14-04-25
Original work is to be started soon. Demolishing of old existing structure is in progress.       April'25 50.000   50.000   400.000     LOA Issued dt. 18/3/2023   ₹ 10,19,35,279     Not yet started    
125 Third
Circle
Jamjuri Adarsha Gram Prokolpo/S.H:Constn of 2(two) nos welcome gates and construction of 01(one) No passenger shed. Special
assistance
131.00 A/A & E/S received vide memo No.F. 1(10)/PCD/PF/FIN/2021/194-216 Dated 29/12/21 of the Secretary, Planning (P&C) Department. 2021-22 29.03.2022 15.07.2022 ₹ 1,02,45,000 Sri Sajal Karmakar. M-8787437039 30.07.2022     Date
06 Month
Alternative proposal as per demand of public and local panchayet samitee is under consideration             0.000   0.000     One file processed to higher authority with alternate proposal as per demand of public and local panchayet samitee.   ₹ 1,02,45,000     Not yet started    
126 Bishalgarh Fourth
Circle
PWD Construction of Divisional office Building (G+2 storied with foundation provision for G+4 storied) of PWD (R&B) at Bishalgarh, Sepahijala District, Tripura Special
assistance
572.00 No.F.16(1)-PWD(W)/2018, Dated-15/12/2022
(Rs. 200.00 Lac allocated  by Finance Deptt under Special Assistance)
2022-23 PNIeT No 46/EE-BSLD/PWD(R&B)/2022-23, Dated-21/12/2022. Buildings)/PWD/DNIT/ACE/Project Unit/90/2022-23 02-05-2023 ₹ 3,19,63,100 Sri Badal Paul, M-9862733424 17-05-2023     600 Days
(22.12.2024)
Clear site handed over to the Agency, but the work not yet started         88.000 0.000 88.000 0.000 0.000     The received fund of Rs 88.00 Lakh not been able to utilize in this financial year   ₹ 3,19,63,100     In progress    
127 Gondatwisa Fifth
Circle
Infrastructural Development of Gandacherra Sub-Division, Dhalai District / 1000 seated capacity Auditorium Special
assistance
1352.00 1(10)/PCD/PF/SCA (united)/2015-16 dated 27/02/2015 2015-16   20-10-2016 ₹ 8,93,29,000 M/s NG Battacharjee Con Com
9436123651
05-11-2016 27-02-2017   21 month
'05-09-2018
Main building completed and IE works started. External connection yet to be executed. Internal road work in Progress. Total value of work done Rs.701.60 Lac 80% 90% 90% August'23 1566.930 1565.960 0.970 1565.960       Fund Rs. 267.21386 Lac suballocated by FO, PWD(R&B) on 9-2-23 for Qtr,Auditorium and Rev Bunglow ₹ 7,01,60,000 ₹ 1,91,69,000     In progress    
128 Infrastructural Development of Gandacherra Sub-Division, Dhalai District / Construction of Revenue Dak Bungalow Special
assistance
462.00 1(10)/PCD/PF/SCA (united)/2015-16 dated 27/02/2015 2015-16   31-12-2021 ₹ 2,82,18,000 Rajib
Prasad
8119003215
15-01-2022 16-01-2022   06 month
'15-07-2022
Building finishing work in progress. Total value of work done Rs.215.38 Lac 50% Tender under acceptance 90% Aug'23 0.000           ₹ 2,15,38,000 ₹ 66,80,000     In progress    
129 Capital Complex Project
Unit
Construction of composite building for accommodation of different officers of PWD at Capital Complex, Khejurbagan , Agartala/ Construction of internal road , boundary wall, protection walletc. in/c works of lower ground floor & upper ground floor for completion of the building /Phase-II                Special
assistance
1406.00 No.F.16(1)-PWD(W)/2011  dtd 12-09-2013 for 14.06 crore 2013-14   26-11-2020 ₹ 5,07,80,000 Arun Kumar Dey 11-12-2020 11.12.2020   18 months
'10-06-2022
Finishing work for building is in progress, road work is also in progress. Total value of work done Rs 350 lakh 10%   90% August'23     0.000   170.000       ₹ 3,50,00,000 ₹ 1,57,80,000     In progress    
130 Capital Complex Project
Unit
Construction of 14(fourteen) nos. new Type-VI quarters and 1(one) no new Type-VII quarter on the land of BRTF handed over to PWD Special Assistance/ SJTNY 2317.58 Approval of P & CNo.1(10)-PCD/SITNY/2022/13-27  dtd 4-1-2023   for Amount Rs.23.17 crores under SJTNY 2022-23
A/A & E/S for Rs. 2317.58 Lac vide memo No.F.16(1)-PWD(W)/2018/ Dated 9/3/23 of the F.O to CE, PWD (R&B)
2022-23   31-05-2022 ₹ 23,20,00,000 Tapesh Ch Debnath 6.06.2022 21.06.2022   720 days
'26-05-2024
i) CS Bunglow:  Structural work completed.
ii) In Type VI(14 Nos)  :- 4 nos F.Floor roof casting completed./1no GF roof casting completed
2 Nos: Ground Floor roof casting is completed/1 no GF roof will be completed very shortly.
5 Nos: Foundation work completed.
2 Nos: Will be taken up.
Upto date Value of work done = 650 Lakh
3%   30% Mar-24 500.000 500.000 0.000 500.000 200.000       ₹ 6,50,00,000 ₹ 16,70,00,000     in progress    
131 Dharmanagar First
Circle
School Education  Construction of Addl. Class rooms (8 nos.), Science lab (3 nos.), Library (1 no), Toilet (2 nos.), Boundary wall (200 mtr) at Bir Bikram Institution, Dharmanagar Division, North Tripura District.
A) Addl Class room
B) B/Wall
Vidyajyoti 417.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton     B) B/Wall: '05-07-2022 B) 2568032 B) Sri Bijoy Saha
9862616440
 B)07-06-2022 B) 08-06-2022   B) 180 Days A) 'Revised estimate under process for addl class room.
B) Boundary wall is in progress, Value of work done Rs 15.00 lac
        0.000 0.000 0.000 0.000 0.000       ₹ 15,00,000 ₹ 10,68,032     In progress    
132 Kanchanpur First
Circle
School Education  Construction of Science lab (3 nos.), Library (1 no.), Toilet (2 nos.), Boundary wall (222 mtr), Cycle stand (1 no.) at Kanchanpur Higher Secondary School.
A) Building
B) Boundary wall
Vidyajyoti 192.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 A) 04/08/2022
B) 25/04/2022
A) 04/11/2022
B) 20/08/2022
₹ 1,43,26,800 A) Sri Rahul Kar
7005530122
B) Sri Swapan Debnath
9612120502
A) 19/11/2022
B) 04/09/2022
A) 19/11/2022
B) 04/09/2022
  A) Jan, 24
15 Months
B) May, 23
8 months
A) 1st floor slab casting completed. Column casting above 1st floor upto lintel level completed.
B) Boundary wall is  almost completed.
Value of work done Rs. 56.00 Lakh
    A) 41%
B) 93%
A) Jan,24
B) May, 23
200.000 200.000 0.000 200.000 460.660       ₹ 56,00,000 ₹ 87,26,800     In progress    
133 Construction of Addl. Class rooms (2 nos.), Science lab (3 nos.), Toilet (2 nos.), Boundary wall (200 mtr), Cycle stand (1 no.) at Satnala H.S. School.
A) Building
B) Boundary wall
Vidyajyoti 248.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 A) 30-06-2022
B) 25/04/2022
A) 26/10/2022
B) 20/08/2022
₹ 1,95,42,800 A) Sri Chiranmay Paul Choudhury
9435079593
B) Sri Swapan Debnath
A) 10/11/2022
B) 04/09/2022
A) 10/11/2022
B) 04/09/2022
  Bld.- Jan, 24
15 Months
B/Wall-May, 23
8 Months
A) Structural work completed. Brick & Plastering work in progress.
Rs.
B)Boundary wall is  almost completed.
Rs. 112.00
    A) 82%
B) 92%
A) Jan, 24
B) May, 23
      ₹ 1,12,00,000 ₹ 83,42,800     In progress    
134 Construction of Addl. Class rooms (1 no.), Science lab (3 nos.), Library (1 No.), Toilet (2 nos.), Boundary wall (200 mtr), Cycle stand (1 no.) at Anandabazar H.S. School.
A) Building
B) Boundary wall
Vidyajyoti 218.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 A) 16/11/2022
B) 20/08/2022
A) 27/03/23
B) 20/08/2022
₹ 1,82,19,758 A) Uday Sankar Barua
9862602385
B) Ahmed Ali
7628882920
A)01/12/2022
B) 04/09/2022
A) 01/12/2022
B) 04/09/2022
  A) Feb, 24
450 Days
B) May, 23
8 months
A) Upto Plinth Beam completed. Work in Progress.
B) Boundary wall is   completed.
Value of work done Rs. 61.00 Lakh
   
A) 7%
B) 100%
A) Feb, 24
B)  Complete
      ₹ 61,00,000 ₹ 1,21,19,758     In progress    
135 Construction of Addl. Class rooms (5 nos.), Science lab (3 nos.), Toilet (2 nos.) at Kanchanpur Govt. Eng. Med. School. Vidyajyoti 266.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 30-06-2022 '26-10-2022 ₹ 1,94,45,700 Sri Ranabir Choudhury
8731033229
10-11-2022 10-11-2022   Jan, 24
15 Months
 1st floor slab casting completed. Fft. Binding for 2nd floor slab in progress.
Rs.73.00 Lakh
    55% Jan, 24       ₹ 73,00,000 ₹ 1,21,45,700     In progress    
136 Construction of Anandabazar  H.S.School Building at Dasda Block,Kanchanpur RIDF-XXV 720.00 No.NB.TRIP/01/56th ISC/PLAN50(XXV)/2019-20 dated 24/03/20 2019-20 18-08-2016 03-02-2017 ₹ 5,31,60,200 M/S Chittaranjan Saha & Others
7005224155
18-02-2017 18-02-2017   Jan, 19
24 months
Work in progress.
Value of work done Rs.275.00 Lakh
    66% Dec, 23 274.00 274.00 0.000 274.00 257.602     Work is in progress. ₹ 2,75,00,000 ₹ 2,56,60,200     in progress    
137 Construction of Gachirampara H.S.School Building at Dasda Block,Kanchanpur RIDF-XXV 455.00 No.NB.TRIP/01/56th ISC/PLAN50(XXV)/2019-20 dated 24/03/20 2019-20 18-08-2016 03-02-2017 ₹ 4,03,77,500 M/S Chittaranjan Saha & Others
7005224155
18-02-2017 18-02-2017   July, 2018
18 months
Finishing  work in progress.
Value of work done Rs. 412.00 Lakh
100% Completed. ----- 99% July. 23 403.775 403.775 0.000 403.775 0.000     Work is in progress. ₹ 4,12,00,000 ₹ 0     in progress    
138 Kailashahar First
Circle
a) Construction of Addl. Class rooms (6 nos.),Toilet (2 nos.),
b) Boundary wall (250 mtr) at Bhagini Nivedita Girls H.S. School, Kailashahar.
Vidyajyoti 248.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 a) 05-09-2022
b) 11-05-2022
a)17-11-2022
b)21-06-2022
₹ 1,74,83,501 a) Siddhartha Dey
9436908670
b) Gopal Das
9436474437
a) 01-12-2022
b) 05-07-2022
a) 01-12-2022
b) 05-07-2022
  a) 27-08-2023
270 days
b) 02-10-2022
Period ?
270 days
Building:- Constn of roof is in progress.

Boundary wall:   120 m completed.
Approx value of work done Rs.42.00 Lac
a) 0%
b) 0%
a)0%
b) 0%
a) 10%
b)50%
a) Aug'23
b) June-23
40.000 40.000 0.000 40.000 0.000   Not required   ₹ 42,00,000 ₹ 1,32,83,501 a)F.25(16)/EE/KLSD/7806-21 dt 17/11/22
b)F.25(16)/EE/KLSD/4035-50 dt 21/6/22
  In progress    
139 a)Construction of Addl. Class rooms (4 nos.), Science lab (3 nos.), Toilet (2 nos.),
b) Boundary wall (300 mtr) at Netaji Vidyapith Eng. Med. H.S. School, Kailashahar
Vidyajyoti 285.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/05/22 of the Jt. Secretary, Secondary Educaton 2022-23 a) 06-12-2022 a) 13-03-2023 ₹ 2,43,89,865 a) Arun Kanti Chanda a) 27-03-2023 Not started   a) 16-04-2024
Period ?
400 Days
a) .Foundation  Work is in progress. Value of work done-5.00 Lac     2% a) Apr-24 0.000 0.000 0.000 0.000 0.000       ₹ 5,00,000 ₹ 2,38,89,865 F.25(65)/EE/KLSD/9484-99 dt 13/3/23   In progress    
140 a) Construction of Addl. Class rooms (5 nos.), Science lab (2 nos.), (7th Call)
b) Boundary wall (200 mtr),
c) Cycle stand (1 no.) at Tilabazar H.S. School, Kailashahar
Vidyajyoti 248.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 a) 23-12-2022
b) 21-03-2022
c) 21-03-2022
a) '12-04-23
b) '12-05-2022
c)'12-05-2022
₹ 1,84,53,289 a) Nripendra Ch Mandol & Compancy
7002585904

b) Yeazid Ali
8414047226
c) Yeazid Ali
8414047226
a) '26-04-23
b) 26-05-2022
c) 26-05-2022
a) Not started
b) 26-05-2022
c) 26-05-2022
  a) 19-02-24
300 Days
b) 25-08-2022
90 Dyas
c) 25-07-2022
60 Days
a) Foundation Work is in progressr for ACR
b&c) 95% for Boundary wall and Cycle stand.
Approx value of work done Rs.28.5Lac
0% 0% a) Nil
b) 100%
c) 100%
a)  Feb-24 40.000 40.00 0.00 40.000 0.000       ₹ 28,50,000 ₹ 1,56,03,289 a) No.F.31(496)/EE/KLSD/952-67 dt 12/4/23
b)No.F.31(473)/EE/KLSD/908-23 dt 12/5/22
c)No.F.31(474)/EE/KLSD/892-907 dt 12/5/22
  In progress    
141 School Education  Construction of Academic and Administrative Block for DIET at Kailashahar Samagra siksha 946.00 No.F.8(2-3)-SE/PLAN/2014 dt 23-12-2014 2014-15 22-08-2015 09-03-2016 ₹ 5,64,54,959 Binode Behari Das
9436583679
23-03-2016 02-04-2016 Due to change in Drawing and design  22-03-2018
Period ?
24 Month
Work rescinded on 28/04/2023 under risk & cost to the agency.. Balance work estimate in progress 30% 0% 65%   901.540 601.540 300.000 601.540 0.000     Work suspended. Proposal sent for recession to the Administrative Department. Approx value of work done Rs.523.00 Lac. Now, Work rescinded. Balance work estimate in progress ₹ 5,22,86,000 ₹ 41,68,959 F.25(57)EE/KLSD/6873-92 dt 09/03/2016   Rescined    
142 Proposed construction of Dalugoan H.S. School, Kailashahar, Unakoti District under RIDF. RIDF-XXVII 867.00 NO.F.8(1-42)/SE/PLAN/2021-22 (L)  dated 17/12/2021 of the Jt Secretary Decondary Education. (RIDF-XXVII) 2021-22 23-05-2022 27-10-2022 ₹ 7,00,86,788 Dipak Nag
9436123542
10-11-2022 10-11-2022   01-07-2024
Period ?
600 Days
Work completed upto tie beam. Work is in progress.
Approx value of work done Rs 40.00 Lakh
0% 0% 6% July 24 218.180 0.000 218.180 0.000 482.690   Not required   ₹ 40,00,000 ₹ 6,60,86,788 F.25(24)/EE/KLSD/7290-7305 dt 27/10/2022 Fund Surrendered Rs 218.18 Lakh vide letter No.F.8-1/EE/KLSD/9564-66 Dt.16-3-23 In progress    
143 Kumarghat Infrastructure development of Pecharthal H,S,School,Pecharthal,Unkoti District NESIDS 867.00 A/A: No.F. 8(1-42)-SE/PLAN/2021-22 (L) Dt. 17/12/21 of theJt Director, Secondary Education Rs. 8.67 Crore
E/S No.F.8(1-42)-SE/PLAN/2021-22(L) dated 08/06/22 of the Jt Director, Secondary Education
2022-23 12-07-2022 07-03-2023 ₹ 7,05,27,000 J.C. Nath & Sons
94361 32164
21-03-2023 21-03-2023   690 days
'09-01-2025
Work in progress.  7 Nos   temporary room  nearly completed after shifting to temporary class room demolition of old structure to be started shortly. Value of work done Rs 50.00 Lac 0 0 1% Mar-25 0.000 0 0.000 0.000 0.000     Project delayed in tendering process. ₹ 50,00,000 ₹ 6,55,27,000 No.F.10(178)/EE/KD/9743-57 dated,07/03/2023   In progress    
144 Khowai Second
Circle
Construction of Addl. Class rooms (4 nos.), Science lab (3 nos.), Toilet (2 nos.), Boundary wall (200 mtr) at Khowai Govt. Class-XII School, Khowai Division, Khowai District, Tripura.
A) Building portion
BI Boundary wall
Vidyajyoti 269.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 A) 29-07-2022
B)13-04-202
A) 10-01-2023
B)08-08-2022
₹ 2,38,84,525 A) Pradip Kr. Deb (9366530211)
B) Shyamal Deb (9436538387)
A) 26-01-2023
B) 24-08-2022
A) 05/03/2023.
B) 25-10-2022
Nil A) 365 Days
(25-01-2024)
B) 4 Months
(23-12-2022)
A) Foundation work in progress
B) Boundary wall 95 % completed.
Value of work done?
0% 0% 0% A) Jan'24
B) Completed
13.000 13.000 0.000 0.000 17.000       ₹ 16,55,000 ₹ 2,22,29,525     In progress    
145 Construction of Addl. Class rooms (4 nos.), Toilet (2 nos.), Boundary wall (300 mtr) at Tulashikhar Rajnagar H.S. School, Khowai Division, Khowai District, Tripura.
A) Building portion
BI Boundary wall
Vidyajyoti 205.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 A) 05/04/2023
B) 14-04-2022
B) 08-08-2022 ₹ 52,82,875 Sujan Dey
(9436513028)
24-08-2022 20-10-2022 Nil 180 Days
(23-02-2023)
A) Tendering stage in 3rd call ( under scrunity).
B) Boundary wall completed
Nil Nil B) 100% B) Completed 37.000 37.000 0.000 37.000 17.000     A) 1st call of Tender for class room has been  cancelled  and  now 2nd call of tender has been invited and no bidder found, the 3rd call invited and under scrunity). ₹ 53,82,875 ₹ -1,00,000   1) Req. for fund Rs. 23.90 Lac has been submitted by the EE, KHW vider letter No.F.7(29)/EE/PWD(R&B)/KHW/11493-495 Dt. 14/2/23 In progress    
146 Proposed construction of Paharmura H.S. School, Khowai Tripura under RIDF. RIDF-XXVII 867.00 NO.F.8(1-42)/SE/PLAN/2021-22 (L)  dated 17/12/2021 of the Jt Secretary Secondary Education. (RIDF-XXVII) 2021-22   Nil ₹ 0 Nil Nil Nil   Nil 2nd call of Tender is under scrutiny. DPC meeting held on 6/6/23 0% 0% 0%   218.180 19.000 199.180 0.000 649.000     1st call of tender has been cancelled as per DPC recommendation. Now 2nd call of Tender has been invited and to be opened on 4-4-2023. Tender under scrutiny   ₹ 0     tendering stage    
147 Second
Circle
School Education  Proposed construction of Bharat Sardar Para H.S. School, Khowai Dist, Tripura under RIDF. RIDF-XXVII 867.00 NO.F.8(1-42)/SE/PLAN/2021-22 (L)  dated 17/12/2021 of the Jt Secretary Decondary Education. (RIDF-XXVII) 2021-22 02-07-2022 13-01-2023 ₹ 7,21,94,673 Sajal Datta
(9436512491)
29-01-2023  Nil The concerned department could not yet hand over clear site to PWD, so work could not be  started yet. 600 Days
(12-07-2024)
The concerned department could not yet hand over clear site to PWD, so work could not be  started yet. 0% 0% 0% July'23 218.180 1.371 216.809 0.000 0.000         ₹ 7,21,94,673   1) The EE, KHW requestedto the Director Secondary Education  for handing over clear site by demolishing the existing old schllol building vide letter  No.F.11(09)/EE?PWD/KHW/11826-830 Dt. 9/3/23. In the mean time, PEE has confirmed that construction of temporary class rooms has also been completed. in progress    
148 Teliamura Construction of Science lab (4 nos.), Toilet (6 nos.), Boundary wall (300 mtr) at Teliamura H.S. School, Teliamura Division, Khowai District, Tripura. Vidyajyoti 256.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 i) Boundary wall 05/04/22

ii) School building - 25/08/22
i)
11/08/22

ii) 12/01/23
₹ 2,13,89,236 i)  Sri Manish Bhowmik
8974438561
ii) Sri Haran Ch. Das
9436168447
i) 26/08/22
ii) 27/01/23
i) 26/08/22
ii) Not yet started
ii) Class room not yet started due non handing over of clear site from the concern department.  i) 25/02/23 (6 Months)
ii) 26/11/23
(10 Months)
i) Boundary wall completed except painting.
Ii) Class room not yet started due non handing over of clear site from the concern department. Total value of work done Rs.43.00 Lac
    95% i) July,23 20.000 20.000 0.000 20.000 130.000       ₹ 43,00,000 ₹ 1,70,89,236   1) Req. for fund Rs. 23.90 Lac has been submitted by the EE, KHW vider letter No.F.7(29)/EE/PWD(R&B)/KHW/11493-495 Dt. 14/2/23 In progress    
149 Construction of Addl. Class rooms (5 nos.), Head Master room (1 no), Science Lab (3 nos), Library (1 no.), Toilet (2 nos.), Boundary wall (300 mtr), Cycle stand (1 no) at Kalyanpur H.S. School, Khowai Division, Khowai District, Tripura. Vidyajyoti 367.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 i) Boundary wall 05/04/2022
ii) Cycle stand- 12/04/2022
iii) School building - 01/08/2022
i) 17/06/22
ii) 20/06/22
iii) 08/11/22
₹ 3,28,35,412 i) Sri Nityananda Das
ii) Sri Nityananda Das
iii) Sri Sajal Datta
i) 03/07/22
ii) 05/07/22
iii) 23/11/22
i) 08/07/22
ii) 20/07/22
iii) 12/12/22
  i) 02/01/23
(6 Months)
ii) 04/10/22
(3 Months)
iii) 22/08/23
(9 Months)
 Cycle stand & Boundary wall  completed. Addl. Class room etc in progress. RCC structure completed for 4th block.
Total value of work done Rs.185.00 Lac
    60% iii) Sept,23 55.000 55.000 0.000 55.000 312.000       ₹ 1,85,00,000 ₹ 1,43,35,412     In progress    
150 Second
Circle
School Education  Construction of 100 seated (G+2) girls hostel at  Kalyanpur HS school NESIDS 609.00 No.F.14(54-1)/SE/IT/2021(part-17) dated 28/04/22 2022-23 30-09-2022 '13-01-2023 ₹ 4,61,20,217 Sri Pradip Kr. Deb
9856029969
28-01-2023 10-04-2023 Work could not be started in time  due to non received of structural drawing. 27-07-2024
(18 Months)
Work is in progress. Foundation work completed Total value of work done Rs. 50.00 lakh.     15% July-24     0.000   350.000       ₹ 50,00,000 ₹ 4,11,20,217     In progress    
151 Agt Div-III Construction of Addl. Class rooms (4 nos.), Toilet (2 nos.), Boundary wall (350 mtr) at Maharani Tulsibati Girls H.S. School, Agartala Division No.III, West Tripura. Vidyajyoti 205.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23                 Modified Arch. Drg. at alternate site is to be prepared by Sr. Arch. After getting decision from the Edn. Deptt.         0.000 0.000 0.000 0.000 0.000     Fund Surrendered   ₹ 0   1) Fund Surrendered for Rs. 25.00 Lac vide letter No.F.8-16/EE-III/PWD(R&B)/10294-98 Dt. 19/03/23. Not yet started    
152  Constn. of Addl. Class rooms (8 Nos) , Sc.lab(3 Nos), Computer Lab (1 No), Library ( 1 No) & Toilet (2 Nos) at Umakanta Academy H.S. School, Agartala, under Agartala Division-III, West Tripura  Vidyajyoti 399.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23                 Tender will be accepted after demolision of Old structure by the Education department.         0.000 0.000 0.000 0.000 100.000     Fund Surrendered   ₹ 0   1) Fund Surrendered for Rs. 25.00 Lac vide letter No.F.8-16/EE-III/PWD(R&B)/10294-98 Dt. 19/03/23. Not yet started    
153 School Education  Construction of Kshetra Mohan New English Medium Academy at Agartala, Shantipara, West Tripura SJTNY & Samagra Shiksha 321.00 Administrative approval and Expenditure sanction accored for Rs. 3,21,00,000/- and communicated by the by the Director, Elementary Education & SPD, Samagra Shiksha vide Memo No.F. 1(6-2)/SE/Samagra/Civil/West/2022-23 ( L-II)/5522-29 dated 07/01/2023.
Rs. 1,00,00,000/- ( Samagra Sikhsha under School Education)  & Rs. 2,21,00,000/- from SJTNY.
2022-23 NIeT No.01/EE/Divn-III/PWD(R&B)/23-24 Dt. 06/04/2023               1) 'Tenderis under scrutiny. ( TEC meeting held on 06/06/23) T
2) The SDM,Sadar has been requested to demarcate available land along with approch road.
        0.000 0.000 0.000 0.000 30.000     Estimate is under preparation in Project Unit, PWD , Buildings. ( Geo tech investigation report submitted by EE, Div-III vide letter No.21(211)/EE-III/PWD (R&B)/10488-91 Dt. 16/3/2023.   ₹ 0     Not yet started    
154 Agt Div-V Infrastructure development of Vivekananda High school,West Tripura( Part of Ground Floor & First Floor ) Special
assistance
612.00 No F.8(7-284)-SE/PLAN/2022 dated 23/05/22 2022-23 20 /EE-V/AGT/PWD(R&B)/22-23 Dated  26th   18-05-23 5,27,24,479.28 Sri Tapan Saha 20.05.2023 York yet to start Demolishing of existing structure is required. Reserve price value of old existing structure is under preparation for approval 04.11.2024
(18 Months)
Reserve price value estimate sent to the CE, Building for kind approval after approval of the rate present existing old structire will be demolished by the existing agency and reserve price value will be deposited to the SED. 0.00 N/A 0.00 Nov-2024     0.000   300.000         ₹ 5,27,24,479   Rs. 612.00 Lac is not sufficient for total built up area.therefore, built up area is reduced to keep the amount within sanctioned amount. Correctred drawing sent to the Director, Secondary education.(Ref Letter No.F.13(2)/PWD/ACE/Project Unit/2022/4648-47 Dated 29/11/22 of the SE, PU, Blgd)
Oct ,2022
DNIT No. CE(Buildings)/PWD/DNIT/ACE/Project Unit/68/2022-23
PNIT No.20 /EE-V/AGT/PWD(R&B)/22-23 Dated  26th  Oct ,2022
Work order isued. After demolishing of existing structure, work will be started. Reserved price value will be processed soon for necessary approval by the Competent Authority.

Reserve price value estimate sent to the CE, Building for kind approval after approval of the rate present existing old structire will be demolished by the existing agency and reserve price value will be deposited to the SED.
In progress    
155 Amarpur Third
Circle
Construction of Addl. Class rooms (3 nos.), Library (1 No) , Science lab (3 nos.), Toilet (2 nos.), Boundary wall (200 mtr), Cycle stand (1 no.) at Karbook Panjihum H.S School, Amarpur Division, Gomati District, Tripura.
A)  Addl Class room
B) Boundary wall & Cycle stand
Vidyajyoti 277.00 Modified sanction vide No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 A)   ?
B) '04-12-2022
B) '29-09-2022 ₹ 24,54,945 B) Sri Bijoy Krishna Saha,Contact No.7630041953 B) 15-10-2022 15-10-2022     A) Tender for addl classroom etc to be invited. DNIT issued on 02/06/2023
B) Boundary wall and Cycle stand completed
        40.000 40.17           B) 18-06-2022   08/NIT/EE/PWD/AMP/2022-23.
A) Addl Class room: DNIT issued on 02/06/2023 for Rs. 1,84,00,913/-, Time : 480 Days. DNIT No: ACE/Project Unit/PWD Buildings/DNIT/14/2023-24 Dt. 02/06/23
  ₹ 24,54,945 B) '29-09-2022                        Memo. No.F. TC/5/EE/PWD/AMP/2021-22/8913-27     In progress    
156 Construction of Addl. Class rooms (3 nos.), Science lab (3 nos.), Toilet (2 nos.), Library (1 no), Boundary wall (200 mtr), Cycle stand (1 no.) at Silachari H.S. School, Amarpur Division, Gomati District, Tripura.
A)  Addl Class room
B) Boundary wall & Cycle stand
Vidyajyoti 277.00 Modified sanction vide No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 B) '18-06-2022 B) 29-09-2022 B) 26,10,558.00 B) Sri Bijoy Krishna Saha,Contact No.7630041953 13-10-2022 13-01-2023   13-01-2023                90 day B) Cycle Stand completed.
A) Fund may be utilished for another work of same School (Silachari H.S Balance work ). Decision awaited for T.S estimate and DNIT.
        40.000 0.000 40.000 0.000 28.000     B) NIeT: 18-06-2022   08/NIT/EE/PWD/AMP/2022-23.   #VALUE! B) '29-09-2022                  Memo. No.F. TC/5/EE/PWD/AMP/2021-22/8898-8912   In progress    
157 Proposed construction of  Silachari H.S. School at Silachari, Gomati Tripura./Balance work RIDF-XXV 972.00 No.NB.TRIP/01/56th ISC/PLAN50(XXV)/2019-20 dt24/03/20 (Gap funding . Initial funding from SPA and later on Gap funding by RIDF Rs.500.00 Lac) 2019-20 13-12-2022               Agreement closed.Balance work tender under scrutiny. Revised estimate will be sent for A/A & E/S due to cost overrun.             0.000         1) NIeT : '13-12-2022  50/NIT/EE/PWD/AMP/2022-23.
2) Balance work tender under scrutiny
  ₹ 0     tendering stage    
158 Proposed construction of new double storied school building at Ampinagar H.S. School, Gomati District under RIDF. RIDF-XXVII 867.00 NO.F.8(1-42)/SE/PLAN/2021-22 (L)  dated 17/12/2021 of the Jt Secretary Decondary Education. (RIDF-XXVII), Rs. 8.67 2021-22 10-08-2022 15/3/2023 ₹ 6,65,66,694 Sri Tapan Chakraborty,Contact No.9436472595 30/3/2023     31-03-2024
700  days
Work just started 0.00 0.00 0.00 Mar,24 0.00 0.00 0.00 0.00 665.67     1) NIeT: 10-08-2022 15/NIT/EE/PWD/AMP/2022-23.
II)  Boundary wall and Cycle stand completed
  ₹ 6,65,66,694 Work order No.F.TC/5/EE/PWD/AMP/20006-23 Dt. 15/3/23   In progress    
159 Udaipur Third
Circle
School Education  Construction of Addl. Class rooms (4 nos.), Science lab (3 nos.), Cycle stand (1 no.) at Kirit Bikram Institution, Udaipur Division, Gomati District, Tripura.
A) Cycle Stand
B) Addl Class room:
Vidyajyoti 215.00 Modified sanction vide No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 A) 29-03-22
B) Addl. Class room: 
A) 10.08.2022 A) 775144.82 Sri Dip Narayan Kar. A) 25.08.2022 23-08-22   A) 22.10.2022
2 Month
A) Cycle Stand completed. B) Tender for additonal class etc invited     a) 100%   0.000   0.000     a)  Cycle Stand completed on 19-09-22 a) No
A) Handed over 23.11.2022
B) DNIT issued on 29/05/2023. Estimated Cost Rs. 1,66,42,061/-. DNIT No/CE/Buldings/PWD/ACE/Project Unit/11/2023-24 Dt. 29/05/23
  #VALUE!     In progress    
160 Proposed construction of Khilpara H.S. School, Udaipur, Gomati District under RIDF. RIDF-XXVII 867.00 NO.F.8(1-42)/SE/PLAN/2021-22 (L)  dated 17/12/2021 of the Jt Secretary Decondary Education. (RIDF-XXVII) 2021-22 11.10.2022     SREE MAA INFRATECH. M-9436131712       24 Month DPC recommended for acceptance of Tender.         218.180 83.000 135.180 83.000 784.000         ₹ 0     Tendering Stage    
161 Constn of double storied school of Jamjuri HS School RIDF-XXVI 795.00 No.F.8(7-230)-SE/PLAN/2016 dated 20.07.2021. Amount : 795.08 Lakh 2020-21 24.09.2021 07.04.2022 ₹ 6,39,46,000 Sri Jiban Kumar Saha. M-9436122376 22.04.2022 13.07.2022 Due to dealy of setting in layout 21.10.2023
18 Month
Roof casting completed for 01(one block. Foundation work completed for rest portion.

Value of work done Rs.1,93,31,784.00
    26% Jan-24 214.670 191.050 23.620 191.050 602.950 Not yet completed. Delayed due to seeting of layout an arrangement of available land     ₹ 1,93,31,784 ₹ 4,46,14,216     In progress    
162 Infrastructure development of South Bagma H.S.school,Tepania,Gomati district NESIDS 867.00 A/A: No.F. 8(1-42)-SE/PLAN/2021-22 (L) Dt. 17/12/21 of theJt Director, Secondary Education Rs. 8.67 Crore
E/S No.F.8(1-42)-SE/PLAN/2021-22(L) dated 08/06/22 of the Jt Director, Secondary Education
2022-23 04.08.2022 28-06-23 ₹ 6,93,93,061 SREE MAA INFRATECH. M-9436131712 31-05-23   Initial delay due to demolision of Old school buildings / structure  by the school authority partly. Date?
22 Month
Work order issued on 28.06.2023 & site handed over.       Mar-25     0.000   0.000         ₹ 6,93,93,061   1)DPC recommended for acceptance of tender on 15/12/2022 and the Admn deptt approved on 1/4/2023. Work will be awarded accordingly very shortly on observing codal formalities. tendering stage    
163 Santirbazar Third
Circle
School Education  Construction of Addl. Class rooms (4 nos.), Science lab (3 nos.), Library (1 no), , Toilet (0 nos.), Boundary wall (200 mtr) at Baikhora Eng. Med. H.S. School. Vidyajyoti 277.00 Modified sanction vide No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 PNIeT- No:- 17/EE/PWD(R&B)/STB/2022-23 dated, 18-07-2022 28-10-2022 ₹ 1,83,93,937 Gatan Datta
9862453230
13-11-2022 08-11-2022 Work started in due time. 270 days
10-08-2023
1 Block roof casting completed and work in progress.
Value of work done= Rs. 55.00 Lakh
yet to start Not Required 45% Dec' 23 30.000 28.200 1.800 0.000 153.940   Yes, required   ₹ 55,00,000 ₹ 1,28,93,937 No.F. 9(3)/EE/PWD/STB/7396-7407   In progress    
164 Infrastructure development of Twaikorma H.S. school,South Tripura Special assistance 498.00 No F.8(7-284)-SE/PLAN/2022 dated 23/05/22 2022-23 PNIeT- No:- 44/EE/PWD(R&B)/STB/2022-23 dated:- 09-01-2023             540days. 2nd call of tender and DPC recommended for acceptance of Tender.          0.000 0.000 0.000 0.000 4.980     2nd call of tender is under scrutiny   #VALUE!     tendering stage    
165 Infrastructure development of Takma Paticharri  High school,Santir Bazar, South Tripura Special assistance 268.00 No F.8(7-284)-SE/PLAN/2022 dated 23/05/22 2022-23 PNIeT- No:- 40/EE/PWD(R&B)/STB/2022-23 dated:- 06-12-2022 18-01-2023. ₹ 2,26,51,617 Shri Sajal Bhattacherjee
( 9774910015)
02-02-23 45000 Initially delayed, Due to MCC wrt. Assembly Election'2023 which held on 16-02-2023 & result declared on 02-03-2023 365 days
01-02-2024
Foundation work in Progress.
Value of work done= Rs. 5.00 Lakh
yet to start Not Required 5% Jan'25 0.000 0.000 0.000 0.000 2.680   Yes, required   ₹ 5,00,000 ₹ 2,21,51,617 No.F. 9(3)/EE/PWD/STB/11734-47   in progress    
166 Infrastructure development of Srikantabari H,S,School,Santirbazar NESIDS 867.00 A/A: No.F. 8(1-42)-SE/PLAN/2021-22 (L) Dt. 17/12/21 of theJt Director, Secondary Education Rs. 8.67 Crore
E/S No.F.8(1-42)-SE/PLAN/2021-22(L) dated 08/06/22 of the Jt Director, Secondary Education
2022-23 PNIeT- No:- 19/EE/PWD(R&B)/STB/2022-23 dated, 20-07-2022 18-01-2023 ₹ 7,18,52,409 Shri Tapan Chakraborty
[7085782033]
02-02-23 15-03-2023 Initially delayed Due to MCC wrt. Assembly Election'2023 which held on 16-02-2023 & result declared on 02-03-2023 690 days
'09-01-2025
Foundation work in Progress.
Value of work done= Rs. 5.00 Lakh
0% Not Required 5% Jan'25 0.000 0.000 0.000 0.000 8.670 In progress     ₹ 5,00,000 ₹ 7,13,52,409 No.F. 9(3)/EE/PWD/STB/11748-61   in progress    
167 Santirbazar Third
Circle
School Education  Proposed construction of Santirbazar H.S. School, South Tripura under RIDF. RIDF-XXVII 867.00 NO.F.8(1-42)/SE/PLAN/2021-22 (L)  dated 17/12/2021 of the Jt Secretary Decondary Education. (RIDF-XXVII) 2021-22 PNIeT- No:- 11/EE/PWD(R&B)/STB/2022-23  dated, 01-06-2022 17-01-2023 ₹ 7,18,33,604 Sanjib Kumar Prasad
9402166076
01-02-2023 19-01-2023 Work started in due time. 540 days
30-12-2025
Work in progress up to plinth level.
Value of Work done= Rs. 80.00 Lakh
Yet to start Not Required 10% Dec' 24 218.180 2.117 216.063 0.000 0.000       ₹ 80,00,000 ₹ 6,38,33,604 No.F. 9(3)/EE/PWD/STB/11550-63   In progress    
168 Belonia Third
Circle
School Education  Construction of Addl. Class rooms (5 nos.), Science lab (3 nos.), Toilet (2 nos.), Boundary wall (200 mtr), Cycle stand (1 no.) at Hrishyamukh EM H.S. School, Belonia
A) Addl. Classroom
B) Boundary wall  
Vidyajyoti 307.00 Modified sanction vide No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 A.35/EE(PWD)/BLN/2022-23, Dt.20.03.23
B 01/EE((P WD)/BLN/2022-23                                     Dt 04-04-2022
A) Tendering stage

B) 21.06.2022 
₹ 31,86,000 B) Amal Majumder
9436518511 
A) Tendering Stage

B) 06.07.2022 
A) Tendering stage

B) 08.07.2022 
A) Due to tendering issue. A) Tendering Stage

B) 01.01.2023
180 Days
A) Addl. Classroom 6th call tender received and under scrutiny.

B) Work completed. (Rs.31.86 lakh).  
B) NA B) NA A. 0%
B.95%
B) Completed 22.500 22.500 0.000 22.500 9.360 B) Final bill not yet submitted   A).Addl. Classroom
 1st call=No bids found.
2nd Call= No bids found.
3rd Call= Single bid found but tender cancelled due to high rate.
4th Call=No bids found
5th Call= Tender invited.
₹ 31,86,000 ₹ 0   1) EE, BLN placed req for Rs. 82.00  Lac vide letter No.F.5(11)/EE/PWD/R&B/DIVN/8117-18 Dt. 7/2/23 to the Director, Secondary edn. B) Work completed    
169 Belonia Third
Circle
School Education  Construction of Addl. Class rooms (4 nos.), Science lab (3 nos.), Library (1 no.), Toilet (2 nos.), Boundary wall (300 mtr) at B.K. Institute, Belonia.
A) Addl. Classroom
B) Boundary wall  
Vidyajyoti 315.00 Modified sanction vide No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 A.10/EE(PWD)/BLN/2022-23 Dt.29.06.2022
B 01/EE((P WD)/BLN/2022-23                                     Dt 04-04-2022
A) 29.11.2022

B) 17.06.2022 
₹ 2,50,62,000 A) Biijan Bhuiyan9436502419

B) Swapan Debnath
9436526243 
A) 14.12.2022

B) 02.07.2022 


B) 02.07.2022 
A) Due to demolishing of existing old school building within the proposed area of nes construction.
B) For non-handing over of Clear working site for boundary wall by the School authority
A) 08.11.2023
330 Days

B) 28.12.22
180 days
A) Casting of plinth beam is completed & work is in progress Rs.50.00 lakh

B) 125.00 Mtr completed. For balance portion site yet to be handed over fully by the School authority
Rs.15.00 lakh
Not yet NA A. 2.5%
B.75%
A) Dec.23

B) Aug 2023
14.00 12.000 2.000 12.000 236.620     Site handed over for Addl. Classroom. Work will be started very shortly ₹ 1,15,00,000 ₹ 1,35,62,000 A) No.F.7(20 )Pt-I/EE(PW D)/BLN/DIV N/6101-10 Dt.29.11.2022

B) No.F.7(20 )Pt-I/EE(PW D)/BLN/DIV N/1721-29 Dt.17.06.22 
  In progress    
170 Belonia Third
Circle
School Education  Construction of Addl. Class rooms (4 nos.), Science lab (3 nos.), Library (1 no), Auditorium (1 no), Toilet (2 nos.), Boundary wall (300 mtr) at Belonia Govt. Eng. Med. H.S. School.
A) Addl. Classroom
B) Boundary wall  
Vidyajyoti 403.00 Modified sanction vide No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 A.07/EE(PWD)/BLN/2022-23 Dt. 07.06.22
B 01/EE((P WD)/BLN/2022-23                                     Dt 04-04-2022
A) 04.11.2022

B) 14.06.2022 
₹ 3,29,46,000 A) Sankar Kanti Saha 9436124030

B) Bijan Bhuiyan
9436502419 
A) 19.11.2022

B) 29.06.2022 
A) 02.12.2022

B) 29.06.2022 
Works commenced in time A) 18.11.2023
365 Days

B) 25.12.2022
180 Days
A) Centering shuttering and reinforcement binding of roof slab is completed except hall room portion and will be casted shortly
Rs.120.00 lakh

B) Boundary wall Completed except main gate due to fixation of formation level of NH108(A).
Rs.36.86 lakh
A) Not yet for Addl. Classroom etc.

B) NA
  A.30%
B.98%
A) Dec.23

B) Aug 2023
91.50 91.50 0.00 91.50 201.00     For boundary wall work almost completed ₹ 1,56,86,000 ₹ 1,72,60,000 A) No.F.7(20 )Pt-I/EE(PW D)/BLN/DIV N/5312-21 Dt.04.11.22

B) No.F.7(20 )Pt-I/EE(PW D)/BLN/DIV N/1661-69 Dt.14.06.22 
1) EE, BLN placed req for Rs. 46.00 Lac vide letter No.F.5(11)/EE/PWD/R&B/DIVN/8117-18 Dt. 7/2/23 to the Director, Secondary edn. In progress    
171 Belonia Third
Circle
School Education  Construction of Science lab (3 nos.), Boundary wall (200 mtr), Cycle stand (1 no.) at Barpathari H.S. School, Belonia Vidyajyoti 130.00 Modified sanction vide No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 01/EE(PWD)/BLN/2022-23                                     Dt. 04-04-2022 15.06.2022 ₹ 26,39,000 Nikhil Majumder
8837237503
30.06.2022 22.08.2022 Work commenced in time 26.12.2022
180 Days
Work almost completed.
Rs.25.00 lakh
NA NA 97% July-23 22.000 17.000 5.000 17.000 4.390       ₹ 25,00,000 ₹ 1,39,000 No.F.7(20 )Pt-I/EE(PW D)/BLN/DIV N/1670-78 Dt.15.06.22  1) EE, BLN placed req for Rs. 22.00  Lac vide letter No.F.5(11)/EE/PWD/R&B/DIVN/8117-18 Dt. 7/2/23 to the Director, Secondary edn. In progress    
172 Mohanpur Fourth
Circle
School Education  Proposed construction of Gandhigram H.S. School, West Tripura under RIDF.  RIDF-XXVII 867.00 NO.F.8(1-42)/SE/PLAN/2021-22 (L)  dated 17/12/2021 of the Jt Secretary Decondary Education. (RIDF-XXVII) 2021-22   16-11-2022 ₹ 6,68,00,000 Tapesh Ch Debnath 01-12-2022 03-12-2022   02-06-2024
Period?
Ground Floor Structural work completed upto roof level.
Value of work done as on reporting date 
    40% June' 24 218.000 218.000 0.000 0 6.49     UC will be submitted shortly   ₹ 6,68,00,000     In progress    
173 Mohanpur Fourth
Circle
School Education  Infrastructure development of Madhu Chowdhury Para H.S. school,West Tripura, Mohanpur, West Tripura ( RIDF-XXVIII RIDF-XXVIII 399.00 No.F.8(2-7)- SE/PLAN/2019 -20 dated 07.12.2022 of the Additional Secretary to the Govt. of Tripura. 2022-23 PNIT No: 86/EE/MNP/PWD        (R&B) dt: 05.01.23   ₹ 3,26,43,899 M/S Swapan Ch Dey         Tender accepted             0.000         Tender accepted.
DNIT approved for Rs. 2,97,00,572/- on 22/12/22.2nd call Tender has been sent to the authority for approval on 27.02.2023.
  ₹ 3,26,43,899     Tendering Stage    
174 Mohanpur Fourth       Circle School Education Infrastructure development of Gopal Nagar  H.S. school,West Tripura/Constn. Of new double storied school building RIDF- XXVIII 399.00 No.F.8(2-7)- SE/PLAN/2019 -20 dated 07.12.2022 of the Additional Secretary to the Govt. of Tripura. 2022-23 PNIT No: 80/EE/MNP/PWD(R&B) dt: 23.12.22               Tender in 2nd call is under scrutiny.                       Tender has been sent to the authority for approval on 06.01.2023.         Tendering Stage    
175 Mohanpur Fourth       Circle School Education Infrastructure development of Tarapur  H.S. school,West Tripura/Constn. Of new double storied school building RIDF- XXVIII 399.00 No.F.8(2-7)- SE/PLAN/2019 -20 dated 07.12.2022of the Additional Secretary to the Govt. of Tripura. 2022-23 1st Call:
'20-03-23
              Tender accepted on 23/06/2023                       1) DNIT issued on 16-03-23 for calling of tender.PNIeT No 89/EE/MNP/PWD (R&B)/2022-23 Dt. 20-03-23. Last date of receipt: 18/04/23. E.Cost: 2,98,05,366/- Time:
2) Tender accepted on 23/06/2023 for Rs. 3,27,26,292/- in favour of Sri Jayanta Saha, Usha Bazar.
      DNIT issued on 16-03-23 for calling of tender.PNIeT No 89/EE/MNP/PWD (R&B)/2022-23 Dt. 20-03-23. Last date of receipt: 18/04/23. E.Cost: 2,98,05,366/- Time:  Tendering Stage    
176 Mohanpur Fourth
Circle
School Education  Infrastructure development of Mohanpur H.S. school,West Tripura Special assistance 812.00 No F.8(7-284)-SE/PLAN/2022 dated 23/05/22 2022-23   12.01.2023 ₹ 6,34,00,000 Jayanta Saha 12.01.2023       Construction of temporary class room has just started and completion of these the main building work will be started       July'24               Tender accepted by the CE, PWD, Buildings and communicated to EE, MNP by the SE, PU, Bldg vide letter No F. 5(35)/PC (PD-II)/2022 ( S)/5674-77 Dated 11/1/23. Accepted amount Rs, 6,34,00,200/-, CL XII: 8.50 % above.. Agency: Sri Jayantaq Saha.   ₹ 6,34,00,000     tendering stage    
177 Bishalgarh Fourth
Circle
School Education  Construction of Addl. Class rooms (6 nos.), Head Master (1 no), Science lab (3 nos.), Library (1 no), Toilet (2 nos.), Boundary wall (200 mtr), Cycle stand (1 no.) at Amtali H.S. School. Vidyajyoti 380.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 PNIeT No 06/EE-BSLD/PWD(R&B)/2022-23, Dated-13/05/2022, DNIeT-CE(Buildings)/PWD/DNIT/ACE/Project Unit/04/2022-23 A) 09-09-2022,   B) 09-09-2022,   C) 28-10-2022 ₹ 3,33,42,088 A) Tapan Saha (9436123393), B) Pradip Saha (9862514081), C) Pradip Saha (9862514081) A) 24-09-2022,          B) 24-09-2022,  C) 12-11-2022 A) 24-09-2022,          B) 24-09-2022,                  C )12-11-2022    A) 300 Dyas             (22-07-2023)               B) 120 Days                    (21-01-2023)                  C) 90 Days                           (09-02-2023) A) Building portion Brick work etc  in progress. 70% Work Completed. Rs 189.00 Lakh.
B)  Boundary wall completed,
C) Cycle Stand work completed
Not Started Nil a) 70%
b)100%
c) 100%
July-23 139.000 139.000 0.000 119.000 50.000  (b) 21/01/2023, (c) 09/02/2023     ₹ 1,89,00,000 ₹ 1,44,42,088   1) Requistion placed by the EE, BLG vide letter No.F. 10(11)/EE-BSL/10790-92 Dt. 14/3/23 to the Director , Secondary education for Rs.50.00 Lac.
2) UC submitted for Rs. 119.oo Lac vide letter No.F.10(11)/Pt-VI/EE-BSL/10732-34 Dt. 13/3/23
in progress    
178 Bishalgarh Fourth
Circle
School Education  Construction of Addl. Class rooms (6 nos.), Head Master (1 no), Science lab (3 nos.), Library (1 no), Toilet (2 nos.), Boundary wall (200 mtr), Cycle stand (1 no.) at Surjamani Nagar H.S. School, Bishalgarh Division, Sepahijala District, Tripura. Vidyajyoti 380.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 PNIeT No 06/EE-BSLD/PWD(R&B)/2022-23, Dated-13/05/2022, DNIeT-CE(Buildings)/PWD/DNIT/ACE/Project Unit/05/2022-23 a) 23-09-2022,   b) 24-05-2022,      c) 24-05-2022      ₹ 3,31,57,059 a) Sankar Kanti Saha, (9436124030),
 b) Pradip Saha (9862514081)
a) 08-10-2022,           b) 07-06-2022,                c) 07-06-2022 a) 08-10-2022,           b) 07-06-2022,                c) 07-06-2022   a) 300 Days
(03-08-2023),             b) 120 Days                (05-10-2022)                      c) 90 Days                         (05-09-2022)
A) Building portion Brickwork, Finishing work etc  in progress. 85% Work Completed. Rs 220.00 Lakh
B) Boundary wall completed,
C) Cycle Stand work completed
Not Started Nil a) 85%
b)100%
c) 100%
a) Aug-23 140.000 140.000 0.000 120.000 50.000 (b) 05/10/2022, (c) 05/09/2022     ₹ 2,20,00,000 ₹ 1,11,57,059   1) Requistion placed by the EE, BLG vide letter No.F. 10(11)/EE-BSL/10790-92 Dt. 14/3/23 to the Director , Secondary education for Rs.50.00 Lac
2) UC submitted for Rs. 120.00 Lac vide letter No.F.10(11)/Pt-VI/EE-BSL/10732-34 Dt. 13/3/23
in progress    
179 Bishalgarh Fourth
Circle
School Education  Construction of 100 seated (G+2) girls hostel at  Amtali HS school NESIDS 609.00 No.F.14(54-1)/SE/IT/2021(part-17) dated 28/04/22 2022-23 PNIeT No 40/EE-BSLD/PWD(R&B)/2022-23, Dated-07/12/2022 10-04-2023 ₹ 4,93,43,465 Kashinath Bhattacharjee, M-9436124681 15-04-2023   Initial delay slightly as clear site was not received 540 Days
(05.10.2024)
Foundation Work in progress         0.000 0.000 0.000 0.000 0.000         ₹ 4,93,43,465     Not yet started    
180 Bishramganj  Fourth
Circle
School Education  Construction of 5 Nos. Additional Class room, Cycle stand, B/Wall 200 mtr of SD Memorial H/S School
A) ACR 5 Nos
B) Cycle Stand
C) Boundary Wall
Vidyajyoti 189.00 No. F. 14(54-1)/SE/19/2021(Part-17) dated 23/05/2022 of Joint Secretary, Govt. of Tripura 2022-23 A) 06-09-2022
B) 29-06-2022
C)29-06-2022
A) 01-10-2023
B)06-09-2022
C)06-09-2022
₹ 1,81,64,656 A) Swapan Debbarma , 9862035089
B) Hrishikesh Debbarma
9862361022
C) Khalil Mia
7640947714
A) 25-01-2023
B) 21-09-2022
C) 21-09-2022
A) 25-01-2023
B) 31-10-2022
C) 20-09-2022
  A) 365 days/
24-01-2024
B) 90 Days
20-12-2022
C) 120 Days
20-01-2023
A) Col casting in progress
B) Completed
C) B/Wall Completed.
Value of work done Rs 55.82 Lac
A) 0%
B) N/A
C) N/A
A) N/A
B) N/A
C) N/A
A) Nil
B) 100%
C) 100%
A) 'Oct-23 76.000 39.51 36.490 36.490 113.000     Work in progress. ₹ 55,82,000 ₹ 1,25,82,656     in progress    
181 Sonamura Fourth
Circle
School Education  Construction of Addl. Class rooms (4 nos.), Head Master (1 no), Science lab (3 nos.), Toilet (2 nos.), Boundary wall (250 mtr) at Melaghar Eng. Med. H.S. School.  Vidyajyoti 292.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 34/B/DNIeT/SE-IV/
PWD(R&B)/2022-23.
&
CE(Buildings)/PWD/DNIT/
ACE/Project Unit/14/2022-23.
Dt………….
09-01-2023 ₹ 2,23,75,431 Shri Kanu Lal Saha
(8575354399)
24-01-23 19-01-2023   300 Days
20-11-24
70% boundary wall completed and building work will be started very shortly.
. Value of work done Rs. ……………. Lac
    10% Nov-24 0.000 0.000 0.000 0.000 0.000      CL XII 9.00 % above on SoR2020  ₹ 25,00,000 ₹ 1,98,75,431 Vide No.F.10(30)/EE/SNM/PWD/7455-69 Dt.09/01/2023.   in progress    
182 Sonamura Fourth
Circle
School Education  Construction of Boundary wall (500 mtr), Cycle stand (1 no.) at Boxnagar HS School Vidyajyoti 88.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton 2022-23 33/B/DNIeT/SE-IV
PWD(R&B)/2022-23.
Dt. ……….
24-05-2022 ₹ 7,70,409 Homayan Kabir
7005959683
09-06-2022     09-09-2022 Letter issued for BG against boundary wall,Work order issued for cycle stand But land not available         0.000   0.000             ₹ 7,70,409     Not yet started    
183 LTV Fifth
Circle
School Education  Construction of Addl. Class rooms (9 no.),  Toilet (2 nos.), at Chawmanu H.S. School, L.T. Valley Division, Dhalai District, Tripura. Vidyajyoti 378.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton
Further revised sanction received for Rs.378.00 Lac Lac dt. 12/04/2023, Directore Scl Education.
2022-23 1st Call:
29/05/23
              Bid  opened on 30/06/2023. Two bidders found and tender under scrutiny         0.000   0.000         DNIT Issued on 23/05/23. Estimated Cost Rs.2,72,20,525/-. Bid  opened on 30/06/2023. Two bidders found and tender under scrutiny   ₹ 0     Not yet started    
184 Ambassa Fifth
Circle
School Education  Up-gradation of Infrastructure  of  Chandraipara H. S. School, Ambassa, Dhalai, Tripura under ACA (SPA Tied) during the year 2011-12 (1st Phase)./Balance work SPA Tied 500.00 8(2-7)-SE/PLAN/2011 Dt. 08/09/11 of School Education 2021-22 PNIeT.No:10/EE/PWD(R&B)/AMB/2021-22  Dated: 05-08-2021 27.12.21 ₹ 1,56,09,640 Sujit Ghosh
[ 9436136057]
12.01.2022 18.05.2022 After several persuation a considerable time was spent by the Agency to stat the work without any valid reason. 11.01.2023 Work Completed  Completed  - Completed   500.000 496.050 3.950 496.050 0.000 Completed on 30th June, 2023 and yet to be handed over to concerned Deptt.  Yes
120 Days
Work delayed by the agency. ₹ 5,00,00,000 ₹ -3,43,90,360     In progress    
185 Ambassa Fifth
Circle
School Education  Infrastructure development of Kulai H,S,School, Ambassa/Constn. Of New Double storied school building NESIDS 867.00 A/A: No.F. 8(1-42)-SE/PLAN/2021-22 (L) Dt. 17/12/21 of theJt Director, Secondary EducationRs. 8.67 Crore
 E/S No.F.8(1-42)-SE/PLAN/2021-22(L) dated 08/06/22 of the Jt Director, Secondary Education
2022-23 PNIeT No. 19/EE/PWD(R&B)/AMB/2022-23 Dt. 29/08/2022 17-03-2023 ₹ 7,08,43,397 Shri Tapan Chakraborty
[7085782033]
02-02-2023     700 days
[02-01-2025]
Work yet to be started.Letter issued  to the District Education Officer Dhalai to handover clear siteby the EE, Ambassa on 18/05/23 NIL NIL 0% Jan-25 0.000 0.000 0.000 0.000 708.434     Clear site yet to be handed over by the Education Department. Dismantling of existing school building in progress carried by the education Deptt.   ₹ 7,08,43,397 No.F.17(26)/EE/PWD(R&B)/AMB/8651-621 Dt. 17/03/23 LoA issued to Sri Tapan Chakraborty, Contractor (Mob: 7085782033) vide letter No. F.17(26)/EE/PWD(R&B)/AMB/7660-71 Dt. 12/01/2023 of the EE, Ambassa, R&B. Tendered amount Rs. 7,08,43,397/- Cl XII: 4.99 % above on , Time for completion 700 days. Not yet started    
186 Kamalpur Fifth
Circle
School Education  Construction of Addl. Class rooms (8 nos.),  Toilet (2 nos.), Boundary wall (555 mtr),  at Kamalpur Govt. Eng. Med. H.S. School, Kamalpur, Dhalai District, Tripura. Vidyajyoti 540.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton
Further revised sanction received for Rs.540.00 Lac dt. 12/04/2023, Directore Scl Education.
2022-23 PNIeT No.: 03/EE/PWD(R&B)/KMP/DIV/2023-24, dated, 21-06-2023               Tender invited on 21-06-2023 & last date of online bidding 20-07-2023 0.000 0.000 0.000   0.000 0.000 0.000 0.000 0.000 Nil Nil Date of opening of Tender 21-07-2023   ₹ 0     Not yet started    
187 Gondatwisa Fifth
Circle
School Education  Construction of Addl. Class rooms (9 nos.), Science lab (1 nos.),HM room-1 No, Smart Class-1 No, Staff room-1 No Toilet (2 nos.), at Ananda Roaja Memerial Govt. Eng. Med. High School, Gandatuisa Division, Dhalai District, Tripura. Vidyajyoti 562.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton
Further revised sanction received for Rs.562.00 Lac dt. 12/04/2023, Directore Scl Education.
2022-23 Please fill up the column               Single Tender is under scrutiny.         0.000   0.000             ₹ 0   DNIT Issued on 02-05-23 tendering stage    
188 Gondatwisa Fifth
Circle
School Education  Construction of Addl. Class rooms (8 nos.), Science lab (1 no.), Toilet (2 nos.),Smart Class-1 No. Staff Room, Auditorium-1 No  at Raishyabari Eng. Med H.S. School, Gandatuisa Division, Dhalai District, Tripura. Vidyajyoti 430.00 Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton
Further revised sanction received for Rs.430.00 Lac dt. 12/04/2023, Directore Scl Education.
2022-23 02/EE/PWD (G)/(R&B)/GNT/2023-24 Dt. 03-05-2023                In the 1st  & 2nd call no bidder participated the tender. 3rd call will be floated very shortly.                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                      0.000   0.000             ₹ 0     Not yet started    
189 Gondatwisa Fifth
Circle
School Education  Construction of 100 seated (G+2) girls hostel at  Raishabari English MediumHS school (NESIDS) NESIDS 609.00 No.F.14(54-1)/SE/IT/2021(part-17) dated 28/04/22 2022-23 28/EE/PWD(R&B)/AMB/2022-23
Dt. 28-10-2022 
24-05-23 ₹ 4,83,30,267 Tapan Chakraborty
(7085782033/9436472595)
09-06-2023 09-06-2023   17 Months 25 days (540 days)
04-12-2024
Work order issued. Work in progress.
Plz give Value of work done (Approx): 
    3% Dec'24     0.000             ₹ 4,83,30,267     In progress    
190 Kumarghat First
Circle
SC Welfare Construction of 50 seated SC Girl's Hostel (G+1)at Pabiacherra H.S School BJRCY 286.00 No.F.5-1(P-I)/SCW/PLG(HOSTEL)/BJRCY/2019/9057-80 dated 14/09/22 2022-23 26-09-2022 13-01-2023 ₹ 2,56,39,000 Biprojit Chakraborty
70052 27620
28.01.23 06.03.23 Delay in approval of drawing 28.06.24
18 Months
Piling Work in progress . Value of work done Rs 20.00 Lac  letter issued to IE division NA 7% Sept-24 0.000 0.000 0.000 0.000 100.000     Delay in issuance of drawing ₹ 20,00,000 ₹ 2,36,39,000 No.F.10(178)/EE/KD/9023-37 dated,13/01/2023 Tender accepted by the CE, PWD, Buildings and communicated to EE, Kumarghat by the SE, PU, Bldg vide letter No F. 5(35)/PC (PD-II)/2022 ( S)/5795-98 Dated 13/1/23. Accepted amount Rs, 2,56,39,840/-, CL XII: 10.00 % above.. Agency: Sri Biprojit Chakraborty In progress    
191 Amarpur Third
Circle
SC Welfare Construction of 100 seated SC Girl's Hostel (G+1) at Rangamati H.S School CSS 350.00 No.F.5-1(P-I)/SCW/PLG(HOSTEL)/BJRCY/2019/23345-66 dated 25/04/22,  Rs. 3.50 2022-23 30/6/2022 23-11-2022 ₹ 3,03,87,887 Sri Rajib Prasad
Contact No 8119003215
12-08-2022     31/11/2023
450 days
Earth cutting completed, work is in progress. Value of work done Rs. 5.00 Lakh.     10% July,24         303.88     1) NIeT: 30-06-2022 10/NIT/EE/PWD/AMP/2022-23. ₹ 5,00,000 ₹ 2,98,87,887 Work order dated '23-11-2022                Memo. No.F. TC/5/EE/PWD/AMP/11419-35   In progress    
192 Sabroom Third
Circle
SC Welfare Construction of 50 seated SC Girl's Hostel (G+1) at Harina High School(BRJCY) CSS 175.00 No.F.5-1(P-I)/SCW/PLG(HOSTEL)/BJRCY/2019/23324-44 dated 25/04/22 of the Addl Secretary, Welfare of S.C 2022-23 25-07-2022 25-11-2022 ₹ 1,51,13,280 Shri Bishnu Pada Paul
(Mob# 6436519065)
05-12-2022 05-12-2022   365 days
05-12-2023
Finishing work in progress. Value of work done Rs.110.00 Lac Tender under Evaluation   67% Oct-23 87.000 85.730 1.270 45.000 64.130     Overall progress is satisfactory ₹ 1,10,00,000 ₹ 41,13,280     In progress    
193 Sonamura Fourth
Circle
SC Welfare Common facility centre for skill developmentat Baganbari English Medium School  RURBAN 70.00 No.F. 18(103)-DM/SPJ/DEV/RURBAN(FUND)/2020-21/1129, Dt. 07-07-2020 2020-21 DNIeT No. 13/B/DNIe-T/SE-IV/PWD(R&B)
/2021-22.
Dt………………….
12-11-2021 ₹ 1,28,60,145 Asok Roy
9436559127
27-11-2021 02-12-2021   03-12-2022
12 Months
Work upto roof level. Value of work done Rs. 118.00 Lac     90% July-23   94.000 -94.000           ₹ 1,18,00,000 ₹ 10,60,145 Vide No.F.10(30)/EE/SNM/PWD/10720-32 Dt.12-11-2021   In progress    
194 Dharmanagar First
Circle
SW & SE Const. of creation of barrier free environment  under AIC / Dharmanagar court Sugamya Bharat 96.00 No.F.2(112)-SW/DC/2010/Vol-III/PART/5890(6)dt23/03/21 2020-21 08-07-2021 01-09-2021 ₹ 37,73,275 Sri Jagatjyoti Deb & 9612233650 15-09-2021 15-09-2021   14-01-2022
04 Months
Civil work completed. Lift to be installed.
Value of work done Rs. 90.00 Lac
100% 0 95% Aug-23 72.716 49.360 0.000 49.500 23.350       ₹ 90,00,000 ₹ -52,26,725     In progress    
195 Kailashahar First
Circle
SW & SE Const. of creation of barrier free environment  under AIC /  Kailashahar Court Sugamya Bharat 99.00 No.F.2(112)-SW/DC/2010/Vol-III/PART/5890(6)dt23/03/21 2020-21 22-07-2021 16-09-2021 ₹ 56,60,561 Bhaskar Roy
9436907056
30-09-2021 30-09-2021   29-03-2022

180 days
Work in progress.Site for lift handed over to the agency. Work to be started soon.Approx value of work done Rs.26.65 Lac 0% 0% 80% Oct-23 74.770 26.850 47.920 26.850 0.000       ₹ 26,65,000 ₹ 29,95,561 F.31(474)/EE/KLSD/3103-21 dt 16/9/21   In progress    
196 Agt Div-I Second
Circle
SW & SE Const. of creation of barrier free environment  under AIC / for 7 nos. different existing building under Agartala Div-I/Balance work Sugamya Bharat 1041.00 No.F.2(112)-SW/DC/2010/Vol-III/7992268 dt18/03/22 2019-20                 Tender accepted on 18-04-23 and work will be awarded soon.     Mar.23 Balance work estimate to be prepared due to sudden demise of agency and tender is under scrutiny.     0.000             ₹ 0     In progress    
197 Agt Div-III Second
Circle
SW & SE Const. of creation of barrier free environment  under AIC / for 5 nos. different existing building under Agartala Div. No.III Sugamya Bharat 826.00 No.F.2(112)-SW/DC/2010/Vol-III/7992268 dt18/03/22 2019-20 17/EE/Div-III/PWD(R&B)/2019-20, Dt. 05/03/2020 19.03.2021 ₹ 5,28,41,923 Sri Kashinath Bhattacharjee 03.04.2021 15-06-2021 Civil work completed and Lift not yet installed.
 Tender invited and finalised by the EE,Mechanical Division.
09 months /02.01.2022 Civil work 100% completed. Lift to be installed. 80% Tender invited and finalised by the EE,Mechanical Division. 90% Aug-23 345.283 345.283 0.000 345.283 100.000     i)ARDD=Structure & Brick work completed & Plastering work in progress.
ii)TBSE=All structural work completed & Brick work in progress.
iii)Sc & Tech=Roof of 1st floor work  in progress.
Iv)Aranya Bhavan= Ground floor roof casting to be taken up shortly & balance work in progress.
  ₹ 5,28,41,923     In progress    
198 Agt Div-V Second
Circle
SW & SE Proposed Construction for creation of barrier free environment in 14(fourteen) State Government buildings at Agartala for the benefit of persons with Disabilities under the Accessible India Campaign (AIC) during the year 2019-20 / SH:- Construction of Parking bay, Accessible pathway with tactile guiding, Handrails on stair, corridors, Unisex toilet for disable persons etc. for different existing buildings of Ramthakur College, Agartala and Panchayati Raj Training Institute (PRTI) adjacent to SIPARD, Arundhutinagar, Agartala, Tripura(3rd Call).(Agartala Div. No.V) Sugamya Bharat 554.00 Memo No.F.2(112)-SW/DC/2010/Vol-III/792268 dt18/03/22
(Annexure -B)
2019-20
PNIT No. 09/B/EE-V/AGT/PWD/(R&B)/2021-22. dated 03.12.2020
11.06.2021 3,60,86,189.00 Sri Uttam Dey 26.06.2021 03.04.2022 Initial delay for selection of  site  26.03.2022 Civil work in progress and lift to be installed. Work delayed due to approval of tentative deviation. Tendering stage 20% ( Tender procces to Higher authority for Approval) 50% Nov - 23
(Except installation of lift & IE works)
545.000 65.000 480.000 480.000 0      Work was suspended due to non approval of Extra items/ deviation. Very recently approval of deviation communicated to this end on dated , Hence work resumed and now in progress. ₹ 80,00,000 ₹ 2,80,86,189 F.6(360)/EE-V/AGT/PWD/2020-21/976-94 dated 11.06.2021 DNIT No. CE(Building)/PWD/DNIT/ACE/Project Unit/04/2020-21 In progress    
199 Agt Div-I Second
Circle
SW & SE Const. of creation of barrier free environment  under AIC / Agartala Court Sugamya Bharat 361.00 No.F.2(112)-SW/DC/2010/Vol-III/PART/5890(6)dt23/03/21 2020-21                 Work in progress       Sr Architect will be issue drawing  of toilet &lift 0.000 0.000 0.000 0.000 0.000         ₹ 0     In progress    
200 Udaipur Third
Circle
SW & SE Const. of creation of barrier free environment  under AIC / Udaipur court Sugamya
Bharat
75.00 No.F.2(112)-SW/DC/2010/Vol-III/PART/5890(6)dt23/03/21 2020-21 24.08.2021 21.01.2022 ₹ 40,35,000 Sri Ashit Banik. M-9436490187 05.02.2022 21-01-22   04.08.2022
6 Month
Civil work almost completed. Mechanical part to be started now.

Value of work done Rs.40,34,000/-
Work in progress   95% Aug'23 55.500 55.500 0.000 55.500 12.000 31.12.2022. Attributable to the agency. Yes Work Order for installation of lift has been issued by Mechanical Division. ₹ 40,34,000 ₹ 1,000 Agreemt. No. 61/SE-III/EE/UDP-DIVN/UDP/2021-22   In progress    
201 Belonia Third
Circle
SW & SE Const. of creation of barrier free environment  under AIC /  Belonia Court Sugamya
Bharat
112.00 No.F.2(112)-SW/DC/2010/Vol-III/PART/5890(6)dt23/03/21 2020-21 11/EE(PWD)/BLN/2021-22                                     Dt 01-10-2021 14.12.2021 ₹ 97,53,000 Rajib Nandi
9436517634
19.12.2021 01.01.2022   24.09.2022
9 Months
Civil work completed  & lift to be installed.
Rs.97.53 lakh
  Not yet 100% Aug'23 112.880 57.500 55.380 57.500 70.260     Lift installation yet to be done by the Mechanical Division ₹ 97,53,000 ₹ 0     In progress    
202 Agt Div-V Second
Circle
Science & Technology Establishment of Science Park at Vigyan Gram, Tripura NEC 1039.58 Dated 12/2/2021 2020-21 33/EE-V/AGT/PWD(R&B)/22-23 Dated 30th Nov. 2022               4th Call of Tender cancelled by the competent authority on dated 05.06.2023         10.000 0.000 10.000 0.000       4th Call of Tender cancelled by the competent authority on dated 05.06.2023   #VALUE!     Tendering Stage    
203 Kanchanpur First
Circle
Tribal Welfare Constn of 24 nos Qtr RMM School, Kanchanpur/Balance work   567.00 25-17/TW/REIS/2011/7330-337, dated 16-11-2016 of Tripura Tribal Welfarr Residential Educational Institutions Society 2016-17 28.12.2021 28-06-2022 ₹ 4,58,94,000 Sri Chiranmay Paul Choudhury
9435079593
13-07-2022 13-07-2022   18 months
Dec, 2023
Type -I-Finishing work in progress,Type III-Structural work completed. Brick and Plastering work in progress
Value of work done Rs. 215.00 Lakh
    85% Oct, 23 383.000 383.000 0.000 383.000 184.000       ₹ 2,15,00,000 ₹ 2,43,94,000     In progress    
204 Kumarghat First
Circle
Tribal Welfare Re-construction of 50seated  ST Girl's Hostel attached to Pabiacherra H.S.School,Kumarhat MC,Unakoti District(double decker) including boundary wall,inbuilt Supdt.quarter/ Ground Floor & Boundary wall (150 Mtr) Special Assistance Capital 200.00 No.F.22-131/TW/PLG/ENGG/2010-11/68687-68704  dt.23/12/22.
No.F22.298/TW/PLG/ENGG/2022-23/91125-140 dt16/06/22 & 
2022-23 06-01-2023            Initially there was site problem   Tender opened on 19/04/2023  and now tender under scrutiny.( Letter issued to Bidder for submission of shortfall documents)             0.000             ₹ 0     tendering stage    
205 Kumarghat First
Circle
Tribal Welfare Constn of 24 Nos Staff quarters (12 Nos Type-I & 12 Nos Type-III; (G+2): Four unit at each floor attached to Ekalavya Model residential School, Darchawi, Kumarghat Special Assistance Capital 567.00 No F 25-19/TW/RESI/2019-20/7495-508 dt. 18/07/2022 of the Jt Sec, TW 2022-23                 DNIT to be prepared within the earlier sanctioned amount as Phase-I and estimate is under preparation for Phase-II             0.000         1) Revised Preliminary estimate amounting to Rs.867.17 Lac submitted to TW Deptt vide letter No.F.13(2)/PWD/ACE/Project Unit/2022/5855-59 Dt. 16/3/2023 of the SE, Project Unit, for accord of revised A/A & E/S
2) DNIT to be prepared within the earlier sanctioned amount as Phase-I and estimate is under preparation for Phase-II
  ₹ 0     Not yet started    
206 Khowai Second
Circle
Tribal Welfare Re-construction of 50seated  ST Girl's Hostel attached to Baijalbari H.S.School,Padmabil,Khowai District Special
Assistance
200.00 No.F22.298/TW/PLG/ENGG/2022-23/91125-140 dt16/06/24 2022-23 29-07-2022 31-12-2022 ₹ 1,80,23,652 Sarajit Kr. Paul
(9436503533)
15-01-2023    Due to Initial delay in handing over the clear site work could not be started in time.   365 Days
('14-01-2024)
Work just started. 0% 0% 0% May'24 75.000 0.214 74.786 0.000 75.000         ₹ 1,80,23,652   1) The EE, KHW has surrended fund amounting to Rs. 74,78,601/- and requested for revalidation of the same to the Jt. Secretary, TW Deptt. vide letter No.F.7(29)/EE/PWD/KHW/11561-565 Dt. 17/3/23. Rs.21,399/- has been utilised and balance Rs.74,78,601/- is surrendered by the concerned EE vide letter No.F. 7(29)/EE/PWD/KHW/11561-565 dt. 24/02/23.
The Addl Director, TW has taken up the issue with Directore, Sec Edn for issuance of NOC to EE, KHW vide letter No.F. 22-190/TW/PLG/ENGG/2010-11/79923-34 Dt. 24/3/23. 
In progress    
207 Amarpur Third
Circle
Tribal Welfare Re-construction of 50seated  ST Girl's Hostel attached to Silachari  H.S.School,Silachari,Gomati District(double decker) (2nd Call) Special
Assistance
200.00 No.F22.298/TW/PLG/ENGG/2022-23/91125-140 dt10/06/22 of the Joint Secretary  to the Govt. of Tripura, Tribal Welfare Deptt.                  Rs. 2.00 2022-23 08-03-2022 13-01-2023 ₹ 1,59,45,966 Shri Swapan Datta
(Mob No: 
29-01-23     28-01-24
365 Days
Up to tie beam level completed ,work is in progress. Value of work done Rs. 32.00 lakh .     10% Dec'24 75.00 0.000 75.00 0.000 84.46     1) NIeT :03-08-2022    14/NIT/EE/PWD/AMP/2022-23.   ₹ 1,59,45,966 No.F.2-127/BLD/EE/PWD/AMP/2022-23/17127-43 Dt. 13/10/23   In progress    
208 Gondatwisa Fifth
Circle
Tribal Welfare Re-construction of 50 seated  ST Boys Hostel attached to   Jagabandhupara H.S.School,Dumburnagar,Dhalai District. Special
 Assistance
200.00 No.F22.298/TW/PLG/ENGG/2022-23/91125-140 dt16/06/22 2022-23   20-12-2022 ₹ 1,75,77,000 Shri Sumanta Gupta
(9436457880)
04-01-23 07-01-2023   03-01-2024
12 months
Foundation and plinth beam work completed. Column in Progress.
Value of work done (Approx): Rs. 75.00 Lac
    30% June 24 75.000 75.000 0.000 0.000 0.000       ₹ 75,00,000 ₹ 1,00,77,000     In progress    
209 Agt Div-III Second
Circle
Tourism Constn of conference block,wayside Amenities(Cafeteria)in/c site development at Border Ceremony Facility, Akhaura, Agartala Swadesh
Darshan
476.00 Please fill up the columns                   Conference Hall completed upto Ground Floor level and handed over as and  where basis on 04/05/2023         433.000 433.000 0.000 433.000 10.000     Work suspended due to objection of Border Guards Bangladesh    ₹ 0     suspended    
210 Agt Div-I Second
Circle
Tourism Constn of covered gallery with Barrack at Akhaura checkpost. Swadesh
Darshan
314.00                     i) Toilet block=Work completed in all respect.
Ii)General Gallery with Barrack= Foundation work completed & structural work suspended due to objection raised by the BGB.
Iii)VIP gallery=Clear site yet to be finalised due to objection raised by BGB.
Iv) Main Gate/Entrance Gate= Clear site not finalized due to objection raised by BGB.
v) Parking Zone=Work completed.
      Work suspended due to objection of Border Guards Bangladesh  354.430 111.313 243.117 111.313       Rs. 243.117 Lac has already been lapsed.
Handed over in incompleted stage Dated 01-10-2022 (handing over note ofAE, Central-III,Taken over by Er Dipankar Ghosh, Tourism Department)
  ₹ 0     suspended    
211 Udaipur Third
Circle
Tourism Proposed waterfront Development  of Jaganath Dighi PH-II Swadesh
Darshan
787.00 F.2(180)-PI/TT/2016(UDP-II)/Part/201-08, dt.12.04.2021 2021-22 13.05.2020 29.11.2021 ₹ 5,78,54,000 Sri Raja Raw Ghosh. M-8132804119 14.12.2021 14.12.2021 Finalization of ghat location and receiving of drawing. 13.12.2022
12 Month
Boundary wall, drain, foot track, seating arrangement & ghat ( in progress).
Value of work done Rs.4,90,25,000.00
60%   90% Aug-23 787.000 669.950 117.050 669.950 0.000   Yes   ₹ 4,90,25,000 ₹ 88,29,000     In progress    
212 Udaipur Third
Circle
Transport Construction of Motor Stand at Rajarbag, Udaipur,Gomati District/2nd Call Special
assistance
1000.00 E/S: Memo No.F. 18(8)/Trans/2021/751-57 Dt. 10/02/22 of the DS, Transport Deptt for Rs. 10.00 Crore.Administrative appoval vide memo No.F.18(8)-Trans/2021/1303-13 dt14/03/22 of D.S, Transport Deptt.( Fund sub-allocated for Rs. 333.71 Lakh) 2021-22 Ist Call: 16/7/22
2nd Call: '17.08.2022
22-05-23 ₹ 7,89,32,802 Sri Kajal Saha. M-9436490187 11-05-23   Delay due to pending demolision of Old structure by appropripate authority Date?
18 Month
Work will be started after getting clear site from the Client Department.       Dec-24 133.710 0.000 133.710 0.000 0.000         ₹ 7,89,32,802   The EE,UDP has surrendered fund Rs. 333.71 Lac vide his letter No.F./EE-PWD-UDP-DIVN/ACTT-UC-10/10219-22 Dt, 3/3/23 to the Deputy Sectary, Transport  department, since work is not yet taken up. E/S: Dt. 10/02/22 of the DS, Transport Deptt for Rs. 10.00 Crore.A/A 14/03/22 with fund Fund sub-allocattion for Rs. 333.71 Lakh.
Ist Call: 16/7/22 (No Bidder).
2nd call: 17/8/22.
E/Cost: Rs.744.79 Lac. Time : 18 Months. Tendered value: 789.33 Lac. DPC: 2/11/22. Acceptance of Admin Deptt: 21/3/23. Formal acceptance will conveyed very shortly forllowed by issuance of LoA by EE, SNM.
Sri Kajal Saha, Ushabazar, Chinaihani, Agartala, West Tripura, Pin-799009
fAccepted for an amount of `7,89,32,801.60  which is @5.98% (five point nine eight percent) above
the estimated cost of `7,44,78,959.81 put to tender.
Tendering Stage    
213 Jirania Fourth
Circle
Transport Construction of Terminus building for Interstate Truck Terminus (ISTT) at Madhabbari, Jirania, West Tripura /SH: Construction of 1st floor of Terminus building (Vertical extension). NEC 303.00 18(2)-Trans/2003(P-II)/(Vol-X)  dt.23/10/2019 2019-20   17-03-2021 ₹ 2,53,97,179 Sri Mintu Debnath
M-9436126343
01-04-21 01-04-2021   15 month

30-06-2022
Civil completed (245.35 Lakhs). Installation of lift is started 100% 100% 100% Completed 291.5 291.28 0.22 286.80 Nil Civil work:12-12-2022
Mechanical work: 
164 days delay   ₹ 2,45,00,000 ₹ 0     Completed    
214 Institute  of Driving Training & Research at Jirania.

Construction of 2(two) lane approach road at IDTR Jirania

Other Subheads as follows separately
Special Assistance 256.63 No.F.11(3)-Trans/2009(P-17)/4592-99 dt.21/09/2022 of the Deputy Secretary, Transport Deptt. Rs.256.63 lakh 2021-22   25-11-2022 ₹ 2,31,00,060 Sri Josoda Lal Roy 10-12-2022 30-11-2022 - 180 days
08-06-2023
 2(two) lane approach: CD, Protection work, GSB, WMM, Surface course work, Drainage work completed (242.937 Lakhs) Not requied Not requied 100% Completed on 06-06-23 256.63 191.00 0.00 191 51.937 06-06-2023 No  Unspent Rs. 65.63 Lac was surrendered end of F.Y 2022-23  ₹ 2,42,93,700 ₹ -11,93,640     In progress    
214(I)  Construction of Control Room including Sanitary installation etc. Special Assistance 117.00 No.F.11(3)-Trans/2009(P-14)/795-800 dt.10/02/2022 of the Deputy Secretary, Transport Deptt. Rs.117.00lakh 2021-22   29-06-2022 ₹ 22,38,000.00 Sri Bapan Nandi 21-07-2022 28-07-2022 Delay as per memo of Deputy Secretary, Transport vide No.F.11(3)-Trans/2009(P-14)/Part  dt.12/09/2022 17-01-2023
180 Days
Control Room=95% work completed, Roof casted, BW Wall , toilet, grill fittings, completed, flooring,  drainage work, window, door, sanitary installation complete & finishing work in progress. (21.34 Lakhs)   Not requied 95% Aug'23 117.79 21.08 35.54 47.492         ₹ 21,34,000       In progress    
214(II)  Construction of footpath, CC drain   29-06-2022 ₹ 28,38,000.00 Sri Anujit Das 14-07-2022 05-07-2022 10-01-23
180 Days
Footpath= work completed (28.40 Lakhs)   Do 100% Completed 28.40       ₹ 28,40,000            
214(III)  Construction of Observation Room (watch Tower) including sanitary installation etc   29-06-2022 ₹ 25,81,000.00 Sri Suman Debnath 14-07-2022 14-07-2022 10-01-23
180 Days
Observation room= 75% Work completed,  slab and brick work completed for GF and FF. Flooring and Finishing work in progress . (14.55 Lakhs)   Do 75% Aug'23 14.25       ₹ 14,55,000            
214(IV)  Construction of Security Room
including sanitary installation etc (Two Nos)
  18-08-2022 ₹ 30,64,000.00 Sri Raju Das 02-09-22 22-08-2022 01-03-23
180 Days
Security room= 65% work completed, Roof casted, BW Wall , toilet, grill fittings, completed & flooring,  drainage work, window, door, sanitary installation, finishing work in progress. (18.86 Lakhs)   Do 65% Aug'23 18.50       ₹ 18,86,000            
215 Sonamura Fourth
Circle
Transport Construction of Entrance Gate & approach road for Floating Jetty at Srimantapur, Sonamura   24.00 No.F. 34(2)-Trans/2010(Part-2)(L), Dated 09-07-2020 2020-21 20/EE/SNM/PWD/2021
Dt…………….
Vide No.F.10(30)/EE/SNM/PWD/10172-85 Dt.'05-02-2021. ₹ 24,26,110 Gautam Laskar
8416015192
20-02-2021       Site is  not finalized by Land Port Authority.         24.989 0.000 24.989             ₹ 24,26,110 Vide No.F.10(30)/EE/SNM/PWD/10172-85 Dt.05-02-2021.   not yet started    
216 Teliamura Second
Circle
UDD Setting up of Electric cremation furnace at Teliamura Municipal Council in/c Civil,Mechanical works. 15-Finance (Un-tied) 111.00 Rs. 111.23 Lakh
No. 2420-25/F.2(6)/TMC/2017 dt. 13/01/2022 of the Chief Executive Officer, Teliamura Municipal Council.
2021-22 24-02-2022 10-05-2022 ₹ 83,24,647 Sri Haran Ch. Das
9436168447
25-05-2022 25-05-2022   24-02-2023
(9 Months)
Civil,  Mechanical & Internal electrification work completed. External electriication work is in progress. Total value of work done Rs.83.25 Lac 100% 100% 100%   111.000 111.000 0.000 111.000 0.000 25-06-23     ₹ 83,25,000 ₹ -353     Completed    
217 Constn of Teliamura Motor Stand TIIFB 500.00 Rs. 500.00 lakh
Memo No.F. 18(1)-UDD/DUD/DEV/2020/15508-16 dt. 19/01/2022 of the Additional Secretary to the Govt. of Tripura.
2021-22 23-07-2021 26-10-2021 ₹ 4,29,18,220 Sri Prafulla Das
9436135082
10-11-2021 13-12-2021 Delay occurred due to the effect of model code of conduct for Municipal Election. 09-02-2023
(15 Months)
RCC structure completed. Fitting fixing of roofing truss is in progress.
Total value of work done Rs.250.00 Lac. Tubular truss, Roofing and road works are in progress.
0%   65% July,23 200.000 200.000 0.000 200.000 300.000       ₹ 2,50,00,000 ₹ 1,79,18,220     in progress    
218 Agt Div-V 1. Construction of Bus Terminal at Nagerjala, Agartala under NLCPR  ruction of Terminal building,
(ii) Construction of Rehabilitated Shops/SH: Building portion including internal water supply and sanitary installation. 
NLCPR 1668.00 Memo No. 16(1)-UDD/DUD/2006/39669-76 dated 26.03.2014 .
MoDONER/NLCPR
2013-14
PNIT No. 03/B/EE-V/AGT/PWD/2014-15 dated '04.06.2014
29.11.2014 ₹ 6,27,50,221 Arun Kr. Dey 13-12-14 02.11.2015   Clear site could be available in time.  Also NLCPR fund is not in flow.Further works delayed due to pandemic. 13-06-16
18 Months
Work in progress.(Finishing work of terminal buildings)
Internal road GSB: 100%, WBM-II: 100%, WBM-III: 100%,)

Work almost completed @ 95%.
75% N.A 95% Aug-23 1319.27 1319.27 0.000 1288.82 369.000 Delayed as explained . Time extension required for 889 days  Agreement of Arun Kr. Dey was closed.
Balance Work in separate Agreement is in progress.
Name of Agency : Sri Jasoda Lal Roy
Agreement No. 28/B/SE-II/EE-V/AGT/PWD/2022-23
Agreement Value : Rs. 1,89,74,605.60
External Electrification / Sub station work yet to be taken by TSECL authority.
Fund required at present 200.00 lakh urgently.
₹ 15,19,00,000 Rs. 1,70,00,000
(Including IE works)
No.F.6(354)/EE-V/AGT/PWD/5829-46 dated 29.11.2014 DNIT No. CE/PWD/(R&B)/DNIT/SE (Project)/15/2014-15

Project is nearing completion stage. Tentative date of completion is August, 2023, subject to immediate release of fund of 200 Lacs.
Tentative deviation for Rs. 15.00 lakh processed to the competent authority for necessary approval of the Agency, Jasoda Lal Roy for remaining Balance work.
in progress    
219 Construction of Bus Terminal at Nagerjala, Agartala under NLCPR :
Construction of internal road and road side drain , waiting shed and parking area for different types of Vehicle .
NLCPR      
PNIT No. 01/B/EE-V/AGT/PWD/2016-17 dated 02.03.2017
02.03.2017 ₹ 6,07,74,256 Arun Kr. Dey 16-03-17 24.07.2017   Clear site could be available in time.  Also NLCPR fund is not in flow.Further works delayed due to pandemic. 16-06-18
15 Months
                  No.F.6(354)/EE-V/AGT/PWD/6028-45 dated 02.03.2017 DNIT No. CE(Building)/PWD/DNIT/SE
(Project)/81/2016-17

Project is nearing completion stage. Tentative date of completion is August, 2023, subject to immediate release of fund. 
in progress    
220 Santirbazar Third
Circle
UDD Construction of Fish Market at Santirbazar under Santirbazar Municipal Council under Special Central Assistance (SCA- Untied)  SCA (United) 100.00 No F.16(5)/UDD/DUD/2014/8999-9009 dated, 11-11-2016 2016-17 PNIeT- No:- 29/EE/PWD(R&B)/STB/2019-20 dated, 04-02-2020 17-07-2020. ₹ 1,11,29,506 Nikhil Ch. Dey.
9436123287
01-08-2020 17-07-2020 Work started in due time. 15(fifteen) Months
'31-10-2021
Finishing Work in progress
Value of work Done= Rs. 115  Lakh
Yet to start. Separate fund is required for I.E Not Required 95% Oct'23 100.000 100.000 0.000 100.000 11.300   Yes, required   ₹ 1,15,00,000 ₹ -3,70,494 No.F. 9(3)/EE/PWD/STB/2153-66   in progress    
221 Construction of Santirbazar Municipal Council at Santirbazar, South Tripura. URBAN 317.00 No F.16(5)/UDD/DUD/2008/11237-51 dated, 09-01-2014 2013-14 PNIeT- No:- 03/EE/PWD(R&B)/STB/2016-17 dated, '04-06-2016 21-02-2017 ₹ 2,52,70,658 Samir Chakraborty
9436131489
07-03-2017 02-11-2017 Initial delay,  because of clear site which can't handed  over in time by the concerned Dept. 18(eighteen) Months
'06-09-2018
1st floor building finishing. work is in progress.
 Value of work Done= Rs. 230  Lakh
Work in progress Not Required 85% July' 23 252.700 232.470 20.230 174.470 0.000   Yes, required   ₹ 2,30,00,000 ₹ 22,70,658 No.F. 9(3)/EE/PWD/STB/5693-5706   in progress    
222 Belonia Setting up Tertiary Waste Processing Center for Belonia Municipal Council at Baspadua near Municipal Dumping station UDD 149.00 No.F.9(5)-SWM/CEO/BMC/BLN/2020-2021/5940-44 dated,10-02-2021  2020-21 12/EE(PWD)/BLN/2021-22                                     Dt 31-03-2021 28.06.2021 ₹ 1,22,24,000 Amal Majumder
9436518511
13.07.2021 26.07.2021 Due to execution of site development work 08.01.2022
06 Months
Work almost completed.Rs.122.24 lakh. Not yet NA 95% Sept-23 139.000 96.100 42.900 50.000   ------       1) Due to earth cutting work for site development and also delay by the agency.
2) Tertiary waste processing centre agreement work completed. Due to few  additional work tender invited. In all respects the work will be completed and handed over to concerned deptt by September 2023.
₹ 1,22,24,000 ₹ 0 No.F.7(20 )Pt-I/EE(PW D)/BLN/DIV N/1057-69 Dt.28.06.21    in progress    
223 Bishalgarh Fourth
Circle
Const Bishalgarh Municipal Council Office/G.F only with foundation provision G+2 UDD 288.00 F.4(1-1)/BMC/BLG/2014/3293-96 dated 12/09/22 of the CEO, Bishalgarh Mucipal council 2022-23 PNIeT No 31/EE-BSLD/PWD(R&B)/2022-23, Dated-'04/11/2022. DNIeT-CE(Buildings)/PWD/DNIT/ACE/Project Unit/78/2022-23 LoA
'24-03-23
₹ 2,82,95,022 Ashim Kr Saha
9436131061
08.04.2023     300 Days
(01.02.2024)
Clear site not handed over by the  Bishalgarh Municipal Council authority         125.000 0.000 125.000 0.000 0.000     Est Cost: 2,62,55,008/-
Contract value: 2,82,95,022/-. Tender accepted on 14/03/23 by the Department on the recommendation of DPC
  ₹ 2,82,95,022     not yet started    
224 Ambassa Construction of Ambassa Municipal Council office  State Plan 317.00 16(05)-UDD/DUD/ 2008/11237-51 Dt.09/01/14 by the UD Deptt. 2013-14 PNIeT.No: 14/EE/PWD(R&B)/AMB/2021-22  Dated:'24-08-2021 20-01-2022 ₹ 2,26,49,938 Sumanta Gupta
[9436457880]
05-02-2022 04-05-2022 Initial delay in handing over of clear site by the Municiapal Authority  15 months
[04-05-2023]
Final roof Slab casting completed and masonry wall work in progress

Value of Work Done = 130.00 lacs ( approx)
Nil Nil 80% Sept,23 221.000 96.000 125.000 96.000 0.000     Rs. 125 lakh lapsed and  processed for revalidation ₹ 1,30,00,000 ₹ 96,49,938     in progress    
NEW Sonamura   Construction of Sports Complex at Shantinagar H.S School, Sonamura, Sepahijala District, Tripura under RURBAN Mission/SH: Building portion including internal water supply, Sanitary installation, Swerage and Drainage works/2nd Call RURBAN 5.05 No.F.18(103)-DM/SPJ/DEB/RURBAN(FUND)/2020-21/2231, Dt. 21-10-2020. 2020-21 2ndCall:
'12/04/23
              2nd Call of tender  invited on 12-04-2023 and to be opend on 11-05-2023.                               2nd Call: PNIeT No. 01/EE/SNM/PWD/2023-24 Dated 12/04/2023. Last date of receipt: 11/05/2023. Estimated Cost: 3,53,09,782/-Time for completion 365 Days      
NEW   Construction of 16 Nos Staff quarter building at ........... ( Type-1: 6 Nos, One Block, Twin, G+2), (Type-II 6 Nos, One Block, Twin, G+2) and Type-III: 4 Nos, one Block, Twin, G+1) /SH: Building portion including internal water supply, Sanitary installation, Sewarage and Drainage works/2nd Call         2ndCall:
'12/04/23
                                              2nd Call: PNIeT No. 01/EE/SNM/PWD/2023-24 Dated 12/04/2023. Last date of receipt: 11/05/2023. Estimated Cost: 3,94,03,210/-Time for completion 540 Days      
NEW Jirania   Construction of 10 Nos Staff quarter at Ranirbazar Primary Health Centre (PHC) santioned under NHM/ SH:Construction of 6 Nos Type-II quarters (one Nlcok Twin G+2 Storied) for Ranir bazar Primary Health Centre(PHC) at Ranir bazar, West Tripura/ Building portion including water supply, sanitary installation, sewage and Drainage works NHM       1st Call
'12/04/23
              Tender under scrutiny. ( TEC meeting held on 23/6/23)                               1st Call: PNIeT No. 36/EE-JRN/PWD/2022-23 Dated 27/03/2023.       
NEW Dharmanagar First
Circle
Health Construction of office building(G+1 Storied) for Chief Medical Officer ( CMO ) at Dharmanagar, North Tripura/SH: Building portion including internal water supply, sanitary installation, sweage and drainage works State Plan 603.8 No.F.19(538)-PLAN/DFWPM/2013(Sub)/4857-62(V-1)-dated 08/11/2022 of the Deputy Secretary, Govt. of Tripura 2022-23 04-04-2023             450 days Tender under scrutiny.  ( TEC meeting held )                               ( NIeT No. 02/EE/DD/PWD(R&B)/2023-24 Dated 04-04-23) Est Cost: Rs. 3,16,57,998/-
DNIT No. CE(Buildings)/PWD/DNIT/ACE/Project unit/103/2022-23
     
NEW Sabroom Third
Circle
School Education  Infrastructure Development of Chalita Bankul Colony H.S School under Rupaichari Block, South District/SH: Building portion including internal water supply, Sanitary Installation, Sewage, Drainage works, Internal Electricfication works, Fire Fighting works, Installation of Iron Removal Plant and Installation of 1 No Small Bore Tube Well (SBDTW), Rain water harvesting including 200 Mtr long Boundary wall, 130 Mtr long barbed wire fencing and Environmental & Social Management Plan( ESMP) Budget World Bank 946.24 IN-PWD(B)-358058-CW-RFB….Dated……… 2023-24 29-04-2023             540 days                                 Estimated Cost Rs.9,46,24,147.00 Tendering stage    
NEW Dharmanagar First
Circle
Health Development of District Hospital, North Tripura, Dharmanagar during the year 2023-24/SH: Parking site for vehicles by earth filling, GSB, WBM & providing intern locking paver block. Subarna Jayanti 120.94 No.F.3(5-137)-PLAN/DHS/2022-23/3676-87 dated 28/04/2023 of the Deputy Secretary, Govt. of Tripura 2023-24 17-06-2023 No.09/SE(II)/KGT/2023-24               Tendering Stage                                      
NEW Construction of Boundary wall around Jail Complex at Kalikapur, Dharmanagar North Tripura during the year 2022-23 Major Work Home 153.55 No.F.I-604/IGP/2021/1438-43 dated 17/03/2023 of the Deputy Secretary,Home (Jail) Department  Govt. of Tripura 2023-24 23-05-2023 No.1/SE(I)/KGT/2023-24             180 days Tender under scrutiny.                                      
NEW Up-gradation of infrastructure facilities of Dharmanagar District Hospital during the year 2016-17 / SH: Constructionof boundary wall along the periphery of the Hospital campus in/c Gate, Retaining wall, Grill etc. SJTNY 240.96 No.F.3(5-137)-PLAN/DHS/2022-23/1105-1116(V-V) dated 17/01/2023 of the Deputy Secretary, Govt. of Tripura 2023-24 18-12-2017 07-08-2018 ₹ 2,12,21,157 Sri Debobrata Chakraborty & 8729833185 21-08-2018 21-08-2018 Non availibility of funds. 20-02-2019
06 Months
 
Boundary wall length 400.00 Mtrs. completed Further work in progress.Value of work done Rs. 170.00 Lakhs     70.00% Aug'23 120.48 120.48     120.480 Non avalibility of Funds Yes The work is in progress and will complete shortly. Approx. ₹ 1,70,00,000            
Physically completed 22-23

Physically completed 22-23

Published: August 03, 2023
NOTE: LIST OF WORKS PHYSICALLY COMPLETED DURING THE F.Y 2022-23 UPTO 31-03-2023. KINDLY UPDATE THE COLUMNS HIGHLIGHTED UNTIL PROJECT IS FINANCIALLY COMPLETED AND SEND REPORT FOR  PREPARING FINANCIAL REPORTS BY THE CE OFFICE.            
                                                                                                                             Status of Works of various departments entrusted to PWD(Buildings) as on 30-04-2023                                        
Project Details                                                Tendering Details                                                                        Physical Progress Details                            Financial Progress Details Project Completion  Remarks                                                                                      Additional Informations  
Sl.
No.
Division Circle Client Department Name of Work Scheme Sanctioned Project Cost
(Rs.in Lac)
Ref of Sanction in/c name of authority & Amount. Sanction year Dt. Of NIeT/
(Details if not finalished)
Dt. Of Work order Awarded Value
(Rs.)
Name of Contractor & Contact No Dt. Of Commencement as per W/Order Actual Dt. Of Commencement Reason for delay in commencement & action taken/initiated (If any) Stipulated Period & Date of Completion as per agreement Brief Physical Progress and approx. Value of work done as on reporting date  Progress of IE works in percentage Progress of Mechanical works in percentage Overall Progress  in Percentage  Target date/Month  of Completion Fund received
(Upto Date)
(In Lac upto 3 Decimal)
Expenditure incurred
(Upto Date)
(In Lac upto 3 Decimal)
Balance in Hand
(In Lac upto 3 Decimal)
U.C Submitted (Upto date),
(In Lac upto 3 Decimal) 
Fund required (Upto date),
(In Lac upto 3 Decimal) 
 Date of actual Completion and reason for delay/, if any.   Whether Time extn  required (No of days)/Levy /LD realised during execution (With ref.)   (Detailed overall observation and information to include not covered in rest columns)     Approx Value of work done   Remaining value of work done  Ref Of Work order Other informations  
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30            
1 Udaipur Third
Circle
ARDD j) Do at Dudh Pushkarani unde Kakraban Block / Do Special
Assistance
17.82 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 03.01.2022 10.03.2022 1722000 Sri Ashis Kanti Sarkar. M-9862081435 25.03.2022 17.03.2022   24.09.2022
6 Month
Completed 100%   Completed
(100%)
  17.590 17.590 0.000 17.590   11.09.2022 No
Approximate Value of work after completion: Rs……Lac
Handed over
21.03.2023
    ₹ 17,22,000      
2 k) Do at Atharobhola under Killa Block / Do Special
Assistance
17.82 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22 03.01.2023 19.02.2022 1722000 Sri Ranjan Paul. M-9436472587 05.03.2022 04.03.2022   04.09.2022
6 Month
Completed 100%   Completed
(100%)
  17.590 17.590 0.000 17.590 0.000 03.09.2022 No

Approximate Value of work after completion: Rs……Lac
Yet to be handed over.
    ₹ 17,22,000      
3 Jirania Fourth
Circle
A. Veterinary Sub-Centre
Strengthening of Veterinary Health Care Infrustructure through construction of Veterinary Sub-Centre at Vrigubari under Mandwai Block / Construction of building, Shed for Animal, Electrification & Water supply facility.
Special
Assistance
17.82 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22   01-04-2022 ₹ 17,61,758 Sri Subash Acharjee 05-04-2022 09-04-2022   15-01-2023 Completed 100%   Completed
(100%)
  93.19 17.69 6.790 0.000 0.000 12-11-2022    Approximate Value of work after completion: Rs……Lac
Consolidated fund for SL 20,21,22,23,24=  (67+27.9 Lac) 
  ₹ 17,68,984 ₹ 0      
4 a) Do at Purbanoabadi under Mandwai Block / Do Special
Assistance
17.82 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22   28-02-2022 ₹ 17,61,758 Sri Abhijit Laskar 03-03-2022 02-03-2022   14-12-2022 Completed 100%   Completed
(100%)
    16.87 0.000 0.000 0.000 12-11-2022    Approximate Value of work after completion: Rs……Lac    ₹ 16,87,402 ₹ 0      
5 b) Do at Bishrambari under Mandwai Block / Do Special
Assistance
17.82 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22   28-02-2022 ₹ 17,61,758 Sri Subash Acharjee 03-03-2022 05-03-2022 Delay due to dispute in selection of worksite. 14-12-2022 Completed 100%   Completed
(100%)
    17.19 0.000 0.000 0.000 21-01-2023    Approximate Value of work after completion: Rs……Lac    ₹ 17,19,262 ₹ 0      
6 c) Do at Khengrai under Mandwai Block / Do Special
Assistance
17.82 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22   28-02-2022 ₹ 17,61,758 Sri Pradip Saha 03-03-2022 04-04-2022 Delay due to dispute in selection of worksite. 14-12-2022 Completed Completed   Completed
(100%)
    17.39 0.000 0.000 0.000 21-12-2022    Approximate Value of work after completion: Rs……Lac    ₹ 17,38,366 ₹ 0      
7 d) Do at Santirnagar undre Belbari Block / Do Special
Assistance
0.18 Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD 2021-22   28/02/2022 ₹ 17,61,660 Rajina Begam , Cont. No. 9402179641 15/03/2022 15/03/2022   12-09-2022 Completed 100% 100% Completed
(100%)
Work completed   17.26 0.000 0.000 0.000 15-09-2022    Approximate Value of work after completion: Rs……Lac    ₹ 17,26,605 ₹ 0      
8 Santirbazar Third
Circle
FCS & CA Construction of 1000 MT capacity godwan including Guard room and boundary wall at Santirbazar under Santirbazar Sub-division. PLAN 252.00 NO.F.F.18-(44)-PLAN/DFCS & CA/2012-13/1314-20 dated 29/01/2022 of the Addl. Secretary & Director, Food civil Supplies & Consumer Affairs .  2021-22 PNIeT- No:- 18/EE/PWD(R&B)/STB/2020-21 dated, 10-11-2020 02-03-2021 ₹ 1,37,85,050 Subhas Podder 17-03-2021 30-03-2021 Conerened deprtment was delayed for handing over the clear site. 12(Twelve) Months
16-03-2022
Work completed and handed over  to the concerned Department 100%   Completed
(100%)
  202.000 202.000 0.000 202.000 0.000 03-03-2022    Approximate Value of work after completion: Rs.137 Lac
Handed over on 31-12-2022 
  ₹ 1,37,85,050 ₹ 0 No.F. 9(3)/EE/PWD/STB/7173-87    
9 Kumarghat First
Circle
Health(DFWPM) Construction of 10 bedded PHC  including 10 Nos staff Qtrs at Santipur under Unakoti District RIDF-XX 540.00 F.19(554)-PLAN/DFWPM/2014  dt.07/03/2015. 2014-15 30-08-2016 18-12-2019 ₹ 3,58,36,000 N.K. Dhar
94361 22664
03-01-2020 05-03-2020 Covid-19 & Site dispute. 02-11-2021 Completed 100% Completed
(100%)  & handed over.
  471.200 471.200 0.000 471.200 0.000 26-03-2023 10 (ten) months Approximate Value of work after completion: Rs 471.20 Lac
completed and handed over on ……….to health department
  ₹ 4,71,20,000 ₹ -1,12,84,000      
10 Amarpur Third
Circle
Health(NHM) Proposed construction of single storied 30(Thirty) bedded Primary Health Centre (PHC) building including 10(ten) Nos. Staff Quarters Kitchen, Morgue, Garage & Generator with Driver Room Building and Boundary wall at Ompi, Amarpur Sub-division, Gomati District, Tripura under NHM during the year 2017-18  NHM 894.00 No.F.19(610)-PLAN/DFWPM/2017. Dt.3-7-17. of the Under Secretary to the Govt of Tripura ,Health & Family Welfare Deptt.                             Rs.8.94 2017-18 12-07-2017 07-04-2018 ₹ 6,91,70,753 Sri Ajit Bhattacharjee,Contact No.9436123912 18-07-2018 13-03-2019 Land dispute, drawing, pedamic Covid-19 12-03-2021 Completed 0.00 0.00 Completed
(100%)
  550.000 550.000 0.000 550.000 344.00 07-12-2022    Approximate Value of work after completion: Rs……Lac      ₹ 6,91,70,753      
11 Up-Gradation of Karbook Community health Centre (CHC) to 50(Fifty) bedded Sub-Divisional Hospital including 16(Sixteen) Nos. Staff quarters at Karbook under Gomati District, Tripura.    NHM 1227.00  No.F.(4-93)-PLAN/ DHS /2016 /1437-47/3993(V-III) Dt. 5-9-16.of the Under Secretary to the Govt of Tripura ,Health & Family Welfare Deptt.                      Rs.  12.27 2021-22 07-04-2017 29-12-2017 ₹ 8,23,42,451 Sri Ajit Bhattacharjee,Contact No.9436123912 01-12-2018 27-01-2018 Land dispute, drawing, pedamic covid-19 26-01-2020 Completed 0.00 0.00 Completed
(100%)
  600.000 600.000 0.000 600.000 223.42 22-08-2022    Approximate Value of work after completion: Rs……Lac      ₹ 8,23,42,451      
12 Belonia Construction of 10 bedded PHC with quarters at Tripura Bazar under Hrishyamukh block, Belonia Sub-Division, South Tripura District. NHM 385.00 No.F.5(13)-PLAN/DFWPM/ 2015/RIDF/1724-29 dated, 13.06.2016  2016.17 07/EE(PWD)/BLN/2016-17 Dt.24.08.2016 21.12.2016 ₹ 3,06,22,000 Radh Raman Datta
8119953376
05.01.2017 04.01.2017 Delayed by the agency 26.10.2018 Completed.
Rs.277.00 lakh
100% NA Completed
(100%)
  -----   449.000 435.000 14.000 435.000   14.10.2022 Yes Delay for getting of clear working site due to rubber garden exist in the proposed area and for Type-II & III Approximate Value of work after completion: Rs……Lac
quarter delay for land demarcation.
  ₹ 2,77,00,000 ₹ 29,22,000 No.F.7(20) Pt-I/EE(PWD ) /BLN/DIVN /8069-80 Dt.21.12.2016    
13 Construction of MCH wing at Belonia Sub-Divisional Hospital, South Tripura NHM 797.00 No.F.3(2)-425-PLAN/DHS/2016-17/3650-60 dated, 06.03.2017 2016-17 09/EE(PWD)/BLN/2017-18 Dt. 18.07.2017 16.01.2018 ₹ 4,79,84,000 Ajit Bhattacharjee
9436123912
31.01.2018 12.12.2018 Due to shifting of existing electric transformer within the proposed working area departmentally. 30.01.2020 Civil & I.E works completed  accept lift.
Rs.479.84 lakh
100% Not yet Completed
(100%)
  -----   425.000 425.000 0.000 425.000 100.000   Yes Approximate Value of work after completion: Rs……Lac
Civil work completed on
15.02.2022
  ₹ 4,79,84,000 ₹ 0 No.F.7(20) Pt-I/EE(PWD ) /BLN/DIVN /5710-21 Dt.27.11.2017 1) Req for Rs.100.00 Lac placed by the EE, BLN vide letter No.F.5(11)/EE/PWD/R&B/BLN/8115-16 Dt. 07/02/23 to the CE, Bldg.  
14 Udaipur Construction of 10(ten) Nos. (type.I- 04 Nos, Type.II - 4 Nos. & Type.III - 2 Nos,) staff quarter at Maharani PHC. NHM 225.00 No.F.19(42)-PLAN/DFWPM/2000(S) dated 19/11/2018 2018-19 04.09.2020 09.06.2021 ₹ 2,09,80,000 Sri Nihar Chandra Debnath. M-9436131064 24.06.2021     23.11.2022
18 Month
Completed 100%   Completed
(100%)
  225.000 205.000 20.000 205.000 0.000 16.12.2022   Approximate Value of work after completion: Rs……Lac
Handed over on 07.02.2021
    ₹ 2,09,80,000      
15 Santirbazar Health
(DFWPM)
Proposed construction of 10 (ten) nos. staff quarters at Kwaifang Primary Health Centre (PHC), Santirbazar, South Tripura District, Tripura.
 
IMR-13th F.C 213.00 NO.F.20(80)-BUDGET/DFWPM/2016-17(V-I)/179-82(V-II) DATED, 24-09-2021 of the Deputy Secretary Government of Tripura 2021-22 PNIeT- No:- 20/EE/PWD(R&B)/STB/2013-14 dated, 25-02-2014 30-07-2014 ₹ 1,70,89,222 Gathan Datta
9862453230
14-08-2014 13-08-2014 Work started in due time. 18(Eighteen) Months
13-02-2016
Work completed and handed over to the concerned Department 100% Not Required Completed
(100%)
  212.710 212.710 0.000 212.710 0.000 08-07-2022,
Shortage of Fund.
2336 days,
Time extension under process.
Approximate Value of work after completion: Rs.170 Lac
Handed over on 11-11-2022
  ₹ 1,70,89,222 ₹ 0 No.F. 9(3)/EE/ PWD/STB/1674-1685    
16 Health(DHS) Capacity Building for Developing Trauma Care  Facilities in Government Hospitals in National Highway under 12th Five Year Plan/ SH: Proposed Construction of Single storied Building for Trauma Care Centre (Level-III) in the South District Hospital at Santirbazar, South Tripura CASP 390.00 NO.F.3(2-412)-PLAN/DHS/2016/2016/6092-7001 dated 17-07-2017 of the Under Secretary to the Govt. of Tripura.  2017-18 PNIeT- No:- 06/EE/PWD(R&B)/STB/2018-19 dated, 06-06-2018 14-06-2019 ₹ 3,12,01,081 Jahar Sur Choudhury
9436133138
29-06-2019 05-08-2019 Delay due to Covid Pandemic 18(eighteen) Months
28-12-2020
Work completed and handed over to the concerned department 100% Not Required Completed
(100%)
All ready completed & handed over 390.000 360.320 29.680 333.597 0.000 30-10-2022,
Due to COVID Pendamic Situtation.
668 days  Approximate Value of work after completion: Rs.325 Lac
Handed over on 21-12-2022 
  ₹ 3,25,00,000 ₹ -12,98,919 No.F. 9(3)/EE/PWD/STB/1616-28    
17 Bishalgarh Fourth
Circle
Health(NHM) Construction of 10 bedded PHC building including , Kitchen,  Morgue  and  Garage & Generator with Driver room building at existing Kanchanmala PHC  NHM 210.00 F.19(63)-PLAN(DFWPM)/2000(S)/7575-80 (V1), Dated-19/06/2019 2019-20 PNIeT No 06/EE-BSLD/PWD(R&B)/2019-20, Dated-09/08/2019. DNIeT-CE(Buildings)/PWD/DNIT/ACE/Project Unit/14/2019-20 29-04-2020 ₹ 2,21,37,982 Tapas Dutta (9436469955/ 9612092053) 14-05-2020     15 Months                   (13-08-2021) Work Completed 100% Nil Completed
(100%)
Dec.22 210.000 210.000 0.000 181.510 0.000 01-11-2022. Specially delayed due to COVID 19   Approximate Value of work after completion: Rs……Lac
Handed over on 25/11/2022
    ₹ 2,21,37,982      
18 Constn of 10 bedded PHC building in/c Kitchen,Morgue,Garrage & Generator with Driver room in place of exsting Dayarampara PHC   210.00 No. F. 19(63-PLAN/DFWPM/200(S)/7572-80 (V-I) dt 19/06/2019 2019-20 02-11-2020 12-05-2021 ₹ 1,82,41,710 Sankar Kanti Saha, 9436124030 27-05-2021 26-06-2021 Non availability of clear site. 15 Months
(13-04-24)
Completed.
Value of work done Rs. 217.29 Lac
100% NA Completed
(100%)
Dec.22 210.000 205.360 4.640 145.000 0.000 16-09-2022 23 days required. Prayer for granting of T.E process and approval is awaited.  Approximate Value of work after completion: Rs. 217.29 Lac
Main Building completed. Due to cost over run Kitchen,Morgue,Garrage & Generator with Driver room construction not taken up.
    ₹ 1,82,41,710      
19 Mohanpur Construction of 10 nos staff qtrs at Katlamara PHC. NHM 175.00 No.F.19(610)-PLAN/DFWPM/2017/1258-85 Dated.03/07/2017 of the Under Secretary to the Govt. of Tripura. 2017-18   12.08.2021 ₹ 1,52,00,000 Satyabrata Roy 12.08.2021 25.08.2021   11.08.2022 Work completed and handed over to hospital authority on 25.11.2022. Total value of work incurred during construction of project is Rs 1,62,46,649.00 100% N/A Completed
(100%)
  100.00 50.000 50.000 0.000 0.000 10.08.2022 N/A Work completed and handed over to hospital authority on 25.11.2022. Total value of work on completion   is Rs 1,62,46,649.00            
20 Construction of 10 nos bedded PHC at Katlamara including Kitchen, Morgue & Garrage.. NHM 225.00 No.F.19(610)-PLAN/DFWPM/2017/1258-85 Dated.03/07/2017 of the Under Secretary to the Govt. of Tripura. 2017-18   12.08.2021 ₹ 1,58,00,000 Satyabrata Roy 12.08.2021 25.08.2021   11.08.2022 Completed 100% N/A Completed
(100%)
  175.000 175.000 0.000 175.000 0.000 10.08.2022 N/A Main building completed and handed over to hospital authority on 25.11.2022  except Kitchen,Generator room and Morgue which are  already completed and will be handed over to hospital authority on Mar'2023. Total value of work done on completion is Rs. 1,70,17,124.00            
21 LTV Fifth
Circle
Health(NHM) Construction of 10 beded PHC with 10 (ten) Nos. staff quarters (Type-I-04 Units, Type-II-04 Units and Type-III-02 Units] in the existing Primary Health Centres (PHCs) at 82 Miles PHC, L.T. Valley Sub-Division, Dhalai District, Tripura. NHM 486.00 No.F.19(42)-PLAN/DFWPM/2000(S) dated 19/11/2018 2018-19 06-05-2019. 02-03-2020 ₹ 4,36,37,246 Sri Sanjib Kr. Prasad    9436543587 17-03-2020. 17-12-2020. Delay for handing over of clear site 16-03-2022. Ready to hand over & 466.00 lakh 100.00% Not required Completed
(100%)
  486.000 466.000 20.000 486.000 0.000 30-03-2023 & delay occurred due to handing over of clear site & Covid. No & delay occurred due to Covid. Total value of work Rs.486.00 on completion (Civil-460.00 lakh & IE work-26.00 lakh)
Ready to hand over
  ₹ 4,60,00,000 ₹ -23,62,754      
22 Proposed construction of 12(twelve) Nos. Staff Quarters building at Manu Community Health Centre (CHC), L.T. Valley Sub-division under Dhalai District, Tripura. NHM 295.00 No.F.19(226)-PLAN/DFWPM/2000(SUB)                                                                                          /3190-96    Dated.26-09-2018 2018-19 14-12-2018. 15-04-2020. ₹ 2,54,33,889 Sri Gour Gobinda Saha  8787367268 30-04-2020. 30-12-2020. Delay for handing over of clear site 29-10-2021 Completed & 295.00 lakh 100.00% Not required Completed
(100%)
Completed 295.000 295.000 0.000 295.000 0.000 15-12-2022 & delay occurred due to handing over of clear site & Covid. No & delay occurred due to Covid. Total value of work Rs.295.00 on completion (Civil-285.00 lakh & IE work-10.00 lakh)
Handed over on 15.12.2022
  ₹ 2,95,00,000 ₹ -40,66,111      
23 Medical College Project
Unit
Health(DHS) Construction of Ayush Hospital at Paradise chowmuhani (B+G+3) NHM 569.00 F.NO.1(267)AYUSH/DHS/2016  dt……of the ……… 2016   17-10-2019 ₹ 3,71,39,000 Narayan Chandra Saha
Contact No……
01-11-2019 01-11-2019 Due to Covid situation 540 days
Date….
Civil/ Internal  Electrification works completed.Lifts to be installed by Mechanical.
Approx value of work done…………….
100% Lifts to be installed Completed and handed over without lift.   569.330 469.33 100.000 569.33 0.000 Date of Completion:    Approximate Value of work after completion: Rs……Lac
Completed and handed over without lift.
    ₹ 3,71,39,000      
24 Sabroom Third
Circle
Minority
Welfare
Constn of school Building at Chatakchari H.S School at Rupaichari RD Block,South Tripura under PMJVK PMJVK 250.00 No.F.32/MW/PMJVK/2018-19/3369-75 Dt. 03/11/2019 of the Addl. Secretary, Deptt. of welfare of Minorities 2019-20 17-12-2020 24-06-2021 ₹ 2,21,40,462 Shri Bishnu Pada Paul
(Mob# 6436519065)
12-07-2021 20-07-2021   365 days
11-07-2022
Completed  100% 100% Completed
(100%)
Completed 251.000 237.500 13.500 217.500 0.000 12-05-2022         ₹ 2,21,40,462      
25 Agt Div-V Second
Circle
Panchayet  Construction of Auditorium at Panchayati Raj Training Institute at A. D. Nagar, Agartala, West Tripura / SH. Civil Works, Plumbing Works, Stage Works including Stage Lighting, Internal Electrification, Sound System & HVAC Work.     SPA 1154.00 Memo No. 2(18-7)-PE/PR/2013/43686-92 dated 30.03.2015.
 Addl. Sec. Panchayat Dept. Govt. ofTripura.
2015-16 CE/PWD(R&B)/DNIT/SE-II (Project)/29/2015-16 22.02.2016 9,63,63,688.00 Bimalendu Chakraborty / Partha Pratim Saha / Sunil Kr Banik /Somjit Das 07.03.2016 07.03.2016 Scope of original Work drawing design Changed as per requisition of user department . 18 Months /07.09.2017 Work completed 100% 100% Completed
(100%)
Completed 1153.010 1132.210 20.800 1000.000 0.00 03.01.2022 Time extention required for 1585 days. Approximate Value of work after completion: Rs. 1019.13 Lac
Work completed But yet to be Taken over by the User Department as intimated.EE Div-V vide his letter No.F.6(355)/EE-V/AGT/PWD/1625-30 Dt.13/06/23 to the Addl. Director, PRT Institute to take over the completed building
  ############ ₹ -55,49,455 No.F.6(355)/EE-V/AGT/PWD/7815-30 dated 22.02.2016 Estimate for additional works amounting to Rs. 54.00 lakh sent to the Director, Panchayats as per their requisition for obtaining necessary A/A & E/S. Sanction yet to be accorded.  
26 Amarpur Third
Circle
School Education  Proposed construction of Punjiham H.S. School at Karbook, District Gomati, Tripura. RIDF-XXV 742.00 No.NB.TRIP/01/56th ISC/PLAN50(XXV)/2019-20 dt24/03/20
(Gap funding . Initial funding from SPA and later on Gap funding by RIDF Rs.495.00 Lac)
2019-20 07-06-2015 29-12-2015 ₹ 4,63,00,000 Sri Ashutosh Bandhopadhaya,Contact No.9436527307 13-01-2016 20-07-2016   20-07-2018  Completed     Completed
(100%)
  395.000 395.000 0.000 395.000 68.00     Approximate Value of work after completion: Rs……Lac
 Completed & handed over to the School Education.
    ₹ 4,63,00,000      
27 Santirbazar School Education  Construction of Baikhora H.S. School at Santirbazar, South Tripura. RIDF 609.00 No.NB.TRIP/01/56th ISC/PLAN50(XXV)/2019-20 dt24/03/20 2019-20 PNIeT- No:- 09/EE/PWD(R&B)/STB/2015-16 dated, 18-09-2015 29-04-2016 ₹ 4,35,22,985 Raja Raw Gosh
9436131203
04-05-2016 04-05-2016 Work started in due time. 24 (Twenty Four) Months
03-05-2018
Work completed and handed over to the concerned department. 100% Not Required Completed
(100%)
Completed 533.000 453.325 79.675 353.200 0.000 23-12-2022,
Due to Shortage of fund
1955 Days, Approximate Value of work after completion: Rs.425 Lac
Handed over on 23-12-2022
Inagurated on 31-12-2022
  ₹ 4,25,00,000 ₹ 10,22,985 No.F. 9(3)/EE/PWD/STB/467-80    
28 Sonamura Fourth
Circle
School Education  Proposed Construction of Boxanagar H.S. School at Boxanagar, Sonamura, Sepahijala  District, Tripura  undern  SCA (un-tied) during the year 2012-13. RIDF 777.00 TIIFB   CE(R&B)/DNIT/SE(Project)/26/2013-14, Dt. 19.07.2013.         14-03-2014     Work  completed. Value of work done 597.00 lac  on completion 28-01-2023. 100%   Completed
(100%)
    597.000       Date of completion 28-01-2023   Approximate Value of work after completion: Rs 597.00 Lac
Handed over to School Education 
  ₹ 5,97,00,000 ₹ -5,97,00,000      
29 SC Welfare 50 seated Girl's Hostel at Sonamura Girl's School BJRCY 290.00 No.F.5-1(P-I)/SCW/PLG (Hostel)/BIRCY/2017/11728-51 Dt. 28/10/2022 for Rs. 1,32,50,000/- of the Addl Secretary, Govt. of Tripura 2022-23 DNIT No. ACE/Project Unit/ PWD(Buildings)/DNIT/41/2020-21.
Dt……………….
10-06-2021 ₹ 2,17,31,252 Bishnu Pada Paul
9436519065
25-06-2021     25-12-2022 Work Completed. Value of work done on completion Rs208.740Lac 100%   Completed
(100%)
  290.000 208.740 81.260 208.740   Date of actual completion     Approximate Value of work after completion: Rs……Lac     ₹ 2,17,31,252 Vide No.F.10(30)/EE/SNM/PWD/3022-37 Dt.10/06/2021. 1) UC for Rs. 208.74 Lac has been submitted by EE, SNM vide letter No.F.7(53)/EE/SNM/8070-72 Dt. 27/02/23.
Will be reflected in next years achievement……..i.e 2023-24
 
30 Medical College Project
Unit
SW & SE  Const. of creation of barrier free environment  under AIC / for 1 no. existing building under Medical College Sugamya
Bharat
312.00 No.F.2(112)-SW/DC/2010/Vol-III/7992268 dt18/03/22 2019-20   20-03-2021 ₹ 1,56,72,982 M/S Chittaranjan Saha 04-04-2021 24-03-2021   270 days
Date….
Work completed and handed over
value of work done Rs……. 
100% Lift not yet installed Completed
(100%)
  156.730 129.510 27.220 129.510 0.000 Date of Completion:    Approximate Value of work after completion: Rs……Lac
Balance fund is lying for Mechanical works only
    ₹ 1,56,72,982      
31 Udaipur Third
Circle
Tribal Welfare Constn of 100 [one hundred] seated ST Girl's Hostel[G+2 storied]Building attached to  Udaipur Girl's H.S.School under Udaipur Sub-Division.   182.00 F. No.15-53/TW/SP/2018-19/17460-474 dt. 24.09.2019. Amount 200.00 Lakh 2019-20 01.12.2020 20.05.2021 ₹ 1,81,75,000 M/s N.G.Bhattacharjee. M-9436123651. 05.06.2021 14.07.2021 Pile work could not be continued due torainey season. It is also to mention here that it is a low land. 04.09.2022
15 Month
 Completed & handed over 100%   Completed
(100%)
  200.000 200.000 0.000 200.000 0.000 31.12.2022 Yes
Approximate Value of work after completion: Rs……Lac
Handed over on
03.02.2023
    ₹ 1,81,75,000   Completed and handed over in Feb 2023.
(1st phase , part of ground & 1st floor) UC submitted for Rs. 200.00 Lac on 18/03/2023. Fund available for 2nd Phase Rs.2.00 Crore with the Client department. Estimate amounting to Rs. 405.00 Lac submitted to T.W Deptt vide letter No.F.3(568)/PC (PD-II)/2012 ( S)/974-77 dated 17/05/23 accord of A/A & E/S.
 
32 Santirbazar Construction of sport complex for Ekalavya Residential (EMR) School At  B.C Manu/ Play ground PLAN 106.00 A/A: No.F. 25-18/TW/REIS/2018/3395-3405 Dt. 26-07-2019 of the Member Secretary Tripura Tribal Welfare Residential Educational Institutions Society. Rs. 1.06 Crore
E/S No.F.25-18/TW/REIS/2018/177-87 dated, 04-04-2019  of the Member Secretary Tripura Tribal Welfare Residential Educational Institutions Society
2018-19 PNIeT- No:- 19/EE/PWD(R&B)/STB/2019-20 dated, 17-10-2019 06-01-2020. ₹ 60,60,145 Biswajit Majumder
9862406055
21-01-2020 30-01-2020 Clear site was not available 5(Five) Months
20-06-2020
Work Completed.
Value of work done= Rs. 106 Lkah
Not required Not Required Completed
(100%)
Completed 86.030 83.500 2.530 83.500 20.470 31-03-2021
Due to Site Disput & COVID Pendamic Situtation
281 days,  Approximate Value of work after completion: Rs. 106Lac
handed over on…..
  ₹ 1,06,00,000 ₹ -45,39,855 No.F. 9(3)/EE/PWD/STB/7332-45    
33 Udaipur UDD Setting up of Tertiary waste Processing center at Chandrapur Colony(near Central FCI Godown) under Udaipur Municipal Council. 15th FC 145.00 No.F2(26)/ Accounts/UMC/UDP/2021-22/7356-61, dated 12.03.2020 2020-21 21.12.2020 04.02.2021 ₹ 1,47,87,000 Sri Biswajit Majumder. M-9862406055 19.02.2021     18.08.2021
6 Month
completed 100%   Completed
(100%)
  135.350 112.850 22.500 112.850 0.000 31.12.2022   Approximate Value of work after completion: Rs……Lac     ₹ 1,47,87,000      
34 Mohanpur Fourth
Circle
Law Constn of Tripura Judicial Academy at Narsingarh Special
assistance
2400.00 A/A & E/S received vide memo No.F. 1(10)/PCD/PF/FIN/2021/194-216 Dated 29/12/21 of the Secretary, Planning (P&C) Department. 2021-22   17.02.2020 ₹ 18,93,00,000 Tapesh Ch Debnath 03.02.2020 05-08-2020 Clear site  was not available 16.02.2022 Civil Work Completed 70% 80% 83% June' 2023 2400.000 2400.000 0.000 2400.000 0.000     Revised estimate amounting to Rs. 32,99,64,355/- has been submitted to the Director, Tripura Judicial Academy by the SE, PWD, PU vide No. 10(3)/ACE/Project Unit/2022/7196-7200 dt. 27/3/23 for accord of revised A/A & E/S. Revision required due to execution of extra and additional works as per requisition of the client department.     ₹ 18,93,00,000   1) EE, Mech invited tender for installation of 2 nos Lift for Hostel building. Amt Rs.30.92 , PNIeT No. 118/EE/Mech/DIVN/AGT/2022-23 Dt. 14/3/23.
Since the building is functioning therefore, shown in completed list of work during 2022-23
In progress
35 Agt Div-V Second
Circle
Science & Technology Science City at Agartala (Phase -I) NLCPR 2745.40
(On dated 25.03.2015) and revised A/A & E/S for Rs. 2968.10 (on dated 22.07.2021) 
Memo No. F.No.16(8)/TSCST/Vol-I /1029-34 dated 22.107.2021
Joint Member Secretary , Deirector , Science & Technology
2012-13
PNIT No. 30/B/EE-V/AGT/PWD/2012-13 dated 24.01.2013
22.07.2013 25,19,58,517.00 Reacon Engineers(Ind) Pvt Ltd  06.08.2013 09.01.2014 Due to change of Design Drawing , structural work , COVID 19 effects and Progress delayed from  the Agency.  730 days/  07.8.2015  Finishing work in progress. 75% 75% 95.50% Oct 23 3038.6 2997.60 41.00 2661.80 656.00 (for Additional works)   Yes i)  Main Building handed over to the User Department .

ii) Tentative Deviation amounting to Rs. 2959.89 (Tentative executed value) processed to the Higher authority for approval in the month of January, 2023.

iii) Revised estimate/ revised santion is required for taking up additional work.
  ₹ 29,97,60,000 735.65 (Additional works) F.6(346)/EE-V/AGT/PWD/1093-1111 datd 22.07.2013   Additional works for an amount of 735.65 lakh beyond the original sanctioned amount is to be taken up with separate A/A & E/S. In progress
                                                                       

 

Don't have an account yet? Register Now!

Sign in to your account