Building Projects Status
Published: August 03, 2023
Status of Works of various departments entrusted to PWD(Buildings) as on 30-06-2023 |
Project Details |
Tendering Details |
Physical Progress Details |
Financial Progress Details |
Project Completion |
Remarks |
Additional Informations |
|
|
Sl. No. |
Division |
Circle |
Client Department |
Name of Work |
Scheme |
Sanctioned Project Cost (Rs.in Lac) |
Ref of Sanction in/c name of authority & Amount. |
Sanction year |
Dt. Of NIeT/ (Details if not finalished) |
Dt. Of Work order |
Awarded Value (Rs.) |
Name of Contractor & Contact No |
Dt. Of Commencement as per W/Order |
Actual Dt. Of Commencement |
Reason for delay in commencement & action taken/initiated (If any) |
Stipulated Period & Date of Completion as per agreement |
Brief Physical Progress and approx. Value of work done as on reporting date |
Progress of IE works in percentage |
Progress of Mechanical works in percentage |
Overall Progress in Percentage |
Target date/Month of Completion |
Fund received (Upto Date) (In Lac upto 3 Decimal) |
Expenditure incurred (Upto Date) (In Lac upto 3 Decimal) |
Balance in Hand (In Lac upto 3 Decimal) |
U.C Submitted (Upto date), (In Lac upto 3 Decimal) |
Fund required (Upto date), (In Lac upto 3 Decimal) |
Date of actual Completion and reason for delay/, if any. |
Whether Time extn required (No of days)/Levy /LD realised during execution (With ref.) |
(Detailed overall observation and information to include not covered in rest columns) |
Approx Value of work done |
Remaining value of work done |
Ref Of Work order |
Other informations |
Status ( Column for Filtering the status) For use of CE office only |
|
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
16 |
17 |
18 |
19 |
20 |
21 |
22 |
23 |
24 |
25 |
26 |
27 |
28 |
29 |
30 |
1 |
2 |
3 |
4 |
|
|
|
1 |
Dharmanagar |
First Circle |
ARDD |
Veterinary Dispensary at Panisangar |
Special Assistance |
81.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/9641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
24-02-2022 |
03-08-2022 |
₹ 77,45,201 |
Sri Raju Roy 9774915677 |
17-08-2022 |
08-11-2022 |
Initially delayed due to site problem |
14-05-2023 270 days |
Foundation workplinth beam beam complete . Value of work done Rs 20.00 lakhs |
|
|
20% |
Dec-23 |
90.730 |
56.000 |
34.730 |
56.000 |
190.910 |
|
|
|
₹ 20,00,000 |
₹ 57,45,201 |
|
Rs. 34.73 Lac lapsed during March 2023. |
In progress |
|
|
2 |
First Circle |
ARDD |
Veterinary Dispensary at Uptakhali |
Special Assistance |
81.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/9641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
24-02-2022 |
03-08-2022 |
₹ 77,45,201 |
Sri Raju Roy 9774915677 |
17-08-2022 |
25-09-2022 |
Initially delayed due to site problem |
14-05-2023 270 days |
Shuttering and reinforcement work under progress for roof casting. Value of work done Rs. 50.00 Lac approx. |
|
Not reqd. |
55% |
Oct-23 |
|
|
|
₹ 55,00,000 |
₹ 22,45,201 |
|
|
In progress |
|
|
3 |
First Circle |
ARDD |
Veterinary Hospital at Dharmanagar |
Special Assistance |
118.00 |
Memo No.F. 5(672)/ARDD/PLAN/2015/9641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
04-08-2022 |
29-12-2022 |
₹ 91,52,052 |
M/S S.N Bhattacharjee & Sons 9612705733 |
12-01-2023 |
12-01-2023 |
No delay |
11-01-2024 365 Days |
Brick work completed upto roof level. Shuttering and reinforcement work for ground floor roof is in progress. Value of work done Rs 55 lakhs |
|
Not reqd. |
55% |
Jan-24 |
|
|
|
₹ 55,00,000 |
₹ 36,52,052 |
|
|
In progress |
|
|
4 |
Kanchanpur |
First Circle |
ARDD |
Veterinary Dispensary Strengthening of Veterinary Health Care Infrustructure through construction of Veterinary Dispensary at Dasda |
Special Assistance |
81.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/9641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
10-03-2021 |
09-11-2022 |
₹ 77,45,000 |
Fountain Head 9435565557 |
24-11-2022 |
08-03-2023 |
Clear site was not available and the concerned dept. has cleared the site on 07.03.2023 |
July, 2023 240 Days |
Upto Plinth beam completed. Work is in progress. Value of work done Rs. 20.00 Lakh |
|
|
22% |
Nov-23 |
12.590 |
12.590 |
0.000 |
|
|
|
|
Work in progress. |
₹ 20,00,000 |
₹ 57,45,000 |
|
|
In progress |
|
|
5 |
Kumarghat |
First Circle |
ARDD |
Veterinary Dispensary Strengthening of Veterinary Health Care Infrustructure through construction of Veterinary Dispensary at at Kanchanbari |
Special Assistance |
81.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/9641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
54/SE(I)/Kgt/2021-22 23-02-2022 |
15-06-2022 |
₹ 77,45,000 |
Jayanta Das 70056 61542 |
30-06-2022 |
05-07-2022 |
Initially delayed due to site problem |
10-06-2023 11 Months |
Approximate 70% of the total work completed Rs. 56.00 Lac |
0.00% |
N.A. |
80% |
Sept-23 |
48.000 |
48.000 |
0.000 |
0.000 |
33.820 |
|
3(Three) months |
For internal electrification work, letter issued to IE, IED |
₹ 40,00,000 |
₹ 37,45,000 |
|
Fund is required for making Payment |
In progress |
|
|
6 |
First Circle |
ARDD |
Construction of Modern Abatitoir for Pig cum pork processing plant at Pecharthal, Unakoti District |
NEC |
344.00 |
No.F.8(92)/E-Cell/ARDD/CONSTN/14/1281301 dt13/08/21 |
2021-22 |
21-12-2021 |
12-04-2022 |
₹ 2,66,29,000 |
Sushen Ch. Das 98623 18088 |
27-04-2022 |
27-09-2022 |
Initial delay due to no accessibility to work site for 6 months |
26-03-2023 11 Moths |
Work is in progress and completed upto roof level , boundary wall & S-tank in progress Rs. 200.00 Lac |
20% |
0% |
70% |
Dec-23 |
10.000 |
50.000 |
0.000 |
10.000 |
334.000 |
|
3 (Three) months |
internal electrification work in progress |
₹ 2,00,00,000 |
₹ 66,29,000 |
|
|
In progress |
|
|
7 |
Khowai |
Second Circle |
ARDD |
Veterinary Hospital at Khowai |
Special Assistance |
118.00 |
No. F. 5(672)/ARDD/PLAN/2015/9691-29, Dated 16-09-2021 |
2021-22 |
05-09-2022 |
29-12-2022 |
₹ 1,02,20,945 |
Sujan Dey (9436513028) |
13-01-2023 |
15-06-2023 |
The concerned department could not yet handed over clear site to PWD, so work could not started yet. |
180 Days (12-07-2023) |
Work just started. |
Nil |
Nil |
Nil |
Dec'23 |
125.450 |
0.000 |
125.450 |
0.000 |
0.000 |
|
|
|
|
₹ 1,02,20,945 |
|
1) The EE, KHW has surrendered fund for Rs. 125.45 Lac and communicated to the Addl. Secretary, Directorate of ADD vide letter No.F>7(29)/EE/PWD/KHW/11566-570 Dated 24/02/23 2) EE, Khowai requested the Dy Director, ARDD vide his letter No.F.10(27)/EE/PWD/KHW/12058-12062 Dt. 15-3-23 for handing over the work site. |
Not yet started |
|
|
8 |
Teliamura |
Second Circle |
ARDD |
Veterinary Dispensary Strengthening of Veterinary Health Care Infrustructure through construction of Veterinary Dispensary at Kalyanpur |
Special Assistance |
81.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/9641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
25-04-2022 |
29-07-2022 |
₹ 79,66,486 |
Sri Sajal Datta 9436512491 |
13-08-2022 |
05-01-2023 |
initial delay in handing over over of clear site from the concern department |
12-05-2023 (9 months) |
Finishing work is in progress. Total value of work done Rs.60.00 Lac |
|
|
70% |
Aug,23 |
18.440 |
18.440 |
0.000 |
18.440 |
63.500 |
|
|
|
₹ 60,00,000 |
₹ 19,66,486 |
|
|
In progress |
|
|
9 |
Teliamura |
Second Circle |
ARDD |
Veterinary Dispensary at Teliamura |
Special Assistance |
81.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/9641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
01-04-2022 |
12-08-2022 |
₹ 80,03,368 |
Sri Haran Ch. Das 9436168447 |
27-08-2022 |
02-11-2022 |
Delay in handing over over of clear site from the concern department |
26-05-2023 (9 months) |
Finishing work is in progress. Total value of work done Rs.75.00 Lac |
|
|
90% |
Aug,23 |
48.000 |
48.000 |
0.000 |
48.000 |
33.700 |
|
|
|
₹ 70,00,000 |
₹ 10,03,368 |
|
|
In progress |
|
|
10 |
Udaipur |
Third Circle |
ARDD |
Veterinary Hospital at Udaipur |
Special Assistance |
118.00 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
16.08.2022 |
28.11.2022 |
₹ 1,09,80,000 |
Sri Samar Ranjan Sarkar. M-7005461138 |
13.12.2022 |
24.05.2023 |
The client department changed the work site. Hance delayed |
12.08.2023 8 Month |
Demolition of old existing structure completed. Earthwork for foundation is to be started. But now suspended due to again indecision of site selection by ARD authority. |
|
|
|
Dec'23 |
|
|
0.000 |
|
0.000 |
|
|
The requiring department changed the work site. Hence delayed( Letter No. F.4(37)/DDARD (G)/Store/2022/2847-48 Dt.21/03/2023 of the Deputy Director, ARDD.Accordingly, EE, UDP has furnished sueveryed site plan for proposed site. |
|
₹ 1,09,80,000 |
|
|
In progress |
|
|
11 |
Amarpur |
Third Circle |
ARDD |
Veterinary Sub-Centre at West Malbasha under Amarpur Block |
Special Assistance |
17.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
06-04-22 |
18-06-2022 |
₹ 14,20,146 |
Sri Prantosh Saha,Contact No.9436189750 |
03-07-2022 |
10-12-2022 |
Initially delayed due to tland problem |
180 days 02-01-2023 |
Foundation work completed and column up to lintel level completed. Work in progress. Value of work done Rs. 8.00 Lac |
0 |
0 |
50% |
Nov' 23 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
|
|
|
₹ 8,00,000 |
₹ 6,20,146 |
|
|
In progress |
|
|
12 |
Third Circle |
ARDD |
Veterinary Sub-Centre at Ekjancharra under Ompi Block |
Special Assistance |
17.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
04-06-2022 |
28-07-2022 |
₹ 13,03,207 |
Sri Prabal Das,Contact No.9366074685. |
12-08-2022 |
07-01-2023 |
Initially delayed due to tland problem |
180 days 31-02-2023 |
Foundation work in progress. Value of work done Rs. 2.50 Lac |
_ |
_ |
40% |
Aug'23 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
|
|
|
₹ 2,00,000 |
₹ 11,03,207 |
|
1) The EE, KHW has surrendered fund for Rs. 125.45 Lac and communicated to the Addl. Secretary, Directorate of ADD vide letter No.F>7(29)/EE/PWD/KHW/11566-570 Dated 24/02/23 2) EE, Khowai requested the Dy Director, ARDD vide his letter No.F.10(27)/EE/PWD/KHW/12058-12062 Dt. 15-3-23 for handing over the work site. |
In progress |
|
|
13 |
Third Circle |
ARDD |
Veterinary Dispensary at Nutanbazar |
Special Assistance |
81.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
13/4/2022 |
29-08-2022 |
₹ 65,22,933 |
Sri Ratan Paul,Contact No.9436472211 |
13-09-2022 |
20-10-2022 |
Initially delayed due to tland problem |
270 days 31-06-2023 |
First floor roof Slab Work completed. And other ancillary work is in progress. Value of work done Rs. 47.00 Lac |
_ |
_ |
70% |
Mar'24 |
34.53 |
34.00 |
0.53 |
34.00 |
31.23 |
|
|
Fund revalidation submitted on 15/6/2023 for an amount of Rs. 0.53 lakhs |
₹ 47,00,000 |
₹ 18,22,933 |
Memo No.F. F.TC/5/EE/PWD/AMP/6295-309 dt '29-08-2022, |
|
In progress |
|
|
14 |
Santirbazar |
Third Circle |
ARDD |
Veterinary Dispensary at Betaga |
Special Assistance |
81.82 |
NO.F.F.5(672)/ARDD/PLAN/2015/9691-29 dated 16/09/2021 of the Jt Secretary Decondary Education. |
2021-22 |
PNIeT- No:- 16/EE/PWD(R&B)/STB/2022-23 dated, 04-07-2022 |
20-10-2022 |
₹ 80,03,523 |
Gathan Datta 9862453230 |
04-11-2022 |
04-11-2022 |
Work started in due time |
270 days 01-08-2023 |
Roof casting completed. Work in progress. Value of work done= Rs. 45.00 Lakh |
Yet to start |
Not Required |
40% |
Oct' 23 |
0.000 |
0.000 |
0.000 |
0.000 |
10.000 |
|
|
|
₹ 45,00,000 |
₹ 35,03,523 |
No.F. 9(3)/EE/PWD/STB/7256-68 |
|
In progress |
|
|
15 |
Third Circle |
Veterinary Dispensary at Jolaibari |
Special Assistance |
81.82 |
NO.F.F.5(672)/ARDD/PLAN/2015/9691-29 dated 16/09/2021 of the Jt Secretary Decondary Education. |
2021-22 |
PNIeT- No:- 21/EE/PWD(R&B)/STB/2021-22 dated, 22-02-2022 |
17-06-2022 |
₹ 80,33,029 |
Bikram Mitra 7005852266 |
02-07-2022 |
14-10-2022 |
Conerened deprtment was delayed for handing over the clear site. |
270 days 10-04-2023 |
Roof custing completed. Work in progress. Value of work done= Rs. 46.00 Lakh |
Yet to start |
Not Required |
35% |
Oct' 23 |
0.000 |
0.000 |
0.000 |
0.000 |
10.000 |
|
|
|
₹ 46,00,000 |
₹ 34,33,029 |
No.F. 9(3)/EE/PWD/STB/2650-62 |
|
In progress |
|
|
16 |
Belonia |
Third Circle |
Veterinary Hospital at Belonia |
Special Assistance |
118.00 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
12/EE(PWD)/BLN/2022-23 Dt 13-07-2022 |
26.10.2022 |
₹ 91,89,451 |
Sankar Kanti Saha 9436124030 |
10.11.2022 |
10.11.2022 |
Work commenced in time |
09.11.2023 365 days |
Finishing work is in progress. Rs.70.00 lakh |
Not yet |
NA |
90% |
Nov.23 |
45.927 |
45.927 |
0.000 |
45.927 |
72.080 |
|
----- |
|
₹ 70,00,000 |
₹ 21,89,451 |
No.F.7(20 )Pt-I/EE(PW D)/BLN/DIV N/5103-12 Dt.26.10.22 |
|
In progress |
|
|
17 |
Sabroom |
Third Circle |
Veterinary Dispensary Strengthening of Veterinary Health Care Infrustructure through construction of Veterinary Dispensary at Sabroom ( G+1 Storied)/ Phase-I , Ground Floor only |
Special Assistance |
118.00 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
25-07-2022 |
23-09-2022 |
₹ 90,61,261 |
Shri Ratan Paul (Mob# 9436472211) |
28-10-2022 |
28-10-2022 |
|
365 Days 27-10-2023 |
Brick work completed, Plastering work is in progress. Value of work done: Rs. 60.00 Lakh(Approx) |
|
|
60% |
Oct-23 |
52.180 |
33.600 |
18.580 |
0.000 |
30.000 |
|
|
|
₹ 60,00,000 |
₹ 30,61,261 |
|
|
In progress |
|
|
18 |
Jirania |
Fourth Circle |
ARDD |
Vertical extension of Veterinary College under NABARD |
RIDF |
446.34 |
A/A and E/S: No. Board F.5(672)/ARD/PLAN/2015/1239-45 Dt. 30/04/2021 of the D.S , ARDD for 1) Vertical extension Vetenary College 2) Internal raod 3)Internal road 4) Boundrary wall & Guard room For Rs,446.34 Lac |
2021-22 |
Combine Tender Veterinary College and Veterinary Science , Animal husbandary College |
|
|
|
|
|
|
|
Recommended by the DPC for acceptasnce of the tender and sent to the Administrative Department for approval. |
|
|
|
|
Rs.50.00 lakhs but surrendered |
|
|
|
|
|
|
(Reporting of project: Physical status, Tendering etc combine and Separate for Financial status.) Technical bid sent to the SE, 4th Circle, PWD(R&B) on dated 13/02/2023. Est Cost Rs.13,42,45,934/- |
|
₹ 0 |
|
|
Tendering Stage |
|
|
19 |
Jirania |
Fourth Circle |
ARDD |
Vertical extension of Veterinary Science & Animal husbandary College/ 1) Admn Block (First floor), 2) Academic Block (part of 3rd floor,lift block 4th floor, Lift Machine room 5th Floor3) Boy's Hostel' (2nd Floor)4) Girls' Hostel (2nd Floor) 5) 2 Nos Lift |
Special Assistance |
1500.00 |
A/A: No.F.8(132)/E-Cell/ARDD/CONStr/22/1616-1625 dated 12/09/22 of the Director ARDD. 1) Admn Block (First floor), Rs. 604.12 Lac 2) Academic Block (part of 3rd floor,lift block 4th floor, Lift Machine room 5th Floor Rs. 340.69 Lac 3) Boy's Hostel (2nd Floor)Rs. 253.72 Lac 4) Girls' Hostel (2nd Floor) Rs. 253.72 Lac 5) 2 Nos Lift Rs. 47.76 Lac. (Total: Rs. 1500.00 Lac). E/S: No.8(133)/E-Cell/ARDD/CONSTN/2022/895-905 Dt. 8/7/22 of the Director , ARDD for Rs, 1500.00 Lac |
2022-23 |
|
|
|
|
|
|
|
|
₹ 0 |
|
|
Tendering Stage |
|
|
20 |
Mohanpur |
Fourth Circle |
ARDD |
Veterinary Sub-Centre at Barkathal under Hezamara Block |
Special Assistance |
17.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
Project Dropped |
Project Dropped |
Project Dropped |
Project Dropped |
Project Dropped |
Project Dropped |
Project Dropped |
Project Dropped |
Project Dropped |
|
|
|
|
|
|
|
|
|
|
|
|
|
#VALUE! |
|
|
Cancelled |
|
|
21 |
Veterinary Dispensary Strengthening of Veterinary Health Care Infrustructure through construction of Veterinary Dispensary at Hezamara / Construction of building for Vety. Dispensaries including Doctor/staff room with lavatory, Dispensing room, medicine store, small laboratory, animal shed including water supply facility & electification |
Special Assistance |
81.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
|
20-10-2022 |
₹ 76,58,000 |
Tamal sur Chowdury |
05-11-2022 |
|
Demolishing work in progress by the ARDD. Work will be started soon |
July' 2023 Period? |
Work not yet started |
|
|
|
|
|
0.000 |
0.000 |
0.000 |
0.000 |
|
|
|
|
₹ 76,58,000 |
|
|
Not yet started |
|
|
22 |
Modernization of State Poultry farm with Automated layer Unit at Gandhigram, West Tripura |
NEC |
444.00 |
No.F.8(92)/E-Cell/ARDD/CONSTN/08/1095-1104 dt29/07/21 |
2021-22 |
|
16-03-2022 |
₹ 3,59,00,000 |
Tapesh Ch Debnath |
04.01.2022 |
29.04.2022 |
Initial delay for clear site |
15.03.2023 Period? |
All structural work completed in Hatchery,Layer and Brooder house building. In Grower House building structural work completed upto slab level. |
|
|
60% |
Dec-23 |
10.000 |
10.000 |
0.000 |
10.000 |
433.440 |
|
|
|
|
₹ 3,59,00,000 |
|
|
In progress |
|
|
23 |
Bishramganj |
Fourth Circle |
ARDD |
Veterinary Sub-Centre at Brajapur (replaced by Lalsinmura) under Charalim Block |
Special Assistance |
17.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
19-11-2022 |
17-04-2023 |
₹ 17,96,713 |
Basu Ranjan Shil, 7005581944 |
02.05.2023 |
|
Delay due to Location modified by client dept and non handing over of clear site |
Date: 270 days |
Work order issued. Clear site yet to be handed over by client Dept. |
0.00 |
NA |
0.00 |
|
15.710 |
|
15.710 |
|
|
|
|
Delayed due to Location modified by client dept. |
|
₹ 17,96,713 |
|
|
Not yet started |
|
|
24 |
Bishramganj |
Fourth Circle |
ARDD |
Veterinary Sub-Centre at Sutarmura (replaced by Ramnagar) under Charalim Block |
Special Assistance |
17.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
19-11-2022 |
|
|
|
|
|
Delay due to Location modified by client dept and non handing over of clear site |
Date:? 270 days |
Clear site not yet handed over by client de[pt. |
0.00 |
NA |
0.00 |
|
|
0.000 |
|
|
|
|
Delayed due to Location modified by client dept. LOA issued. |
|
₹ 0 |
|
|
Not yet started |
|
|
25 |
Bishramganj |
Fourth Circle |
ARDD |
Veterinary Sub-Centr at South Charilam under Charalim Block /4th Call |
Special Assistance |
17.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
17-12-2022 '06-03-2023 (Fourth Call) |
23-05-2012 |
₹ 15,01,231 |
Kausik Das 7085736503 |
23-05-2001 |
Not started |
Delay due to Location modified by client dept and non handing over of clear site |
270 days Date? |
Clear site not yet handed over by client deptt..LoA issued |
0.00 |
NA |
0.00 |
|
|
0.000 |
|
|
|
|
In 3rd call no tender received. Tender invited in 4th Call. |
|
₹ 15,01,231 |
|
|
Not yet started |
|
|
26 |
Sonamura |
Fourth Circle |
ARDD |
Veterinary Sub-Centre at Veluarchar under Boxonagar Block |
Special Assistance |
17.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
DNIT No. 88/EE/SNM/PWD/2021-22. Dt…………. |
28-04-2022 |
₹ 16,13,131 |
Najrul Islam 8974367745 |
12-05-2022 |
17-05-2022 |
|
12-11-2022 Period? |
GCI sheet roofing work in progress. Approx value of work done Rs 11.53 |
|
|
65% |
June-23 |
58.590 |
11.530 |
21.560 |
|
|
|
|
Recept of fund together for SL No 26,27,32 |
₹ 11,53,000 |
₹ 4,60,131 |
Vide No.F.10(30)/EE/SNM/PWD/461-76 dt.28-04-2022 |
|
In progress |
|
|
27 |
Veterinary Sub-Centre at Putia under Boxonagar Block |
Special Assistance |
17.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
DNIT No. 87/EE/SNM/PWD/2021-22. Dt…….. |
28-04-2022 |
₹ 16,13,131 |
Basar Miah 9863266448 |
12-05-2022 |
28-09-2022 |
|
12-11-2022 Period? |
Work Completed on 22-03-2023 |
|
|
100% |
|
|
6.500 |
|
|
|
22-03-2023 |
|
Work Completed on 22-03-2023 |
₹ 15,93,000 |
₹ 20,131 |
Vide No.F.10(30)/EE/SNM/PWD/445-60 dt.28-04-2022 |
|
Completed in all respect |
|
|
28 |
Veterinary Dispensary at Kathalia |
Special Assistance |
81.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
24/B/DNIeT/SE-IV/PWD(R&B)/ 2021-22 Dt……... |
06-07-2022 |
₹ 78,92,722 |
Bishnu Pada Paul 9436519065 |
21-07-2022 |
11-11-2022 |
|
21-07-2023 Period? |
first floor slab custing is completed. Value of work done Rs. 48.93 Lac |
|
|
60% |
Dec.23 |
|
19.000 |
|
|
|
|
|
|
₹ 48,93,000 |
₹ 29,99,722 |
Vide No.F.10(30)/EE/SNM/PWD/2253-66 dt.06-07-2022 |
|
In progress |
|
|
29 |
ARDD |
Veterinary Dispensary at Melaghar |
Special Assistance |
81.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
23/B/DNIeT/SE-IV/ PWD(R&B)/2021-22. Dt……….. |
|
|
|
|
|
|
|
Clear site is not handed over by the authority till now. |
|
|
|
|
|
|
0.000 |
|
|
|
|
|
|
₹ 0 |
|
|
Not yet started |
|
|
30 |
LTV |
Veterinary Sub-Centre at Dhumacherra under Ganganagar Block |
Special Assistance |
17.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
|
|
|
|
|
|
|
|
Work order not issued due to non-availability of land. |
|
|
|
|
|
|
0.000 |
|
|
|
|
Work order not issued due to non-available of Land |
|
₹ 0 |
|
|
Not yet started |
|
|
32 |
Gondatwisa |
Veterinary Dispensary at Raishyabari |
Special Assistance |
81.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
|
20-07-2022 |
₹ 79,00,000 |
Rajib Prasad 8119003215 |
05-08-2022 |
20-02-2023 |
Delay due to Hand over of clear site |
6 Month '19-02-2023 |
Roof Slab casting completed. Value of work done (approx): Rs. 40.00 Lac |
|
|
51% |
Sept'23 |
29.000 |
29.000 |
0.000 |
|
|
|
|
|
₹ 40,00,000 |
₹ 39,00,000 |
|
|
In progress |
|
|
33 |
Dharmanagar |
Fifth Circle |
Fishery |
Construction of Fish Farmer training Institute at Dharmanagar |
|
100.00 |
F.4(2)-EE(FY)/CONSTN/2008-09/13461-64, DATED: 12-05-2016. |
2016-17 |
10-03-2017 |
25-07-2017 |
₹ 87,59,673 |
Sri Sajal Paul 9436132786 |
08-08-2017 |
08-08-2017 |
Work delayed due to non availibility of additional funds |
24-11-2018 15 Months |
Building Portion including plaster work completed. Flooring and Finishing work in progress.Value of work done Rs. 95.00 Lac |
|
|
90% |
Dec-23 |
100.000 |
86.000 |
14.000 |
86.000 |
20.000 |
|
|
Additional fund required for additional works and internal electrification |
₹ 95,00,000 |
₹ -7,40,327 |
|
|
In progress |
|
|
34 |
Teliamura |
Second Circle |
FCS & CA |
Proposed Construction of single storied laboratory cum office building of Legal Metrology at Teliamura |
Strengthening Legal Metrology insfrastructure of state & Uts. |
50.00 |
Rs. 50.00 Lakh Memo No.F. 14(10)/LM/TLM/LAB/193-200 dt. 31/01/2022 of the Addl. Secretary to the Govt. of Tripura. |
2021-22 |
06-06-2022 |
30-09-2022 |
₹ 44,31,342 |
Sri Debashish Debnath 8014492537 |
15-10-2022 |
09-11-2022 |
initial delay in handing over over of clear site by the client department |
14-04-2023 (6 months) |
Work completed except Internal electrification. Total value of work done Rs.44.31 Lac |
Tender will be opened on 06-07-23 |
|
100% |
July,23 |
20.000 |
20.000 |
0.000 |
20.000 |
30.000 |
|
|
|
₹ 44,31,000 |
₹ 342 |
|
|
In progress |
|
|
35 |
Santirbazar |
Third Circle |
Forest |
Construction of Indian Bison conservation park at Patichari under North Takmacharra Mouja,Santirbazar,South Tripura. |
Special assistance |
252.00 |
NO.F.8(196)/WL/2008-2012/2781-95 dated 23/03/2021 |
2020-21 |
PNIeT- No:- 15/EE/PWD(R&B)/STB/2021-22 dated, 11-01-2022 |
26-04-2022 |
₹ 2,55,94,718 |
Shri Sajal Bhattacharjee (Mob: 9774910015) |
11-05-2022 |
28-04-2022 |
Work started in due time. |
365 Days 10-05-2023 |
50% work completed, Work in progress Value of work done= Rs. 100.00 Lakh |
Yet to start |
Not Required |
50% |
July' 23 |
100.000 |
100.000 |
0.000 |
0.000 |
156.947 |
|
|
|
₹ 1,00,00,000 |
₹ 1,55,94,718 |
No.F. 9(3)/EE/ PWD/STB/620-32 |
|
In progress |
|
|
36 |
Belonia |
Third Circle |
Forest |
Construction of Type-V quarter for District Forest Officer, South Tripura near Sarasima under Belonia Sub-Division during the year 2022-2023 |
State Plan |
91.00 |
No.F.5(672)/ARDD/PLAN/2015/9691-29 dt,. 16-09-2021 of the Joint Secretary to the Govt. of Tripura |
2021-22 |
24/EE(PWD)/BLN/2022-23 Dt 14-10-2022 |
09.01.2023 |
₹ 77,15,000 |
Rajib Nandi 9436517634 |
24.01.2023 |
25.04.2023 |
Delayed by the agency |
20.11.2023 270 Days |
Work completed upto plinth level. Column work is in p rogress at Ground Floor Rs. 15.00 Lakh |
Not yet |
NA |
---- |
Nov-23 |
91.000 |
0.000 |
91.000 |
0.000 |
0.000 |
Not yet completed |
|
|
₹ 15,00,000 |
₹ 62,15,000 |
No.F.7(20) Pt-I/EE(PWD ) /BLN/DIVN /7443-51 Dt.09.01.2023 |
|
In progress |
|
|
37 |
Bishalgarh |
Fourth Circle |
Construction of Aviary at Sepahijala sanctuary |
Forest |
150.00 |
F.8(127)/WL-2020-21/APO-CZA/Part/612-58, Dated-29/06/2022 |
2022-23 |
PNIeT No 12/EE-BSLD/PWD(R&B)/2022-23, Dated-08/07/2022, DNIeT-05/B/DNIeT/SE-IV/PWD(R&B)/22-23 |
09-09-2022 |
₹ 1,18,29,255 |
Nikhil Rn. Chakraborty (8256939330) |
24-09-2022 |
21-12-2022 |
Due to late receipt of structural drawing |
180 Days (22-03-2023) |
Foundation work is in progress. Fabrication of steel work is in progress. 48% Work Completed. Rs 56.80 Lakh |
Nil |
Nil |
48% |
July-23 |
100.000 |
35.000 |
65.000 |
0.000 |
0.000 |
|
|
|
₹ 56,80,000 |
₹ 61,49,255 |
|
|
In progress |
|
|
38 |
Construction of Reptile House at Sepahijala Zoological Park. |
Forest |
103.00 |
F.8(127)/For-WL-2019-20/APO-CZA/Part/2277-87, Dated-13/02/2020 |
2019-20 |
PNIeT No 09/EE-BSLD/PWD(R&B)/2020-21, Dated-19/11/2020, DNIeT-04/B/DNIeT/SE-IV/PWD(R&B)/2020-21 |
18-01-2021 |
₹ 1,02,89,419 |
Tapas Kumar Saha, (9862068690) |
02-02-2021 |
10-08-2021 |
|
31-07-2021 Period? |
Work completed in all respect except few Finishing work. 90% Work Completed. Rs 102.60 Lakh |
Nil |
Nil |
90% |
July-23 |
79.774 |
79.774 |
0.000 |
0.000 |
34.000 |
|
|
|
₹ 1,02,60,000 |
₹ 29,419 |
|
|
In progress |
|
|
39 |
Kailashahar |
First Circle |
Home(Jail) |
Constn of Kailashahar jail/Balance work (5th Call) |
SPA |
1598.00 |
No.F.5(35)/PC/PD-II/2014 dt 22/03/2014 |
2013-14 |
31-05-2022 |
12-10-2022 |
₹ 5,87,23,201 |
Tantia Construction Ltd 9903900530 |
26-10-2022 |
26-10-2022 |
|
25-07-2023 Period 9 Month |
Plastering work is in progress. Tiles flooring at qtr building in progress.Approx value of work done Rs.50.00 Lac |
Preparing estimate |
0% |
8% |
Oct'23 |
0.000 |
0.000 |
0.000 |
0.000 |
100.000 |
|
Not required |
|
₹ 50,00,000 |
₹ 5,37,23,201 |
F.23(01)EE/KLSD/6998-7023 dt 12-10-22 |
|
In progress |
|
|
40 |
Bishalgarh |
Constn of 56 nos staff qtr at Bishalgarh jail /BALANCE WORK |
SPA |
696.00 |
F.I-604/IGP/2020/663-70, Dated-18/02/2020 |
|
PNIeT No 26/EE-BSLD/PWD(R&B)/2021-22, Dated-09/02/2022, DNIeT-21/B/DNIeT/SE-IV/PWD(R&B)/2021-22 |
29-08-2022 |
₹ 1,97,52,218 |
Tapas Kumar Saha, (9862068690) |
12-09-2022 |
14-09-2022 |
|
180 Days (11-03-2023) |
Out of 36 nos quarter 24 Nos completed in all respect, rest work is in progress. 95% Work Completed. Rs 187.65 Lakh |
100% |
Nil |
95% |
Oct-23 |
133.950 |
133.950 |
0.000 |
Nil |
0.000 |
|
|
|
₹ 1,87,65,000 |
₹ 9,87,218 |
|
|
In progress |
|
|
41 |
Construction of Unit Quarter guard in respect of 1st BN.TSR.at Gakulnagar,Sepahijala District,Tripura. |
No Scheme |
273.00 |
No AA & ES received |
|
|
|
|
|
|
|
|
|
Arch Drawing prepared & sent to the DIG,Police.After getting the A/A & E/S further process will be started. |
|
|
|
|
|
|
0.000 |
|
|
|
|
|
|
₹ 0 |
|
|
Not yet started |
|
|
42 |
Fourth Circle |
Home(Fire) |
Constn of Ananda nagar Fire station |
Major works capital (4059 |
462.00 |
No.F.5(7)-PD/2015/212 Dated 20/01/2022 of the DS, Home (Fire & Emergency Service) for Rs. 462.14 Lac (A/A) & Rs. 130.00 Lac (E/S) |
2022-23 |
PNIeT No 23/EE-BSLD/PWD(R&B)/2021-22, Dated-16/12/2021. DNIeT-CE(Buildings)/PWD/DNIT/ACE/Project Unit/48/2021-22 |
18-03-2022 |
₹ 3,04,58,107 |
Malay Lodh (8974947801) |
01-04-2022 |
01-04-2022 |
|
15 Months ('30-06-2023) |
Ground Floor work completed, First Floor finishinh work is in progress. 85% Work Completed. Rs 258.90 Lakh |
Ground Floor completed. 50% work completed |
Nil |
85% |
Aug-23 |
300.000 |
148.250 |
151.750 |
0.000 |
0.000 |
|
|
|
₹ 2,58,90,000 |
₹ 45,68,107 |
|
|
In progress |
|
|
43 |
LTV |
Fifth Circle |
Home (Police) |
Constn of 8th BN TSR Head quarter at Lalcherra, L.T. Valley. |
TFC |
1337.00 |
No.F.8(226)/PC(PD-I)/2006/S-I/S/9132 dated 11/12/2008 of the CE,PWD(R&B). |
2008-09 |
Cost Plus Basis |
24-01-2009. |
Cost Plus Basis (TSR-2008 + 23.69% above) |
NPCC Ltd. |
09-02-2009. |
'24-02-2009 |
Delay occurred due to non-available of clear site |
24 months from the date of approval of DPR or handing over of site. |
70.00% physical progress and 11.80 crore work done.Now, work suspended by the agency. |
70% |
Not required |
70% |
|
1179.720 |
1179.720 |
0.000 |
1179.720 |
|
|
Initially 2(two) years delay occurred due to forest land diversion and thereafter delayed by the Agency. Recision proposal will be initiated. |
Rescision proposal to be initiated. |
₹ 11,80,00,000 |
= |
|
|
In progress |
|
|
44 |
Dharmanagar |
First Circle |
Health(DFWPM) |
Construction of 10 bedded PHC with 10 nos. quarters at existing Uptakhali PHC |
NHM |
645.00 |
No.F.19(109)-PLAN/DFWPM/ 4547-57)V-I0 dated 14/07/2021 |
2021-22 |
07-12-2021 |
23-03-2022 |
₹ 4,91,79,788 |
M/S J.C Nath & Sons 9436132164 |
06-04-2022 |
06-04-2022 |
No Delay |
02-07-2024 18 Months |
Finshing work for PHC mainblock in progress. Type-I, Type-II quarter slab casting complete up to F-II level. Brick work in progrsss. Foundation work upto plinth level for Type-III quarter completed. value of work done 240 lakhs |
Consealed pipeline installed |
Not reqd. |
60% |
June-24 |
215.410 |
215.410 |
0.000 |
215.410 |
429.590 |
|
|
|
₹ 2,40,00,000 |
₹ 2,51,79,788 |
|
|
In progress |
|
|
45 |
Dharmanagar |
First Circle |
Health(DHS) |
Construction of single storied building for Trauma Care Centre (Level-III) in the North District Hospital at Dharmanagar, North Tripura. |
RIDF |
390.00 |
F.3(2-396)-PLAN/DHS/2015/287-94/685, DATED: 29-05-2017. |
2017-18 |
16-04-2018 |
11-10-2018 |
₹ 3,53,68,858 |
M/S S.N Bhattacharjee & Sons 9612705733 |
25-10-2018 |
25-10-2018 |
Delayed due to demolition work of existing structures. |
|
Finishing (painting) work is in progress. Value of work done Rs. 340.00 Lac approx. |
80.00% |
|
95% |
Aug-23 |
230.000 |
230.000 |
0.000 |
230.000 |
160.000 |
|
|
|
₹ 3,40,00,000 |
₹ 13,68,858 |
|
|
In progress |
|
|
46 |
Vertical extension of Trauma Centre of District Hospital for constn. Of 50 seated Field Hospital at Dharmanagar under ECRP-II/ Building portion in/c internal electification ' Sanitary & Swerage |
NHM (ECRP-II) |
256.77 |
F.3(208)/DHFWS/CMO/N/ECRP-II/2022/5041-45 Dt. 12/04/2023 of the DM & Collector, North Tripura |
2023-24 |
( Date of Notice inviting e-tender) |
|
|
|
|
|
|
|
Tender under scrutiny ( TEC meeting held 21/6/23) |
|
|
|
|
|
|
|
|
|
|
|
DNIT issued for Rs. 180.06 Lac on 18-04-2023. Tender under scrutiny at CE Office. |
|
|
|
|
Tendering Stage |
|
|
47 |
Kanchanpur |
Health(NHM) |
Proposed construction of single storied 10(ten) bedded Primary Health Centre (PHC) building including 10(ten) Nos. Staff Quarters Kitchen, Morgue, Garage & Generator with Driver Room Building at existing Damcherra PHC under Kanchanpur Sub-division, North Tripura under NHM |
NHM |
486.00 |
No.F.19(42)-PLAN/DFWPM/2000(S) dated 19/11/2018 |
2018-19 |
31-05-2019 |
17-10-2019 |
₹ 4,34,57,000 |
Sri Arun Kanti Chanda 9436132072 |
01-11-2019 |
01-11-2019 |
|
Oct, 2021 24 Months |
Finishing work of Main Building in progress. T-III qtr columns upto lintel level casting complted. T II Qtr 2nd floor slab casting completed. Brick and Plastering work in progress. T-I qtr clear site yet to be finalized. Rs. 215.00 Lakh |
|
|
43% |
Nov.23 |
200.000 |
200.000 |
0.000 |
200.000 |
286.000 |
|
|
Work is in progress. |
₹ 2,15,00,000 |
₹ 2,19,57,000 |
|
|
In progress |
|
|
48 |
Kanchanpur |
First Circle |
Health(DHS) |
Constn of 16 nos staff qtr Kanchanpur Hospital in Sub-Divisional Hospital Complex. |
SJTNY |
598.00 |
1)Administrative approval only (No.F. 3(5-137)-PLAN/DHS/2022-23 Dt. 17/01/23 of the D.S, Health & Family Welfare Deptt) 2) E/S received vide memo No.F.(5-137)-PLAN/DHS/2022-23 Dt. 28/04/2023 of the D.S of Health & Family Welfare Deptt. for Rs. 598.00 Lac. |
2022-23 |
24-05-2023 |
|
|
|
|
|
|
|
1st Call of tender received and under scrutiny. |
|
|
|
|
|
|
|
|
|
|
|
|
|
₹ 0 |
|
DNIT issued on 20/05/23 , |
Not yet started |
|
|
49 |
Kailashahar |
Health(NHM) |
Construction of 10 nos quarter at Kanika Memorial PHC |
NHM |
169.00 |
No.F19(42)=PLAN/DFWPM/2000(S)/3043-67 dt19/11/18 of the Under Secretary Health and Family Welfare Department. |
2018-19 |
09-12-2021 |
03-03-2022 |
₹ 2,16,24,939 |
Mohan Lal Singha 9436120514 |
17-03-2022 |
17-03-2022 |
|
16-09-2023 (Period) 18 Month |
Structural and brick work complted.Finishing work is in progress.Approx value of work done Rs.190.00 Lac |
100% |
0% |
88% |
Sept.23 |
150.000 |
150.000 |
0.000 |
0.000 |
66.000 |
|
Not required |
|
₹ 1,90,00,000 |
₹ 26,24,939 |
F.25(56)EE/KLSD/6711-26 dt 3/3/22 |
|
In progress |
|
|
50 |
Health(DFWPM) |
Proposed construction of District Training Centre at Kailashahar, Unakoti District, Tripura. |
IMR |
597.00 |
No.F.5(35)/PC/PD-II/2015 dt 23-04-2016 |
2016-17 |
11-02-2016 |
28-10-2016 |
₹ 3,61,61,952 |
Salil Acharjee 7308686797 |
11-11-2016 |
11-11-2016 |
|
10-11-2018 (Period) 24 Months |
Tiles flooring, alluminium, sanitary, constn of water reservoir and boundary wall work is in progress.Approx value of work done Rs.340.00 Lac |
100% |
0% |
95% |
Aug-23 |
314.850 |
314.850 |
0.000 |
314.850 |
40.000 |
|
Not required |
|
₹ 3,40,00,000 |
₹ 21,61,952 |
F.26(51)EE/KLSD/4407-25 dt 28/10/16 |
Fund surrendered Rs 32.90 Lakh |
In progress |
|
|
51 |
Kailashahar |
First Circle |
Health(DFWPM) |
Construction of 10 bedded PHC at existing Irani PHC(6th Call) |
NHM |
358.00 |
No.F.19(109)-PLAN/DFWPM/ 4547-57)V-I0 dated 14/07/2021 |
2021-22 |
03-05-2023(6th Call) |
|
|
|
|
|
|
|
6th Call tender under scrutiny.( Letter issued to Bidder regarding shortfall of Documents) |
|
|
|
|
|
|
0.000 |
|
|
|
|
|
|
₹ 0 |
|
|
Tendering Stage |
|
|
52 |
Kailashahar |
First Circle |
Health(DHS) |
Constn 48 nos staff qtr,Kailashahar Hospital under NLCPR |
NLCPR |
1110.00 |
No.F.5(35)/PC/PD-II/2017 dt 22-12-2017 |
2017-18 |
28-06-2016 |
07-03-2018 |
₹ 9,04,45,776 |
M/S J.C Nath & Sons 9436132164 |
21-03-18 |
21-03-2018 |
|
20-03-20 (Period) 24 Month |
Completed & Just handed over (Date?). |
100% |
0% |
100% |
Completed on 02/05/2022. |
904.450 |
904.450 |
0.000 |
904.450 |
0.000 |
02-05-2022 |
Yes 773 days time extension required Levy /LD ? |
|
₹ 9,04,45,776 |
₹ 0 |
F.25(1)EE/KLSD/5971-89 dt 7/3/18 |
|
Completed in all respect |
|
|
53 |
Kumarghat |
First Circle |
Health(NHM) |
Construction of 10 Bedded PHC at Pecharthal, Kumarghat |
NHM |
210.00 |
No.F.19(610)-PLAN/DFWPM/2017/1258-85 (V-I) dt.03/07/2017. |
2017-18 |
09-03-2022 |
12-08-2022 |
₹ 2,03,00,000 |
Sushen Ch. Das 98622 02500 |
27-08-2022 |
20-09-2022 |
Initially, delayed for 12 months due to site problem & Covid |
19-06-2023 10 Moths |
Work in progress. Above lintel level. Value of work done Rs. 160.00 Lac |
50% |
0% |
55% |
Dec-23 |
150.000 |
150.000 |
0.000 |
150.000 |
65.000 |
|
6 (Six) months |
Work is in progress full swing. Project is delayed due to cancellation of First call of tender and finalisation of 2nd call of tender on 15-03-2022. |
₹ 1,60,00,000 |
₹ 43,00,000 |
No.F.34(14A)/EE/KD/2913-2927 dated,12/08/2022 |
|
In progress |
|
|
54 |
Kumarghat |
First Circle |
Health(NHM) |
Construction of 10 beded PHC with 10 (ten) Nos. staff quarters at Kanchanbari under Kumarghat Subdivision |
NHM |
458.00 |
F.19(219)-PLAN/DFWPM/2000 dt.04/01/2018. |
2017-18 |
04-07-2018 |
02-03-2020 |
₹ 4,46,84,000 |
Sanjib Kr. Prasad 94021 66076 |
17-03-2020 |
24-12-2020 |
Initially delayed fof Covid-19 & Site dispute. |
01-03-2022 12 Months |
Main building completed, Finishing Work in progress, T-III Qtr Finishing work in progress. Work of T-I & T-II Qtr first flour at roof level. Value of wrok done (approx) Rs 350.00 Lac |
100% |
N.A. |
75% |
Jul 23 |
400.000 |
225.000 |
175.000 |
200.000 |
400.000 |
Delay in finalisation of tender and site dispute. |
6 (Six) months |
|
₹ 3,50,00,000 |
₹ 96,84,000 |
|
|
In progress |
|
|
55 |
Health(DHS) |
Proposed 1000 seated capacity town Hall at Kumarghat |
UDD |
1180.00 |
F.16(15)-UDD/DUD/2014/8839-46 dt.31/10/14. |
2014-15 |
19-05-2015 |
14-09-2016 |
₹ 11,80,00,000 |
N.K. Dhar 94361 22664 |
29-09-2016 |
28-02-2017 |
Site dispute, Drawing, Non availability of required fund. |
28-09-2018 12 Moths |
All completed except chair. Value of work done Rs……..Lac |
100% |
100% |
99% |
May-23 |
1180.000 |
1070.00 |
110.000 |
1070.000 |
0.000 |
|
2 Years requied |
Completed except auditorium chair |
|
₹ 11,80,00,000 |
|
|
In progress |
|
|
56 |
Khowai |
Second Circle |
Health(NHM) |
Constn of 10 bedded PHC in/C 8 Nos Qtr( Ty-I: 4 Nos, Ty-II:2 Nos, Ty-III: 2 Nos. at Chebri PHC |
NHM |
486.00 |
No.F.19(42)-PLAN/DFWPM/2000(S) dated 19/11/2018 |
2018-19 |
02-11-2020 |
14-06-2021 |
₹ 4,44,53,888 |
Jasodalal Roy (9436137937) |
29-06-2021 |
10-07-2021 |
|
24 Months (13-06-2023) |
Flooring and painting work in progress ( Rs. 400.00 Lac) |
55% |
Nil |
91% |
Aug'23 |
200.000 |
200.000 |
0.000 |
200.000 |
244.538 |
|
|
|
₹ 4,00,00,000 |
₹ 44,53,888 |
|
1) Demand of Rs. 100.00 lac placed by the EE, KHW to the State Prog Office vide letter No.F.7(29)/EE/PWD (R&B)/KHW/11614-617 dated 27/02/23 |
In progress |
|
|
57 |
Agt Div-V |
Health(NHM) |
Proposed construction of Urban Primary Health Centre(UPHC) at A.D.nagar, Agartala |
NHM |
210.00 |
Memo No. F.19(637)-PLAN/DFWPM/2020 dated 15.06.2020. Under Secretary , Govt. of Triura. |
2020-21 |
12.07.2021 |
08.10.2021 |
1,69,50,518 |
Sri Satyabrata Roy |
23.10.2021 |
04.02.2022 |
Initially delayed due to change of site & layout plan. |
9 Months/ 23.07.2022 |
Grond floor roof castng completed.Plastering completed. Approx. value of work done Rs 150.00Lac |
20% |
N.A. |
50% |
Sept-23 |
150.000 |
150.00 |
0 |
0 |
73.00 |
|
|
Work is in progress. Delayed due to selection of site . Clear site was not available. Architechtural/ Structural drawing modified. |
₹ 1,50,00,000 |
Rs.73.00 (Including deviation & IE works) |
No.F.7(7)/EE-V/AGT/PWD/2020-21/3748-65 dated 08.10.2021 |
1) DNIT No. ACE/Project Unit/PWD/(Building)/DNIT/16/2021-22 PNIT No. 04/B/EE-V/AGT/PWD/(R&B)/2021-22. dated 12.07.2021 2) Tentative Deviation for an amount of 39.00 Lakh processed to the competent authority for approval. 3) Completion of the project is August, 2023 subject to the approval of this Tentative deviation. Mainly Deviation occurred due to site condition as part of the foundation of building raised from the ditch (low lying area), the resulting addtional tie , column, grade slab etc. matter earlier comunicated to the competent authority and Director, NHM before execution |
In progress |
|
|
58 |
Amarpur |
Third Circle |
Health(NHM) |
Proposed construction of single storied 10(ten) bedded Primary Health Centre (PHC) building including 10(ten) Nos. Staff Quarters [ Kitchen, Morgue, Garage & Generator with Driver Room Building and Boundary wall at Silachari, Karbook Sub-division, Gomati District, Tripura |
NHM |
486.00 |
No.F.19(610)-PLAN/ DFWPM / 2017, Date,3-7-17 of the Under Secretary to the Govt of Tripura ,Health & Family Welfare Deptt. Rs.4.86 |
2017-18 |
11-06-2017 |
04-09-2018 |
₹ 3,92,63,612 |
Sri Ashutosh Bandhopadhaya,Contact No.9436527307 |
23-04-2018 |
02-01-2019 |
Work has been suspended by the agency in long time many show cuase letter issued against agency. Now LD proposal sent to higher authority for approval. |
24(Twenty four Month) 22-04-2020 |
T-I Qtr= Completed upto Plinth level. T-II Qtr= Completed upto roof level. T-III Qtr= Structural work in progress,Work suspended by the agency. Work re-started. Value of work done 102.14 lakhs. |
0.00 |
0.00 |
50% |
Dec-23 |
250.000 |
250.000 |
0.000 |
250.000 |
142.64 |
|
|
Notice issued under CL 54( Rescision of contract under risk & cost on 20/05/2023). Accordingly the liquidated damaged report submitted to SE-III circle Udaipur on 12-06-2023. |
₹ 1,02,14,000 |
₹ 2,90,49,612 |
04-09-2018, Memo No.F. F.TC/5/EE/PWD/AMP/311-26 |
|
In progress |
|
|
59 |
Health(DHS) |
Constn of 16 nos staff qtr Amarpur Hospital at Amarpur Sub-Divisional Hospital Complex/Balance work |
SJTNY |
553.00 |
Administrative approval only (No.F. 3(5-137)-PLAN/DHS/2022-23 Dt. 17/01/23 of the D.S, Health & Family Welfare Deptt). E/S vide Memo No.F. 3(5-137)-PLAN/DHS/2022-23 Dt. 28/04/23 of the D.S, Health & Family Welfare Deptt) for Rs.552.77 Lac |
2022-23 |
24/5/2022 |
|
|
|
|
|
|
|
DPC recommended for acceptance and sent to the administrative department for approval of the tender. |
|
|
|
|
200.000 |
|
200.000 |
|
|
|
|
1) NIeT: 24-05-2022 07/NIT/EE/PWD/AMP/2022-23. |
|
₹ 0 |
|
1) Previously sanction Rs. 406.00 Lac vide A/A & E/S memo No.F. 3(1-560)-PLAN/DHS/2010/2462-69/10128(V-III) dated 15/11/2016 of the U.S , Health & Family Welfare Deptt. Head of A/C Central Assistance to State Plan. 2) SE, PU vide letter No.F.5(35)/PC(PD-II)/2022 (S)/380-83 Dt. 17/04/23 has requested to accord E/S for Rs. 552.00 lac to the Director of Health Services. |
Tendering Stage |
|
|
60 |
Udaipur |
Health(NHM) |
Proposed construction of 50 ( fifty) bedded MCH Wing [ G+3 Storied ] building at Gomati District Hospital, Tepania, Udaipur, Gomati District, Tripura (2nd Call). |
NHM |
798.00 |
No.3(2-425)-PLAN/DHS/2016-17/3650-60, dt.06.03.2017. Amount : 797.00 Lakh |
2015-16 |
20.01.2021 |
31.08.2021 |
₹ 6,49,54,000 |
Sri Jiban Kumar Saha. M-9436122376 |
12.09.2021 |
06.11.2021 |
1st structural drawing was received on 07.09.2021 but there was some discripency regarding location of ramp. Finaly 2nd and rectified drawing had been received on 09.12.2021 hance delay. |
11.09.2023 24 Month |
Structural work completed.Finishing work completed. Value of work done Rs.4,43,11,857.00 |
|
|
82% |
Aug'23 |
595.000 |
503.000 |
92.000 |
503.000 |
190.000 |
|
|
|
|
₹ 6,49,54,000 |
|
|
In progress |
|
|
61 |
Health (DFWPM) |
Proposed construction of 10 (ten) nos. staff quarters at Tulamura Primary Health Centre (PHC) under Kakraban Block, Udaipur Sub-Division, Gomati District, Tripura. |
Special Assistance |
225.00 |
No.F.19(57)-PLAN/DFWPM/2000(SUB)/3387-3400(V-II), dated 07.08.2015. |
2015-16 |
02.02.2021 |
29.05.2021 |
₹ 2,13,99,000 |
Sri Nihar Chandra Debnath. M-9436131064 |
14.06.2021 |
01.11.2021 |
Lack of required drawing and design |
12.02.2023 18 Month |
Civil work completed on 29.04.23 Value of work done Rs2,14,00,000.00 |
100% |
|
100% |
|
223.910 |
209.130 |
14.780 |
209.130 |
14.770 |
Due to Non-availability of drawing. |
|
|
|
₹ 2,13,99,000 |
|
|
Completed |
|
|
62 |
Construction of 10 bedded Primary Health Centre (PHC) including 10(ten) Nos. Staff Quarters at Nityabazar under Killa Block, Gomati District, Tripura Under RIDF - XX. |
RIDF-XX |
540.00 |
No.F.19(554)/PLAN/DFWPM/2014, dated 19.03.2015 |
2014-15 |
07.05.2015 |
22.09.2015 |
₹ 4,04,90,000 |
Sri Binode Bihari Datta. M- 9612807882 |
07.10.2015 |
01.07.2016 |
Delay for site Development |
06.10.2017 24 Month |
Finishing work in progress for PHC & Quarters. Value of work done Rs. 3,32,00,000.00 |
|
- |
76% |
Dec' 23 |
509.360 |
416.490 |
92.870 |
416.690 |
0.000 |
|
Yes |
Initialy land problam was there & Slow Progress of work by the agency |
|
₹ 4,04,90,000 |
|
EE, Udp requested to Director, Health & Family Welfare to revalid the balance unutilsed fund Rs. 92.874 vide letter No F/EE-PWD-DIVN/ACTT-UC-10/477-79 Dt. 01-05-2023. |
In progress |
|
|
63 |
Santirbazar |
Third Circle |
Proposed Construction of 20 (twenty) bedded Primary Health Centre (PHC) building [ double storied ] including Kitchen, Morgue and Garage & Generator with Driver room building at existing Muhuripur PHC Complex under Jolaibari Block, Santirbazar, South Tripura. |
IMR - 13th FC |
416.00 |
NO.F.19(83)-PLAN/DFWPM/2015(Sub)/1582-89(VII) dated 29-07-2017 of the Under Secretary to the Govt. of Tripura. ( Project Cost for Gap Fund: Rs. 340.02 Lac) |
2017-18 |
PNIeT- No:- 09/EE/PWD(R&B)/STB/2021-22 dated, 16-08-2021 |
15-01-2022 |
₹ 3,01,99,829 |
Pankaj Mallik 9436471344 |
31-01-2022 |
24-01-2022 |
Work started in due time. |
12(twelve) months 30-01-2023 |
Finishing work in progress. In addition Kitchen, Morgue and Garage work in progress Value of work done= 240.00 Lakh |
50% |
Not Required |
90% |
June'23 |
221.800 |
166.290 |
55.510 |
91.800 |
130.000 |
In progress, Delay due to getting drawing of garrage & Kitchen in late. However, as per work volume, completion period is not sufficient. |
|
|
₹ 2,40,00,000 |
₹ 61,99,829 |
No.F. 9(3)/EE/PWD/STB/6748-60 |
The EE, STB has placed demand to the Director vide letter No.F.23(02)/EE/PWD/STB/15183-88 Dt. 0/2/2023 for placement of fund Rs. 130.00 Lac. |
In progress |
|
|
64 |
Construction of 10 bedded PHC at Durpabari with 10 nos. quarters under Santirbazar Sub-Division, Bagafa Block, South Tripura including Staff quarters. |
RIDF-XX |
540.00 |
vide A/A & E/S memo No.F. 19(554)-PLAN/DFWPM/2014 dated06-12-2014 of the Health & Family Welfare Deptt. |
2014-15 |
PNIeT- No:- 25/EE/PWD(R&B)/STB/2020-21 dated, 29-01-2021 |
06-07-2021 |
₹ 4,89,23,754 |
Shri Sumanta Gupta (9436457880) |
21-07-2021 |
16-07-2021 |
Work started in due time. |
24 Months (20-07-23) |
PHC building finishing work is in progress, Type-I work done upto foundation level; Type-II & Type-III completed upto roof casting. Value of work Done= Rs. 260 Lakh |
Work in progress |
Not Required |
70% |
Oct' 23 |
451.970 |
451.940 |
0.030 |
151.330 |
37.300 |
|
Yes, required |
|
₹ 2,60,00,000 |
₹ 2,29,23,754 |
No.F. 9(3)/EE/PWD/STB/1811-24 |
|
In progress |
|
|
65 |
Health(DHS) |
Constn of 24 nos staff qtr for 100 bedded District Hospital at Santirbazar ( Type-I: 6, Type-II: 6 units, Type-III: 6 unit, Type-IV:6 Nos) |
SPA |
583.00 |
vide A/A & E/S memo No.F. 3(5-44)-PLAN/DHS/2013/2(Sub-II)/1735-43 dated 26/09/2016 of the U.S , Health & Family Welfare Deptt. Head of A/C Central Assistance to State Plan. |
2016-17 |
PNIeT- No:- 22/EE/PWD(R&B)/STB/2017-18 dated, 29-12-2017 |
25-05-2018 |
₹ 4,68,20,780 |
Jahar Sur Choudhury 9436133138 |
10-06-2018 |
13-06-2019 |
Initial delay because as clear site could not be handed over in time by the client Dept. |
24 Months 09-06-2020 |
Ty-I, Ty-II, Ty-III: Completed and likes to be handed over by 15th July. Type-IV second floor roof custing completed. Value of Work done= Rs. 370.00 Lakh |
85% |
Not Required |
80% |
Oct' 23 |
568.000 |
440.000 |
128.000 |
407.525 |
0.000 |
Delay Due to Fund |
Yes, required |
|
₹ 3,70,00,000 |
₹ 98,20,780 |
No.F. 9(3)/EE/PWD/STB/1556-69 |
|
In progress |
|
|
66 |
Belonia |
Health(NHM) |
Proposed Construction of new single storied 10(ten) bedded PHC building at existing Niharnagar PHC complex, Niharnagar under Rajnagar Block |
NHM |
173.00 |
No.F.19(248)-PLAN/DFWPM/2001/4983-5004 (V-II) dated, 09.11.2015 |
2014-15 |
19/EE(PWD)/BLN/2015-16 Dt. 09.02.2016 |
18.05.2016 |
₹ 1,44,06,000 |
Radh Raman Datta 8119953376 |
02.06.2016 |
20.08.2017 |
Initially, delayed by the agency. |
02.06.2016 12 Month |
Finishing work in progress. Rs.115.00 lakh |
70% |
NA |
85% |
July-23 |
221.650 |
221.220 |
0.430 |
221.220 |
0.000 |
Work is in progress |
Yes |
Work delayed by the agency. |
₹ 1,15,00,000 |
₹ 29,06,000 |
No.F.7(20) Pt-I/EE(PWD ) /BLN/DIVN /3264-75 Dt.18.05.2016 |
|
In progress |
|
|
67 |
Health (DFWPM) |
Proposed construction of 10 (ten) nos. staff quarters [ Type -I quarter - 04 units (one block - twin double storey ), Type-II quarter - 04 units (one block - twin double storey ) and Type-III quarter - 02 units (one block - twin single storey ) ] at Chottakhola Primary Health Centre (PHC), Rajnagar, Belonia, South Tripura District, Tripura ./2nd call |
IMR |
221.00 |
No.F.20(96)-BUDGET/ DFWPM/ 2013/7482(V-II) dated, 25.01.2014 |
2013-14 |
03/EE(PWD)/BLN/2014-15 Dt.23.05.14 |
11.11.2014 |
₹ 1,78,11,000 |
Arun Kr. Dey 9436483072 |
25.06.2015 |
15.06.2015 |
Delayed by the agency. EE, BLN issued show casue notice to the agency under clause 54 ( FOR L.D) vide letter No.F.F.08(80)/EE (PWD)/BLN/DIVN/8599-8604 Dt. 22/3/23 and also for LD on 19-4-23 |
25.05.2016 12 Months |
Type-III =Completed & Handed over. Type-I & Type-II=Structure completed. Rs.132.00 lakh |
Not yet done in Type-I & Type-II Quarter |
NA |
70% |
Oct-23 |
211.370 |
211.370 |
0.000 |
211.370 |
|
|
|
Agency has suspended the work for long time. Now work is in progress. |
₹ 1,32,00,000 |
₹ 46,11,000 |
|
|
In progress |
|
|
68 |
Health(DHS) |
Construction of Boundary wall at Ratanpur PHC |
IMR |
28.00 |
No.F.19(56)-PLAN/DFWPM/2000/2558-65 (V-II) dated, 27.06.2017 |
2016-17 |
17/EE(PWD)/BLN/2017-18 Dt.04.11.2017 |
10-01-2018 |
₹ 27,88,000 |
Sri Babul Saha 7085306543 |
25.01.2018 |
20.11.2018 |
Due to site dispute |
24.07.2018 6 Month |
50% work completed.Land dispute . Rs.10.00 lakh |
NA |
NA |
50% |
----- |
28.340 |
10.000 |
18.340 |
10.000 |
|
|
|
Due to land dispute balance work could not be completed for which letter has been issued addressed to the Director H&FWD vide this Office letter No.F.8(80)/EE(PWD)/BLN/DIVN/5947-52 Dt.22.11.22 |
₹ 10,00,000 |
₹ 17,88,000 |
No.F.7(20) Pt-I/EE(PWD ) /BLN/DIVN /6994-7002 Dt.10.01.2018 |
|
In progress |
|
|
69 |
Belonia |
Health(DHS) |
Construction of District Ware House at Belonia, South Tripura |
IMR |
250.00 |
no.F.1991670-PLAN/DFWPM/2014 dated 28/12/2016 |
2016-17 |
PNIeT No. 02/EE/PWD/BLN/2022-23 Dt. 26-04-22 |
10.03.2023 |
₹ 1,83,43,000 |
Biplab Choudhuri 9862970796 |
25.03.2023 |
25-04-2023 |
Due to tendering issue. |
24.03.2024 365 days |
Excavation for foundation trenches almost in completion stage. PCC work will be started shortly |
|
NA |
5% |
Mar-24 |
100.000 |
0.000 |
100.000 |
0.000 |
|
|
|
At the 1st time work order was issued but clear working site not handed over by the health authority to PWD. Hence work has been cancelled on 12.10.18. After that DNIT has been modified for e-tender where in the 1st call tender has been cancelled on 27.01.21 due to all participated bidders are found non-responsive. In the 2nd Call, the tender has been cancelled on 15.03.22 due to 1st lowest bidder has surrendered. After that the DNIeT has been changed as per SOR 2020. Now work order has been issued & work will be started very shortly |
|
₹ 1,83,43,000 |
No.F.7(20)/Pt-1/EE/PWD/BLN/DIVN/8346-56 Dt.10-03-23 |
|
In progress |
|
|
70 |
Sabroom |
Health(NHM) |
Construction of singled storied Integrated Ayush Hospital at paschim Jalefa under Sabroom Sub-Division. |
NHM & SAMT |
900.00 |
No.F. 1(63)/SAMT/M5/AYUSH/2019 dated 22-01-2021 of the U/S to Govt of Tripura for Rs. 900.00 Lac |
2021-22 |
13-05-2021 |
16-10-2021 |
₹ 5,44,07,805 |
Shri Tapesh Ch Debnath (Mob# 9436120787) |
02-11-2021 |
01-12-2021 |
There was a verbal proposal for shifting of site at somewhere nearby NH-08 which lead one month delay in commencement of the work. |
365 days 01-11-2022 |
Work Completed |
80% |
|
Civil Work 100% Completed |
Completed |
342.260 |
342.260 |
0.000 |
342.260 |
202.000 |
05-06-2023 There was a verbal proposal for shifting of site at somewhere nearby NH-08 which lead one month delay in commencement of the work. |
|
|
₹ 5,00,00,000 |
₹ 44,07,805 |
|
1) Fund requirement by EE, STB for Rs. 202.00 Alc vide letter No.F. AC(05)/EE/PWD/SBM/11239-41 Dt. 01/02/23 to the Mission Director. |
Completed |
|
|
71 |
Bishalgarh |
Fourth Circle |
Health(DHS) |
Construction of 8 ( Eight) nos staff quarters building 4 nosType-I , (one block twin double storey), , 2 nos Type -II Units (one block single storey), 2 Nos Type-III units(one block double storey) at Madhupur PHC under Bishalgarh Sub-Division. |
NHM |
235.00 |
No.F.19(80)-PLAN/DFWPM/2000(S)/11015-21/(V-II), Dated-15/03/2017 |
2016-17 |
PNIeT No 09/EE-BSLD/PWD(R&B)/2022-23, Dated-04/06/2022, DNIeT-CE(Buildings)/PWD/DNIT/ACE/Project Unit/36/2021-22 |
30-12-2022 |
₹ 2,13,35,925 |
Shri Jahar Sur (9436133138) |
14-01-23 |
27-02-2023 |
Due to late receipt of structural drawing |
15 Months (13-04-24) |
Foundation, Sub-Structure work completed. Super structure work is in progress. 45% Work Completed. Rs 95.00 Lakh |
Not Started |
Nil |
45% |
Mar-24 |
69.500 |
0.000 |
69.500 |
0.000 |
0.000 |
|
|
|
₹ 85,00,000 |
₹ 1,28,35,925 |
No.F. 21(1)/EE-BSLD/PWD(R&B)/9051-9065 Dated 30/12/22 of the EE, Bishalgarh |
|
In progress |
|
|
72 |
Bishramganj |
Fourth Circle |
Health(NHM) |
Proposed construction of (i) New 30 (thirty) bedded Community Health Centre (CHC) building including Ramp [ GF + Part of FF ] (ii) Kitchen (iii) Morgue and (iv) Garage & Generator with Driver room building at existing Takarjala CHC under Jampuijala Sub-Division, Sepahijala District, Tripura |
NHM |
670.00 |
No.F. 19(263)-PLAN/DFWPM/2001(V-II)/94-99 dated 01/04/2017 of Under Secretary, Govt. of Tripura |
2017-18 |
05-06-2017 |
17-01-2018 |
₹ 5,86,70,414 |
Binode Bihari Datta, 9436131276 |
01-02-2018 |
04-09-2019 |
Initiall delayed due to Non availability of clear site, |
24 months/ 02-02-2020 |
Civil works of all component of CHC building under scope of present agreement is completed. IE work of morgue pending. Value of work done Rs. 630,00,000.00 |
90% |
NA |
90.00 |
June.23 |
500.000 |
500.000 |
0.000 |
500.000 |
170.000 |
|
|
Work is in progress. |
₹ 6,30,00,000 |
₹ -43,29,586 |
|
|
In progress |
|
|
73 |
Constructin of 50 bedded fieled hosptilal for COVID patient under emergency COVID response Plan -II at Bishramganj |
NHM |
250.00 |
No. F. 2(63)/DHFWS/CMO/SPJ/ECRP-II/Accounts/2021-222/6729-38 dated 05/09/2022. of Joint Secretary, Govt. of Tripura |
2022-23 |
a) 01.10.2022 b) 29.06.2022 |
a) 04-03-2023 b) 13-10-2022 |
₹ 2,15,57,256 |
a) Pradip Nag 8787752787 b) Ranjan Debnath 8956939330 |
a) 19-03-2023 b) 28-10-2022 |
b) 17/10/2022 |
A) Delayed, as the Site is not suitible to accommodate building. Accordingly CMO, SPJ has initiated proposal sent to the Mission Director , NHM to shift the proposed building at Bishalgarh vide letter No.2(63)/DHFWS/CMO/SP/ECRP-II/Account/2021-22/4374-78 Dated 29/05/2023.. |
a) 300 days 12/01/2024 b) 180 days 26/04/2023 |
A) Not yet started. Site will be changed. B) Finishing and tiles works in progress. (Approx. value of work: Rs. 6.00 Lac) |
|
NA |
a) 0.00 b) 30% |
a) Feb, 24 b) June, 24 |
250.000 |
19.75 |
230.250 |
0.000 |
0.000 |
|
|
A) Site is not suitible to accommodate building. Accordingly CMO, SPJ has initiated proposal sent to the Mission Director , NHM to shift the proposed building at Bishalgarh vide letter No.2(63)/DHFWS/CMO/SP/ECRP-II/Account/2021-22/4374-78 Dated 29/05/2023.. B) Finishing and tiles works in progress. |
₹ 6,00,000 |
₹ 2,09,57,256 |
|
|
In progress |
|
|
74 |
Sonamura |
Health (DFWPM) |
Construction of 10 bedded PHC with 10 nos. quarters at existing Kamalnagar PHC |
|
645.00 |
No.F.19(109)-PLAN/DFWPM/ 4547-57)V-I0 dated 14/07/2021 |
2021-22 |
DNIT No : CE (Buildings)/PWD/ DNIT/ACE/ Project Unit/43/2021-22 Dt………. |
28-04-2022 |
₹ 5,29,51,364 |
Swapan Kr. Dey 9436121336 |
12-05-2022 |
02-12-2022 |
|
12-11-2023 18 Months |
work is in progress up to 1st floor roof lavel type 1 and PHC block. Value of work done Rs. 150 Lac |
|
|
|
Dec.23 |
100.000 |
150.000 |
|
0.000 |
0.000 |
|
|
|
₹ 1,50,00,000 |
₹ 3,79,51,364 |
Vide No.F.10(30)/EE/SNM/PWD/421-37 dt.28-04-2022 |
|
In progress |
|
|
75 |
Health (DFWPM) |
Construction of 16 nos staff quarter building for Boxnagar CHC under Sepahijala District/ Type-I, 6 Units, Type-II: 6 Nos, Type-III: 4 Nos) |
|
527.00 |
No.F.19(32)-PLAN/DFWPM/2000(Sub-1)/4203-10(V-i)dt 13/10/22 |
2022-23 |
CE(Buildings)/PWD/DNIT/ACE/Project Unit/89/2022-23, Dt. 19-12-2022 Dt……… |
|
|
|
|
|
|
|
2nd call of tender invited on 12-04-2023 and to be opened on 11-05-2023 |
|
|
|
|
|
|
0.000 |
|
|
|
|
In the 1st call of tender no bids found and Tender documents sent to the Competent Athority for further necessary instruction. 2nd call of tender invited on 12-04-2023 and to be opened on 11-05-2023 |
|
₹ 0 |
|
|
Tendering Stage |
|
|
76 |
Health(DHS) |
Up- Gradation of Melaghar Sub- Divisional Hospital as First Referral Units (FRU) / Construction of new OPD Complex and 10 (ten) Bedded Eye Ward with Eye OT building (G+1 storied) at Melaghar, Sonamura Sub-Division, Sepahijala District, Tripura under SPA (CASP) during the year 2016-17 |
|
196.00 |
No.F. 3(1-386)-PLAN/DHS/2010/1713-19/7967(v-III), Dt. 21-09-2016. Rs. 6.15 |
2016-17 |
CE(Buildings)/PWD/DNIT /ACE/Project Unit/59/2021-22. Dt……….. |
13-07-2022. |
₹ 2,03,59,836 |
Kanu Lal Saha 8575354399 |
28-07-2022 |
28-07-2022 |
|
25-02-2023 (Period?) |
Finishing work is in progress. Value of work done Rs. 132.00 Lac |
|
|
70% |
Oct-23 |
250.000 |
112.000 |
138.000 |
112.000 |
|
|
|
|
₹ 1,32,00,000 |
₹ 71,59,836 |
Vide No.F.10(30)/EE/SNM/PWD/2313-27 Dt.13-07-2022. |
|
In progress |
|
|
77 |
LTV |
Fifth Circle |
Health(DHS) |
Proposed Expansion of Longtharai Valley (LTV) Sub-Divisional Hospital Building [ Ground Floor + Part of First Floor ] by 20 (twenty) beds at Chailengta under Dhalai District, Tripura under Special Central Assistance to Tribal Sub-Plan (SCA to TSP) |
CASP |
808.00 |
No.F.3(2-410)-PLAN/DHS/2016/480-85 Dated.26-03-2018 for an amount of Rs.808.00 Lakh |
2017-18 |
16-05-2018 |
13-09-2019. |
₹ 6,98,62,467 |
Sri Gour Gobinda Saha 8787367268 |
28-09-2019. |
28-04-2020. |
Delay for handing over of clear site |
27-09-2021. 24(twenty four) months |
Completed and inaugurated 0n 12/04/2023 & 808.00 lakh |
100.00% |
Not required |
100.00% |
Completed on 20.03.2023 |
808.000 |
739.000 |
69.000 |
739.000 |
0.000 |
20-03-2023 & delay occurred due to handing over of clear site & Covid. |
No & delay occurred due to Covid. |
Total value of work Rs.808.00 on completion (Civil-753.00 lakh & IE work-55.00 lakh) Inaugurated on 12/04/2023 by the Hon'ble Chief Minister. |
₹ 8,08,00,000 |
₹ -1,09,37,533 |
|
|
Completed in all respect |
|
|
78 |
Ambassa |
Fifth Circle |
Health(NHM) |
Proposed construction of staff quarter [8 nos.] (Type-I=04 nos. & Type-II=04 nos.) for Ganganagar PHC, Jawharnagar Sub-division, Dhalai District, Tripura. |
IMR Incentive |
170.00 |
19(254)-PLAN/DFWPM/ 12001/6033/ Dt. 30/12/16 |
2016-17 |
PNIeT No: 09/EE/PWD(R&B)/AMB/2021-22 Dated:30-07-2021 |
19-01-2022 |
₹ 72,45,371 |
Sajal Karmakar [8731837723] |
03.02.2022 |
08.02.2022 |
Due to willful delay of the agency |
09 Months '02-11-2022 |
Type-I= Painting work is in progress. Type-II= Painting work is in progress. Value of Work Done = Rs. 40.00 lac (approx) |
In Progress 80% |
0 |
80% |
July, 23 |
225.000 |
125.000 |
100.000 |
125.000 |
0.000 |
|
Yes 180 Days |
Work is in progress |
₹ 40,00,000 |
₹ 32,45,371 |
|
|
In progress |
|
|
79 |
Fifth Circle |
Health(NHM) |
Construction of New 10 nos. staff quarters (Type-I-4, Type-II-4 & Type-III-2) at Ambassa under Ambassa block, Ambassa Sub-Division, Dhalai District, Tripura./ A) 10 nos. staff quarters (Type-I-4, Type-II-4 & Type-III-2) B) Balance works |
IMR Incentive |
225.00 |
F.19(43)-PLAN/DFWPM/2000(S)/97-105 Under Secretary,H&FW Department |
2016-17 |
08-05-2016 |
A) 03.01.2017 & B) 05.04.2022 |
₹ 2,42,30,000 |
Shri Riot Narayan Ghosh (Mob#) 8787305670 |
A) 18.01.2017 & B) 20.04.2022 |
A) 18.04.2017 & B) 20.04.2022 |
Due to willful delay of the agency |
A) 18.06.2018 & B) 180 days 15-11-2022 |
Work Completed Value of Work Done = 259.00 lacs (approx) |
Completed |
NIL |
100% |
|
225.000 |
225.000 |
0.000 |
223.550 |
34.000 |
Completed on 30th May,2023. [ Not yet taken over by the Health Dept. water supply connection from DWS Deptt. Yet to be made ] |
Yes 180 days (Aprox). Plz provide information if Levy or LD imposed with reference. |
The work which was awarded vide agreement No. T/17/SE(Project)/PWD(R&B)/EE/PWD(R&B)/AMB/2016-17 was not complete upto within agreement value plus 10% of the agreement amount . Therefore balance work agreement was awarded to the same agency vide agreement No. T/01/SE-V/EE/PWD(R&B)/AMB/2022-23 Requisition of additional fund for an amounting Rs. 34.00 Lacs placed to the Health Deptt. but not yet received. |
₹ 2,59,00,000 |
₹ -16,70,000 |
|
|
Completed in all respect |
|
|
80 |
Fifth Circle |
Health(DHS) |
Construction of Dhalai District Hospital, Phase-II (Hospital Quarters ) at Kulai, Ambassa, Tripura under NLCPR Scheme / SH:- Construction of 48 Nos. Staff quarters A) 36 Nos qtrs B) 12 Nos Qtrs |
NLCPR |
1131.90 |
No. F. Arch /N/ 2(6)/ 567-572, Dated- 21/08/2018 and No. F. 3 (5-93)-Plan/ DHS/ 2017-18/ 1353-59, Dated- 01/08/2018, By the computent authority |
2017-18 |
PNIeT.No: 21/EE/PWD(R&B)/AMB/2019-20 Dated:02-01-2020 |
A) 21-10-2020. B) 17-12-2020. |
₹ 10,17,31,442 |
A) Shri Kashinath Bhattacherjee B) Shri Ajit Bhattacherjee |
A) 06.11.2020 & B) 01.01.2021 |
A) 16.12.2020 & B) 03.08.2022 |
The work was delayed because clear site was not available at Ambassa for type-III and Type-IV and at Kulai for Type-II and Type-IV. Concerned department didn’t provide land initially as there was some dispute regarding land for proposed medical college. |
A) 15 Months [06.02.2022] & B) 12 Months [03.01.2022] |
Type - I(12 Nos) : - 95% Completed except Painting & Internal electrification. Type II(12 Nos): - Upto 2nd & Final Floor Slab casting Completed, Brick Masonry Work In progress. Type III(12 Nos):-95% Completed except Painting & Internal Type IV :- Column completed upto 1st Floor Slab level Approximate value of work done Rs.680 Lac |
Type-I:- [Work order issued] Type-II:- Type-III:-[Tender Invited] Type-IV:- |
NIL |
77% |
Dec, 2023 |
418.380 |
418.380 |
0.000 |
418.380 |
713.470 |
|
Yes 570 Days(Aprox) |
|
₹ 6,80,00,000 |
₹ 3,37,31,442 |
|
|
In progress |
|
|
81 |
Medical College |
Project Unit |
Health(DHS) |
Balance work for Construction of 750 Capacity Auditorium cum workshop & Cafeteria etc for of Tripura Medical college and Dr.BRAM Teaching Hospital at Hapania |
Deposite Work of TMC |
845.00 |
NO.F.2(Acctts-89)SFTMC/11/Vol-1/2610-15 dated 16th December 2020 of CEO,TMC |
2020-21 |
|
28-03-2022 |
₹ 8,42,00,000 |
Swapan Chandra Dey |
11-04-2022 |
30-09-2021 |
Due to Covid situation |
365 days 12/04/2023 |
Roofing work completed, ceiling work and other finishing works in progress. Approx. value of work done Rs 421.00 Lac |
awaiting for approval of tentative deviation |
Work order issued on 21/3/23 for AC Rs.112.42 Lac |
40% |
August -23 |
200.000 |
199.00 |
1.000 |
199.00 |
641.85 |
|
Time extension required,, no of days can be assessed on submission of final bill |
|
₹ 4,21,00,000 |
₹ 4,21,00,000 |
7(72)/EE/MCD/PWD/20-21/9581-99, Dt-28/03/22 |
1) The CEO, Society for TMC has placed fund through Banker Ch No 031097 dated 9-3-23 for Rs. 200.00 Lac |
In progress |
|
|
82 |
Constn of 40 bedded Girls Hostel,(RIPSAT) in Regional Institute of Pharmaceutical Science and Technology Complex,Abhoynagar, Agartala, |
AICTE |
260.00 |
No.F.12(1)-RIPSAT)/FUNDING/2018/198-205 RIPSAT |
2018 |
|
27-09-2021 |
₹ 2,00,89,000 |
Sri Krishna Gopal Saha |
12-10-2021 |
12-10-2021 |
|
450 days 05-01-2022 |
Completed and Handed over on 04/07/23. Approx. value of work done Rs 200.89 Lac |
100% |
not required |
100% |
|
150.000 |
150.000 |
0.000 |
0.000 |
50.890 |
Date of completion please. |
|
Handed over on 04-07-2023 |
₹ 2,00,89,000 |
₹ 0 |
7(212)/EE/MCD/PWD/20-21/8284-8301 Dated 27-09-2021 |
|
Completed in all respect |
|
|
83 |
Upgradation/strengthening of ANM School at Durjoynagar,Agartala,Tripura/Construction of Administrative and Academic (G+2 ) storied building/Building portion including internal water supply and sanitary installation, sewege and drainage works |
CASP |
843.00 |
No.F.3(2-403)-PLAN/DHS/2016(sub)/1822-33 dt 12-12-2017 DHS |
2017-18 |
|
18-10-2022 |
₹ 8,12,42,000 |
Swapan Kumar Dey |
11-10-2022 |
02-11-2022 |
Intially delayed due to existing old structure and felling of trees by forest deptt. |
720 days 08-11-2024 |
Work completed upto FGL Approx. value of work done Rs 121.86 Lac |
Architectural drawing sent to EE,IE |
Architectural drawing sent to EE,Mech, lift block works in progress. |
13% |
Oct 24 |
105.000 |
105.000 |
0.000 |
105.000 |
707.410 |
|
|
|
₹ 1,21,86,300 |
₹ 6,90,55,700 |
7(203)/EE/MCD/PWD/9729-40 Dated 18-10-2023 |
|
In progress |
|
|
84 |
Medical College |
Constn of proposed OPD building for Dr.BRAM &TMC at Hapania ,Agartala/SH:-Vertical extension OPD building from (G+3) to (G+4) level. |
NHM |
415.00 |
No.F4(7)/ED/TMC/2009-2010/Vol-III/1342-46 dated 6-7-2020 of CEO,TMC |
2020-21 |
|
04-09-2021 |
₹ 4,15,13,890 |
Samir Lal Saha |
19-09-2021 |
01-10-2022 |
Due to Covid situation |
365 days 18-09-2022 |
Roof Castintg Completed. value of work done Rs 290.60 |
IE estimate |
N/A |
30% |
Nov 23 |
100.000 |
100.000 |
0.000 |
100.000 |
315.139 |
|
|
Due to Covid-19 TMC occupied this building till Nov.21. |
₹ 2,90,59,723 |
₹ 1,24,54,167 |
7(71)/EE/MCD/PWD/20-21/3864-81 Dated 04-09-2021 |
1) The EE, Med Collage submitted requistion to the CEO for placememnt of fund Rs.150.00 Lac vide letter No.F.7(13)/EE/MCD/PWD/22-23/14762-64 Dt. 24/2/23 |
In progress |
|
|
85(A) |
Project Unit |
Health(DHS) |
Establishment of Mechanised Laundry System at A) Cancer Hospital hospital, Agartala. |
SJTNY |
300.00 |
Administrative approval only (No.F. 3(5-137)-PLAN/DHS/2022-23 Dt. 17/01/23 of the D.S, Health & Family Welfare Deptt) E/S received vide memo No.F.(5-137)-PLAN/DHS/2022-23 Dt. 28/04/2023 of the D.S of Health & Family Welfare Deptt. for Rs. 300.00 Lac. |
2022-23 |
|
|
₹ 78,09,646 |
Krishna Gopal Saha |
|
|
|
|
Tender accepted on 06-05-23 |
|
|
|
|
150.000 |
|
150.000 |
|
|
|
|
7(243)/EE/MCD/PWD/(R&B)/721-24,Dt-11/05/2023. |
|
₹ 78,09,646 |
|
Approval under SJTNY Memo No.1 (10)/PCD/ SJTNY/2022/28-52 Dated 04/01/2023 of the (P(P&C)D., S.C.GoT. A/A received vide Memo No.F.3 (5-137)-PLAN/DHS/2022-23/ Dated 17/01/2023 of the D.S., HFWD. E/S received vide memo No.F.(5-137)-PLAN/DHS/2022-23 Dt. 28/04/2023 of the D.S of Health & Family Welfare Deptt. for Rs. 300.00 Lac. |
Tendering Stage |
|
|
85(B) |
Health(DHS) |
B) IGM Hospital, Agartala |
SJTNY |
|
31-05-2023 |
₹ 1,19,32,010 |
Narayan Ch Saha |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Tender accepted on 03-05-23 |
|
₹ 1,19,32,010 |
7(244)/EE/MCD/PWD/(R&B)/661-676,Dt-31/05/2023. |
Tendering Stage |
|
|
86 |
Dharmanagar |
First Circle |
Higher Education |
Consruction of hostel at North Tripura District Polytechnic Dharmanagar |
AICTE |
150.00 |
F.1(1)-NTDP/AICTE/CAFES/2021-22 dated: 18/07/22 |
2021-22 |
|
|
|
|
|
|
|
|
Selected site is encroached by local inhabitants. Letter issued to higher Education for decision to resolve land issue. |
|
|
|
|
0.000 |
0.000 |
0.000 |
0.000 |
|
|
|
Intervention of higher authority of the concerned department is rquired. |
|
₹ 0 |
|
|
Not yet started |
|
|
87 |
Agt Div-III |
Second Circle |
Construction of MBB Auditorium/1000 seated capacity |
NLCPR |
919.00 |
|
|
|
|
|
|
|
|
|
|
DPR is under scrutiny |
|
|
|
|
|
|
0.000 |
|
|
|
|
|
|
#VALUE! |
|
|
Not yet started |
|
|
88 |
Agt Div-V |
Constn of Womens Polytechnic at Hapania |
Special assistance |
300.00 |
Memo No. 1(10)/PCD/PF/FIN/ 2021/Part/533563 dated 01.09.2022 of the Secretary P&C Department. |
2021-22 |
DNIT No. CE(Building)PWD/DNIT/ACE/Project Unit/41/2021-22 PNIT No. 15/B/EE-V/AGT/PWD/(R&B)/2021-22. dated 15.12.2021 |
28.04.2022 |
2,70,24,486 |
Jasoda Lal roy |
13.05.2022 |
28.05.2022 |
Non availibilty of drawing |
18 months/'28.10.2023 |
Ground floor Roof ( Balance portion) in progress.Marble flooring in progress in other part of building. .Approx. value of work done Rs 180.00 Lac |
Tender invited |
Nil |
50% |
Dec,23 |
150.00 |
140.19 |
9.81 |
140.19 |
150.00 |
|
|
Structure completed, work is in progress. |
₹ 1,80,00,000 |
₹ 90,24,486 |
F.No.6(337)/EE-V/AGT/PWD/2020-21/356-731 dated 28.04.2022 |
Balance part: Ground floor slab completed, 1st floor slab work is in progress. Rest vertical extension part completed except IE works. |
In progress |
|
|
89 |
Agt Div-III |
Second Circle |
Higher Education |
Construction of Annexure block of Birchandra State Central library ( Balance work of Phase-I) |
NLCPR |
975.00 |
9.75 vide F.No. DNER/NLCPR/TRI/104/2011 on 20.02.2014/ Higher Education |
2013-14 |
24.03.2022 |
05-09-2022 |
5,18,76,772 |
Sri Tapan saha |
19.09.2022 |
|
Initial delay as Clear site was not handed over by the Higher Education Deptt |
28.02.2024 18 Months |
Piling work in progress . Value of work done Rs 20.00 Lac |
0 |
0 |
5% |
Feb-24 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
|
|
|
₹ 20,00,000 |
₹ 4,98,76,772 |
|
|
Not yet started |
|
|
91 |
Agt Div-V |
Construction of Ramthakur College Auditorium/Balance work |
|
1207.00 |
|
|
|
|
|
|
|
|
|
|
Revised Estimate amounting Rs. 1599.00 Lakhs, yet to be approved from Higher Education Department |
|
|
|
|
|
|
|
|
|
|
|
During Review meeting chaired by the Secretary, PWD, it was decided for a joint site visit along with officials of Higher Education. Accordingly joint site visit have been conducted along with Dy. Director, Higher Education, Principal of Ramthakur College, where it was decided to prepare a fresh balance work estimate it present rate/ requirement including civil, electrical, mechanical scope of works to complete the project as a whole functional and to process the estimate to the Higher Education Deprtment through competent authority. The matter was also discussed with the C.E, PWD(Building). Accordingly estimate is under preparation from all wings of PWD. |
|
₹ 0 |
|
|
Not yet started |
|
|
92 |
Agt Div-III |
Construction of Science buildings(G+4) at MBB College( Construction of Ground floor only with provision of G+4 storied foundation) |
|
1500.00 |
No.F5(415)-DHE/PLG/2022 dt 26/08/2022/Higher Education & Memo. No.F.5(415)-DHE/PLG/2022/3602(04) dated 30-11-2022 |
2022-23 |
16.01.2023 |
|
|
|
|
|
|
|
DPC recommended for acceptance of the tender on 03/06/2023 |
|
|
|
|
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
|
|
Estimated cost: Rs. 12,04,12,258/- |
|
₹ 0 |
|
|
Tendering Stage |
|
|
93 |
Jirania |
Fourth Circle |
Construction of Girls' hostel for student /Researchers of TTADC Polytecnic Institute, Khumulwng under CAFES-NER Scheme of AICTE |
CAFES-NER |
150.00 |
(AA Rs. 3.00 Crore and ES Rs. 1.50 Crore) vide No.F. 1(49)-TP/Estt/2021-22/AICTE-AQIS (CAFES-NER)/261 Dated 12/01/23 of the Addl. Secretary, Higher Education |
2022-23 |
|
|
|
|
|
|
|
|
Letter issued to higher Education for decision.DNIT to be issued for inviting tender |
|
|
|
|
|
|
0.000 |
|
|
|
|
DNIT to be issued for inviting tender |
|
#VALUE! |
|
|
Not yet started |
|
|
94 |
Kamalpur |
Fifth Circle |
Constn of Kamalpur Degree College/Vrtical extension |
Special Assistance |
234.00 |
No. F. 5(187)-DHE/PLG/ 09/2805(7) Dt. 28-12-2016 of the Under Secretary to the Govt. of Tripura. |
2016-17 |
|
12-10-2017 |
₹ 1,78,37,809 |
Sri Sukumar Ghosh & 9436499162 |
26-10-2017 |
17-10-2017 |
|
12 Month / 25-10-2018 |
Superstructure almost completed and finishing work is going on. Value of work done Rs. 60.50 lac. |
Nil |
Nil |
50% |
Sept.23 |
|
0.000 |
0.000 |
0.000 |
89.470 |
Progress of work is very slow by the Agency |
Yes |
Fund for 2022-23Rs. 89.47 Lac has already been surrendered. Progress of work is very slow by the Agency |
₹ 60,50,000 |
₹ 1,17,87,809 |
|
|
In progress |
|
|
95 |
Dharmanagar |
Industry |
Strengthening of ITI Dharmanagar |
Not assigned |
147.00 |
F.DI/TRG/C-II/02/2015/ITI/DMN/PART-II/16556-59, DATED: 20-11-2017. |
2018-19 |
15-03-2018 |
31-10-2018 |
₹ 1,43,69,380 |
BBR (India) PVT. LTD. 9612164078 |
14-11-2018 |
14-11-2018 |
Work delayed due to non availibility of funds, pandemic, and non availibility of specific materials for retrofitting and micro concrete of local market. |
13-11-2019 12 Months |
Structural and strengthing work completed. Flooring work completed.Finshing work is in progress. Value of work done Rs. 143.00 Lac approx. |
80% |
Not reqd. |
98% |
June-23 |
147.000 |
147.000 |
0.000 |
147.000 |
0.000 |
|
|
|
₹ 1,43,00,000 |
₹ 69,380 |
|
|
In progress |
Toilet block and parking shed, work order issued on 9/12/2022 for Rs. 24,27,000/- |
|
96 |
Law |
Construction of residential quarters for Grade-II Judicial officers at Dharmanagar, North Tripura |
CSS |
278.00 |
No.F.4(1)-LAW/ESTT(I)/2009(PART-1)/10302-308 dated 25/10/19 |
2019-20 |
05-11-2020 |
30-06-21 |
₹ 2,10,32,418 |
M/S J.C Nath & Sons 9436132164 |
14-07-2021 |
14-07-2021 |
Delayed due to change in foundation and demolishing of existing structures |
14-01-2023 18 Months |
Finishing work of main building is in progress and sentry room, boundary wall work will start soon Value of work done Rs. 180.00 Lac approx. |
|
Not reqd. |
75% |
Oct-23 |
415.000 |
371.700 |
43.300 |
371.700 |
370.300 |
|
|
|
₹ 1,80,00,000 |
₹ 30,32,418 |
|
1) UC Submitted by the EE, DMR for Rs. 51.00 Lac vide letter No. F. 34-117/EE/DD 14/3/23. |
In progress |
|
|
97 |
Construction of residential quarters for Grade-III Judicial officers at Dharmanagar, North Tripura |
CSS |
236.00 |
No.F.4(1)-LAW/ESTT(I)/2009(PART-1)/12068-07 dated 21/10/19 |
2019-20 |
05-11-2020 |
30-06-21 |
₹ 1,93,39,162 |
M/S Narmada Ranjan Das & Co. 9436132208 |
25-06-2021 |
25-06-2021 |
Delayed due to second time soil testing and demolishing of existing structures |
24-12-2022 18 Months |
First Floor Roof Casting completed. Brick work in progress Value of work done Rs. 150.00 Lac approx. |
|
Not reqd. |
60% |
July-23 |
|
|
|
₹ 1,50,00,000 |
₹ 43,39,162 |
|
In progress |
|
|
98 |
Proposed vertical extension of Court Building of District & sessions Judge,North Tripura Judicial District, Dharmanagar, North Tripura |
CSS |
228.00 |
No.F.4(1)/LAW/ESTT/2009(P-1)/9551-54 Dated 14/07/2022 |
2022-23 |
04-08-2022 |
09-12-2022 |
₹ 1,21,86,410 |
Sri Saurajit Deb 8974360194 |
23-12-2022 |
23-12-2022 |
No delay |
22-09-2023 270 Days |
Column & Brickwork completed up to roof level. Tubulsr Truss work in progrss Value of work done Rs. 115.00 Lac approx. |
|
|
70% |
Sept'23 |
|
|
|
₹ 1,15,00,000 |
₹ 6,86,410 |
|
In progress |
|
|
99 |
Kailashahar |
Constn.of 07 Numbers of new residential quarters for Judicial officers of various Grade at Kailashahar under Unakoti District Tripura |
CSS |
884.00 |
No.F.4(9)/LAW/KLS/22/1225-29 dt 6/2/2023 |
2022-23 |
23-12-2022 |
|
|
|
|
|
|
|
DPC recommended on 30-03-23 and accordingly, sent to the administrative department for acceptance of the tender. |
|
|
|
|
|
|
0.000 |
|
|
|
|
Tender invited: 1st Call: 12/09/2022 2nd Call 06-12-2022 3rd Call 23-12-2022 |
|
₹ 0 |
|
|
Tendering Stage |
|
|
100 |
First Circle |
Construction of New Court Building for District & Sessions Judge at Kailashahar, Unakoti District,Tripura. |
CSS |
1361.00 |
No.F.4(6)LAW/CONS/2013/8135-39 Dated 09/06/2022 |
2022-23 |
19-08-2022 |
|
|
Sri Pranab Paul |
|
|
|
|
Tender accepted on 23/06/2023 (Rs. 9,87,71,770/- i.e 12% above on SoR 2021 ) and communicated to EE, KLS |
|
|
|
|
|
|
0.000 |
|
|
|
|
|
|
₹ 0 |
|
|
Tendering Stage |
|
|
101 |
Khowai |
Second Circle |
Law |
Proposed construction of Judicial officer's quarters [Grade-I: 02 no's,Grade-II: 3 no's,Grade-III: 02 no's ]with sentry post & Boundary wall for District & sessions Judge's Court at Khowai, Khowai District,Tripura/ |
CSS |
973.00 |
No.F.4(4)/LAW/CONS/KHW/2019/5770-73 Dt. 7/4/2021 of the DLC & Deputy Secretary, LAW |
2021-22 |
30-12-2021 |
17-05-2022 |
₹ 7,52,21,376 |
Dipak Nag (9436123542) |
02-06-2022 |
01-05-2023 |
'Delay in handing over of land. 'New land is handed over on 12-04-23 and work will be started. |
18 Months (01-12-2023) |
Foundation work for grade 3 quarter building has just started. |
0% |
0% |
0% |
Dec'24 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
|
|
After demolishing of old structure it is found that the land is not adequate to set out the proposed buikding and thefore, alternative land to be handed over by the Law Deptt. ( Ref. Letter No. F.11(10)/EE/PWD/KHW/11932-936 dt. 13/03/2023 of the EE, KHW) |
|
₹ 7,52,21,376 |
|
|
In progress |
|
|
102 |
Law |
Vertical extension of New Multistoreyed Court building(G+2 to G+3) in the premises of Addl.District & Sessions Judge's Court Khowai Sub-Division,District Khowai Tripura/SH: Building portion in/c internal water supply,sanitary installations and 66.00 metre retaining wall. |
CSS |
391.00 |
No.F4(7)-Law/Cons/2000/4121-27 dt06/05/2019 |
2019-20 |
10-01-2022 |
17-05-2022 |
₹ 3,13,72,796 |
Dipak Nag (9436123542) |
02-06-2022 |
01-10-2023 |
Commencement of the work delayed for shifting of Solar Panel on the roof of the existing structure. |
12 Months (16-05-2023) |
Column work completed. Preparation for roof slab casting in progress.( Rs. 30.00 Lac) |
0% |
0% |
35% |
Dec'23 |
0.000 |
0.00 |
0.00 |
0.00 |
100.000 |
|
|
|
₹ 30,00,000 |
₹ 2,83,72,796 |
|
|
In progress |
|
|
103 |
Teliamura |
Construction of Judicial officers Quarters at Teliamura |
|
208.00 |
Awaited |
|
14-09-2022 |
|
|
|
|
|
|
|
Tender under finalistion. A/A & E/S is awaited. |
|
|
|
|
|
|
0.000 |
|
|
|
|
Tender under finalistion. A/A & E/S is awaited. The SE-II has persuaded for E/S vide letter No.F.14(4)/SE-II/3384-87 Dated 20/12/22. |
|
#VALUE! |
|
|
Tendering Stage |
|
|
104 |
Amarpur |
Third Circle |
Construction of 2 nos New Grade -III Judicial officers Quarters (G+2) storied at Amarpur, Gomati District,Tripura |
CSS |
338.00 |
No.F.4(8)-LAW/ESTT(I)/2009(PART)/15307-13 dated 03/12/21 |
2021-22 |
08-03-2022 |
30-06-2022 |
₹ 1,75,51,850 |
Sri Tapan Chakraborty,Contact No.9436472595 |
15-07-2022 |
01-11-2022 |
0.00 |
300 days 30-09-2023 |
First floor slab reinforcement work ground floor & brick work is in progress. Rs.70.00 lakh |
0.00 |
0.00 |
40% |
March-24 |
40.000 |
20.000 |
20.000 |
20.000 |
50.000 |
|
|
1) NIeT: 08-03-2022 20/NIT/EE/PWD/AMP/2021-22. |
₹ 65,00,000 |
₹ 1,10,51,850 |
'30-06-2022 Memo No.F. F.TC/5/EE/PWD/AMP/2967-80 |
|
In progress |
|
|
105 |
Udaipur |
Law |
Construction of Judicial officers Quqrters G+2 storied (02nos Grade -II quarters having parking facilities at GF in the Judicial Officers Quarter Complex situated at Koilar Math,Udaipur |
CSS |
259.00 |
No.F.4(2)-Law/Estt(UDP)/2017/173-76dated 24th August2022 |
2022-23 |
02.11.2022 |
20.03.2023 |
₹ 2,05,56,583 |
Sri Nihar Chandra Debnath. M-9436131064 |
24-03-23 |
|
Initial delay due to demolition of existing structure for new construction. |
23.092024 18 Month |
Work is to be started soon |
|
|
|
Dec'24 |
|
|
0.000 |
|
130.000 |
|
|
Work Order Issued vide No.TC/03/EE/UDP-DIVN/UDP/10577-91 Dt.20/03/2023 of the EE, UDP |
|
₹ 2,05,56,583 |
|
|
not yet started |
|
|
106 |
Sabroom |
Construction of Judicialofficers Quarters at Subroom |
CSS |
221.00 |
F.4(6)-LAW/ESTT/09(PART-I)/13819-23 dated 26/09/22 |
2022-23 |
12-0-2022 |
07-12-2022 |
₹ 1,79,79,542 |
Shri Bishnu Pada Paul (Mob# 6436519065) |
10-01-2023 |
10-01-2023 |
|
450 Days 04-04-2024 |
1st floor slab casteing completed. Value of work done Rs. 50.00 Lakh |
|
|
10% |
Mar'24 |
40.000 |
40.000 |
0.000 |
40.000 |
165.000 |
|
|
|
₹ 50,00,000 |
₹ 1,29,79,542 |
|
|
In progress |
|
|
107 |
Mohanpur |
Fourth Circle |
Construction of SDJM & Civil Judge (Jr.Div) court building (G+1) storied including 02(Two) nos Residential quarter for Grade-III Judiciary officer at mouja Taranagar under Mohanpur Sub-Division. |
CSS |
2340.00 |
No.F.4(7)/LAW/CONS/MNP/2019/14628-34 Dated 12/11/2021 |
2021-22 |
|
16.03.2022 |
₹ 11,89,00,000 |
Tapesh Ch Debnath |
16.03.2022 |
19.03.2022 |
|
15.09.2023 Period ? |
Roof casting upto 2nd floor completed. Brick work for superstructure in progress Value of work done as on reporting date |
0 |
0 |
70% |
Nov' 23 |
1035.000 |
1035.000 |
0.000 |
1035.000 |
800.000 |
|
|
|
|
₹ 11,89,00,000 |
|
|
In progress |
|
|
108 |
Fourth Circle |
Law |
Construction of National Law University(Ph-I) |
|
2100.00 |
|
|
|
|
|
|
|
|
|
|
Survey Site Plan submitted to authority. Drawing under preparation. |
|
|
|
|
|
|
|
|
|
|
|
Survey Site Plan submitted to authority. Drawing under preparation. |
|
₹ 0 |
|
|
not yet started |
|
|
109 |
Bishramganj |
Construction of 08 Numbers of New Residential Quarters for Judicial Officers of various Grade [ Grade-I: 03 nos, Grade-II: 03 nos, Grade-III: 02 Nos.] at Bishramganj under Sepahijala District, Tripura |
CSS |
2208.00 |
No.F.4(7)/LAW/CONS/MNP/2019/14628-34 Dated 12/11/2021 |
2021-22 |
03-01-2023 |
|
|
|
|
|
|
720 days |
DPC recommended for acceptance of tender on 30/3/23 and processed to Admn deptt for acceptance |
|
|
|
|
|
|
0.000 |
|
|
|
|
|
|
₹ 0 |
|
|
Tendering stage |
|
|
110 |
Construction of New Court Building of District and Sessions Judge at Bishramganj under Sepahijala District to accommodate all Civil & Criminal Courts under one Building |
CSS |
3529.00 |
No.F. 4(7)-LAW/ESTT (I)/2013/15497-500 Dt. 10-11-22 |
2021-22 |
19-11-2022 |
|
|
|
|
|
|
720 days |
DPC recommended for acceptance of tender on 30/3/23 and processed to Admn deptt for acceptance |
|
|
|
|
|
|
0.000 |
|
|
|
|
DPC recommended for acceptance of tender on 30/3/23 and processed to Admn deptt for acceptance |
|
₹ 0 |
|
|
Tendering stage |
|
|
111 |
Kamalpur |
Fifth Circle |
Constn of Kamalpur Court/Balance work |
CSS |
1640.00 |
F.4(7)-Law-Estt/09/7210-14 dt 04/08/17 Revised sanction F.45(24)-Hc/2021/19827-30 dated 07/09/21 |
2017-18 |
|
12-05-2022 |
₹ 7,77,45,950 |
M/S L.K. Builders & 9436123268 |
26-05-2022 |
26-05-2022 |
Nil |
15 Month / 25-08-2023 |
i) Boundary wall completed. ii) Superstructure work almost completed except dome portion. iii) Finishing work is in progress. Value of work done Rs. 534.24 lac. |
Nil |
Nil |
80% |
Aug.23 |
534.240 |
534.240 |
0.000 |
534.240 |
243.220 |
Nil |
N/A |
Work is in progress |
₹ 4,14,24,000 |
₹ 3,63,21,950 |
|
|
In progress |
|
|
112 |
Capital Complex |
Project Unit |
Constn of 1 no Bunglow for Hon'ble judge's of High court of Tripura/Balance work |
State Plan |
300.00 |
4(1)Law/ESTT/CONS/JB/2020/1072 dtd 24.1.23 for Rs. 145 lakh |
2022-23 |
27.06.2022 |
|
|
|
|
|
|
|
Tender under scrutiny. Revised estimate sent to LAW Deptt for revised A/A & E/S |
|
|
|
|
|
|
0.000 |
|
|
|
|
|
|
#VALUE! |
|
|
Tendering stage |
|
|
113 |
Construction of multistoried (G+4) building in High court premise at Agartala,West Tripura |
Special Assistance |
858.00 |
4(3)Law/ESTT/4C/2001/6778-83 dtd 29.10.2016 A/A & E/S for Rs. 19.17 Crore |
2016-17 |
15.10.2022 |
15.10.2022 (LOA issued) |
₹ 8,58,00,000 |
Swapan Ch. Dey |
23.11.2022 |
2.02.2023 |
At the initial stage work could not be started due to non availability of sufficient land. Thereafter, land made available. |
24 months 22-11-2024 |
Building,:-Foundation work completed. R/Wall: 32 mtr retaining wall is acompleted upto 80 % of ht. Reinforcement for raft footing for balnce portion is going on. Value of work done = 250 Lakh |
|
|
20% |
Oct'24 |
50.000 |
0.000 |
50.000 |
50.000 |
200.000 |
|
|
|
₹ 2,50,00,000 |
₹ 6,08,00,000 |
|
|
In progress |
|
|
114 |
Agt Div-III |
Second Circle |
Minority Welfare |
Construction of Nazrul Chatrabash-PH-II/Balance work |
Special Assistance |
328.00 |
|
|
|
|
|
|
|
|
|
|
Tender(4th call) under scrutiny and will be finalised on accord of sanction |
|
|
|
|
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
|
|
|
|
₹ 0 |
|
|
Tendering Stage |
|
|
115 |
Amarpur |
Third Circle |
Proposed construction of School Building at EK-Jatan Kr. H.S. School at Karbook RD Block, Gomati District, Tripura under PradhanMantri Jan VikasKrayakram (PMJVK) Scheme during the year 2019-20/ SH: Building portion including internal water supply, sanitary installation, sewage and drainage works. |
PMJVK |
250.00 |
No.F. 3-2/MW/PMJVK/2018-19/1804-10 date, 26-07-2019 |
2021-22 |
11-08-2021 |
02-03-2022 |
₹ 1,92,99,612 |
Sri Swapan Datta,Contact No.9436131286 |
16-03-2022 |
12-05-2022 |
|
12(Twelve Month) '15-03-2023 |
2nd floor both slab completed, work in progress. Value of work done Rs.1.30 Cr. |
0.00 |
0.00 |
85% |
Aug'23 |
112.50 |
6.98 |
105.52 |
6.98 |
80.50 |
|
|
fund revelidation submitted on 14-10-2022 but yet not received till date |
₹ 1,30,00,000 |
₹ 62,99,612 |
02-03-2022 Memo No.F. F.TC/5/EE/PWD/AMP/11044-59 |
|
In progress |
|
|
116 |
Sonamura |
Fourth Circle |
Proposed constn of school Building at UNC School under PMJVK |
PMJVK |
250.00 |
No.F. 3-2/MW/PMJVK/2018-19/4127-36, Dated 16-12-2019 |
2019-20 |
DNIeT No. ACE/Project Unit/ PWD(Buildings)/DNIT/07/2021-22. Dt…… |
30-09-2021. |
₹ 2,17,46,553 |
Bishnu Pada Paul 9436519065 |
15-10-2022 |
15-10-2022 |
|
14-10-2023 Period ? |
Work executed upto 1st floor level. Total value of work done Rs.100.0 Lac |
|
|
45% |
Sept-23 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
|
|
|
₹ 1,00,00,000 |
₹ 1,17,46,553 |
Vide No.F.10(30)/EE/SNM/PWD/9642-55 Dt.30-09-2021. |
|
In progress |
|
|
117 |
Proposed constn of school Building at Sovapur School under PMJVK |
PMJVK |
250.00 |
No.F. 3-2/MW/PMJVK/2018-19/4127-36, Dated 16-12-2019 |
2019-20 |
DNIeT No. ACE/Project Unit/ PWD(Buildings)/DNIT/06/2021-22. Dt……… |
11-11-2021. |
₹ 2,07,92,416 |
Tapash Datta 9612092053 |
26-11-2022 |
|
|
25-11-2023 12 Months |
Clear site is not handed over by the school authority still now. |
|
|
|
|
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
|
|
Clear site is not available. |
|
₹ 2,07,92,416 |
Vide No.F.10(30)/EE/SNM/PWD/10672-85 Dt.11-11-2021. |
|
In progress |
|
|
118 |
Proposed constn of school Building at Baniacherra School under PMJVK |
PMJVK |
250.00 |
No.F. 3-2/MW/PMJVK/2018-19/4127-36, Dated 16-12-2019 |
2019-20 |
DNIeT No. ACE/Project Unit/ PWD(Buildings)/DNIT/05/2021-22. Dt……. |
30-11-2021. |
₹ 2,19,51,923 |
Kanu Lal Saha 8575354399 |
15-12-2022 |
19-01-2023 |
|
14-12-2023 12 Months |
Foundation work is in progress. Work suspended by the agency. |
|
|
1% |
Dec-23 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
|
|
|
|
₹ 2,19,51,923 |
Vide No.F.10(30)/EE/SNM/PWD/11068-81 Dt.30-11-2021. |
|
in progress |
|
|
119 |
LTV |
Fifth Circle |
Proposed constn of school Building at Annadhan School under PMJVK |
PMJVK |
250.00 |
No.F.3-2/MW/PMJVK/2018-19/4145-52 dated.1/12/2019 for an amount of 250.00 lakhs |
2019-20. |
24-06-2021 |
09-11-2021. |
₹ 2,36,99,414 |
Avinash Kumar 7903703109 |
24-11-2021. |
24-11-2021. |
No delay |
23-11-2022. 12 months |
Structutal work completed, now brick works in progress & 190.00 lakh |
Not required |
Not required |
80% |
Sept-23 |
125.000 |
125.000 |
0.000 |
112.500 |
125.000 |
Delay occurred due to Covid. |
No & delay occurred due to Covid. |
Fund required |
₹ 1,25,00,000 |
₹ 1,11,99,414 |
|
|
In progress |
|
|
120 |
Kailashahar |
First Circle |
PWD |
Construction of building for Kailashahar, PWD(R&B) Division and Sub-Division office at Kailashahar,Unakoti District |
Special Assistance |
308.00 |
|
2017-18 |
10-03-2022 |
31-10-2022 |
₹ 3,08,55,924 |
Salil Acharjee 7308686797 |
14-11-2022 |
14-11-2022 |
|
13-05-2024 Period ? 18 Months |
Work suspended by the agency. Show cause notice issued on 16/05/2023. File to be processed for rescind the work |
0% |
0% |
2% |
May-24 |
200.000 |
31.430 |
168.570 |
31.430 |
108.000 |
|
|
|
|
₹ 3,08,55,924 |
F.29(16)EE/KLSD/7329-44 dt 31/10/22 |
Fund Surrendered Rs 100.00 Lakh |
In progress |
|
|
121 |
Agt Div-III |
Second Circle |
Construction of Community Hall at Madhya Bhubanban, Barjala under 4-Barjala Assembly Constituency, West Tripura |
SJTNY |
234.00 |
A/A & E/S for Rs.234.00 Lac under SJTNY 2022-23 vide memo No.F.16(1)-PWD(W)/2018/ Dated 9/3/23 of the F.O to CE, PWD (R&B) for Rs. 234.00 Lac |
2022-23 |
24-04-23 |
|
|
|
|
|
|
|
Tender under scrutiny |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Tendering Stage |
|
|
122 |
Agt Div-I & Agt Div-V |
Second Circle |
Improving Earth Quake resileny of Masonry lifeline building in Tripura a) Retrofitting: 4 Buildings b) Constn. Of TDU |
CSS |
205.00 |
|
|
|
|
₹ 2,41,65,000 |
|
|
|
|
|
Work in progress. a) Retrofitting: 4 Buildings (Progress) 90% b) Constn. ff TDU: Will be taken up shortly |
|
|
|
May'23 |
|
|
0.000 |
|
|
|
|
LoA issued on 13/3/2023 for b. |
|
₹ 2,41,65,000 |
|
|
In progress |
|
|
123 |
Agt Div-III |
Second Circle |
Construction of Office building (B+G+14 storied) for accomodation of different State Government offices in a complex |
Special assistance |
12600.00 |
1(13)/CE(buildings)/2692-2724 dt.11.03.2022 Public Works Deptt |
2021-22 |
20.01.2022 |
06.09.2022 |
######### |
Engineering Projects (India) Ltd |
27.09.2022 |
11.01.2023 |
|
915 days 24.03.2025 |
Preliminary Survey work & Soil testing are completed. Layout plan to be finalized. The revised architectural drawing sent to the higher authority for scrutiny and the agency has been requested to submit detailed PERT network. |
0 |
0 |
|
Mar-25 |
51.450 |
51.450 |
0.000 |
0.000 |
3000.000 |
|
|
|
|
₹ 1,06,48,08,225 |
|
Fund Rs. 950.00 Lac has been surrendered by the EE, Div-III and communicated to the CE, PWD vide letter No.F. 8-16/EE-III/PWD(R&B)/10288-92 Dated 13-03-2023. |
Not yet started |
|
|
124 |
Udaipur |
Third Circle |
Proposed constructon of the SE (D.W.S) and SE(W.R.) including Conference Hall of PWD office Complex at Udaipur, Gomati District, Tripura. |
Special AssistanceCapital |
1193.00 |
A/A & E/S: Vide Memo No.F.16(1)-PWD(W)/2018 dated 09/03/2023 of the F.O, PWD(R&B) for Rs. 1105.00 Lakh undder 4059-Special Assistance -Capital. |
2022-23 |
04.08.2022 |
28-03-23 |
₹ 10,19,35,279 |
Sri Jiban Kumar Saha. M-9436122376 |
02.04.2023 |
|
Delay due to Demolishing of old existing structure |
24 Month '14-04-25 |
Original work is to be started soon. Demolishing of old existing structure is in progress. |
|
|
|
April'25 |
50.000 |
|
50.000 |
|
400.000 |
|
|
LOA Issued dt. 18/3/2023 |
|
₹ 10,19,35,279 |
|
|
Not yet started |
|
|
125 |
Third Circle |
Jamjuri Adarsha Gram Prokolpo/S.H:Constn of 2(two) nos welcome gates and construction of 01(one) No passenger shed. |
Special assistance |
131.00 |
A/A & E/S received vide memo No.F. 1(10)/PCD/PF/FIN/2021/194-216 Dated 29/12/21 of the Secretary, Planning (P&C) Department. |
2021-22 |
29.03.2022 |
15.07.2022 |
₹ 1,02,45,000 |
Sri Sajal Karmakar. M-8787437039 |
30.07.2022 |
|
|
Date 06 Month |
Alternative proposal as per demand of public and local panchayet samitee is under consideration |
|
|
|
|
|
|
0.000 |
|
0.000 |
|
|
One file processed to higher authority with alternate proposal as per demand of public and local panchayet samitee. |
|
₹ 1,02,45,000 |
|
|
Not yet started |
|
|
126 |
Bishalgarh |
Fourth Circle |
PWD |
Construction of Divisional office Building (G+2 storied with foundation provision for G+4 storied) of PWD (R&B) at Bishalgarh, Sepahijala District, Tripura |
Special assistance |
572.00 |
No.F.16(1)-PWD(W)/2018, Dated-15/12/2022 (Rs. 200.00 Lac allocated by Finance Deptt under Special Assistance) |
2022-23 |
PNIeT No 46/EE-BSLD/PWD(R&B)/2022-23, Dated-21/12/2022. Buildings)/PWD/DNIT/ACE/Project Unit/90/2022-23 |
02-05-2023 |
₹ 3,19,63,100 |
Sri Badal Paul, M-9862733424 |
17-05-2023 |
|
|
600 Days (22.12.2024) |
Clear site handed over to the Agency, but the work not yet started |
|
|
|
|
88.000 |
0.000 |
88.000 |
0.000 |
0.000 |
|
|
The received fund of Rs 88.00 Lakh not been able to utilize in this financial year |
|
₹ 3,19,63,100 |
|
|
In progress |
|
|
127 |
Gondatwisa |
Fifth Circle |
Infrastructural Development of Gandacherra Sub-Division, Dhalai District / 1000 seated capacity Auditorium |
Special assistance |
1352.00 |
1(10)/PCD/PF/SCA (united)/2015-16 dated 27/02/2015 |
2015-16 |
|
20-10-2016 |
₹ 8,93,29,000 |
M/s NG Battacharjee Con Com 9436123651 |
05-11-2016 |
27-02-2017 |
|
21 month '05-09-2018 |
Main building completed and IE works started. External connection yet to be executed. Internal road work in Progress. Total value of work done Rs.701.60 Lac |
80% |
90% |
90% |
August'23 |
1566.930 |
1565.960 |
0.970 |
1565.960 |
|
|
|
Fund Rs. 267.21386 Lac suballocated by FO, PWD(R&B) on 9-2-23 for Qtr,Auditorium and Rev Bunglow |
₹ 7,01,60,000 |
₹ 1,91,69,000 |
|
|
In progress |
|
|
128 |
Infrastructural Development of Gandacherra Sub-Division, Dhalai District / Construction of Revenue Dak Bungalow |
Special assistance |
462.00 |
1(10)/PCD/PF/SCA (united)/2015-16 dated 27/02/2015 |
2015-16 |
|
31-12-2021 |
₹ 2,82,18,000 |
Rajib Prasad 8119003215 |
15-01-2022 |
16-01-2022 |
|
06 month '15-07-2022 |
Building finishing work in progress. Total value of work done Rs.215.38 Lac |
50% |
Tender under acceptance |
90% |
Aug'23 |
0.000 |
|
|
|
|
|
₹ 2,15,38,000 |
₹ 66,80,000 |
|
|
In progress |
|
|
129 |
Capital Complex |
Project Unit |
Construction of composite building for accommodation of different officers of PWD at Capital Complex, Khejurbagan , Agartala/ Construction of internal road , boundary wall, protection walletc. in/c works of lower ground floor & upper ground floor for completion of the building /Phase-II |
Special assistance |
1406.00 |
No.F.16(1)-PWD(W)/2011 dtd 12-09-2013 for 14.06 crore |
2013-14 |
|
26-11-2020 |
₹ 5,07,80,000 |
Arun Kumar Dey |
11-12-2020 |
11.12.2020 |
|
18 months '10-06-2022 |
Finishing work for building is in progress, road work is also in progress. Total value of work done Rs 350 lakh |
10% |
|
90% |
August'23 |
|
|
0.000 |
|
170.000 |
|
|
|
₹ 3,50,00,000 |
₹ 1,57,80,000 |
|
|
In progress |
|
|
130 |
Capital Complex |
Project Unit |
Construction of 14(fourteen) nos. new Type-VI quarters and 1(one) no new Type-VII quarter on the land of BRTF handed over to PWD |
Special Assistance/ SJTNY |
2317.58 |
Approval of P & CNo.1(10)-PCD/SITNY/2022/13-27 dtd 4-1-2023 for Amount Rs.23.17 crores under SJTNY 2022-23 A/A & E/S for Rs. 2317.58 Lac vide memo No.F.16(1)-PWD(W)/2018/ Dated 9/3/23 of the F.O to CE, PWD (R&B) |
2022-23 |
|
31-05-2022 |
₹ 23,20,00,000 |
Tapesh Ch Debnath |
6.06.2022 |
21.06.2022 |
|
720 days '26-05-2024 |
i) CS Bunglow: Structural work completed. ii) In Type VI(14 Nos) :- 4 nos F.Floor roof casting completed./1no GF roof casting completed 2 Nos: Ground Floor roof casting is completed/1 no GF roof will be completed very shortly. 5 Nos: Foundation work completed. 2 Nos: Will be taken up. Upto date Value of work done = 650 Lakh |
3% |
|
30% |
Mar-24 |
500.000 |
500.000 |
0.000 |
500.000 |
200.000 |
|
|
|
₹ 6,50,00,000 |
₹ 16,70,00,000 |
|
|
in progress |
|
|
131 |
Dharmanagar |
First Circle |
School Education |
Construction of Addl. Class rooms (8 nos.), Science lab (3 nos.), Library (1 no), Toilet (2 nos.), Boundary wall (200 mtr) at Bir Bikram Institution, Dharmanagar Division, North Tripura District. A) Addl Class room B) B/Wall |
Vidyajyoti |
417.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
|
|
B) B/Wall: '05-07-2022 |
B) 2568032 |
B) Sri Bijoy Saha 9862616440 |
B)07-06-2022 |
B) 08-06-2022 |
|
B) 180 Days |
A) 'Revised estimate under process for addl class room. B) Boundary wall is in progress, Value of work done Rs 15.00 lac |
|
|
|
|
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
|
|
|
₹ 15,00,000 |
₹ 10,68,032 |
|
|
In progress |
|
|
132 |
Kanchanpur |
First Circle |
School Education |
Construction of Science lab (3 nos.), Library (1 no.), Toilet (2 nos.), Boundary wall (222 mtr), Cycle stand (1 no.) at Kanchanpur Higher Secondary School. A) Building B) Boundary wall |
Vidyajyoti |
192.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
A) 04/08/2022 B) 25/04/2022 |
A) 04/11/2022 B) 20/08/2022 |
₹ 1,43,26,800 |
A) Sri Rahul Kar 7005530122 B) Sri Swapan Debnath 9612120502 |
A) 19/11/2022 B) 04/09/2022 |
A) 19/11/2022 B) 04/09/2022 |
|
A) Jan, 24 15 Months B) May, 23 8 months |
A) 1st floor slab casting completed. Column casting above 1st floor upto lintel level completed. B) Boundary wall is almost completed. Value of work done Rs. 56.00 Lakh |
|
|
A) 41% B) 93% |
A) Jan,24 B) May, 23 |
200.000 |
200.000 |
0.000 |
200.000 |
460.660 |
|
|
|
₹ 56,00,000 |
₹ 87,26,800 |
|
|
In progress |
|
|
133 |
Construction of Addl. Class rooms (2 nos.), Science lab (3 nos.), Toilet (2 nos.), Boundary wall (200 mtr), Cycle stand (1 no.) at Satnala H.S. School. A) Building B) Boundary wall |
Vidyajyoti |
248.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
A) 30-06-2022 B) 25/04/2022 |
A) 26/10/2022 B) 20/08/2022 |
₹ 1,95,42,800 |
A) Sri Chiranmay Paul Choudhury 9435079593 B) Sri Swapan Debnath |
A) 10/11/2022 B) 04/09/2022 |
A) 10/11/2022 B) 04/09/2022 |
|
Bld.- Jan, 24 15 Months B/Wall-May, 23 8 Months |
A) Structural work completed. Brick & Plastering work in progress. Rs. B)Boundary wall is almost completed. Rs. 112.00 |
|
|
A) 82% B) 92% |
A) Jan, 24 B) May, 23 |
|
|
|
₹ 1,12,00,000 |
₹ 83,42,800 |
|
|
In progress |
|
|
134 |
Construction of Addl. Class rooms (1 no.), Science lab (3 nos.), Library (1 No.), Toilet (2 nos.), Boundary wall (200 mtr), Cycle stand (1 no.) at Anandabazar H.S. School. A) Building B) Boundary wall |
Vidyajyoti |
218.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
A) 16/11/2022 B) 20/08/2022 |
A) 27/03/23 B) 20/08/2022 |
₹ 1,82,19,758 |
A) Uday Sankar Barua 9862602385 B) Ahmed Ali 7628882920 |
A)01/12/2022 B) 04/09/2022 |
A) 01/12/2022 B) 04/09/2022 |
|
A) Feb, 24 450 Days B) May, 23 8 months |
A) Upto Plinth Beam completed. Work in Progress. B) Boundary wall is completed. Value of work done Rs. 61.00 Lakh |
|
|
A) 7% B) 100% |
A) Feb, 24 B) Complete |
|
|
|
₹ 61,00,000 |
₹ 1,21,19,758 |
|
|
In progress |
|
|
135 |
Construction of Addl. Class rooms (5 nos.), Science lab (3 nos.), Toilet (2 nos.) at Kanchanpur Govt. Eng. Med. School. |
Vidyajyoti |
266.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
30-06-2022 |
'26-10-2022 |
₹ 1,94,45,700 |
Sri Ranabir Choudhury 8731033229 |
10-11-2022 |
10-11-2022 |
|
Jan, 24 15 Months |
1st floor slab casting completed. Fft. Binding for 2nd floor slab in progress. Rs.73.00 Lakh |
|
|
55% |
Jan, 24 |
|
|
|
₹ 73,00,000 |
₹ 1,21,45,700 |
|
|
In progress |
|
|
136 |
Construction of Anandabazar H.S.School Building at Dasda Block,Kanchanpur |
RIDF-XXV |
720.00 |
No.NB.TRIP/01/56th ISC/PLAN50(XXV)/2019-20 dated 24/03/20 |
2019-20 |
18-08-2016 |
03-02-2017 |
₹ 5,31,60,200 |
M/S Chittaranjan Saha & Others 7005224155 |
18-02-2017 |
18-02-2017 |
|
Jan, 19 24 months |
Work in progress. Value of work done Rs.275.00 Lakh |
|
|
66% |
Dec, 23 |
274.00 |
274.00 |
0.000 |
274.00 |
257.602 |
|
|
Work is in progress. |
₹ 2,75,00,000 |
₹ 2,56,60,200 |
|
|
in progress |
|
|
137 |
Construction of Gachirampara H.S.School Building at Dasda Block,Kanchanpur |
RIDF-XXV |
455.00 |
No.NB.TRIP/01/56th ISC/PLAN50(XXV)/2019-20 dated 24/03/20 |
2019-20 |
18-08-2016 |
03-02-2017 |
₹ 4,03,77,500 |
M/S Chittaranjan Saha & Others 7005224155 |
18-02-2017 |
18-02-2017 |
|
July, 2018 18 months |
Finishing work in progress. Value of work done Rs. 412.00 Lakh |
100% Completed. |
----- |
99% |
July. 23 |
403.775 |
403.775 |
0.000 |
403.775 |
0.000 |
|
|
Work is in progress. |
₹ 4,12,00,000 |
₹ 0 |
|
|
in progress |
|
|
138 |
Kailashahar |
First Circle |
a) Construction of Addl. Class rooms (6 nos.),Toilet (2 nos.), b) Boundary wall (250 mtr) at Bhagini Nivedita Girls H.S. School, Kailashahar. |
Vidyajyoti |
248.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
a) 05-09-2022 b) 11-05-2022 |
a)17-11-2022 b)21-06-2022 |
₹ 1,74,83,501 |
a) Siddhartha Dey 9436908670 b) Gopal Das 9436474437 |
a) 01-12-2022 b) 05-07-2022 |
a) 01-12-2022 b) 05-07-2022 |
|
a) 27-08-2023 270 days b) 02-10-2022 Period ? 270 days |
Building:- Constn of roof is in progress. Boundary wall: 120 m completed. Approx value of work done Rs.42.00 Lac |
a) 0% b) 0% |
a)0% b) 0% |
a) 10% b)50% |
a) Aug'23 b) June-23 |
40.000 |
40.000 |
0.000 |
40.000 |
0.000 |
|
Not required |
|
₹ 42,00,000 |
₹ 1,32,83,501 |
a)F.25(16)/EE/KLSD/7806-21 dt 17/11/22 b)F.25(16)/EE/KLSD/4035-50 dt 21/6/22 |
|
In progress |
|
|
139 |
a)Construction of Addl. Class rooms (4 nos.), Science lab (3 nos.), Toilet (2 nos.), b) Boundary wall (300 mtr) at Netaji Vidyapith Eng. Med. H.S. School, Kailashahar |
Vidyajyoti |
285.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/05/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
a) 06-12-2022 |
a) 13-03-2023 |
₹ 2,43,89,865 |
a) Arun Kanti Chanda |
a) 27-03-2023 |
Not started |
|
a) 16-04-2024 Period ? 400 Days |
a) .Foundation Work is in progress. Value of work done-5.00 Lac |
|
|
2% |
a) Apr-24 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
|
|
|
₹ 5,00,000 |
₹ 2,38,89,865 |
F.25(65)/EE/KLSD/9484-99 dt 13/3/23 |
|
In progress |
|
|
140 |
a) Construction of Addl. Class rooms (5 nos.), Science lab (2 nos.), (7th Call) b) Boundary wall (200 mtr), c) Cycle stand (1 no.) at Tilabazar H.S. School, Kailashahar |
Vidyajyoti |
248.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
a) 23-12-2022 b) 21-03-2022 c) 21-03-2022 |
a) '12-04-23 b) '12-05-2022 c)'12-05-2022 |
₹ 1,84,53,289 |
a) Nripendra Ch Mandol & Compancy 7002585904 b) Yeazid Ali 8414047226 c) Yeazid Ali 8414047226 |
a) '26-04-23 b) 26-05-2022 c) 26-05-2022 |
a) Not started b) 26-05-2022 c) 26-05-2022 |
|
a) 19-02-24 300 Days b) 25-08-2022 90 Dyas c) 25-07-2022 60 Days |
a) Foundation Work is in progressr for ACR b&c) 95% for Boundary wall and Cycle stand. Approx value of work done Rs.28.5Lac |
0% |
0% |
a) Nil b) 100% c) 100% |
a) Feb-24 |
40.000 |
40.00 |
0.00 |
40.000 |
0.000 |
|
|
|
₹ 28,50,000 |
₹ 1,56,03,289 |
a) No.F.31(496)/EE/KLSD/952-67 dt 12/4/23 b)No.F.31(473)/EE/KLSD/908-23 dt 12/5/22 c)No.F.31(474)/EE/KLSD/892-907 dt 12/5/22 |
|
In progress |
|
|
141 |
School Education |
Construction of Academic and Administrative Block for DIET at Kailashahar |
Samagra siksha |
946.00 |
No.F.8(2-3)-SE/PLAN/2014 dt 23-12-2014 |
2014-15 |
22-08-2015 |
09-03-2016 |
₹ 5,64,54,959 |
Binode Behari Das 9436583679 |
23-03-2016 |
02-04-2016 |
Due to change in Drawing and design |
22-03-2018 Period ? 24 Month |
Work rescinded on 28/04/2023 under risk & cost to the agency.. Balance work estimate in progress |
30% |
0% |
65% |
|
901.540 |
601.540 |
300.000 |
601.540 |
0.000 |
|
|
Work suspended. Proposal sent for recession to the Administrative Department. Approx value of work done Rs.523.00 Lac. Now, Work rescinded. Balance work estimate in progress |
₹ 5,22,86,000 |
₹ 41,68,959 |
F.25(57)EE/KLSD/6873-92 dt 09/03/2016 |
|
Rescined |
|
|
142 |
Proposed construction of Dalugoan H.S. School, Kailashahar, Unakoti District under RIDF. |
RIDF-XXVII |
867.00 |
NO.F.8(1-42)/SE/PLAN/2021-22 (L) dated 17/12/2021 of the Jt Secretary Decondary Education. (RIDF-XXVII) |
2021-22 |
23-05-2022 |
27-10-2022 |
₹ 7,00,86,788 |
Dipak Nag 9436123542 |
10-11-2022 |
10-11-2022 |
|
01-07-2024 Period ? 600 Days |
Work completed upto tie beam. Work is in progress. Approx value of work done Rs 40.00 Lakh |
0% |
0% |
6% |
July 24 |
218.180 |
0.000 |
218.180 |
0.000 |
482.690 |
|
Not required |
|
₹ 40,00,000 |
₹ 6,60,86,788 |
F.25(24)/EE/KLSD/7290-7305 dt 27/10/2022 |
Fund Surrendered Rs 218.18 Lakh vide letter No.F.8-1/EE/KLSD/9564-66 Dt.16-3-23 |
In progress |
|
|
143 |
Kumarghat |
Infrastructure development of Pecharthal H,S,School,Pecharthal,Unkoti District |
NESIDS |
867.00 |
A/A: No.F. 8(1-42)-SE/PLAN/2021-22 (L) Dt. 17/12/21 of theJt Director, Secondary Education Rs. 8.67 Crore E/S No.F.8(1-42)-SE/PLAN/2021-22(L) dated 08/06/22 of the Jt Director, Secondary Education |
2022-23 |
12-07-2022 |
07-03-2023 |
₹ 7,05,27,000 |
J.C. Nath & Sons 94361 32164 |
21-03-2023 |
21-03-2023 |
|
690 days '09-01-2025 |
Work in progress. 7 Nos temporary room nearly completed after shifting to temporary class room demolition of old structure to be started shortly. Value of work done Rs 50.00 Lac |
0 |
0 |
1% |
Mar-25 |
0.000 |
0 |
0.000 |
0.000 |
0.000 |
|
|
Project delayed in tendering process. |
₹ 50,00,000 |
₹ 6,55,27,000 |
No.F.10(178)/EE/KD/9743-57 dated,07/03/2023 |
|
In progress |
|
|
144 |
Khowai |
Second Circle |
Construction of Addl. Class rooms (4 nos.), Science lab (3 nos.), Toilet (2 nos.), Boundary wall (200 mtr) at Khowai Govt. Class-XII School, Khowai Division, Khowai District, Tripura. A) Building portion BI Boundary wall |
Vidyajyoti |
269.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
A) 29-07-2022 B)13-04-202 |
A) 10-01-2023 B)08-08-2022 |
₹ 2,38,84,525 |
A) Pradip Kr. Deb (9366530211) B) Shyamal Deb (9436538387) |
A) 26-01-2023 B) 24-08-2022 |
A) 05/03/2023. B) 25-10-2022 |
Nil |
A) 365 Days (25-01-2024) B) 4 Months (23-12-2022) |
A) Foundation work in progress B) Boundary wall 95 % completed. Value of work done? |
0% |
0% |
0% |
A) Jan'24 B) Completed |
13.000 |
13.000 |
0.000 |
0.000 |
17.000 |
|
|
|
₹ 16,55,000 |
₹ 2,22,29,525 |
|
|
In progress |
|
|
145 |
Construction of Addl. Class rooms (4 nos.), Toilet (2 nos.), Boundary wall (300 mtr) at Tulashikhar Rajnagar H.S. School, Khowai Division, Khowai District, Tripura. A) Building portion BI Boundary wall |
Vidyajyoti |
205.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
A) 05/04/2023 B) 14-04-2022 |
B) 08-08-2022 |
₹ 52,82,875 |
Sujan Dey (9436513028) |
24-08-2022 |
20-10-2022 |
Nil |
180 Days (23-02-2023) |
A) Tendering stage in 3rd call ( under scrunity). B) Boundary wall completed |
Nil |
Nil |
B) 100% |
B) Completed |
37.000 |
37.000 |
0.000 |
37.000 |
17.000 |
|
|
A) 1st call of Tender for class room has been cancelled and now 2nd call of tender has been invited and no bidder found, the 3rd call invited and under scrunity). |
₹ 53,82,875 |
₹ -1,00,000 |
|
1) Req. for fund Rs. 23.90 Lac has been submitted by the EE, KHW vider letter No.F.7(29)/EE/PWD(R&B)/KHW/11493-495 Dt. 14/2/23 |
In progress |
|
|
146 |
Proposed construction of Paharmura H.S. School, Khowai Tripura under RIDF. |
RIDF-XXVII |
867.00 |
NO.F.8(1-42)/SE/PLAN/2021-22 (L) dated 17/12/2021 of the Jt Secretary Secondary Education. (RIDF-XXVII) |
2021-22 |
|
Nil |
₹ 0 |
Nil |
Nil |
Nil |
|
Nil |
2nd call of Tender is under scrutiny. DPC meeting held on 6/6/23 |
0% |
0% |
0% |
|
218.180 |
19.000 |
199.180 |
0.000 |
649.000 |
|
|
1st call of tender has been cancelled as per DPC recommendation. Now 2nd call of Tender has been invited and to be opened on 4-4-2023. Tender under scrutiny |
|
₹ 0 |
|
|
tendering stage |
|
|
147 |
Second Circle |
School Education |
Proposed construction of Bharat Sardar Para H.S. School, Khowai Dist, Tripura under RIDF. |
RIDF-XXVII |
867.00 |
NO.F.8(1-42)/SE/PLAN/2021-22 (L) dated 17/12/2021 of the Jt Secretary Decondary Education. (RIDF-XXVII) |
2021-22 |
02-07-2022 |
13-01-2023 |
₹ 7,21,94,673 |
Sajal Datta (9436512491) |
29-01-2023 |
Nil |
The concerned department could not yet hand over clear site to PWD, so work could not be started yet. |
600 Days (12-07-2024) |
The concerned department could not yet hand over clear site to PWD, so work could not be started yet. |
0% |
0% |
0% |
July'23 |
218.180 |
1.371 |
216.809 |
0.000 |
0.000 |
|
|
|
|
₹ 7,21,94,673 |
|
1) The EE, KHW requestedto the Director Secondary Education for handing over clear site by demolishing the existing old schllol building vide letter No.F.11(09)/EE?PWD/KHW/11826-830 Dt. 9/3/23. In the mean time, PEE has confirmed that construction of temporary class rooms has also been completed. |
in progress |
|
|
148 |
Teliamura |
Construction of Science lab (4 nos.), Toilet (6 nos.), Boundary wall (300 mtr) at Teliamura H.S. School, Teliamura Division, Khowai District, Tripura. |
Vidyajyoti |
256.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
i) Boundary wall 05/04/22 ii) School building - 25/08/22 |
i) 11/08/22 ii) 12/01/23 |
₹ 2,13,89,236 |
i) Sri Manish Bhowmik 8974438561 ii) Sri Haran Ch. Das 9436168447 |
i) 26/08/22 ii) 27/01/23 |
i) 26/08/22 ii) Not yet started |
ii) Class room not yet started due non handing over of clear site from the concern department. |
i) 25/02/23 (6 Months) ii) 26/11/23 (10 Months) |
i) Boundary wall completed except painting. Ii) Class room not yet started due non handing over of clear site from the concern department. Total value of work done Rs.43.00 Lac |
|
|
95% |
i) July,23 |
20.000 |
20.000 |
0.000 |
20.000 |
130.000 |
|
|
|
₹ 43,00,000 |
₹ 1,70,89,236 |
|
1) Req. for fund Rs. 23.90 Lac has been submitted by the EE, KHW vider letter No.F.7(29)/EE/PWD(R&B)/KHW/11493-495 Dt. 14/2/23 |
In progress |
|
|
149 |
Construction of Addl. Class rooms (5 nos.), Head Master room (1 no), Science Lab (3 nos), Library (1 no.), Toilet (2 nos.), Boundary wall (300 mtr), Cycle stand (1 no) at Kalyanpur H.S. School, Khowai Division, Khowai District, Tripura. |
Vidyajyoti |
367.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
i) Boundary wall 05/04/2022 ii) Cycle stand- 12/04/2022 iii) School building - 01/08/2022 |
i) 17/06/22 ii) 20/06/22 iii) 08/11/22 |
₹ 3,28,35,412 |
i) Sri Nityananda Das ii) Sri Nityananda Das iii) Sri Sajal Datta |
i) 03/07/22 ii) 05/07/22 iii) 23/11/22 |
i) 08/07/22 ii) 20/07/22 iii) 12/12/22 |
|
i) 02/01/23 (6 Months) ii) 04/10/22 (3 Months) iii) 22/08/23 (9 Months) |
Cycle stand & Boundary wall completed. Addl. Class room etc in progress. RCC structure completed for 4th block. Total value of work done Rs.185.00 Lac |
|
|
60% |
iii) Sept,23 |
55.000 |
55.000 |
0.000 |
55.000 |
312.000 |
|
|
|
₹ 1,85,00,000 |
₹ 1,43,35,412 |
|
|
In progress |
|
|
150 |
Second Circle |
School Education |
Construction of 100 seated (G+2) girls hostel at Kalyanpur HS school |
NESIDS |
609.00 |
No.F.14(54-1)/SE/IT/2021(part-17) dated 28/04/22 |
2022-23 |
30-09-2022 |
'13-01-2023 |
₹ 4,61,20,217 |
Sri Pradip Kr. Deb 9856029969 |
28-01-2023 |
10-04-2023 |
Work could not be started in time due to non received of structural drawing. |
27-07-2024 (18 Months) |
Work is in progress. Foundation work completed Total value of work done Rs. 50.00 lakh. |
|
|
15% |
July-24 |
|
|
0.000 |
|
350.000 |
|
|
|
₹ 50,00,000 |
₹ 4,11,20,217 |
|
|
In progress |
|
|
151 |
Agt Div-III |
Construction of Addl. Class rooms (4 nos.), Toilet (2 nos.), Boundary wall (350 mtr) at Maharani Tulsibati Girls H.S. School, Agartala Division No.III, West Tripura. |
Vidyajyoti |
205.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
|
|
|
|
|
|
|
|
Modified Arch. Drg. at alternate site is to be prepared by Sr. Arch. After getting decision from the Edn. Deptt. |
|
|
|
|
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
|
|
Fund Surrendered |
|
₹ 0 |
|
1) Fund Surrendered for Rs. 25.00 Lac vide letter No.F.8-16/EE-III/PWD(R&B)/10294-98 Dt. 19/03/23. |
Not yet started |
|
|
152 |
Constn. of Addl. Class rooms (8 Nos) , Sc.lab(3 Nos), Computer Lab (1 No), Library ( 1 No) & Toilet (2 Nos) at Umakanta Academy H.S. School, Agartala, under Agartala Division-III, West Tripura |
Vidyajyoti |
399.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
|
|
|
|
|
|
|
|
Tender will be accepted after demolision of Old structure by the Education department. |
|
|
|
|
0.000 |
0.000 |
0.000 |
0.000 |
100.000 |
|
|
Fund Surrendered |
|
₹ 0 |
|
1) Fund Surrendered for Rs. 25.00 Lac vide letter No.F.8-16/EE-III/PWD(R&B)/10294-98 Dt. 19/03/23. |
Not yet started |
|
|
153 |
School Education |
Construction of Kshetra Mohan New English Medium Academy at Agartala, Shantipara, West Tripura |
SJTNY & Samagra Shiksha |
321.00 |
Administrative approval and Expenditure sanction accored for Rs. 3,21,00,000/- and communicated by the by the Director, Elementary Education & SPD, Samagra Shiksha vide Memo No.F. 1(6-2)/SE/Samagra/Civil/West/2022-23 ( L-II)/5522-29 dated 07/01/2023. Rs. 1,00,00,000/- ( Samagra Sikhsha under School Education) & Rs. 2,21,00,000/- from SJTNY. |
2022-23 |
NIeT No.01/EE/Divn-III/PWD(R&B)/23-24 Dt. 06/04/2023 |
|
|
|
|
|
|
|
1) 'Tenderis under scrutiny. ( TEC meeting held on 06/06/23) T 2) The SDM,Sadar has been requested to demarcate available land along with approch road. |
|
|
|
|
0.000 |
0.000 |
0.000 |
0.000 |
30.000 |
|
|
Estimate is under preparation in Project Unit, PWD , Buildings. ( Geo tech investigation report submitted by EE, Div-III vide letter No.21(211)/EE-III/PWD (R&B)/10488-91 Dt. 16/3/2023. |
|
₹ 0 |
|
|
Not yet started |
|
|
154 |
Agt Div-V |
Infrastructure development of Vivekananda High school,West Tripura( Part of Ground Floor & First Floor ) |
Special assistance |
612.00 |
No F.8(7-284)-SE/PLAN/2022 dated 23/05/22 |
2022-23 |
20 /EE-V/AGT/PWD(R&B)/22-23 Dated 26th |
18-05-23 |
5,27,24,479.28 |
Sri Tapan Saha |
20.05.2023 |
York yet to start |
Demolishing of existing structure is required. Reserve price value of old existing structure is under preparation for approval |
04.11.2024 (18 Months) |
Reserve price value estimate sent to the CE, Building for kind approval after approval of the rate present existing old structire will be demolished by the existing agency and reserve price value will be deposited to the SED. |
0.00 |
N/A |
0.00 |
Nov-2024 |
|
|
0.000 |
|
300.000 |
|
|
|
|
₹ 5,27,24,479 |
|
Rs. 612.00 Lac is not sufficient for total built up area.therefore, built up area is reduced to keep the amount within sanctioned amount. Correctred drawing sent to the Director, Secondary education.(Ref Letter No.F.13(2)/PWD/ACE/Project Unit/2022/4648-47 Dated 29/11/22 of the SE, PU, Blgd) Oct ,2022 DNIT No. CE(Buildings)/PWD/DNIT/ACE/Project Unit/68/2022-23 PNIT No.20 /EE-V/AGT/PWD(R&B)/22-23 Dated 26th Oct ,2022 Work order isued. After demolishing of existing structure, work will be started. Reserved price value will be processed soon for necessary approval by the Competent Authority. Reserve price value estimate sent to the CE, Building for kind approval after approval of the rate present existing old structire will be demolished by the existing agency and reserve price value will be deposited to the SED. |
In progress |
|
|
155 |
Amarpur |
Third Circle |
Construction of Addl. Class rooms (3 nos.), Library (1 No) , Science lab (3 nos.), Toilet (2 nos.), Boundary wall (200 mtr), Cycle stand (1 no.) at Karbook Panjihum H.S School, Amarpur Division, Gomati District, Tripura. A) Addl Class room B) Boundary wall & Cycle stand |
Vidyajyoti |
277.00 |
Modified sanction vide No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
A) ? B) '04-12-2022 |
B) '29-09-2022 |
₹ 24,54,945 |
B) Sri Bijoy Krishna Saha,Contact No.7630041953 |
B) 15-10-2022 |
15-10-2022 |
|
|
A) Tender for addl classroom etc to be invited. DNIT issued on 02/06/2023 B) Boundary wall and Cycle stand completed |
|
|
|
|
40.000 |
40.17 |
|
|
|
|
|
B) 18-06-2022 08/NIT/EE/PWD/AMP/2022-23. A) Addl Class room: DNIT issued on 02/06/2023 for Rs. 1,84,00,913/-, Time : 480 Days. DNIT No: ACE/Project Unit/PWD Buildings/DNIT/14/2023-24 Dt. 02/06/23 |
|
₹ 24,54,945 |
B) '29-09-2022 Memo. No.F. TC/5/EE/PWD/AMP/2021-22/8913-27 |
|
In progress |
|
|
156 |
Construction of Addl. Class rooms (3 nos.), Science lab (3 nos.), Toilet (2 nos.), Library (1 no), Boundary wall (200 mtr), Cycle stand (1 no.) at Silachari H.S. School, Amarpur Division, Gomati District, Tripura. A) Addl Class room B) Boundary wall & Cycle stand |
Vidyajyoti |
277.00 |
Modified sanction vide No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
B) '18-06-2022 |
B) 29-09-2022 |
B) 26,10,558.00 |
B) Sri Bijoy Krishna Saha,Contact No.7630041953 |
13-10-2022 |
13-01-2023 |
|
13-01-2023 90 day |
B) Cycle Stand completed. A) Fund may be utilished for another work of same School (Silachari H.S Balance work ). Decision awaited for T.S estimate and DNIT. |
|
|
|
|
40.000 |
0.000 |
40.000 |
0.000 |
28.000 |
|
|
B) NIeT: 18-06-2022 08/NIT/EE/PWD/AMP/2022-23. |
|
#VALUE! |
B) '29-09-2022 Memo. No.F. TC/5/EE/PWD/AMP/2021-22/8898-8912 |
|
In progress |
|
|
157 |
Proposed construction of Silachari H.S. School at Silachari, Gomati Tripura./Balance work |
RIDF-XXV |
972.00 |
No.NB.TRIP/01/56th ISC/PLAN50(XXV)/2019-20 dt24/03/20 (Gap funding . Initial funding from SPA and later on Gap funding by RIDF Rs.500.00 Lac) |
2019-20 |
13-12-2022 |
|
|
|
|
|
|
|
Agreement closed.Balance work tender under scrutiny. Revised estimate will be sent for A/A & E/S due to cost overrun. |
|
|
|
|
|
|
0.000 |
|
|
|
|
1) NIeT : '13-12-2022 50/NIT/EE/PWD/AMP/2022-23. 2) Balance work tender under scrutiny |
|
₹ 0 |
|
|
tendering stage |
|
|
158 |
Proposed construction of new double storied school building at Ampinagar H.S. School, Gomati District under RIDF. |
RIDF-XXVII |
867.00 |
NO.F.8(1-42)/SE/PLAN/2021-22 (L) dated 17/12/2021 of the Jt Secretary Decondary Education. (RIDF-XXVII), Rs. 8.67 |
2021-22 |
10-08-2022 |
15/3/2023 |
₹ 6,65,66,694 |
Sri Tapan Chakraborty,Contact No.9436472595 |
30/3/2023 |
|
|
31-03-2024 700 days |
Work just started |
0.00 |
0.00 |
0.00 |
Mar,24 |
0.00 |
0.00 |
0.00 |
0.00 |
665.67 |
|
|
1) NIeT: 10-08-2022 15/NIT/EE/PWD/AMP/2022-23. II) Boundary wall and Cycle stand completed |
|
₹ 6,65,66,694 |
Work order No.F.TC/5/EE/PWD/AMP/20006-23 Dt. 15/3/23 |
|
In progress |
|
|
159 |
Udaipur |
Third Circle |
School Education |
Construction of Addl. Class rooms (4 nos.), Science lab (3 nos.), Cycle stand (1 no.) at Kirit Bikram Institution, Udaipur Division, Gomati District, Tripura. A) Cycle Stand B) Addl Class room: |
Vidyajyoti |
215.00 |
Modified sanction vide No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
A) 29-03-22 B) Addl. Class room: |
A) 10.08.2022 |
A) 775144.82 |
Sri Dip Narayan Kar. |
A) 25.08.2022 |
23-08-22 |
|
A) 22.10.2022 2 Month |
A) Cycle Stand completed. B) Tender for additonal class etc invited |
|
|
a) 100% |
|
0.000 |
|
0.000 |
|
|
a) Cycle Stand completed on 19-09-22 |
a) No |
A) Handed over 23.11.2022 B) DNIT issued on 29/05/2023. Estimated Cost Rs. 1,66,42,061/-. DNIT No/CE/Buldings/PWD/ACE/Project Unit/11/2023-24 Dt. 29/05/23 |
|
#VALUE! |
|
|
In progress |
|
|
160 |
Proposed construction of Khilpara H.S. School, Udaipur, Gomati District under RIDF. |
RIDF-XXVII |
867.00 |
NO.F.8(1-42)/SE/PLAN/2021-22 (L) dated 17/12/2021 of the Jt Secretary Decondary Education. (RIDF-XXVII) |
2021-22 |
11.10.2022 |
|
|
SREE MAA INFRATECH. M-9436131712 |
|
|
|
24 Month |
DPC recommended for acceptance of Tender. |
|
|
|
|
218.180 |
83.000 |
135.180 |
83.000 |
784.000 |
|
|
|
|
₹ 0 |
|
|
Tendering Stage |
|
|
161 |
Constn of double storied school of Jamjuri HS School |
RIDF-XXVI |
795.00 |
No.F.8(7-230)-SE/PLAN/2016 dated 20.07.2021. Amount : 795.08 Lakh |
2020-21 |
24.09.2021 |
07.04.2022 |
₹ 6,39,46,000 |
Sri Jiban Kumar Saha. M-9436122376 |
22.04.2022 |
13.07.2022 |
Due to dealy of setting in layout |
21.10.2023 18 Month |
Roof casting completed for 01(one block. Foundation work completed for rest portion. Value of work done Rs.1,93,31,784.00 |
|
|
26% |
Jan-24 |
214.670 |
191.050 |
23.620 |
191.050 |
602.950 |
Not yet completed. Delayed due to seeting of layout an arrangement of available land |
|
|
₹ 1,93,31,784 |
₹ 4,46,14,216 |
|
|
In progress |
|
|
162 |
Infrastructure development of South Bagma H.S.school,Tepania,Gomati district |
NESIDS |
867.00 |
A/A: No.F. 8(1-42)-SE/PLAN/2021-22 (L) Dt. 17/12/21 of theJt Director, Secondary Education Rs. 8.67 Crore E/S No.F.8(1-42)-SE/PLAN/2021-22(L) dated 08/06/22 of the Jt Director, Secondary Education |
2022-23 |
04.08.2022 |
28-06-23 |
₹ 6,93,93,061 |
SREE MAA INFRATECH. M-9436131712 |
31-05-23 |
|
Initial delay due to demolision of Old school buildings / structure by the school authority partly. |
Date? 22 Month |
Work order issued on 28.06.2023 & site handed over. |
|
|
|
Mar-25 |
|
|
0.000 |
|
0.000 |
|
|
|
|
₹ 6,93,93,061 |
|
1)DPC recommended for acceptance of tender on 15/12/2022 and the Admn deptt approved on 1/4/2023. Work will be awarded accordingly very shortly on observing codal formalities. |
tendering stage |
|
|
163 |
Santirbazar |
Third Circle |
School Education |
Construction of Addl. Class rooms (4 nos.), Science lab (3 nos.), Library (1 no), , Toilet (0 nos.), Boundary wall (200 mtr) at Baikhora Eng. Med. H.S. School. |
Vidyajyoti |
277.00 |
Modified sanction vide No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
PNIeT- No:- 17/EE/PWD(R&B)/STB/2022-23 dated, 18-07-2022 |
28-10-2022 |
₹ 1,83,93,937 |
Gatan Datta 9862453230 |
13-11-2022 |
08-11-2022 |
Work started in due time. |
270 days 10-08-2023 |
1 Block roof casting completed and work in progress. Value of work done= Rs. 55.00 Lakh |
yet to start |
Not Required |
45% |
Dec' 23 |
30.000 |
28.200 |
1.800 |
0.000 |
153.940 |
|
Yes, required |
|
₹ 55,00,000 |
₹ 1,28,93,937 |
No.F. 9(3)/EE/PWD/STB/7396-7407 |
|
In progress |
|
|
164 |
Infrastructure development of Twaikorma H.S. school,South Tripura |
Special assistance |
498.00 |
No F.8(7-284)-SE/PLAN/2022 dated 23/05/22 |
2022-23 |
PNIeT- No:- 44/EE/PWD(R&B)/STB/2022-23 dated:- 09-01-2023 |
|
|
|
|
|
|
540days. |
2nd call of tender and DPC recommended for acceptance of Tender. |
|
|
|
|
0.000 |
0.000 |
0.000 |
0.000 |
4.980 |
|
|
2nd call of tender is under scrutiny |
|
#VALUE! |
|
|
tendering stage |
|
|
165 |
Infrastructure development of Takma Paticharri High school,Santir Bazar, South Tripura |
Special assistance |
268.00 |
No F.8(7-284)-SE/PLAN/2022 dated 23/05/22 |
2022-23 |
PNIeT- No:- 40/EE/PWD(R&B)/STB/2022-23 dated:- 06-12-2022 |
18-01-2023. |
₹ 2,26,51,617 |
Shri Sajal Bhattacherjee ( 9774910015) |
02-02-23 |
45000 |
Initially delayed, Due to MCC wrt. Assembly Election'2023 which held on 16-02-2023 & result declared on 02-03-2023 |
365 days 01-02-2024 |
Foundation work in Progress. Value of work done= Rs. 5.00 Lakh |
yet to start |
Not Required |
5% |
Jan'25 |
0.000 |
0.000 |
0.000 |
0.000 |
2.680 |
|
Yes, required |
|
₹ 5,00,000 |
₹ 2,21,51,617 |
No.F. 9(3)/EE/PWD/STB/11734-47 |
|
in progress |
|
|
166 |
Infrastructure development of Srikantabari H,S,School,Santirbazar |
NESIDS |
867.00 |
A/A: No.F. 8(1-42)-SE/PLAN/2021-22 (L) Dt. 17/12/21 of theJt Director, Secondary Education Rs. 8.67 Crore E/S No.F.8(1-42)-SE/PLAN/2021-22(L) dated 08/06/22 of the Jt Director, Secondary Education |
2022-23 |
PNIeT- No:- 19/EE/PWD(R&B)/STB/2022-23 dated, 20-07-2022 |
18-01-2023 |
₹ 7,18,52,409 |
Shri Tapan Chakraborty [7085782033] |
02-02-23 |
15-03-2023 |
Initially delayed Due to MCC wrt. Assembly Election'2023 which held on 16-02-2023 & result declared on 02-03-2023 |
690 days '09-01-2025 |
Foundation work in Progress. Value of work done= Rs. 5.00 Lakh |
0% |
Not Required |
5% |
Jan'25 |
0.000 |
0.000 |
0.000 |
0.000 |
8.670 |
In progress |
|
|
₹ 5,00,000 |
₹ 7,13,52,409 |
No.F. 9(3)/EE/PWD/STB/11748-61 |
|
in progress |
|
|
167 |
Santirbazar |
Third Circle |
School Education |
Proposed construction of Santirbazar H.S. School, South Tripura under RIDF. |
RIDF-XXVII |
867.00 |
NO.F.8(1-42)/SE/PLAN/2021-22 (L) dated 17/12/2021 of the Jt Secretary Decondary Education. (RIDF-XXVII) |
2021-22 |
PNIeT- No:- 11/EE/PWD(R&B)/STB/2022-23 dated, 01-06-2022 |
17-01-2023 |
₹ 7,18,33,604 |
Sanjib Kumar Prasad 9402166076 |
01-02-2023 |
19-01-2023 |
Work started in due time. |
540 days 30-12-2025 |
Work in progress up to plinth level. Value of Work done= Rs. 80.00 Lakh |
Yet to start |
Not Required |
10% |
Dec' 24 |
218.180 |
2.117 |
216.063 |
0.000 |
0.000 |
|
|
|
₹ 80,00,000 |
₹ 6,38,33,604 |
No.F. 9(3)/EE/PWD/STB/11550-63 |
|
In progress |
|
|
168 |
Belonia |
Third Circle |
School Education |
Construction of Addl. Class rooms (5 nos.), Science lab (3 nos.), Toilet (2 nos.), Boundary wall (200 mtr), Cycle stand (1 no.) at Hrishyamukh EM H.S. School, Belonia A) Addl. Classroom B) Boundary wall |
Vidyajyoti |
307.00 |
Modified sanction vide No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
A.35/EE(PWD)/BLN/2022-23, Dt.20.03.23 B 01/EE((P WD)/BLN/2022-23 Dt 04-04-2022 |
A) Tendering stage B) 21.06.2022 |
₹ 31,86,000 |
B) Amal Majumder 9436518511 |
A) Tendering Stage B) 06.07.2022 |
A) Tendering stage B) 08.07.2022 |
A) Due to tendering issue. |
A) Tendering Stage B) 01.01.2023 180 Days |
A) Addl. Classroom 6th call tender received and under scrutiny. B) Work completed. (Rs.31.86 lakh). |
B) NA |
B) NA |
A. 0% B.95% |
B) Completed |
22.500 |
22.500 |
0.000 |
22.500 |
9.360 |
B) Final bill not yet submitted |
|
A).Addl. Classroom 1st call=No bids found. 2nd Call= No bids found. 3rd Call= Single bid found but tender cancelled due to high rate. 4th Call=No bids found 5th Call= Tender invited. |
₹ 31,86,000 |
₹ 0 |
|
1) EE, BLN placed req for Rs. 82.00 Lac vide letter No.F.5(11)/EE/PWD/R&B/DIVN/8117-18 Dt. 7/2/23 to the Director, Secondary edn. |
B) Work completed |
|
|
169 |
Belonia |
Third Circle |
School Education |
Construction of Addl. Class rooms (4 nos.), Science lab (3 nos.), Library (1 no.), Toilet (2 nos.), Boundary wall (300 mtr) at B.K. Institute, Belonia. A) Addl. Classroom B) Boundary wall |
Vidyajyoti |
315.00 |
Modified sanction vide No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
A.10/EE(PWD)/BLN/2022-23 Dt.29.06.2022 B 01/EE((P WD)/BLN/2022-23 Dt 04-04-2022 |
A) 29.11.2022 B) 17.06.2022 |
₹ 2,50,62,000 |
A) Biijan Bhuiyan9436502419 B) Swapan Debnath 9436526243 |
A) 14.12.2022 B) 02.07.2022 |
B) 02.07.2022 |
A) Due to demolishing of existing old school building within the proposed area of nes construction. B) For non-handing over of Clear working site for boundary wall by the School authority |
A) 08.11.2023 330 Days B) 28.12.22 180 days |
A) Casting of plinth beam is completed & work is in progress Rs.50.00 lakh B) 125.00 Mtr completed. For balance portion site yet to be handed over fully by the School authority Rs.15.00 lakh |
Not yet |
NA |
A. 2.5% B.75% |
A) Dec.23 B) Aug 2023 |
14.00 |
12.000 |
2.000 |
12.000 |
236.620 |
|
|
Site handed over for Addl. Classroom. Work will be started very shortly |
₹ 1,15,00,000 |
₹ 1,35,62,000 |
A) No.F.7(20 )Pt-I/EE(PW D)/BLN/DIV N/6101-10 Dt.29.11.2022 B) No.F.7(20 )Pt-I/EE(PW D)/BLN/DIV N/1721-29 Dt.17.06.22 |
|
In progress |
|
|
170 |
Belonia |
Third Circle |
School Education |
Construction of Addl. Class rooms (4 nos.), Science lab (3 nos.), Library (1 no), Auditorium (1 no), Toilet (2 nos.), Boundary wall (300 mtr) at Belonia Govt. Eng. Med. H.S. School. A) Addl. Classroom B) Boundary wall |
Vidyajyoti |
403.00 |
Modified sanction vide No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
A.07/EE(PWD)/BLN/2022-23 Dt. 07.06.22 B 01/EE((P WD)/BLN/2022-23 Dt 04-04-2022 |
A) 04.11.2022 B) 14.06.2022 |
₹ 3,29,46,000 |
A) Sankar Kanti Saha 9436124030 B) Bijan Bhuiyan 9436502419 |
A) 19.11.2022 B) 29.06.2022 |
A) 02.12.2022 B) 29.06.2022 |
Works commenced in time |
A) 18.11.2023 365 Days B) 25.12.2022 180 Days |
A) Centering shuttering and reinforcement binding of roof slab is completed except hall room portion and will be casted shortly Rs.120.00 lakh B) Boundary wall Completed except main gate due to fixation of formation level of NH108(A). Rs.36.86 lakh |
A) Not yet for Addl. Classroom etc. B) NA |
|
A.30% B.98% |
A) Dec.23 B) Aug 2023 |
91.50 |
91.50 |
0.00 |
91.50 |
201.00 |
|
|
For boundary wall work almost completed |
₹ 1,56,86,000 |
₹ 1,72,60,000 |
A) No.F.7(20 )Pt-I/EE(PW D)/BLN/DIV N/5312-21 Dt.04.11.22 B) No.F.7(20 )Pt-I/EE(PW D)/BLN/DIV N/1661-69 Dt.14.06.22 |
1) EE, BLN placed req for Rs. 46.00 Lac vide letter No.F.5(11)/EE/PWD/R&B/DIVN/8117-18 Dt. 7/2/23 to the Director, Secondary edn. |
In progress |
|
|
171 |
Belonia |
Third Circle |
School Education |
Construction of Science lab (3 nos.), Boundary wall (200 mtr), Cycle stand (1 no.) at Barpathari H.S. School, Belonia |
Vidyajyoti |
130.00 |
Modified sanction vide No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
01/EE(PWD)/BLN/2022-23 Dt. 04-04-2022 |
15.06.2022 |
₹ 26,39,000 |
Nikhil Majumder 8837237503 |
30.06.2022 |
22.08.2022 |
Work commenced in time |
26.12.2022 180 Days |
Work almost completed. Rs.25.00 lakh |
NA |
NA |
97% |
July-23 |
22.000 |
17.000 |
5.000 |
17.000 |
4.390 |
|
|
|
₹ 25,00,000 |
₹ 1,39,000 |
No.F.7(20 )Pt-I/EE(PW D)/BLN/DIV N/1670-78 Dt.15.06.22 |
1) EE, BLN placed req for Rs. 22.00 Lac vide letter No.F.5(11)/EE/PWD/R&B/DIVN/8117-18 Dt. 7/2/23 to the Director, Secondary edn. |
In progress |
|
|
172 |
Mohanpur |
Fourth Circle |
School Education |
Proposed construction of Gandhigram H.S. School, West Tripura under RIDF. |
RIDF-XXVII |
867.00 |
NO.F.8(1-42)/SE/PLAN/2021-22 (L) dated 17/12/2021 of the Jt Secretary Decondary Education. (RIDF-XXVII) |
2021-22 |
|
16-11-2022 |
₹ 6,68,00,000 |
Tapesh Ch Debnath |
01-12-2022 |
03-12-2022 |
|
02-06-2024 Period? |
Ground Floor Structural work completed upto roof level. Value of work done as on reporting date |
|
|
40% |
June' 24 |
218.000 |
218.000 |
0.000 |
0 |
6.49 |
|
|
UC will be submitted shortly |
|
₹ 6,68,00,000 |
|
|
In progress |
|
|
173 |
Mohanpur |
Fourth Circle |
School Education |
Infrastructure development of Madhu Chowdhury Para H.S. school,West Tripura, Mohanpur, West Tripura ( RIDF-XXVIII |
RIDF-XXVIII |
399.00 |
No.F.8(2-7)- SE/PLAN/2019 -20 dated 07.12.2022 of the Additional Secretary to the Govt. of Tripura. |
2022-23 |
PNIT No: 86/EE/MNP/PWD (R&B) dt: 05.01.23 |
|
₹ 3,26,43,899 |
M/S Swapan Ch Dey |
|
|
|
|
Tender accepted |
|
|
|
|
|
|
0.000 |
|
|
|
|
Tender accepted. DNIT approved for Rs. 2,97,00,572/- on 22/12/22.2nd call Tender has been sent to the authority for approval on 27.02.2023. |
|
₹ 3,26,43,899 |
|
|
Tendering Stage |
|
|
174 |
Mohanpur |
Fourth Circle |
School Education |
Infrastructure development of Gopal Nagar H.S. school,West Tripura/Constn. Of new double storied school building |
RIDF- XXVIII |
399.00 |
No.F.8(2-7)- SE/PLAN/2019 -20 dated 07.12.2022 of the Additional Secretary to the Govt. of Tripura. |
2022-23 |
PNIT No: 80/EE/MNP/PWD(R&B) dt: 23.12.22 |
|
|
|
|
|
|
|
Tender in 2nd call is under scrutiny. |
|
|
|
|
|
|
|
|
|
|
|
Tender has been sent to the authority for approval on 06.01.2023. |
|
|
|
|
Tendering Stage |
|
|
175 |
Mohanpur |
Fourth Circle |
School Education |
Infrastructure development of Tarapur H.S. school,West Tripura/Constn. Of new double storied school building |
RIDF- XXVIII |
399.00 |
No.F.8(2-7)- SE/PLAN/2019 -20 dated 07.12.2022of the Additional Secretary to the Govt. of Tripura. |
2022-23 |
1st Call: '20-03-23 |
|
|
|
|
|
|
|
Tender accepted on 23/06/2023 |
|
|
|
|
|
|
|
|
|
|
|
1) DNIT issued on 16-03-23 for calling of tender.PNIeT No 89/EE/MNP/PWD (R&B)/2022-23 Dt. 20-03-23. Last date of receipt: 18/04/23. E.Cost: 2,98,05,366/- Time: 2) Tender accepted on 23/06/2023 for Rs. 3,27,26,292/- in favour of Sri Jayanta Saha, Usha Bazar. |
|
|
|
DNIT issued on 16-03-23 for calling of tender.PNIeT No 89/EE/MNP/PWD (R&B)/2022-23 Dt. 20-03-23. Last date of receipt: 18/04/23. E.Cost: 2,98,05,366/- Time: |
Tendering Stage |
|
|
176 |
Mohanpur |
Fourth Circle |
School Education |
Infrastructure development of Mohanpur H.S. school,West Tripura |
Special assistance |
812.00 |
No F.8(7-284)-SE/PLAN/2022 dated 23/05/22 |
2022-23 |
|
12.01.2023 |
₹ 6,34,00,000 |
Jayanta Saha |
12.01.2023 |
|
|
|
Construction of temporary class room has just started and completion of these the main building work will be started |
|
|
|
July'24 |
|
|
|
|
|
|
|
Tender accepted by the CE, PWD, Buildings and communicated to EE, MNP by the SE, PU, Bldg vide letter No F. 5(35)/PC (PD-II)/2022 ( S)/5674-77 Dated 11/1/23. Accepted amount Rs, 6,34,00,200/-, CL XII: 8.50 % above.. Agency: Sri Jayantaq Saha. |
|
₹ 6,34,00,000 |
|
|
tendering stage |
|
|
177 |
Bishalgarh |
Fourth Circle |
School Education |
Construction of Addl. Class rooms (6 nos.), Head Master (1 no), Science lab (3 nos.), Library (1 no), Toilet (2 nos.), Boundary wall (200 mtr), Cycle stand (1 no.) at Amtali H.S. School. |
Vidyajyoti |
380.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
PNIeT No 06/EE-BSLD/PWD(R&B)/2022-23, Dated-13/05/2022, DNIeT-CE(Buildings)/PWD/DNIT/ACE/Project Unit/04/2022-23 |
A) 09-09-2022, B) 09-09-2022, C) 28-10-2022 |
₹ 3,33,42,088 |
A) Tapan Saha (9436123393), B) Pradip Saha (9862514081), C) Pradip Saha (9862514081) |
A) 24-09-2022, B) 24-09-2022, C) 12-11-2022 |
A) 24-09-2022, B) 24-09-2022, C )12-11-2022 |
|
A) 300 Dyas (22-07-2023) B) 120 Days (21-01-2023) C) 90 Days (09-02-2023) |
A) Building portion Brick work etc in progress. 70% Work Completed. Rs 189.00 Lakh. B) Boundary wall completed, C) Cycle Stand work completed |
Not Started |
Nil |
a) 70% b)100% c) 100% |
July-23 |
139.000 |
139.000 |
0.000 |
119.000 |
50.000 |
(b) 21/01/2023, (c) 09/02/2023 |
|
|
₹ 1,89,00,000 |
₹ 1,44,42,088 |
|
1) Requistion placed by the EE, BLG vide letter No.F. 10(11)/EE-BSL/10790-92 Dt. 14/3/23 to the Director , Secondary education for Rs.50.00 Lac. 2) UC submitted for Rs. 119.oo Lac vide letter No.F.10(11)/Pt-VI/EE-BSL/10732-34 Dt. 13/3/23 |
in progress |
|
|
178 |
Bishalgarh |
Fourth Circle |
School Education |
Construction of Addl. Class rooms (6 nos.), Head Master (1 no), Science lab (3 nos.), Library (1 no), Toilet (2 nos.), Boundary wall (200 mtr), Cycle stand (1 no.) at Surjamani Nagar H.S. School, Bishalgarh Division, Sepahijala District, Tripura. |
Vidyajyoti |
380.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
PNIeT No 06/EE-BSLD/PWD(R&B)/2022-23, Dated-13/05/2022, DNIeT-CE(Buildings)/PWD/DNIT/ACE/Project Unit/05/2022-23 |
a) 23-09-2022, b) 24-05-2022, c) 24-05-2022 |
₹ 3,31,57,059 |
a) Sankar Kanti Saha, (9436124030), b) Pradip Saha (9862514081) |
a) 08-10-2022, b) 07-06-2022, c) 07-06-2022 |
a) 08-10-2022, b) 07-06-2022, c) 07-06-2022 |
|
a) 300 Days (03-08-2023), b) 120 Days (05-10-2022) c) 90 Days (05-09-2022) |
A) Building portion Brickwork, Finishing work etc in progress. 85% Work Completed. Rs 220.00 Lakh B) Boundary wall completed, C) Cycle Stand work completed |
Not Started |
Nil |
a) 85% b)100% c) 100% |
a) Aug-23 |
140.000 |
140.000 |
0.000 |
120.000 |
50.000 |
(b) 05/10/2022, (c) 05/09/2022 |
|
|
₹ 2,20,00,000 |
₹ 1,11,57,059 |
|
1) Requistion placed by the EE, BLG vide letter No.F. 10(11)/EE-BSL/10790-92 Dt. 14/3/23 to the Director , Secondary education for Rs.50.00 Lac 2) UC submitted for Rs. 120.00 Lac vide letter No.F.10(11)/Pt-VI/EE-BSL/10732-34 Dt. 13/3/23 |
in progress |
|
|
179 |
Bishalgarh |
Fourth Circle |
School Education |
Construction of 100 seated (G+2) girls hostel at Amtali HS school |
NESIDS |
609.00 |
No.F.14(54-1)/SE/IT/2021(part-17) dated 28/04/22 |
2022-23 |
PNIeT No 40/EE-BSLD/PWD(R&B)/2022-23, Dated-07/12/2022 |
10-04-2023 |
₹ 4,93,43,465 |
Kashinath Bhattacharjee, M-9436124681 |
15-04-2023 |
|
Initial delay slightly as clear site was not received |
540 Days (05.10.2024) |
Foundation Work in progress |
|
|
|
|
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
|
|
|
|
₹ 4,93,43,465 |
|
|
Not yet started |
|
|
180 |
Bishramganj |
Fourth Circle |
School Education |
Construction of 5 Nos. Additional Class room, Cycle stand, B/Wall 200 mtr of SD Memorial H/S School A) ACR 5 Nos B) Cycle Stand C) Boundary Wall |
Vidyajyoti |
189.00 |
No. F. 14(54-1)/SE/19/2021(Part-17) dated 23/05/2022 of Joint Secretary, Govt. of Tripura |
2022-23 |
A) 06-09-2022 B) 29-06-2022 C)29-06-2022 |
A) 01-10-2023 B)06-09-2022 C)06-09-2022 |
₹ 1,81,64,656 |
A) Swapan Debbarma , 9862035089 B) Hrishikesh Debbarma 9862361022 C) Khalil Mia 7640947714 |
A) 25-01-2023 B) 21-09-2022 C) 21-09-2022 |
A) 25-01-2023 B) 31-10-2022 C) 20-09-2022 |
|
A) 365 days/ 24-01-2024 B) 90 Days 20-12-2022 C) 120 Days 20-01-2023 |
A) Col casting in progress B) Completed C) B/Wall Completed. Value of work done Rs 55.82 Lac |
A) 0% B) N/A C) N/A |
A) N/A B) N/A C) N/A |
A) Nil B) 100% C) 100% |
A) 'Oct-23 |
76.000 |
39.51 |
36.490 |
36.490 |
113.000 |
|
|
Work in progress. |
₹ 55,82,000 |
₹ 1,25,82,656 |
|
|
in progress |
|
|
181 |
Sonamura |
Fourth Circle |
School Education |
Construction of Addl. Class rooms (4 nos.), Head Master (1 no), Science lab (3 nos.), Toilet (2 nos.), Boundary wall (250 mtr) at Melaghar Eng. Med. H.S. School. |
Vidyajyoti |
292.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
34/B/DNIeT/SE-IV/ PWD(R&B)/2022-23. & CE(Buildings)/PWD/DNIT/ ACE/Project Unit/14/2022-23. Dt…………. |
09-01-2023 |
₹ 2,23,75,431 |
Shri Kanu Lal Saha (8575354399) |
24-01-23 |
19-01-2023 |
|
300 Days 20-11-24 |
70% boundary wall completed and building work will be started very shortly. . Value of work done Rs. ……………. Lac |
|
|
10% |
Nov-24 |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
|
|
CL XII 9.00 % above on SoR2020 |
₹ 25,00,000 |
₹ 1,98,75,431 |
Vide No.F.10(30)/EE/SNM/PWD/7455-69 Dt.09/01/2023. |
|
in progress |
|
|
182 |
Sonamura |
Fourth Circle |
School Education |
Construction of Boundary wall (500 mtr), Cycle stand (1 no.) at Boxnagar HS School |
Vidyajyoti |
88.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton |
2022-23 |
33/B/DNIeT/SE-IV PWD(R&B)/2022-23. Dt. ………. |
24-05-2022 |
₹ 7,70,409 |
Homayan Kabir 7005959683 |
09-06-2022 |
|
|
09-09-2022 |
Letter issued for BG against boundary wall,Work order issued for cycle stand But land not available |
|
|
|
|
0.000 |
|
0.000 |
|
|
|
|
|
|
₹ 7,70,409 |
|
|
Not yet started |
|
|
183 |
LTV |
Fifth Circle |
School Education |
Construction of Addl. Class rooms (9 no.), Toilet (2 nos.), at Chawmanu H.S. School, L.T. Valley Division, Dhalai District, Tripura. |
Vidyajyoti |
378.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton Further revised sanction received for Rs.378.00 Lac Lac dt. 12/04/2023, Directore Scl Education. |
2022-23 |
1st Call: 29/05/23 |
|
|
|
|
|
|
|
Bid opened on 30/06/2023. Two bidders found and tender under scrutiny |
|
|
|
|
0.000 |
|
0.000 |
|
|
|
|
DNIT Issued on 23/05/23. Estimated Cost Rs.2,72,20,525/-. Bid opened on 30/06/2023. Two bidders found and tender under scrutiny |
|
₹ 0 |
|
|
Not yet started |
|
|
184 |
Ambassa |
Fifth Circle |
School Education |
Up-gradation of Infrastructure of Chandraipara H. S. School, Ambassa, Dhalai, Tripura under ACA (SPA Tied) during the year 2011-12 (1st Phase)./Balance work |
SPA Tied |
500.00 |
8(2-7)-SE/PLAN/2011 Dt. 08/09/11 of School Education |
2021-22 |
PNIeT.No:10/EE/PWD(R&B)/AMB/2021-22 Dated: 05-08-2021 |
27.12.21 |
₹ 1,56,09,640 |
Sujit Ghosh [ 9436136057] |
12.01.2022 |
18.05.2022 |
After several persuation a considerable time was spent by the Agency to stat the work without any valid reason. |
11.01.2023 |
Work Completed |
Completed |
- |
Completed |
|
500.000 |
496.050 |
3.950 |
496.050 |
0.000 |
Completed on 30th June, 2023 and yet to be handed over to concerned Deptt. |
Yes 120 Days |
Work delayed by the agency. |
₹ 5,00,00,000 |
₹ -3,43,90,360 |
|
|
In progress |
|
|
185 |
Ambassa |
Fifth Circle |
School Education |
Infrastructure development of Kulai H,S,School, Ambassa/Constn. Of New Double storied school building |
NESIDS |
867.00 |
A/A: No.F. 8(1-42)-SE/PLAN/2021-22 (L) Dt. 17/12/21 of theJt Director, Secondary EducationRs. 8.67 Crore E/S No.F.8(1-42)-SE/PLAN/2021-22(L) dated 08/06/22 of the Jt Director, Secondary Education |
2022-23 |
PNIeT No. 19/EE/PWD(R&B)/AMB/2022-23 Dt. 29/08/2022 |
17-03-2023 |
₹ 7,08,43,397 |
Shri Tapan Chakraborty [7085782033] |
02-02-2023 |
|
|
700 days [02-01-2025] |
Work yet to be started.Letter issued to the District Education Officer Dhalai to handover clear siteby the EE, Ambassa on 18/05/23 |
NIL |
NIL |
0% |
Jan-25 |
0.000 |
0.000 |
0.000 |
0.000 |
708.434 |
|
|
Clear site yet to be handed over by the Education Department. Dismantling of existing school building in progress carried by the education Deptt. |
|
₹ 7,08,43,397 |
No.F.17(26)/EE/PWD(R&B)/AMB/8651-621 Dt. 17/03/23 |
LoA issued to Sri Tapan Chakraborty, Contractor (Mob: 7085782033) vide letter No. F.17(26)/EE/PWD(R&B)/AMB/7660-71 Dt. 12/01/2023 of the EE, Ambassa, R&B. Tendered amount Rs. 7,08,43,397/- Cl XII: 4.99 % above on , Time for completion 700 days. |
Not yet started |
|
|
186 |
Kamalpur |
Fifth Circle |
School Education |
Construction of Addl. Class rooms (8 nos.), Toilet (2 nos.), Boundary wall (555 mtr), at Kamalpur Govt. Eng. Med. H.S. School, Kamalpur, Dhalai District, Tripura. |
Vidyajyoti |
540.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton Further revised sanction received for Rs.540.00 Lac dt. 12/04/2023, Directore Scl Education. |
2022-23 |
PNIeT No.: 03/EE/PWD(R&B)/KMP/DIV/2023-24, dated, 21-06-2023 |
|
|
|
|
|
|
|
Tender invited on 21-06-2023 & last date of online bidding 20-07-2023 |
0.000 |
0.000 |
0.000 |
|
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
Nil |
Nil |
Date of opening of Tender 21-07-2023 |
|
₹ 0 |
|
|
Not yet started |
|
|
187 |
Gondatwisa |
Fifth Circle |
School Education |
Construction of Addl. Class rooms (9 nos.), Science lab (1 nos.),HM room-1 No, Smart Class-1 No, Staff room-1 No Toilet (2 nos.), at Ananda Roaja Memerial Govt. Eng. Med. High School, Gandatuisa Division, Dhalai District, Tripura. |
Vidyajyoti |
562.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton Further revised sanction received for Rs.562.00 Lac dt. 12/04/2023, Directore Scl Education. |
2022-23 |
Please fill up the column |
|
|
|
|
|
|
|
Single Tender is under scrutiny. |
|
|
|
|
0.000 |
|
0.000 |
|
|
|
|
|
|
₹ 0 |
|
DNIT Issued on 02-05-23 |
tendering stage |
|
|
188 |
Gondatwisa |
Fifth Circle |
School Education |
Construction of Addl. Class rooms (8 nos.), Science lab (1 no.), Toilet (2 nos.),Smart Class-1 No. Staff Room, Auditorium-1 No at Raishyabari Eng. Med H.S. School, Gandatuisa Division, Dhalai District, Tripura. |
Vidyajyoti |
430.00 |
Modified sanction vide memo No.F.14(54-1)/SE/2021/(part-17) dated 23/04/22 of the Jt. Secretary, Secondary Educaton Further revised sanction received for Rs.430.00 Lac dt. 12/04/2023, Directore Scl Education. |
2022-23 |
02/EE/PWD (G)/(R&B)/GNT/2023-24 Dt. 03-05-2023 |
|
|
|
|
|
|
|
In the 1st & 2nd call no bidder participated the tender. 3rd call will be floated very shortly. |
|
|
|
|
0.000 |
|
0.000 |
|
|
|
|
|
|
₹ 0 |
|
|
Not yet started |
|
|
189 |
Gondatwisa |
Fifth Circle |
School Education |
Construction of 100 seated (G+2) girls hostel at Raishabari English MediumHS school (NESIDS) |
NESIDS |
609.00 |
No.F.14(54-1)/SE/IT/2021(part-17) dated 28/04/22 |
2022-23 |
28/EE/PWD(R&B)/AMB/2022-23 Dt. 28-10-2022 |
24-05-23 |
₹ 4,83,30,267 |
Tapan Chakraborty (7085782033/9436472595) |
09-06-2023 |
09-06-2023 |
|
17 Months 25 days (540 days) 04-12-2024 |
Work order issued. Work in progress. Plz give Value of work done (Approx): |
|
|
3% |
Dec'24 |
|
|
0.000 |
|
|
|
|
|
|
₹ 4,83,30,267 |
|
|
In progress |
|
|
190 |
Kumarghat |
First Circle |
SC Welfare |
Construction of 50 seated SC Girl's Hostel (G+1)at Pabiacherra H.S School |
BJRCY |
286.00 |
No.F.5-1(P-I)/SCW/PLG(HOSTEL)/BJRCY/2019/9057-80 dated 14/09/22 |
2022-23 |
26-09-2022 |
13-01-2023 |
₹ 2,56,39,000 |
Biprojit Chakraborty 70052 27620 |
28.01.23 |
06.03.23 |
Delay in approval of drawing |
28.06.24 18 Months |
Piling Work in progress . Value of work done Rs 20.00 Lac |
letter issued to IE division |
NA |
7% |
Sept-24 |
0.000 |
0.000 |
0.000 |
0.000 |
100.000 |
|
|
Delay in issuance of drawing |
₹ 20,00,000 |
₹ 2,36,39,000 |
No.F.10(178)/EE/KD/9023-37 dated,13/01/2023 |
Tender accepted by the CE, PWD, Buildings and communicated to EE, Kumarghat by the SE, PU, Bldg vide letter No F. 5(35)/PC (PD-II)/2022 ( S)/5795-98 Dated 13/1/23. Accepted amount Rs, 2,56,39,840/-, CL XII: 10.00 % above.. Agency: Sri Biprojit Chakraborty |
In progress |
|
|
191 |
Amarpur |
Third Circle |
SC Welfare |
Construction of 100 seated SC Girl's Hostel (G+1) at Rangamati H.S School |
CSS |
350.00 |
No.F.5-1(P-I)/SCW/PLG(HOSTEL)/BJRCY/2019/23345-66 dated 25/04/22, Rs. 3.50 |
2022-23 |
30/6/2022 |
23-11-2022 |
₹ 3,03,87,887 |
Sri Rajib Prasad Contact No 8119003215 |
12-08-2022 |
|
|
31/11/2023 450 days |
Earth cutting completed, work is in progress. Value of work done Rs. 5.00 Lakh. |
|
|
10% |
July,24 |
|
|
|
|
303.88 |
|
|
1) NIeT: 30-06-2022 10/NIT/EE/PWD/AMP/2022-23. |
₹ 5,00,000 |
₹ 2,98,87,887 |
Work order dated '23-11-2022 Memo. No.F. TC/5/EE/PWD/AMP/11419-35 |
|
In progress |
|
|
192 |
Sabroom |
Third Circle |
SC Welfare |
Construction of 50 seated SC Girl's Hostel (G+1) at Harina High School(BRJCY) |
CSS |
175.00 |
No.F.5-1(P-I)/SCW/PLG(HOSTEL)/BJRCY/2019/23324-44 dated 25/04/22 of the Addl Secretary, Welfare of S.C |
2022-23 |
25-07-2022 |
25-11-2022 |
₹ 1,51,13,280 |
Shri Bishnu Pada Paul (Mob# 6436519065) |
05-12-2022 |
05-12-2022 |
|
365 days 05-12-2023 |
Finishing work in progress. Value of work done Rs.110.00 Lac |
Tender under Evaluation |
|
67% |
Oct-23 |
87.000 |
85.730 |
1.270 |
45.000 |
64.130 |
|
|
Overall progress is satisfactory |
₹ 1,10,00,000 |
₹ 41,13,280 |
|
|
In progress |
|
|
193 |
Sonamura |
Fourth Circle |
SC Welfare |
Common facility centre for skill developmentat Baganbari English Medium School |
RURBAN |
70.00 |
No.F. 18(103)-DM/SPJ/DEV/RURBAN(FUND)/2020-21/1129, Dt. 07-07-2020 |
2020-21 |
DNIeT No. 13/B/DNIe-T/SE-IV/PWD(R&B) /2021-22. Dt…………………. |
12-11-2021 |
₹ 1,28,60,145 |
Asok Roy 9436559127 |
27-11-2021 |
02-12-2021 |
|
03-12-2022 12 Months |
Work upto roof level. Value of work done Rs. 118.00 Lac |
|
|
90% |
July-23 |
|
94.000 |
-94.000 |
|
|
|
|
|
₹ 1,18,00,000 |
₹ 10,60,145 |
Vide No.F.10(30)/EE/SNM/PWD/10720-32 Dt.12-11-2021 |
|
In progress |
|
|
194 |
Dharmanagar |
First Circle |
SW & SE |
Const. of creation of barrier free environment under AIC / Dharmanagar court |
Sugamya Bharat |
96.00 |
No.F.2(112)-SW/DC/2010/Vol-III/PART/5890(6)dt23/03/21 |
2020-21 |
08-07-2021 |
01-09-2021 |
₹ 37,73,275 |
Sri Jagatjyoti Deb & 9612233650 |
15-09-2021 |
15-09-2021 |
|
14-01-2022 04 Months |
Civil work completed. Lift to be installed. Value of work done Rs. 90.00 Lac |
100% |
0 |
95% |
Aug-23 |
72.716 |
49.360 |
0.000 |
49.500 |
23.350 |
|
|
|
₹ 90,00,000 |
₹ -52,26,725 |
|
|
In progress |
|
|
195 |
Kailashahar |
First Circle |
SW & SE |
Const. of creation of barrier free environment under AIC / Kailashahar Court |
Sugamya Bharat |
99.00 |
No.F.2(112)-SW/DC/2010/Vol-III/PART/5890(6)dt23/03/21 |
2020-21 |
22-07-2021 |
16-09-2021 |
₹ 56,60,561 |
Bhaskar Roy 9436907056 |
30-09-2021 |
30-09-2021 |
|
29-03-2022 180 days |
Work in progress.Site for lift handed over to the agency. Work to be started soon.Approx value of work done Rs.26.65 Lac |
0% |
0% |
80% |
Oct-23 |
74.770 |
26.850 |
47.920 |
26.850 |
0.000 |
|
|
|
₹ 26,65,000 |
₹ 29,95,561 |
F.31(474)/EE/KLSD/3103-21 dt 16/9/21 |
|
In progress |
|
|
196 |
Agt Div-I |
Second Circle |
SW & SE |
Const. of creation of barrier free environment under AIC / for 7 nos. different existing building under Agartala Div-I/Balance work |
Sugamya Bharat |
1041.00 |
No.F.2(112)-SW/DC/2010/Vol-III/7992268 dt18/03/22 |
2019-20 |
|
|
|
|
|
|
|
|
Tender accepted on 18-04-23 and work will be awarded soon. |
|
|
Mar.23 |
Balance work estimate to be prepared due to sudden demise of agency and tender is under scrutiny. |
|
|
0.000 |
|
|
|
|
|
|
₹ 0 |
|
|
In progress |
|
|
197 |
Agt Div-III |
Second Circle |
SW & SE |
Const. of creation of barrier free environment under AIC / for 5 nos. different existing building under Agartala Div. No.III |
Sugamya Bharat |
826.00 |
No.F.2(112)-SW/DC/2010/Vol-III/7992268 dt18/03/22 |
2019-20 |
17/EE/Div-III/PWD(R&B)/2019-20, Dt. 05/03/2020 |
19.03.2021 |
₹ 5,28,41,923 |
Sri Kashinath Bhattacharjee |
03.04.2021 |
15-06-2021 |
Civil work completed and Lift not yet installed. Tender invited and finalised by the EE,Mechanical Division. |
09 months /02.01.2022 |
Civil work 100% completed. Lift to be installed. |
80% |
Tender invited and finalised by the EE,Mechanical Division. |
90% |
Aug-23 |
345.283 |
345.283 |
0.000 |
345.283 |
100.000 |
|
|
i)ARDD=Structure & Brick work completed & Plastering work in progress. ii)TBSE=All structural work completed & Brick work in progress. iii)Sc & Tech=Roof of 1st floor work in progress. Iv)Aranya Bhavan= Ground floor roof casting to be taken up shortly & balance work in progress. |
|
₹ 5,28,41,923 |
|
|
In progress |
|
|
198 |
Agt Div-V |
Second Circle |
SW & SE |
Proposed Construction for creation of barrier free environment in 14(fourteen) State Government buildings at Agartala for the benefit of persons with Disabilities under the Accessible India Campaign (AIC) during the year 2019-20 / SH:- Construction of Parking bay, Accessible pathway with tactile guiding, Handrails on stair, corridors, Unisex toilet for disable persons etc. for different existing buildings of Ramthakur College, Agartala and Panchayati Raj Training Institute (PRTI) adjacent to SIPARD, Arundhutinagar, Agartala, Tripura(3rd Call).(Agartala Div. No.V) |
Sugamya Bharat |
554.00 |
Memo No.F.2(112)-SW/DC/2010/Vol-III/792268 dt18/03/22 (Annexure -B) |
2019-20 |
PNIT No. 09/B/EE-V/AGT/PWD/(R&B)/2021-22. dated 03.12.2020 |
11.06.2021 |
3,60,86,189.00 |
Sri Uttam Dey |
26.06.2021 |
03.04.2022 |
Initial delay for selection of site |
26.03.2022 |
Civil work in progress and lift to be installed. Work delayed due to approval of tentative deviation. |
Tendering stage |
20% ( Tender procces to Higher authority for Approval) |
50% |
Nov - 23 (Except installation of lift & IE works) |
545.000 |
65.000 |
480.000 |
480.000 |
0 |
|
|
Work was suspended due to non approval of Extra items/ deviation. Very recently approval of deviation communicated to this end on dated , Hence work resumed and now in progress. |
₹ 80,00,000 |
₹ 2,80,86,189 |
F.6(360)/EE-V/AGT/PWD/2020-21/976-94 dated 11.06.2021 |
DNIT No. CE(Building)/PWD/DNIT/ACE/Project Unit/04/2020-21 |
In progress |
|
|
199 |
Agt Div-I |
Second Circle |
SW & SE |
Const. of creation of barrier free environment under AIC / Agartala Court |
Sugamya Bharat |
361.00 |
No.F.2(112)-SW/DC/2010/Vol-III/PART/5890(6)dt23/03/21 |
2020-21 |
|
|
|
|
|
|
|
|
Work in progress |
|
|
|
Sr Architect will be issue drawing of toilet &lift |
0.000 |
0.000 |
0.000 |
0.000 |
0.000 |
|
|
|
|
₹ 0 |
|
|
In progress |
|
|
200 |
Udaipur |
Third Circle |
SW & SE |
Const. of creation of barrier free environment under AIC / Udaipur court |
Sugamya Bharat |
75.00 |
No.F.2(112)-SW/DC/2010/Vol-III/PART/5890(6)dt23/03/21 |
2020-21 |
24.08.2021 |
21.01.2022 |
₹ 40,35,000 |
Sri Ashit Banik. M-9436490187 |
05.02.2022 |
21-01-22 |
|
04.08.2022 6 Month |
Civil work almost completed. Mechanical part to be started now. Value of work done Rs.40,34,000/- |
Work in progress |
|
95% |
Aug'23 |
55.500 |
55.500 |
0.000 |
55.500 |
12.000 |
31.12.2022. Attributable to the agency. |
Yes |
Work Order for installation of lift has been issued by Mechanical Division. |
₹ 40,34,000 |
₹ 1,000 |
Agreemt. No. 61/SE-III/EE/UDP-DIVN/UDP/2021-22 |
|
In progress |
|
|
201 |
Belonia |
Third Circle |
SW & SE |
Const. of creation of barrier free environment under AIC / Belonia Court |
Sugamya Bharat |
112.00 |
No.F.2(112)-SW/DC/2010/Vol-III/PART/5890(6)dt23/03/21 |
2020-21 |
11/EE(PWD)/BLN/2021-22 Dt 01-10-2021 |
14.12.2021 |
₹ 97,53,000 |
Rajib Nandi 9436517634 |
19.12.2021 |
01.01.2022 |
|
24.09.2022 9 Months |
Civil work completed & lift to be installed. Rs.97.53 lakh |
|
Not yet |
100% |
Aug'23 |
112.880 |
57.500 |
55.380 |
57.500 |
70.260 |
|
|
Lift installation yet to be done by the Mechanical Division |
₹ 97,53,000 |
₹ 0 |
|
|
In progress |
|
|
202 |
Agt Div-V |
Second Circle |
Science & Technology |
Establishment of Science Park at Vigyan Gram, Tripura |
NEC |
1039.58 |
Dated 12/2/2021 |
2020-21 |
33/EE-V/AGT/PWD(R&B)/22-23 Dated 30th Nov. 2022 |
|
|
|
|
|
|
|
4th Call of Tender cancelled by the competent authority on dated 05.06.2023 |
|
|
|
|
10.000 |
0.000 |
10.000 |
0.000 |
|
|
|
4th Call of Tender cancelled by the competent authority on dated 05.06.2023 |
|
#VALUE! |
|
|
Tendering Stage |
|
|
203 |
Kanchanpur |
First Circle |
Tribal Welfare |
Constn of 24 nos Qtr RMM School, Kanchanpur/Balance work |
|
567.00 |
25-17/TW/REIS/2011/7330-337, dated 16-11-2016 of Tripura Tribal Welfarr Residential Educational Institutions Society |
2016-17 |
28.12.2021 |
28-06-2022 |
₹ 4,58,94,000 |
Sri Chiranmay Paul Choudhury 9435079593 |
13-07-2022 |
13-07-2022 |
|
18 months Dec, 2023 |
Type -I-Finishing work in progress,Type III-Structural work completed. Brick and Plastering work in progress Value of work done Rs. 215.00 Lakh |
|
|
85% |
Oct, 23 |
383.000 |
383.000 |
0.000 |
383.000 |
184.000 |
|
|
|
₹ 2,15,00,000 |
₹ 2,43,94,000 |
|
|
In progress |
|
|
204 |
Kumarghat |
First Circle |
Tribal Welfare |
Re-construction of 50seated ST Girl's Hostel attached to Pabiacherra H.S.School,Kumarhat MC,Unakoti District(double decker) including boundary wall,inbuilt Supdt.quarter/ Ground Floor & Boundary wall (150 Mtr) |
Special Assistance Capital |
200.00 |
No.F.22-131/TW/PLG/ENGG/2010-11/68687-68704 dt.23/12/22. No.F22.298/TW/PLG/ENGG/2022-23/91125-140 dt16/06/22 & |
2022-23 |
06-01-2023 |
|
|
|
|
|
Initially there was site problem |
|
Tender opened on 19/04/2023 and now tender under scrutiny.( Letter issued to Bidder for submission of shortfall documents) |
|
|
|
|
|
|
0.000 |
|
|
|
|
|
|
₹ 0 |
|
|
tendering stage |
|
|
205 |
Kumarghat |
First Circle |
Tribal Welfare |
Constn of 24 Nos Staff quarters (12 Nos Type-I & 12 Nos Type-III; (G+2): Four unit at each floor attached to Ekalavya Model residential School, Darchawi, Kumarghat |
Special Assistance Capital |
567.00 |
No F 25-19/TW/RESI/2019-20/7495-508 dt. 18/07/2022 of the Jt Sec, TW |
2022-23 |
|
|
|
|
|
|
|
|
DNIT to be prepared within the earlier sanctioned amount as Phase-I and estimate is under preparation for Phase-II |
|
|
|
|
|
|
0.000 |
|
|
|
|
1) Revised Preliminary estimate amounting to Rs.867.17 Lac submitted to TW Deptt vide letter No.F.13(2)/PWD/ACE/Project Unit/2022/5855-59 Dt. 16/3/2023 of the SE, Project Unit, for accord of revised A/A & E/S 2) DNIT to be prepared within the earlier sanctioned amount as Phase-I and estimate is under preparation for Phase-II |
|
₹ 0 |
|
|
Not yet started |
|
|
206 |
Khowai |
Second Circle |
Tribal Welfare |
Re-construction of 50seated ST Girl's Hostel attached to Baijalbari H.S.School,Padmabil,Khowai District |
Special Assistance |
200.00 |
No.F22.298/TW/PLG/ENGG/2022-23/91125-140 dt16/06/24 |
2022-23 |
29-07-2022 |
31-12-2022 |
₹ 1,80,23,652 |
Sarajit Kr. Paul (9436503533) |
15-01-2023 |
|
Due to Initial delay in handing over the clear site work could not be started in time. |
365 Days ('14-01-2024) |
Work just started. |
0% |
0% |
0% |
May'24 |
75.000 |
0.214 |
74.786 |
0.000 |
75.000 |
|
|
|
|
₹ 1,80,23,652 |
|
1) The EE, KHW has surrended fund amounting to Rs. 74,78,601/- and requested for revalidation of the same to the Jt. Secretary, TW Deptt. vide letter No.F.7(29)/EE/PWD/KHW/11561-565 Dt. 17/3/23. Rs.21,399/- has been utilised and balance Rs.74,78,601/- is surrendered by the concerned EE vide letter No.F. 7(29)/EE/PWD/KHW/11561-565 dt. 24/02/23. The Addl Director, TW has taken up the issue with Directore, Sec Edn for issuance of NOC to EE, KHW vide letter No.F. 22-190/TW/PLG/ENGG/2010-11/79923-34 Dt. 24/3/23. |
In progress |
|
|
207 |
Amarpur |
Third Circle |
Tribal Welfare |
Re-construction of 50seated ST Girl's Hostel attached to Silachari H.S.School,Silachari,Gomati District(double decker) (2nd Call) |
Special Assistance |
200.00 |
No.F22.298/TW/PLG/ENGG/2022-23/91125-140 dt10/06/22 of the Joint Secretary to the Govt. of Tripura, Tribal Welfare Deptt. Rs. 2.00 |
2022-23 |
08-03-2022 |
13-01-2023 |
₹ 1,59,45,966 |
Shri Swapan Datta (Mob No: |
29-01-23 |
|
|
28-01-24 365 Days |
Up to tie beam level completed ,work is in progress. Value of work done Rs. 32.00 lakh . |
|
|
10% |
Dec'24 |
75.00 |
0.000 |
75.00 |
0.000 |
84.46 |
|
|
1) NIeT :03-08-2022 14/NIT/EE/PWD/AMP/2022-23. |
|
₹ 1,59,45,966 |
No.F.2-127/BLD/EE/PWD/AMP/2022-23/17127-43 Dt. 13/10/23 |
|
In progress |
|
|
208 |
Gondatwisa |
Fifth Circle |
Tribal Welfare |
Re-construction of 50 seated ST Boys Hostel attached to Jagabandhupara H.S.School,Dumburnagar,Dhalai District. |
Special Assistance |
200.00 |
No.F22.298/TW/PLG/ENGG/2022-23/91125-140 dt16/06/22 |
2022-23 |
|
20-12-2022 |
₹ 1,75,77,000 |
Shri Sumanta Gupta (9436457880) |
04-01-23 |
07-01-2023 |
|
03-01-2024 12 months |
Foundation and plinth beam work completed. Column in Progress. Value of work done (Approx): Rs. 75.00 Lac |
|
|
30% |
June 24 |
75.000 |
75.000 |
0.000 |
0.000 |
0.000 |
|
|
|
₹ 75,00,000 |
₹ 1,00,77,000 |
|
|
In progress |
|
|
209 |
Agt Div-III |
Second Circle |
Tourism |
Constn of conference block,wayside Amenities(Cafeteria)in/c site development at Border Ceremony Facility, Akhaura, Agartala |
Swadesh Darshan |
476.00 |
Please fill up the columns |
|
|
|
|
|
|
|
|
|
Conference Hall completed upto Ground Floor level and handed over as and where basis on 04/05/2023 |
|
|
|
|
433.000 |
433.000 |
0.000 |
433.000 |
10.000 |
|
|
Work suspended due to objection of Border Guards Bangladesh |
|
₹ 0 |
|
|
suspended |
|
|
210 |
Agt Div-I |
Second Circle |
Tourism |
Constn of covered gallery with Barrack at Akhaura checkpost. |
Swadesh Darshan |
314.00 |
|
|
|
|
|
|
|
|
|
|
i) Toilet block=Work completed in all respect. Ii)General Gallery with Barrack= Foundation work completed & structural work suspended due to objection raised by the BGB. Iii)VIP gallery=Clear site yet to be finalised due to objection raised by BGB. Iv) Main Gate/Entrance Gate= Clear site not finalized due to objection raised by BGB. v) Parking Zone=Work completed. |
|
|
|
Work suspended due to objection of Border Guards Bangladesh |
354.430 |
111.313 |
243.117 |
111.313 |
|
|
|
Rs. 243.117 Lac has already been lapsed. Handed over in incompleted stage Dated 01-10-2022 (handing over note ofAE, Central-III,Taken over by Er Dipankar Ghosh, Tourism Department) |
|
₹ 0 |
|
|
suspended |
|
|
211 |
Udaipur |
Third Circle |
Tourism |
Proposed waterfront Development of Jaganath Dighi PH-II |
Swadesh Darshan |
787.00 |
F.2(180)-PI/TT/2016(UDP-II)/Part/201-08, dt.12.04.2021 |
2021-22 |
13.05.2020 |
29.11.2021 |
₹ 5,78,54,000 |
Sri Raja Raw Ghosh. M-8132804119 |
14.12.2021 |
14.12.2021 |
Finalization of ghat location and receiving of drawing. |
13.12.2022 12 Month |
Boundary wall, drain, foot track, seating arrangement & ghat ( in progress). Value of work done Rs.4,90,25,000.00 |
60% |
|
90% |
Aug-23 |
787.000 |
669.950 |
117.050 |
669.950 |
0.000 |
|
Yes |
|
₹ 4,90,25,000 |
₹ 88,29,000 |
|
|
In progress |
|
|
212 |
Udaipur |
Third Circle |
Transport |
Construction of Motor Stand at Rajarbag, Udaipur,Gomati District/2nd Call |
Special assistance |
1000.00 |
E/S: Memo No.F. 18(8)/Trans/2021/751-57 Dt. 10/02/22 of the DS, Transport Deptt for Rs. 10.00 Crore.Administrative appoval vide memo No.F.18(8)-Trans/2021/1303-13 dt14/03/22 of D.S, Transport Deptt.( Fund sub-allocated for Rs. 333.71 Lakh) |
2021-22 |
Ist Call: 16/7/22 2nd Call: '17.08.2022 |
22-05-23 |
₹ 7,89,32,802 |
Sri Kajal Saha. M-9436490187 |
11-05-23 |
|
Delay due to pending demolision of Old structure by appropripate authority |
Date? 18 Month |
Work will be started after getting clear site from the Client Department. |
|
|
|
Dec-24 |
133.710 |
0.000 |
133.710 |
0.000 |
0.000 |
|
|
|
|
₹ 7,89,32,802 |
|
The EE,UDP has surrendered fund Rs. 333.71 Lac vide his letter No.F./EE-PWD-UDP-DIVN/ACTT-UC-10/10219-22 Dt, 3/3/23 to the Deputy Sectary, Transport department, since work is not yet taken up. E/S: Dt. 10/02/22 of the DS, Transport Deptt for Rs. 10.00 Crore.A/A 14/03/22 with fund Fund sub-allocattion for Rs. 333.71 Lakh. Ist Call: 16/7/22 (No Bidder). 2nd call: 17/8/22. E/Cost: Rs.744.79 Lac. Time : 18 Months. Tendered value: 789.33 Lac. DPC: 2/11/22. Acceptance of Admin Deptt: 21/3/23. Formal acceptance will conveyed very shortly forllowed by issuance of LoA by EE, SNM. Sri Kajal Saha, Ushabazar, Chinaihani, Agartala, West Tripura, Pin-799009 fAccepted for an amount of `7,89,32,801.60 which is @5.98% (five point nine eight percent) above the estimated cost of `7,44,78,959.81 put to tender. |
Tendering Stage |
|
|
213 |
Jirania |
Fourth Circle |
Transport |
Construction of Terminus building for Interstate Truck Terminus (ISTT) at Madhabbari, Jirania, West Tripura /SH: Construction of 1st floor of Terminus building (Vertical extension). |
NEC |
303.00 |
18(2)-Trans/2003(P-II)/(Vol-X) dt.23/10/2019 |
2019-20 |
|
17-03-2021 |
₹ 2,53,97,179 |
Sri Mintu Debnath M-9436126343 |
01-04-21 |
01-04-2021 |
|
15 month 30-06-2022 |
Civil completed (245.35 Lakhs). Installation of lift is started |
100% |
100% |
100% |
Completed |
291.5 |
291.28 |
0.22 |
286.80 |
Nil |
Civil work:12-12-2022 Mechanical work: |
164 days delay |
|
₹ 2,45,00,000 |
₹ 0 |
|
|
Completed |
|
|
214 |
Institute of Driving Training & Research at Jirania. Construction of 2(two) lane approach road at IDTR Jirania Other Subheads as follows separately |
Special Assistance |
256.63 |
No.F.11(3)-Trans/2009(P-17)/4592-99 dt.21/09/2022 of the Deputy Secretary, Transport Deptt. Rs.256.63 lakh |
2021-22 |
|
25-11-2022 |
₹ 2,31,00,060 |
Sri Josoda Lal Roy |
10-12-2022 |
30-11-2022 |
- |
180 days 08-06-2023 |
2(two) lane approach: CD, Protection work, GSB, WMM, Surface course work, Drainage work completed (242.937 Lakhs) |
Not requied |
Not requied |
100% |
Completed on 06-06-23 |
256.63 |
191.00 |
0.00 |
191 |
51.937 |
06-06-2023 |
No |
Unspent Rs. 65.63 Lac was surrendered end of F.Y 2022-23 |
₹ 2,42,93,700 |
₹ -11,93,640 |
|
|
In progress |
|
|
214(I) |
Construction of Control Room including Sanitary installation etc. |
Special Assistance |
117.00 |
No.F.11(3)-Trans/2009(P-14)/795-800 dt.10/02/2022 of the Deputy Secretary, Transport Deptt. Rs.117.00lakh |
2021-22 |
|
29-06-2022 |
₹ 22,38,000.00 |
Sri Bapan Nandi |
21-07-2022 |
28-07-2022 |
Delay as per memo of Deputy Secretary, Transport vide No.F.11(3)-Trans/2009(P-14)/Part dt.12/09/2022 |
17-01-2023 180 Days |
Control Room=95% work completed, Roof casted, BW Wall , toilet, grill fittings, completed, flooring, drainage work, window, door, sanitary installation complete & finishing work in progress. (21.34 Lakhs) |
|
Not requied |
95% |
Aug'23 |
117.79 |
21.08 |
35.54 |
47.492 |
|
|
|
|
₹ 21,34,000 |
|
|
|
In progress |
|
|
214(II) |
Construction of footpath, CC drain |
|
29-06-2022 |
₹ 28,38,000.00 |
Sri Anujit Das |
14-07-2022 |
05-07-2022 |
10-01-23 180 Days |
Footpath= work completed (28.40 Lakhs) |
|
Do |
100% |
Completed |
28.40 |
|
|
|
₹ 28,40,000 |
|
|
|
|
|
|
214(III) |
Construction of Observation Room (watch Tower) including sanitary installation etc |
|
29-06-2022 |
₹ 25,81,000.00 |
Sri Suman Debnath |
14-07-2022 |
14-07-2022 |
10-01-23 180 Days |
Observation room= 75% Work completed, slab and brick work completed for GF and FF. Flooring and Finishing work in progress . (14.55 Lakhs) |
|
Do |
75% |
Aug'23 |
14.25 |
|
|
|
₹ 14,55,000 |
|
|
|
|
|
|
214(IV) |
Construction of Security Room including sanitary installation etc (Two Nos) |
|
18-08-2022 |
₹ 30,64,000.00 |
Sri Raju Das |
02-09-22 |
22-08-2022 |
01-03-23 180 Days |
Security room= 65% work completed, Roof casted, BW Wall , toilet, grill fittings, completed & flooring, drainage work, window, door, sanitary installation, finishing work in progress. (18.86 Lakhs) |
|
Do |
65% |
Aug'23 |
18.50 |
|
|
|
₹ 18,86,000 |
|
|
|
|
|
|
215 |
Sonamura |
Fourth Circle |
Transport |
Construction of Entrance Gate & approach road for Floating Jetty at Srimantapur, Sonamura |
|
24.00 |
No.F. 34(2)-Trans/2010(Part-2)(L), Dated 09-07-2020 |
2020-21 |
20/EE/SNM/PWD/2021 Dt……………. |
Vide No.F.10(30)/EE/SNM/PWD/10172-85 Dt.'05-02-2021. |
₹ 24,26,110 |
Gautam Laskar 8416015192 |
20-02-2021 |
|
|
|
Site is not finalized by Land Port Authority. |
|
|
|
|
24.989 |
0.000 |
24.989 |
|
|
|
|
|
|
₹ 24,26,110 |
Vide No.F.10(30)/EE/SNM/PWD/10172-85 Dt.05-02-2021. |
|
not yet started |
|
|
216 |
Teliamura |
Second Circle |
UDD |
Setting up of Electric cremation furnace at Teliamura Municipal Council in/c Civil,Mechanical works. |
15-Finance (Un-tied) |
111.00 |
Rs. 111.23 Lakh No. 2420-25/F.2(6)/TMC/2017 dt. 13/01/2022 of the Chief Executive Officer, Teliamura Municipal Council. |
2021-22 |
24-02-2022 |
10-05-2022 |
₹ 83,24,647 |
Sri Haran Ch. Das 9436168447 |
25-05-2022 |
25-05-2022 |
|
24-02-2023 (9 Months) |
Civil, Mechanical & Internal electrification work completed. External electriication work is in progress. Total value of work done Rs.83.25 Lac |
100% |
100% |
100% |
|
111.000 |
111.000 |
0.000 |
111.000 |
0.000 |
25-06-23 |
|
|
₹ 83,25,000 |
₹ -353 |
|
|
Completed |
|
|
217 |
Constn of Teliamura Motor Stand |
TIIFB |
500.00 |
Rs. 500.00 lakh Memo No.F. 18(1)-UDD/DUD/DEV/2020/15508-16 dt. 19/01/2022 of the Additional Secretary to the Govt. of Tripura. |
2021-22 |
23-07-2021 |
26-10-2021 |
₹ 4,29,18,220 |
Sri Prafulla Das 9436135082 |
10-11-2021 |
13-12-2021 |
Delay occurred due to the effect of model code of conduct for Municipal Election. |
09-02-2023 (15 Months) |
RCC structure completed. Fitting fixing of roofing truss is in progress. Total value of work done Rs.250.00 Lac. Tubular truss, Roofing and road works are in progress. |
0% |
|
65% |
July,23 |
200.000 |
200.000 |
0.000 |
200.000 |
300.000 |
|
|
|
₹ 2,50,00,000 |
₹ 1,79,18,220 |
|
|
in progress |
|
|
218 |
Agt Div-V |
1. Construction of Bus Terminal at Nagerjala, Agartala under NLCPR ruction of Terminal building, (ii) Construction of Rehabilitated Shops/SH: Building portion including internal water supply and sanitary installation. |
NLCPR |
1668.00 |
Memo No. 16(1)-UDD/DUD/2006/39669-76 dated 26.03.2014 . MoDONER/NLCPR |
2013-14 |
PNIT No. 03/B/EE-V/AGT/PWD/2014-15 dated '04.06.2014 |
29.11.2014 |
₹ 6,27,50,221 |
Arun Kr. Dey |
13-12-14 |
02.11.2015 |
Clear site could be available in time. Also NLCPR fund is not in flow.Further works delayed due to pandemic. |
13-06-16 18 Months |
Work in progress.(Finishing work of terminal buildings) Internal road GSB: 100%, WBM-II: 100%, WBM-III: 100%,) Work almost completed @ 95%. |
75% |
N.A |
95% |
Aug-23 |
1319.27 |
1319.27 |
0.000 |
1288.82 |
369.000 |
Delayed as explained . |
Time extension required for 889 days |
Agreement of Arun Kr. Dey was closed. Balance Work in separate Agreement is in progress. Name of Agency : Sri Jasoda Lal Roy Agreement No. 28/B/SE-II/EE-V/AGT/PWD/2022-23 Agreement Value : Rs. 1,89,74,605.60 External Electrification / Sub station work yet to be taken by TSECL authority. Fund required at present 200.00 lakh urgently. |
₹ 15,19,00,000 |
Rs. 1,70,00,000 (Including IE works) |
No.F.6(354)/EE-V/AGT/PWD/5829-46 dated 29.11.2014 |
DNIT No. CE/PWD/(R&B)/DNIT/SE (Project)/15/2014-15 Project is nearing completion stage. Tentative date of completion is August, 2023, subject to immediate release of fund of 200 Lacs. Tentative deviation for Rs. 15.00 lakh processed to the competent authority for necessary approval of the Agency, Jasoda Lal Roy for remaining Balance work. |
in progress |
|
|
219 |
Construction of Bus Terminal at Nagerjala, Agartala under NLCPR : Construction of internal road and road side drain , waiting shed and parking area for different types of Vehicle . |
NLCPR |
|
|
|
PNIT No. 01/B/EE-V/AGT/PWD/2016-17 dated 02.03.2017 |
02.03.2017 |
₹ 6,07,74,256 |
Arun Kr. Dey |
16-03-17 |
24.07.2017 |
Clear site could be available in time. Also NLCPR fund is not in flow.Further works delayed due to pandemic. |
16-06-18 15 Months |
|
|
|
|
|
|
|
|
|
No.F.6(354)/EE-V/AGT/PWD/6028-45 dated 02.03.2017 |
DNIT No. CE(Building)/PWD/DNIT/SE (Project)/81/2016-17 Project is nearing completion stage. Tentative date of completion is August, 2023, subject to immediate release of fund. |
in progress |
|
|
220 |
Santirbazar |
Third Circle |
UDD |
Construction of Fish Market at Santirbazar under Santirbazar Municipal Council under Special Central Assistance (SCA- Untied) |
SCA (United) |
100.00 |
No F.16(5)/UDD/DUD/2014/8999-9009 dated, 11-11-2016 |
2016-17 |
PNIeT- No:- 29/EE/PWD(R&B)/STB/2019-20 dated, 04-02-2020 |
17-07-2020. |
₹ 1,11,29,506 |
Nikhil Ch. Dey. 9436123287 |
01-08-2020 |
17-07-2020 |
Work started in due time. |
15(fifteen) Months '31-10-2021 |
Finishing Work in progress Value of work Done= Rs. 115 Lakh |
Yet to start. Separate fund is required for I.E |
Not Required |
95% |
Oct'23 |
100.000 |
100.000 |
0.000 |
100.000 |
11.300 |
|
Yes, required |
|
₹ 1,15,00,000 |
₹ -3,70,494 |
No.F. 9(3)/EE/PWD/STB/2153-66 |
|
in progress |
|
|
221 |
Construction of Santirbazar Municipal Council at Santirbazar, South Tripura. |
URBAN |
317.00 |
No F.16(5)/UDD/DUD/2008/11237-51 dated, 09-01-2014 |
2013-14 |
PNIeT- No:- 03/EE/PWD(R&B)/STB/2016-17 dated, '04-06-2016 |
21-02-2017 |
₹ 2,52,70,658 |
Samir Chakraborty 9436131489 |
07-03-2017 |
02-11-2017 |
Initial delay, because of clear site which can't handed over in time by the concerned Dept. |
18(eighteen) Months '06-09-2018 |
1st floor building finishing. work is in progress. Value of work Done= Rs. 230 Lakh |
Work in progress |
Not Required |
85% |
July' 23 |
252.700 |
232.470 |
20.230 |
174.470 |
0.000 |
|
Yes, required |
|
₹ 2,30,00,000 |
₹ 22,70,658 |
No.F. 9(3)/EE/PWD/STB/5693-5706 |
|
in progress |
|
|
222 |
Belonia |
Setting up Tertiary Waste Processing Center for Belonia Municipal Council at Baspadua near Municipal Dumping station |
UDD |
149.00 |
No.F.9(5)-SWM/CEO/BMC/BLN/2020-2021/5940-44 dated,10-02-2021 |
2020-21 |
12/EE(PWD)/BLN/2021-22 Dt 31-03-2021 |
28.06.2021 |
₹ 1,22,24,000 |
Amal Majumder 9436518511 |
13.07.2021 |
26.07.2021 |
Due to execution of site development work |
08.01.2022 06 Months |
Work almost completed.Rs.122.24 lakh. |
Not yet |
NA |
95% |
Sept-23 |
139.000 |
96.100 |
42.900 |
50.000 |
------ |
|
|
1) Due to earth cutting work for site development and also delay by the agency. 2) Tertiary waste processing centre agreement work completed. Due to few additional work tender invited. In all respects the work will be completed and handed over to concerned deptt by September 2023. |
₹ 1,22,24,000 |
₹ 0 |
No.F.7(20 )Pt-I/EE(PW D)/BLN/DIV N/1057-69 Dt.28.06.21 |
|
in progress |
|
|
223 |
Bishalgarh |
Fourth Circle |
Const Bishalgarh Municipal Council Office/G.F only with foundation provision G+2 |
UDD |
288.00 |
F.4(1-1)/BMC/BLG/2014/3293-96 dated 12/09/22 of the CEO, Bishalgarh Mucipal council |
2022-23 |
PNIeT No 31/EE-BSLD/PWD(R&B)/2022-23, Dated-'04/11/2022. DNIeT-CE(Buildings)/PWD/DNIT/ACE/Project Unit/78/2022-23 |
LoA '24-03-23 |
₹ 2,82,95,022 |
Ashim Kr Saha 9436131061 |
08.04.2023 |
|
|
300 Days (01.02.2024) |
Clear site not handed over by the Bishalgarh Municipal Council authority |
|
|
|
|
125.000 |
0.000 |
125.000 |
0.000 |
0.000 |
|
|
Est Cost: 2,62,55,008/- Contract value: 2,82,95,022/-. Tender accepted on 14/03/23 by the Department on the recommendation of DPC |
|
₹ 2,82,95,022 |
|
|
not yet started |
|
|
224 |
Ambassa |
Construction of Ambassa Municipal Council office |
State Plan |
317.00 |
16(05)-UDD/DUD/ 2008/11237-51 Dt.09/01/14 by the UD Deptt. |
2013-14 |
PNIeT.No: 14/EE/PWD(R&B)/AMB/2021-22 Dated:'24-08-2021 |
20-01-2022 |
₹ 2,26,49,938 |
Sumanta Gupta [9436457880] |
05-02-2022 |
04-05-2022 |
Initial delay in handing over of clear site by the Municiapal Authority |
15 months [04-05-2023] |
Final roof Slab casting completed and masonry wall work in progress Value of Work Done = 130.00 lacs ( approx) |
Nil |
Nil |
80% |
Sept,23 |
221.000 |
96.000 |
125.000 |
96.000 |
0.000 |
|
|
Rs. 125 lakh lapsed and processed for revalidation |
₹ 1,30,00,000 |
₹ 96,49,938 |
|
|
in progress |
|
|
NEW |
Sonamura |
|
Construction of Sports Complex at Shantinagar H.S School, Sonamura, Sepahijala District, Tripura under RURBAN Mission/SH: Building portion including internal water supply, Sanitary installation, Swerage and Drainage works/2nd Call |
RURBAN |
5.05 |
No.F.18(103)-DM/SPJ/DEB/RURBAN(FUND)/2020-21/2231, Dt. 21-10-2020. |
2020-21 |
2ndCall: '12/04/23 |
|
|
|
|
|
|
|
2nd Call of tender invited on 12-04-2023 and to be opend on 11-05-2023. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2nd Call: PNIeT No. 01/EE/SNM/PWD/2023-24 Dated 12/04/2023. Last date of receipt: 11/05/2023. Estimated Cost: 3,53,09,782/-Time for completion 365 Days |
|
|
|
NEW |
|
Construction of 16 Nos Staff quarter building at ........... ( Type-1: 6 Nos, One Block, Twin, G+2), (Type-II 6 Nos, One Block, Twin, G+2) and Type-III: 4 Nos, one Block, Twin, G+1) /SH: Building portion including internal water supply, Sanitary installation, Sewarage and Drainage works/2nd Call |
|
|
|
|
2ndCall: '12/04/23 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2nd Call: PNIeT No. 01/EE/SNM/PWD/2023-24 Dated 12/04/2023. Last date of receipt: 11/05/2023. Estimated Cost: 3,94,03,210/-Time for completion 540 Days |
|
|
|
NEW |
Jirania |
|
Construction of 10 Nos Staff quarter at Ranirbazar Primary Health Centre (PHC) santioned under NHM/ SH:Construction of 6 Nos Type-II quarters (one Nlcok Twin G+2 Storied) for Ranir bazar Primary Health Centre(PHC) at Ranir bazar, West Tripura/ Building portion including water supply, sanitary installation, sewage and Drainage works |
NHM |
|
|
|
1st Call '12/04/23 |
|
|
|
|
|
|
|
Tender under scrutiny. ( TEC meeting held on 23/6/23) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1st Call: PNIeT No. 36/EE-JRN/PWD/2022-23 Dated 27/03/2023. |
|
|
|
NEW |
Dharmanagar |
First Circle |
Health |
Construction of office building(G+1 Storied) for Chief Medical Officer ( CMO ) at Dharmanagar, North Tripura/SH: Building portion including internal water supply, sanitary installation, sweage and drainage works |
State Plan |
603.8 |
No.F.19(538)-PLAN/DFWPM/2013(Sub)/4857-62(V-1)-dated 08/11/2022 of the Deputy Secretary, Govt. of Tripura |
2022-23 |
04-04-2023 |
|
|
|
|
|
|
450 days |
Tender under scrutiny. ( TEC meeting held ) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
( NIeT No. 02/EE/DD/PWD(R&B)/2023-24 Dated 04-04-23) Est Cost: Rs. 3,16,57,998/- DNIT No. CE(Buildings)/PWD/DNIT/ACE/Project unit/103/2022-23 |
|
|
|
NEW |
Sabroom |
Third Circle |
School Education |
Infrastructure Development of Chalita Bankul Colony H.S School under Rupaichari Block, South District/SH: Building portion including internal water supply, Sanitary Installation, Sewage, Drainage works, Internal Electricfication works, Fire Fighting works, Installation of Iron Removal Plant and Installation of 1 No Small Bore Tube Well (SBDTW), Rain water harvesting including 200 Mtr long Boundary wall, 130 Mtr long barbed wire fencing and Environmental & Social Management Plan( ESMP) Budget |
World Bank |
946.24 |
IN-PWD(B)-358058-CW-RFB….Dated……… |
2023-24 |
29-04-2023 |
|
|
|
|
|
|
540 days |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Estimated Cost Rs.9,46,24,147.00 |
Tendering stage |
|
|
NEW |
Dharmanagar |
First Circle |
Health |
Development of District Hospital, North Tripura, Dharmanagar during the year 2023-24/SH: Parking site for vehicles by earth filling, GSB, WBM & providing intern locking paver block. |
Subarna Jayanti |
120.94 |
No.F.3(5-137)-PLAN/DHS/2022-23/3676-87 dated 28/04/2023 of the Deputy Secretary, Govt. of Tripura |
2023-24 |
17-06-2023 No.09/SE(II)/KGT/2023-24 |
|
|
|
|
|
|
|
Tendering Stage |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
NEW |
Construction of Boundary wall around Jail Complex at Kalikapur, Dharmanagar North Tripura during the year 2022-23 |
Major Work Home |
153.55 |
No.F.I-604/IGP/2021/1438-43 dated 17/03/2023 of the Deputy Secretary,Home (Jail) Department Govt. of Tripura |
2023-24 |
23-05-2023 No.1/SE(I)/KGT/2023-24 |
|
|
|
|
|
|
180 days |
Tender under scrutiny. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
NEW |
Up-gradation of infrastructure facilities of Dharmanagar District Hospital during the year 2016-17 / SH: Constructionof boundary wall along the periphery of the Hospital campus in/c Gate, Retaining wall, Grill etc. |
SJTNY |
240.96 |
No.F.3(5-137)-PLAN/DHS/2022-23/1105-1116(V-V) dated 17/01/2023 of the Deputy Secretary, Govt. of Tripura |
2023-24 |
18-12-2017 |
07-08-2018 |
₹ 2,12,21,157 |
Sri Debobrata Chakraborty & 8729833185 |
21-08-2018 |
21-08-2018 |
Non availibility of funds. |
20-02-2019 06 Months |
Boundary wall length 400.00 Mtrs. completed Further work in progress.Value of work done Rs. 170.00 Lakhs |
|
|
70.00% |
Aug'23 |
120.48 |
120.48 |
|
|
120.480 |
Non avalibility of Funds |
Yes |
The work is in progress and will complete shortly. Approx. |
₹ 1,70,00,000 |
|
|
|
|
|
|
Physically completed 22-23
Physically completed 22-23
Published: August 03, 2023
NOTE: LIST OF WORKS PHYSICALLY COMPLETED DURING THE F.Y 2022-23 UPTO 31-03-2023. KINDLY UPDATE THE COLUMNS HIGHLIGHTED UNTIL PROJECT IS FINANCIALLY COMPLETED AND SEND REPORT FOR PREPARING FINANCIAL REPORTS BY THE CE OFFICE. |
|
|
|
|
|
|
Status of Works of various departments entrusted to PWD(Buildings) as on 30-04-2023 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Details |
|
|
|
|
Tendering Details |
|
Physical Progress Details |
|
|
|
Financial Progress Details |
Project Completion |
Remarks |
|
Additional Informations |
|
Sl. No. |
Division |
Circle |
Client Department |
Name of Work |
Scheme |
Sanctioned Project Cost (Rs.in Lac) |
Ref of Sanction in/c name of authority & Amount. |
Sanction year |
Dt. Of NIeT/ (Details if not finalished) |
Dt. Of Work order |
Awarded Value (Rs.) |
Name of Contractor & Contact No |
Dt. Of Commencement as per W/Order |
Actual Dt. Of Commencement |
Reason for delay in commencement & action taken/initiated (If any) |
Stipulated Period & Date of Completion as per agreement |
Brief Physical Progress and approx. Value of work done as on reporting date |
Progress of IE works in percentage |
Progress of Mechanical works in percentage |
Overall Progress in Percentage |
Target date/Month of Completion |
Fund received (Upto Date) (In Lac upto 3 Decimal) |
Expenditure incurred (Upto Date) (In Lac upto 3 Decimal) |
Balance in Hand (In Lac upto 3 Decimal) |
U.C Submitted (Upto date), (In Lac upto 3 Decimal) |
Fund required (Upto date), (In Lac upto 3 Decimal) |
Date of actual Completion and reason for delay/, if any. |
Whether Time extn required (No of days)/Levy /LD realised during execution (With ref.) |
(Detailed overall observation and information to include not covered in rest columns) |
|
Approx Value of work done |
Remaining value of work done |
Ref Of Work order |
Other informations |
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
16 |
17 |
18 |
19 |
20 |
21 |
22 |
23 |
24 |
25 |
26 |
27 |
28 |
29 |
30 |
|
|
|
|
|
|
1 |
Udaipur |
Third Circle |
ARDD |
j) Do at Dudh Pushkarani unde Kakraban Block / Do |
Special Assistance |
17.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
03.01.2022 |
10.03.2022 |
1722000 |
Sri Ashis Kanti Sarkar. M-9862081435 |
25.03.2022 |
17.03.2022 |
|
24.09.2022 6 Month |
Completed |
100% |
|
Completed (100%) |
|
17.590 |
17.590 |
0.000 |
17.590 |
|
11.09.2022 |
No |
Approximate Value of work after completion: Rs……Lac Handed over 21.03.2023 |
|
|
₹ 17,22,000 |
|
|
|
2 |
k) Do at Atharobhola under Killa Block / Do |
Special Assistance |
17.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
03.01.2023 |
19.02.2022 |
1722000 |
Sri Ranjan Paul. M-9436472587 |
05.03.2022 |
04.03.2022 |
|
04.09.2022 6 Month |
Completed |
100% |
|
Completed (100%) |
|
17.590 |
17.590 |
0.000 |
17.590 |
0.000 |
03.09.2022 |
No |
Approximate Value of work after completion: Rs……Lac Yet to be handed over. |
|
|
₹ 17,22,000 |
|
|
|
3 |
Jirania |
Fourth Circle |
A. Veterinary Sub-Centre Strengthening of Veterinary Health Care Infrustructure through construction of Veterinary Sub-Centre at Vrigubari under Mandwai Block / Construction of building, Shed for Animal, Electrification & Water supply facility. |
Special Assistance |
17.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
|
01-04-2022 |
₹ 17,61,758 |
Sri Subash Acharjee |
05-04-2022 |
09-04-2022 |
|
15-01-2023 |
Completed |
100% |
|
Completed (100%) |
|
93.19 |
17.69 |
6.790 |
0.000 |
0.000 |
12-11-2022 |
|
Approximate Value of work after completion: Rs……Lac Consolidated fund for SL 20,21,22,23,24= (67+27.9 Lac) |
|
₹ 17,68,984 |
₹ 0 |
|
|
|
4 |
a) Do at Purbanoabadi under Mandwai Block / Do |
Special Assistance |
17.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
|
28-02-2022 |
₹ 17,61,758 |
Sri Abhijit Laskar |
03-03-2022 |
02-03-2022 |
|
14-12-2022 |
Completed |
100% |
|
Completed (100%) |
|
|
16.87 |
0.000 |
0.000 |
0.000 |
12-11-2022 |
|
Approximate Value of work after completion: Rs……Lac |
|
₹ 16,87,402 |
₹ 0 |
|
|
|
5 |
b) Do at Bishrambari under Mandwai Block / Do |
Special Assistance |
17.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
|
28-02-2022 |
₹ 17,61,758 |
Sri Subash Acharjee |
03-03-2022 |
05-03-2022 |
Delay due to dispute in selection of worksite. |
14-12-2022 |
Completed |
100% |
|
Completed (100%) |
|
|
17.19 |
0.000 |
0.000 |
0.000 |
21-01-2023 |
|
Approximate Value of work after completion: Rs……Lac |
|
₹ 17,19,262 |
₹ 0 |
|
|
|
6 |
c) Do at Khengrai under Mandwai Block / Do |
Special Assistance |
17.82 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
|
28-02-2022 |
₹ 17,61,758 |
Sri Pradip Saha |
03-03-2022 |
04-04-2022 |
Delay due to dispute in selection of worksite. |
14-12-2022 |
Completed |
Completed |
|
Completed (100%) |
|
|
17.39 |
0.000 |
0.000 |
0.000 |
21-12-2022 |
|
Approximate Value of work after completion: Rs……Lac |
|
₹ 17,38,366 |
₹ 0 |
|
|
|
7 |
d) Do at Santirnagar undre Belbari Block / Do |
Special Assistance |
0.18 |
Memo No.F. 5(672)/ARDD/PLAN/2015/4641-29 Dated 16/9/21 of the Jt Secretary, ARDD |
2021-22 |
|
28/02/2022 |
₹ 17,61,660 |
Rajina Begam , Cont. No. 9402179641 |
15/03/2022 |
15/03/2022 |
|
12-09-2022 |
Completed |
100% |
100% |
Completed (100%) |
Work completed |
|
17.26 |
0.000 |
0.000 |
0.000 |
15-09-2022 |
|
Approximate Value of work after completion: Rs……Lac |
|
₹ 17,26,605 |
₹ 0 |
|
|
|
8 |
Santirbazar |
Third Circle |
FCS & CA |
Construction of 1000 MT capacity godwan including Guard room and boundary wall at Santirbazar under Santirbazar Sub-division. |
PLAN |
252.00 |
NO.F.F.18-(44)-PLAN/DFCS & CA/2012-13/1314-20 dated 29/01/2022 of the Addl. Secretary & Director, Food civil Supplies & Consumer Affairs . |
2021-22 |
PNIeT- No:- 18/EE/PWD(R&B)/STB/2020-21 dated, 10-11-2020 |
02-03-2021 |
₹ 1,37,85,050 |
Subhas Podder |
17-03-2021 |
30-03-2021 |
Conerened deprtment was delayed for handing over the clear site. |
12(Twelve) Months 16-03-2022 |
Work completed and handed over to the concerned Department |
100% |
|
Completed (100%) |
|
202.000 |
202.000 |
0.000 |
202.000 |
0.000 |
03-03-2022 |
|
Approximate Value of work after completion: Rs.137 Lac Handed over on 31-12-2022 |
|
₹ 1,37,85,050 |
₹ 0 |
No.F. 9(3)/EE/PWD/STB/7173-87 |
|
|
9 |
Kumarghat |
First Circle |
Health(DFWPM) |
Construction of 10 bedded PHC including 10 Nos staff Qtrs at Santipur under Unakoti District |
RIDF-XX |
540.00 |
F.19(554)-PLAN/DFWPM/2014 dt.07/03/2015. |
2014-15 |
30-08-2016 |
18-12-2019 |
₹ 3,58,36,000 |
N.K. Dhar 94361 22664 |
03-01-2020 |
05-03-2020 |
Covid-19 & Site dispute. |
02-11-2021 |
Completed |
100% |
… |
Completed (100%) & handed over. |
|
471.200 |
471.200 |
0.000 |
471.200 |
0.000 |
26-03-2023 |
10 (ten) months |
Approximate Value of work after completion: Rs 471.20 Lac completed and handed over on ……….to health department |
|
₹ 4,71,20,000 |
₹ -1,12,84,000 |
|
|
|
10 |
Amarpur |
Third Circle |
Health(NHM) |
Proposed construction of single storied 30(Thirty) bedded Primary Health Centre (PHC) building including 10(ten) Nos. Staff Quarters Kitchen, Morgue, Garage & Generator with Driver Room Building and Boundary wall at Ompi, Amarpur Sub-division, Gomati District, Tripura under NHM during the year 2017-18 |
NHM |
894.00 |
No.F.19(610)-PLAN/DFWPM/2017. Dt.3-7-17. of the Under Secretary to the Govt of Tripura ,Health & Family Welfare Deptt. Rs.8.94 |
2017-18 |
12-07-2017 |
07-04-2018 |
₹ 6,91,70,753 |
Sri Ajit Bhattacharjee,Contact No.9436123912 |
18-07-2018 |
13-03-2019 |
Land dispute, drawing, pedamic Covid-19 |
12-03-2021 |
Completed |
0.00 |
0.00 |
Completed (100%) |
|
550.000 |
550.000 |
0.000 |
550.000 |
344.00 |
07-12-2022 |
|
Approximate Value of work after completion: Rs……Lac |
|
|
₹ 6,91,70,753 |
|
|
|
11 |
Up-Gradation of Karbook Community health Centre (CHC) to 50(Fifty) bedded Sub-Divisional Hospital including 16(Sixteen) Nos. Staff quarters at Karbook under Gomati District, Tripura. |
NHM |
1227.00 |
No.F.(4-93)-PLAN/ DHS /2016 /1437-47/3993(V-III) Dt. 5-9-16.of the Under Secretary to the Govt of Tripura ,Health & Family Welfare Deptt. Rs. 12.27 |
2021-22 |
07-04-2017 |
29-12-2017 |
₹ 8,23,42,451 |
Sri Ajit Bhattacharjee,Contact No.9436123912 |
01-12-2018 |
27-01-2018 |
Land dispute, drawing, pedamic covid-19 |
26-01-2020 |
Completed |
0.00 |
0.00 |
Completed (100%) |
|
600.000 |
600.000 |
0.000 |
600.000 |
223.42 |
22-08-2022 |
|
Approximate Value of work after completion: Rs……Lac |
|
|
₹ 8,23,42,451 |
|
|
|
12 |
Belonia |
Construction of 10 bedded PHC with quarters at Tripura Bazar under Hrishyamukh block, Belonia Sub-Division, South Tripura District. |
NHM |
385.00 |
No.F.5(13)-PLAN/DFWPM/ 2015/RIDF/1724-29 dated, 13.06.2016 |
2016.17 |
07/EE(PWD)/BLN/2016-17 Dt.24.08.2016 |
21.12.2016 |
₹ 3,06,22,000 |
Radh Raman Datta 8119953376 |
05.01.2017 |
04.01.2017 |
Delayed by the agency |
26.10.2018 |
Completed. Rs.277.00 lakh |
100% |
NA |
Completed (100%) |
----- |
449.000 |
435.000 |
14.000 |
435.000 |
|
14.10.2022 |
Yes |
Delay for getting of clear working site due to rubber garden exist in the proposed area and for Type-II & III Approximate Value of work after completion: Rs……Lac quarter delay for land demarcation. |
|
₹ 2,77,00,000 |
₹ 29,22,000 |
No.F.7(20) Pt-I/EE(PWD ) /BLN/DIVN /8069-80 Dt.21.12.2016 |
|
|
13 |
Construction of MCH wing at Belonia Sub-Divisional Hospital, South Tripura |
NHM |
797.00 |
No.F.3(2)-425-PLAN/DHS/2016-17/3650-60 dated, 06.03.2017 |
2016-17 |
09/EE(PWD)/BLN/2017-18 Dt. 18.07.2017 |
16.01.2018 |
₹ 4,79,84,000 |
Ajit Bhattacharjee 9436123912 |
31.01.2018 |
12.12.2018 |
Due to shifting of existing electric transformer within the proposed working area departmentally. |
30.01.2020 |
Civil & I.E works completed accept lift. Rs.479.84 lakh |
100% |
Not yet |
Completed (100%) |
----- |
425.000 |
425.000 |
0.000 |
425.000 |
100.000 |
|
Yes |
Approximate Value of work after completion: Rs……Lac Civil work completed on 15.02.2022 |
|
₹ 4,79,84,000 |
₹ 0 |
No.F.7(20) Pt-I/EE(PWD ) /BLN/DIVN /5710-21 Dt.27.11.2017 |
1) Req for Rs.100.00 Lac placed by the EE, BLN vide letter No.F.5(11)/EE/PWD/R&B/BLN/8115-16 Dt. 07/02/23 to the CE, Bldg. |
|
14 |
Udaipur |
Construction of 10(ten) Nos. (type.I- 04 Nos, Type.II - 4 Nos. & Type.III - 2 Nos,) staff quarter at Maharani PHC. |
NHM |
225.00 |
No.F.19(42)-PLAN/DFWPM/2000(S) dated 19/11/2018 |
2018-19 |
04.09.2020 |
09.06.2021 |
₹ 2,09,80,000 |
Sri Nihar Chandra Debnath. M-9436131064 |
24.06.2021 |
|
|
23.11.2022 18 Month |
Completed |
100% |
|
Completed (100%) |
|
225.000 |
205.000 |
20.000 |
205.000 |
0.000 |
16.12.2022 |
|
Approximate Value of work after completion: Rs……Lac Handed over on 07.02.2021 |
|
|
₹ 2,09,80,000 |
|
|
|
15 |
Santirbazar |
Health (DFWPM) |
Proposed construction of 10 (ten) nos. staff quarters at Kwaifang Primary Health Centre (PHC), Santirbazar, South Tripura District, Tripura. |
IMR-13th F.C |
213.00 |
NO.F.20(80)-BUDGET/DFWPM/2016-17(V-I)/179-82(V-II) DATED, 24-09-2021 of the Deputy Secretary Government of Tripura |
2021-22 |
PNIeT- No:- 20/EE/PWD(R&B)/STB/2013-14 dated, 25-02-2014 |
30-07-2014 |
₹ 1,70,89,222 |
Gathan Datta 9862453230 |
14-08-2014 |
13-08-2014 |
Work started in due time. |
18(Eighteen) Months 13-02-2016 |
Work completed and handed over to the concerned Department |
100% |
Not Required |
Completed (100%) |
|
212.710 |
212.710 |
0.000 |
212.710 |
0.000 |
08-07-2022, Shortage of Fund. |
2336 days, Time extension under process. |
Approximate Value of work after completion: Rs.170 Lac Handed over on 11-11-2022 |
|
₹ 1,70,89,222 |
₹ 0 |
No.F. 9(3)/EE/ PWD/STB/1674-1685 |
|
|
16 |
Health(DHS) |
Capacity Building for Developing Trauma Care Facilities in Government Hospitals in National Highway under 12th Five Year Plan/ SH: Proposed Construction of Single storied Building for Trauma Care Centre (Level-III) in the South District Hospital at Santirbazar, South Tripura |
CASP |
390.00 |
NO.F.3(2-412)-PLAN/DHS/2016/2016/6092-7001 dated 17-07-2017 of the Under Secretary to the Govt. of Tripura. |
2017-18 |
PNIeT- No:- 06/EE/PWD(R&B)/STB/2018-19 dated, 06-06-2018 |
14-06-2019 |
₹ 3,12,01,081 |
Jahar Sur Choudhury 9436133138 |
29-06-2019 |
05-08-2019 |
Delay due to Covid Pandemic |
18(eighteen) Months 28-12-2020 |
Work completed and handed over to the concerned department |
100% |
Not Required |
Completed (100%) |
All ready completed & handed over |
390.000 |
360.320 |
29.680 |
333.597 |
0.000 |
30-10-2022, Due to COVID Pendamic Situtation. |
668 days |
Approximate Value of work after completion: Rs.325 Lac Handed over on 21-12-2022 |
|
₹ 3,25,00,000 |
₹ -12,98,919 |
No.F. 9(3)/EE/PWD/STB/1616-28 |
|
|
17 |
Bishalgarh |
Fourth Circle |
Health(NHM) |
Construction of 10 bedded PHC building including , Kitchen, Morgue and Garage & Generator with Driver room building at existing Kanchanmala PHC |
NHM |
210.00 |
F.19(63)-PLAN(DFWPM)/2000(S)/7575-80 (V1), Dated-19/06/2019 |
2019-20 |
PNIeT No 06/EE-BSLD/PWD(R&B)/2019-20, Dated-09/08/2019. DNIeT-CE(Buildings)/PWD/DNIT/ACE/Project Unit/14/2019-20 |
29-04-2020 |
₹ 2,21,37,982 |
Tapas Dutta (9436469955/ 9612092053) |
14-05-2020 |
|
|
15 Months (13-08-2021) |
Work Completed |
100% |
Nil |
Completed (100%) |
Dec.22 |
210.000 |
210.000 |
0.000 |
181.510 |
0.000 |
01-11-2022. Specially delayed due to COVID 19 |
|
Approximate Value of work after completion: Rs……Lac Handed over on 25/11/2022 |
|
|
₹ 2,21,37,982 |
|
|
|
18 |
Constn of 10 bedded PHC building in/c Kitchen,Morgue,Garrage & Generator with Driver room in place of exsting Dayarampara PHC |
|
210.00 |
No. F. 19(63-PLAN/DFWPM/200(S)/7572-80 (V-I) dt 19/06/2019 |
2019-20 |
02-11-2020 |
12-05-2021 |
₹ 1,82,41,710 |
Sankar Kanti Saha, 9436124030 |
27-05-2021 |
26-06-2021 |
Non availability of clear site. |
15 Months (13-04-24) |
Completed. Value of work done Rs. 217.29 Lac |
100% |
NA |
Completed (100%) |
Dec.22 |
210.000 |
205.360 |
4.640 |
145.000 |
0.000 |
16-09-2022 |
23 days required. Prayer for granting of T.E process and approval is awaited. |
Approximate Value of work after completion: Rs. 217.29 Lac Main Building completed. Due to cost over run Kitchen,Morgue,Garrage & Generator with Driver room construction not taken up. |
|
|
₹ 1,82,41,710 |
|
|
|
19 |
Mohanpur |
Construction of 10 nos staff qtrs at Katlamara PHC. |
NHM |
175.00 |
No.F.19(610)-PLAN/DFWPM/2017/1258-85 Dated.03/07/2017 of the Under Secretary to the Govt. of Tripura. |
2017-18 |
|
12.08.2021 |
₹ 1,52,00,000 |
Satyabrata Roy |
12.08.2021 |
25.08.2021 |
|
11.08.2022 |
Work completed and handed over to hospital authority on 25.11.2022. Total value of work incurred during construction of project is Rs 1,62,46,649.00 |
100% |
N/A |
Completed (100%) |
|
100.00 |
50.000 |
50.000 |
0.000 |
0.000 |
10.08.2022 |
N/A |
Work completed and handed over to hospital authority on 25.11.2022. Total value of work on completion is Rs 1,62,46,649.00 |
|
|
|
|
|
|
20 |
Construction of 10 nos bedded PHC at Katlamara including Kitchen, Morgue & Garrage.. |
NHM |
225.00 |
No.F.19(610)-PLAN/DFWPM/2017/1258-85 Dated.03/07/2017 of the Under Secretary to the Govt. of Tripura. |
2017-18 |
|
12.08.2021 |
₹ 1,58,00,000 |
Satyabrata Roy |
12.08.2021 |
25.08.2021 |
|
11.08.2022 |
Completed |
100% |
N/A |
Completed (100%) |
|
175.000 |
175.000 |
0.000 |
175.000 |
0.000 |
10.08.2022 |
N/A |
Main building completed and handed over to hospital authority on 25.11.2022 except Kitchen,Generator room and Morgue which are already completed and will be handed over to hospital authority on Mar'2023. Total value of work done on completion is Rs. 1,70,17,124.00 |
|
|
|
|
|
|
21 |
LTV |
Fifth Circle |
Health(NHM) |
Construction of 10 beded PHC with 10 (ten) Nos. staff quarters (Type-I-04 Units, Type-II-04 Units and Type-III-02 Units] in the existing Primary Health Centres (PHCs) at 82 Miles PHC, L.T. Valley Sub-Division, Dhalai District, Tripura. |
NHM |
486.00 |
No.F.19(42)-PLAN/DFWPM/2000(S) dated 19/11/2018 |
2018-19 |
06-05-2019. |
02-03-2020 |
₹ 4,36,37,246 |
Sri Sanjib Kr. Prasad 9436543587 |
17-03-2020. |
17-12-2020. |
Delay for handing over of clear site |
16-03-2022. |
Ready to hand over & 466.00 lakh |
100.00% |
Not required |
Completed (100%) |
|
486.000 |
466.000 |
20.000 |
486.000 |
0.000 |
30-03-2023 & delay occurred due to handing over of clear site & Covid. |
No & delay occurred due to Covid. |
Total value of work Rs.486.00 on completion (Civil-460.00 lakh & IE work-26.00 lakh) Ready to hand over |
|
₹ 4,60,00,000 |
₹ -23,62,754 |
|
|
|
22 |
Proposed construction of 12(twelve) Nos. Staff Quarters building at Manu Community Health Centre (CHC), L.T. Valley Sub-division under Dhalai District, Tripura. |
NHM |
295.00 |
No.F.19(226)-PLAN/DFWPM/2000(SUB) /3190-96 Dated.26-09-2018 |
2018-19 |
14-12-2018. |
15-04-2020. |
₹ 2,54,33,889 |
Sri Gour Gobinda Saha 8787367268 |
30-04-2020. |
30-12-2020. |
Delay for handing over of clear site |
29-10-2021 |
Completed & 295.00 lakh |
100.00% |
Not required |
Completed (100%) |
Completed |
295.000 |
295.000 |
0.000 |
295.000 |
0.000 |
15-12-2022 & delay occurred due to handing over of clear site & Covid. |
No & delay occurred due to Covid. |
Total value of work Rs.295.00 on completion (Civil-285.00 lakh & IE work-10.00 lakh) Handed over on 15.12.2022 |
|
₹ 2,95,00,000 |
₹ -40,66,111 |
|
|
|
23 |
Medical College |
Project Unit |
Health(DHS) |
Construction of Ayush Hospital at Paradise chowmuhani (B+G+3) |
NHM |
569.00 |
F.NO.1(267)AYUSH/DHS/2016 dt……of the ……… |
2016 |
|
17-10-2019 |
₹ 3,71,39,000 |
Narayan Chandra Saha Contact No…… |
01-11-2019 |
01-11-2019 |
Due to Covid situation |
540 days Date…. |
Civil/ Internal Electrification works completed.Lifts to be installed by Mechanical. Approx value of work done……………. |
100% |
Lifts to be installed |
Completed and handed over without lift. |
|
569.330 |
469.33 |
100.000 |
569.33 |
0.000 |
Date of Completion: |
|
Approximate Value of work after completion: Rs……Lac Completed and handed over without lift. |
|
|
₹ 3,71,39,000 |
|
|
|
24 |
Sabroom |
Third Circle |
Minority Welfare |
Constn of school Building at Chatakchari H.S School at Rupaichari RD Block,South Tripura under PMJVK |
PMJVK |
250.00 |
No.F.32/MW/PMJVK/2018-19/3369-75 Dt. 03/11/2019 of the Addl. Secretary, Deptt. of welfare of Minorities |
2019-20 |
17-12-2020 |
24-06-2021 |
₹ 2,21,40,462 |
Shri Bishnu Pada Paul (Mob# 6436519065) |
12-07-2021 |
20-07-2021 |
|
365 days 11-07-2022 |
Completed |
100% |
100% |
Completed (100%) |
Completed |
251.000 |
237.500 |
13.500 |
217.500 |
0.000 |
12-05-2022 |
|
|
|
|
₹ 2,21,40,462 |
|
|
|
25 |
Agt Div-V |
Second Circle |
Panchayet |
Construction of Auditorium at Panchayati Raj Training Institute at A. D. Nagar, Agartala, West Tripura / SH. Civil Works, Plumbing Works, Stage Works including Stage Lighting, Internal Electrification, Sound System & HVAC Work. |
SPA |
1154.00 |
Memo No. 2(18-7)-PE/PR/2013/43686-92 dated 30.03.2015. Addl. Sec. Panchayat Dept. Govt. ofTripura. |
2015-16 |
CE/PWD(R&B)/DNIT/SE-II (Project)/29/2015-16 |
22.02.2016 |
9,63,63,688.00 |
Bimalendu Chakraborty / Partha Pratim Saha / Sunil Kr Banik /Somjit Das |
07.03.2016 |
07.03.2016 |
Scope of original Work drawing design Changed as per requisition of user department . |
18 Months /07.09.2017 |
Work completed |
100% |
100% |
Completed (100%) |
Completed |
1153.010 |
1132.210 |
20.800 |
1000.000 |
0.00 |
03.01.2022 |
Time extention required for 1585 days. |
Approximate Value of work after completion: Rs. 1019.13 Lac Work completed But yet to be Taken over by the User Department as intimated.EE Div-V vide his letter No.F.6(355)/EE-V/AGT/PWD/1625-30 Dt.13/06/23 to the Addl. Director, PRT Institute to take over the completed building |
|
############ |
₹ -55,49,455 |
No.F.6(355)/EE-V/AGT/PWD/7815-30 dated 22.02.2016 |
Estimate for additional works amounting to Rs. 54.00 lakh sent to the Director, Panchayats as per their requisition for obtaining necessary A/A & E/S. Sanction yet to be accorded. |
|
26 |
Amarpur |
Third Circle |
School Education |
Proposed construction of Punjiham H.S. School at Karbook, District Gomati, Tripura. |
RIDF-XXV |
742.00 |
No.NB.TRIP/01/56th ISC/PLAN50(XXV)/2019-20 dt24/03/20 (Gap funding . Initial funding from SPA and later on Gap funding by RIDF Rs.495.00 Lac) |
2019-20 |
07-06-2015 |
29-12-2015 |
₹ 4,63,00,000 |
Sri Ashutosh Bandhopadhaya,Contact No.9436527307 |
13-01-2016 |
20-07-2016 |
|
20-07-2018 |
Completed |
|
|
Completed (100%) |
|
395.000 |
395.000 |
0.000 |
395.000 |
68.00 |
|
|
Approximate Value of work after completion: Rs……Lac Completed & handed over to the School Education. |
|
|
₹ 4,63,00,000 |
|
|
|
27 |
Santirbazar |
School Education |
Construction of Baikhora H.S. School at Santirbazar, South Tripura. |
RIDF |
609.00 |
No.NB.TRIP/01/56th ISC/PLAN50(XXV)/2019-20 dt24/03/20 |
2019-20 |
PNIeT- No:- 09/EE/PWD(R&B)/STB/2015-16 dated, 18-09-2015 |
29-04-2016 |
₹ 4,35,22,985 |
Raja Raw Gosh 9436131203 |
04-05-2016 |
04-05-2016 |
Work started in due time. |
24 (Twenty Four) Months 03-05-2018 |
Work completed and handed over to the concerned department. |
100% |
Not Required |
Completed (100%) |
Completed |
533.000 |
453.325 |
79.675 |
353.200 |
0.000 |
23-12-2022, Due to Shortage of fund |
1955 Days, |
Approximate Value of work after completion: Rs.425 Lac Handed over on 23-12-2022 Inagurated on 31-12-2022 |
|
₹ 4,25,00,000 |
₹ 10,22,985 |
No.F. 9(3)/EE/PWD/STB/467-80 |
|
|
28 |
Sonamura |
Fourth Circle |
School Education |
Proposed Construction of Boxanagar H.S. School at Boxanagar, Sonamura, Sepahijala District, Tripura undern SCA (un-tied) during the year 2012-13. |
RIDF |
777.00 |
TIIFB |
|
CE(R&B)/DNIT/SE(Project)/26/2013-14, Dt. 19.07.2013. |
|
|
|
|
14-03-2014 |
|
|
Work completed. Value of work done 597.00 lac on completion 28-01-2023. |
100% |
|
Completed (100%) |
|
|
597.000 |
|
|
|
Date of completion 28-01-2023 |
|
Approximate Value of work after completion: Rs 597.00 Lac Handed over to School Education |
|
₹ 5,97,00,000 |
₹ -5,97,00,000 |
|
|
|
29 |
SC Welfare |
50 seated Girl's Hostel at Sonamura Girl's School |
BJRCY |
290.00 |
No.F.5-1(P-I)/SCW/PLG (Hostel)/BIRCY/2017/11728-51 Dt. 28/10/2022 for Rs. 1,32,50,000/- of the Addl Secretary, Govt. of Tripura |
2022-23 |
DNIT No. ACE/Project Unit/ PWD(Buildings)/DNIT/41/2020-21. Dt………………. |
10-06-2021 |
₹ 2,17,31,252 |
Bishnu Pada Paul 9436519065 |
25-06-2021 |
|
|
25-12-2022 |
Work Completed. Value of work done on completion Rs208.740Lac |
100% |
|
Completed (100%) |
|
290.000 |
208.740 |
81.260 |
208.740 |
|
Date of actual completion |
|
Approximate Value of work after completion: Rs……Lac |
|
|
₹ 2,17,31,252 |
Vide No.F.10(30)/EE/SNM/PWD/3022-37 Dt.10/06/2021. |
1) UC for Rs. 208.74 Lac has been submitted by EE, SNM vide letter No.F.7(53)/EE/SNM/8070-72 Dt. 27/02/23. Will be reflected in next years achievement……..i.e 2023-24 |
|
30 |
Medical College |
Project Unit |
SW & SE |
Const. of creation of barrier free environment under AIC / for 1 no. existing building under Medical College |
Sugamya Bharat |
312.00 |
No.F.2(112)-SW/DC/2010/Vol-III/7992268 dt18/03/22 |
2019-20 |
|
20-03-2021 |
₹ 1,56,72,982 |
M/S Chittaranjan Saha |
04-04-2021 |
24-03-2021 |
|
270 days Date…. |
Work completed and handed over value of work done Rs……. |
100% |
Lift not yet installed |
Completed (100%) |
|
156.730 |
129.510 |
27.220 |
129.510 |
0.000 |
Date of Completion: |
|
Approximate Value of work after completion: Rs……Lac Balance fund is lying for Mechanical works only |
|
|
₹ 1,56,72,982 |
|
|
|
31 |
Udaipur |
Third Circle |
Tribal Welfare |
Constn of 100 [one hundred] seated ST Girl's Hostel[G+2 storied]Building attached to Udaipur Girl's H.S.School under Udaipur Sub-Division. |
|
182.00 |
F. No.15-53/TW/SP/2018-19/17460-474 dt. 24.09.2019. Amount 200.00 Lakh |
2019-20 |
01.12.2020 |
20.05.2021 |
₹ 1,81,75,000 |
M/s N.G.Bhattacharjee. M-9436123651. |
05.06.2021 |
14.07.2021 |
Pile work could not be continued due torainey season. It is also to mention here that it is a low land. |
04.09.2022 15 Month |
Completed & handed over |
100% |
|
Completed (100%) |
|
200.000 |
200.000 |
0.000 |
200.000 |
0.000 |
31.12.2022 |
Yes |
Approximate Value of work after completion: Rs……Lac Handed over on 03.02.2023 |
|
|
₹ 1,81,75,000 |
|
Completed and handed over in Feb 2023. (1st phase , part of ground & 1st floor) UC submitted for Rs. 200.00 Lac on 18/03/2023. Fund available for 2nd Phase Rs.2.00 Crore with the Client department. Estimate amounting to Rs. 405.00 Lac submitted to T.W Deptt vide letter No.F.3(568)/PC (PD-II)/2012 ( S)/974-77 dated 17/05/23 accord of A/A & E/S. |
|
32 |
Santirbazar |
Construction of sport complex for Ekalavya Residential (EMR) School At B.C Manu/ Play ground |
PLAN |
106.00 |
A/A: No.F. 25-18/TW/REIS/2018/3395-3405 Dt. 26-07-2019 of the Member Secretary Tripura Tribal Welfare Residential Educational Institutions Society. Rs. 1.06 Crore E/S No.F.25-18/TW/REIS/2018/177-87 dated, 04-04-2019 of the Member Secretary Tripura Tribal Welfare Residential Educational Institutions Society |
2018-19 |
PNIeT- No:- 19/EE/PWD(R&B)/STB/2019-20 dated, 17-10-2019 |
06-01-2020. |
₹ 60,60,145 |
Biswajit Majumder 9862406055 |
21-01-2020 |
30-01-2020 |
Clear site was not available |
5(Five) Months 20-06-2020 |
Work Completed. Value of work done= Rs. 106 Lkah |
Not required |
Not Required |
Completed (100%) |
Completed |
86.030 |
83.500 |
2.530 |
83.500 |
20.470 |
31-03-2021 Due to Site Disput & COVID Pendamic Situtation |
281 days, |
Approximate Value of work after completion: Rs. 106Lac handed over on….. |
|
₹ 1,06,00,000 |
₹ -45,39,855 |
No.F. 9(3)/EE/PWD/STB/7332-45 |
|
|
33 |
Udaipur |
UDD |
Setting up of Tertiary waste Processing center at Chandrapur Colony(near Central FCI Godown) under Udaipur Municipal Council. |
15th FC |
145.00 |
No.F2(26)/ Accounts/UMC/UDP/2021-22/7356-61, dated 12.03.2020 |
2020-21 |
21.12.2020 |
04.02.2021 |
₹ 1,47,87,000 |
Sri Biswajit Majumder. M-9862406055 |
19.02.2021 |
|
|
18.08.2021 6 Month |
completed |
100% |
|
Completed (100%) |
|
135.350 |
112.850 |
22.500 |
112.850 |
0.000 |
31.12.2022 |
|
Approximate Value of work after completion: Rs……Lac |
|
|
₹ 1,47,87,000 |
|
|
|
34 |
Mohanpur |
Fourth Circle |
Law |
Constn of Tripura Judicial Academy at Narsingarh |
Special assistance |
2400.00 |
A/A & E/S received vide memo No.F. 1(10)/PCD/PF/FIN/2021/194-216 Dated 29/12/21 of the Secretary, Planning (P&C) Department. |
2021-22 |
|
17.02.2020 |
₹ 18,93,00,000 |
Tapesh Ch Debnath |
03.02.2020 |
05-08-2020 |
Clear site was not available |
16.02.2022 |
Civil Work Completed |
70% |
80% |
83% |
June' 2023 |
2400.000 |
2400.000 |
0.000 |
2400.000 |
0.000 |
|
|
Revised estimate amounting to Rs. 32,99,64,355/- has been submitted to the Director, Tripura Judicial Academy by the SE, PWD, PU vide No. 10(3)/ACE/Project Unit/2022/7196-7200 dt. 27/3/23 for accord of revised A/A & E/S. Revision required due to execution of extra and additional works as per requisition of the client department. |
|
|
₹ 18,93,00,000 |
|
1) EE, Mech invited tender for installation of 2 nos Lift for Hostel building. Amt Rs.30.92 , PNIeT No. 118/EE/Mech/DIVN/AGT/2022-23 Dt. 14/3/23. Since the building is functioning therefore, shown in completed list of work during 2022-23 |
In progress |
35 |
Agt Div-V |
Second Circle |
Science & Technology |
Science City at Agartala (Phase -I) |
NLCPR |
2745.40 (On dated 25.03.2015) and revised A/A & E/S for Rs. 2968.10 (on dated 22.07.2021) |
Memo No. F.No.16(8)/TSCST/Vol-I /1029-34 dated 22.107.2021 Joint Member Secretary , Deirector , Science & Technology |
2012-13 |
PNIT No. 30/B/EE-V/AGT/PWD/2012-13 dated 24.01.2013 |
22.07.2013 |
25,19,58,517.00 |
Reacon Engineers(Ind) Pvt Ltd |
06.08.2013 |
09.01.2014 |
Due to change of Design Drawing , structural work , COVID 19 effects and Progress delayed from the Agency. |
730 days/ 07.8.2015 |
Finishing work in progress. |
75% |
75% |
95.50% |
Oct 23 |
3038.6 |
2997.60 |
41.00 |
2661.80 |
656.00 (for Additional works) |
|
Yes |
i) Main Building handed over to the User Department . ii) Tentative Deviation amounting to Rs. 2959.89 (Tentative executed value) processed to the Higher authority for approval in the month of January, 2023. iii) Revised estimate/ revised santion is required for taking up additional work. |
|
₹ 29,97,60,000 |
735.65 (Additional works) |
F.6(346)/EE-V/AGT/PWD/1093-1111 datd 22.07.2013 |
Additional works for an amount of 735.65 lakh beyond the original sanctioned amount is to be taken up with separate A/A & E/S. |
In progress |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|