INDUSTRIES
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Dharmanagar |
Structural Strengthening and repairing of administrative cum academic building of ITI, Dharmanagar, North Tripura. |
Industries |
147.00 |
147.00 |
143.69 |
14-11-2018 |
16.12 |
0.00 |
130.90 |
Nil |
20% |
Work suspended due to fund. |
|
|
|
TOTAL |
|
147.00 |
|
|
|
16.12 |
0.00 |
130.90 |
0.00 |
|
CIVIL ADMINISTRATION DEPARTMENT
CIVIL ADMINISTRATION DEPARTMENT
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Khowai |
Construction of District Administration Complex, Khowai District, Tripura under NLCPR Scheme / SH: Building portion including Internal water supply, Sanitary Installation and Internal Electrification works. ( DM office + SP office) |
NLCPR |
2060.00 |
2060.00 |
1508.00 |
12-09-2018 |
749.71 |
749.71 |
1310.29 |
0.00 |
Main building completed and other component to be executed. |
May.21 |
2 |
Bishramganj |
Construction of District Administration Complex, Sepahijala District, Tripura under NLCPR Scheme / SH: Building portion including Internal water supply, Sanitary Installation and Internal Electrification works. |
NLCPR |
2160.00 |
2160.00 |
1522.05 |
05-07-2018 |
763.41 |
763.41 |
800.00 |
596.59 |
90% |
May.21 |
|
|
|
TOTAL |
|
4220.00 |
|
|
|
1513.12 |
1513.12 |
2110.29 |
596.59 |
|
KRISHI VIGYAN
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund Released |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Dharmanagar |
Construction of double storied Administrative Building for Krishi Vigyan Kendra, Tripura/ KVK North District, Panisagar. |
KVK |
168.07 |
168.07 |
116.60 |
05-09-2019 |
50.00 |
50.00 |
118.07 |
0.00 |
50% |
Apl.21 |
2 |
Kailashahar |
Proposed construction of Double storied Administrative Building for Krishi Vigyan Kendra at Kailashahar,Unakoti, Tripura/SH Building portion including internal water supply and sanitary installation |
Deposit work |
150.00 |
150.00 |
137.07 |
17-09-2019 |
50.00 |
34.94 |
100.00 |
0.00 |
50% |
Apl.21 |
3 |
Udaipur |
Proposed construction of double storied Administrative Building for Krishi Vigyan Kendra, Gomati District, Tripura/ SH:- Building construction including internal water supply & sanitary installation. |
Agriculture /ICAR |
150.00 |
150.00 |
149.87 |
21-09-2019 |
100.00 |
0.00 |
50.00 |
0.00 |
60% |
Apl.21 |
4 |
Kamalpur |
Proposed construction of Double Storied Administrating Building for Krishi Bigyan Kendra, Salema, Dhalai Tripura / SH: - Building construction in/c water supply & sanitary installation. |
P.F.M.S |
168.07 |
168.07 |
149.44 |
20-03-2019 |
100.00 |
50.00 |
68.00 |
0.00 |
80% |
Apl.21 |
|
|
TOTAL |
|
636.14 |
|
|
|
300.00 |
134.94 |
336.07 |
0.00 |
|
|
Animal Resource Development Department (ARDD)
Animal Resource Development Department (ARDD)
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Jirania |
College of Science and Animal Husbandary at R.K.Nagar West Tripura/ SH:- Constn. of internal road (L-2.850 km). |
State Plan |
501.00 (in/c. vertical extension of Academic building vide Sl no.2 of upcoming project statement. |
501.00 |
52.25 |
31/06/18 |
Nil |
Nil |
52.25 |
52.25 |
90% |
Jun.21 |
2 |
Jirania |
Consnt of perimetre Boundary wall of veterinery college including gate and guard room of R.K.Nagar |
State Plan |
74.41 |
02-02-2018 |
Nil |
Nil |
74.41 |
74.41 |
65% |
Jun.21 |
|
|
|
TOTAL |
|
585.01 |
|
|
|
0.00 |
0.00 |
126.66 |
126.66 |
|
HIGHER EDUCATION DEPARTMEN
HIGHER EDUCATION DEPARTMEN
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Kailashahar |
Proposed constrcution of Science Building (G+2) at Kailashahar College, Unakoti District, Tripura/Ground floor only under Phase-I. |
SPA |
1500.00 |
1500.00 |
1054.90 |
29-12-16 |
281.07 |
281.07 |
873.00 |
0.00 |
90% |
Jan.22 |
2 |
Kanchanpur |
Proposed construction of Model Degree College at GDC, Kanchanpur, North Tripura under CASP-RUSA / SH: i] Vertical Extension of Administrative Building (1st Floor) and ii] Construction of Laboratory Block (Ground Floor). |
CASP-RUSA |
300.00 |
300.00 |
200.02 |
02-07-2019. |
275.00 |
150.00 |
25.00 |
0.00 |
92% |
Nov.21 |
3 |
Khowai |
Up-gradation of Dasarath Deb Memorial (DDM) College at Khowai, Tripura / Vertical extension of Administrative building (1st & 2nd floor) and Academic building (2nd floor) under SPA(tied) during the year 2015-16 (Phase-II). |
SPA tied |
500.00 |
500.00 |
327.57 |
12-08-2016 |
200.00 |
169.95 |
206.72 |
0.00 |
90% |
Jan.22 |
4 |
Agt.Div. No.III |
Construction of english medium at old central jail premises, Agartala Tripura /academic building administrative building & library building/SH:- building portion including internal water supply sanitary instalation and concealed conduiting for internal electirification works. |
SPA |
5171.00 |
5171.00 |
2887.30 |
07-03-2016 |
1269.93 |
1269.93 |
400.00 |
|
80% |
The said project has been droped. |
5 |
Agt. Div. No.I |
Special repairs retrofitting and restrotation of MBB College, Agartala tripura(w). |
CASP-SCA |
824.00 |
824.00 |
704.00 |
20-12-2016 |
200.00 |
200.00 |
624.00 |
NIL |
75% |
Nov.21 |
6 |
Agt.Div. No.III |
Construction of Cafeteria cum Boys Common room cum computer centre in MBB College, Agartala / Phase- I/ Construction of canteen of college. |
RUSA |
62.88 |
62.88 |
57.00 |
July, 2018 |
62.88 |
62.88 |
|
|
90% |
Feb.21 |
7 |
Agt. Div. No.I |
Proposed Construction of Annexe Block of Birchandra State Central Library at Agartala, West Tripura/ Phase-I: Western Block. |
SPA/NLCPR |
974.52 |
974.52 |
706.88 |
19-03-2014 |
569.98 |
488.42 |
253.30 |
0.00 |
One part of Phase-I completed |
One part of Phase-I completed and handed over. Phase-II =Balance site not handed over by HED. |
8 |
Agt. Div. No.III |
Development of Infrastructure of MBB College, Agartala, West Tripura. Auditorium of M.B.B. College. |
TFC |
900.00 |
900.00 |
814.00 |
11-07-2012 |
513.00 |
513.00 |
200.00 |
200.00 |
60% |
Rescined / further action required |
9 |
Agt. Div. No.V |
Construction of 1000 seated Auditorium for Ramthakur College , Agartala , West Tripura . |
SPA/NLCPR |
445.20 |
445.20 |
445.19 |
24.03.2012 |
0.00 |
0.00 |
753.81 |
Nil |
85% |
No fund available now |
10 |
Agartala Div. No.V |
Proposed construction of Academic Building (Double storied) in the premises of Women's Polytechnic at Hapania, Amtali, Agartala, West Tripura / SH: Building portion including Internal water supply, Sanitary Installation, Sewage & Drainage works(2nd Call). Sri Jasoda Lal Roy |
SDS |
200.00 |
200.00 |
366.96 |
25.01.2018 |
170.00 |
100.00 |
130.00 |
Nil |
60% |
Nov.21 |
11 |
Santirbazar |
Const. Of Administrative Building (1st Floor) by vertical extension of ground floor to 1st floor in GDC Santirbazar |
CASP-RUSA |
140.00 |
140.00 |
121.00 |
22-09-2019 |
0.00 |
0.00 |
70.00 |
0.00 |
80% |
Mar.21 |
12 |
L.T. Valley |
Construction of Model Degree College at GDC L.T. Valley under RUSA / Vertical extension of Abministrative building 1st floor and Laboratory block etc. |
RUSA |
300.00 |
300.00 |
200.00 |
23-02-2019. |
246.00 |
150.00 |
54.00 |
0.00 |
95% |
May.21 |
13 |
Kamalpur |
Construction of Kamalpur Govt. Degree College at Kamalpur, Dhalai Tripura / SH: Vertical extension of 1st floor of Academic Block during the year 2016-17 (Phase-II). |
SDS |
234.12 |
234.12 |
186.94 |
26-10-2017 |
6.50 |
6.50 |
210.30 |
0.00 |
30% |
Jan.22 |
|
|
|
TOTAL |
|
11551.72 |
|
|
|
3519.36 |
3391.75 |
3800.13 |
200.00 |
|
Fire Service Department
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Ambassa |
Construction of Ambassa Fire Service Station, Dhalai, Tripura. |
State Plan |
134.84 |
134.84 |
122.37 |
19-09-15 |
121.41 |
94.88 |
0.00 |
0.00 |
80% |
Agency expired. Tender to be invited for balance work shortly. |
|
|
|
TOTAL |
|
134.84 |
|
|
|
|
94.88 |
0.00 |
0.00 |
|
Food & Consumer Affairs Department
Food & Consumer Affairs Department
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Udaipur |
Construction of 1000 MT capacity godwan including ancillaries, compound wall and Devolopment of site at Chandrapur Udaipur Sub-Division, Gomati District Tripura. |
Food |
225.00 |
225.00 |
95.68 |
26.11.2017 |
84.65 |
35.54 |
0.00 |
0.00 |
70% |
21-Jul |
2 |
Jirania |
Construction of 500 MT capacity Food Godown in/c ancillaries, compound wall and development at site Mandwi, West Tripura. |
State Plan |
144.63 |
144.63 |
149.64 |
24-01-17 |
144.40 |
144.40 |
32.00 |
0.00 |
100% |
Completed |
3 |
Santirbazar |
Construction of 1000 MT capacity Food Godown including Guard room and boundary wall at Santirbazar, South Tripura. |
State Plan |
252.00 |
252.00 |
0.00 |
0.00 |
202.00 |
0.00 |
0.00 |
0.00 |
0% |
Tender accepted |
4 |
Ambassa |
Construction of 500 MT capacity godown including guard room and boundary wall at Ganganagar, Jawharnagar Sub-division, Dhalai District, Tripura. |
CASP |
143.00 |
143.00 |
119.66 |
21/08/2020 |
143.00 |
0.00 |
0.00 |
0.00 |
70% |
Oct.21 |
5 |
Jirania |
Construction of 500 MT capacity Food Godown in/c ancillaries, compound wall and development at Belbari under Belbari Block, West Tripura. |
State Plan |
109.85 |
143.00 |
111.69 |
31-01-2020 |
143.00 |
22.46 |
0.00 |
0.00 |
65% |
Apl.21 |
|
|
|
TOTAL |
|
874.48 |
|
|
|
717.05 |
202.40 |
32.00 |
0.00 |
|
Handloom Department
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Agartala Div. no.III |
Proposed construction of Godown, Office & Dormitory (Second Phase Development) at THHDC Complex, Purbasha, Agartala, West Tripura. |
State Plan |
880.00 |
880.00 |
579.32 |
29-12-2016 |
270.00 |
270.00 |
420.00 |
0.00 |
65% |
Jan.22 |
|
|
|
TOTAL |
|
880.00 |
|
|
|
270.00 |
270.00 |
420.00 |
0.00 |
|
Health Department
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Kumarghat |
Up-Gradation Kumarghat CHC to 50 (fifty) bedded Sub-Divisional Hospital including Staff Qtr's. |
RIDF-XXI |
2047.04 |
2047.04 |
1630.20 |
14th Feb-2017 |
855.98 |
855.98 |
1191.06 |
Nil |
80% |
July.21 |
2 |
Dharmanagar |
Upgradation of infrastructure facilities of Dharmanagar District Hospital during the year 2016-17/SH: Construction of boundary wall alongwith the periphery of Hospital compus including Gate, Retaining wall, Grill etc. |
Health |
240.96 |
240.96 |
212.21 |
22-08-2018 |
Nil |
Nil |
240.96 |
|
48% |
Jun.21 |
3 |
Dharmanagar |
Construction of single storied building for Trauma Care Centre (Level-III) in the North District Hospital at Dharmanagar, North Tripura. |
Health |
390.00 |
390.00 |
353.07 |
26-10-2018 |
90.00 |
90.00 |
100.00 |
200.00 |
35% |
Jan.22 |
4 |
Kailashahar |
Construction of North District Hospital ( Now Unakoti District Hospital at Bhagabannagar, Kailashahar, Unakoti District ), Phase-II (Hospital Quarters) in Tripura under NLCPR Scheme /Sh Constn of 48 Nos staff qtr |
NLCPR |
1110.05 |
1110.05 |
904.45 |
21-3-18 |
436.60 |
436.60 |
673.45 |
0.00 |
85% |
Sep.21 |
5 |
Kanchanpur |
Construction of 16 No. quarters (Type-IV = 4 Nos., Type-III = 4 Nos., Type - II = 4 Nos. and Type - I = 4 Nos.) for Sub-Divisional Hospital at Kanchanpur. |
Health |
584.68 |
584.68 |
349.76 |
9-Jun-17 |
NIL |
Nil. |
150.00 |
256.00 |
Demolition of old structure completed. Site clearance done. Presently Work is Suspended. |
Nov.22 |
6 |
Udaipur |
Capacity Building for Developing Trauma Care Facilities in Government Hospitals in National Highway under 12th Five Year Plan/ SH: Proposed Construction of Single storied Building for Trauma Care Centre (Level-III) in the Gomati District Hospital at Tepania, Gomati District, Tripura |
CSS |
390.00 |
390.00 |
284.61 |
04.01.2018 |
90.00 |
90.00 |
271.00 |
0.00 |
45% |
Jul.21 |
7 |
Amarpur |
Proposed construction of 16(Sixteen)Nos. Staff Quarters building for the Amarpur Sub-Divisional Hospital at Amarpur, Gomati District, Tripura/ Construction of (i) Type-II quarter - 04 units (one block - twin ( G+1) Storied, (ii) Type-II quarter - 04 units [ one block - twin ( G+1) Storied], (iii) Type-III Staff quarters - 04 units [one block - twin ( G+1) Storied], (iv) Type-II quarter - 04 units {one block - twin ( G+1) Storied] under Infant Mortality grant. |
Health /IMR/RIDF-XXV |
406.00 |
406.00 |
310.60 |
26-06-2017 |
0.00 |
0.00 |
100.00 |
260.00 |
35% |
Mar.22 |
8 |
Santirbazar |
Const. Of patient waiting shed, Toilet Block, Cycle Stand etc. at District Hospital, Santirbazar, South Tripura |
Health |
50.00 |
50.00 |
46.55 |
15-02-2020 |
0.00 |
0.00 |
50.00 |
0.00 |
50% |
Oct.21 |
9 |
Santirbazar |
Special repairs to Santirbazar District Hospital at Santirbazar, South Tripura during the year 2016-17 / Replacement of existing grading outside & inside painting etc. |
Non- Plan |
41.70 |
41.70 |
45.55 |
01-09-2018 |
0.00 |
0.00 |
45.55 |
0.00 |
40% |
Oct.21 |
10 |
Santirbazar |
Construction of 24 nos. staff quarters for 100 bedded District Hospital at Santirbazar [ Type-I = 06 nos., Type-II = 06 nos., Type-III = 06 nos. & Type-IV = 06 nos. ] |
CASP |
583.00 |
583.00 |
468.20 |
10-06-2018 |
0.00 |
0.00 |
300.00 |
200.00 |
20% |
Jul.21 |
11 |
Santirbazar |
Capacity Building for Developing Trauma Care Facilities in Government Hospitals in National Highway under 12th Five Year Plan/ SH: Proposed Construction of Single storied Building for Trauma Care Centre (Level-III) in the South District Hospital at Santirbazar, South Tripura |
CASP |
390.00 |
390.00 |
312.00 |
29-06-2019 |
90.00 |
90.00 |
300.00 |
0.00 |
50% |
Mar.22 |
12 |
Sabroom |
Constn. of 100 bedded Sub-Divisional Hospital at Sabroom South Tripura Dist. Under RIDF-XX-2014-15 / Constn. Of i) Hospital building (G+2) ii) SDMO Office (G+1) iii) Blood bank iv) Isolation ward v) Kitchen Vi) Morgue Vii) Boundary wall (1000 mtr.) / Building portion in/c internal water supply & sanitary installation. |
RIDF-XX |
2750.33 |
2750.33 |
1341.04 |
30-03-2017 |
1009.20 |
742.59 |
600.00 |
0.00 |
95% |
May.21 |
13 |
Sabroom |
Construction of 2 (two) nos Dormitory building alongwith mtc. Of the existing Type - III qtrs. 2 (two) nos, 4 (four) units at Sabroom Sub Divisional Hospital complex / SH : Construction of i) Male ward ii) Female ward & iii) mtc. Of Type - III qtrs. |
MW (Non-Plan) |
51.68 |
51.68 |
51.27 |
07-10-2018 |
0.00 |
0.00 |
51.68 |
0.00 |
60% |
May.21 |
14 |
Sonamura |
Up- Gradation of Melaghar Sub- Divisional Hospital as First Referral Units (FRU) / Construction of new OPD Complex and 10 (ten) Bedded Eye Ward with Eye OT building (G+1 storied) at Melaghar, Sonamura Sub-Division, Sepahijala District, Tripura under SPA (CASP) during the year 2016-17 |
Health |
615.00 |
615.00 |
392.54 |
16-08-2017 |
0.00 |
0.00 |
432.59 |
65.00 |
Structural work completed. |
Jul.21 suspended due to fund |
15 |
Ambassa |
Proposed construction of Dhalai District Hospital, Phase-II (Hospital Quarters ) at Kulai, Ambassa, Tripura under NLCPR Scheme / SH:- Construction of 36 (Thirty six Nos. Staff quarters (i) Type- I- quarter – 12 Units [ 02(two) Blocks- Double storied (GF + Part of FF) ], (ii) Type- II- quarter – 12 Units [ 02(two) Blocks- Double storied (GF + Part of FF) ], (iii) Type- III- quarter – 6 Units [ 01 (One) Blocks- Double storied (GF + Part of FF) ], and (iv) Type- IV- quarter – 6 Units [ 01 (One) Blocks- Double storied (GF + Part of FF) ]. |
NLCPR |
648.58 |
648.58 |
713.37 |
02/01/21 |
|
|
|
|
Work started |
Mar.21 |
16 |
Ambassa |
Proposed construction of Dhalai District Hospital, Phase-II (Hospital Quarters ) at CMO Complex Ambassa and PHC Complex under NLCPR Scheme / SH:- Construction of 12 (Twelve) Nos. staff quarters (i) Type- III- quarter – 6 Units [ 01 (One) Blocks- Double storied (GF + Part of FF) ] and (ii) Type- IV- quarter -6 Units [ 01 (One) Blocks- Double storied (GF + Part of FF) ] |
NLCPR |
274.31 |
274.31 |
303.93 |
02/01/21 |
|
|
|
|
Work started |
Mar.22 |
17 |
L.T. Valley |
Proposed Expansion of Longtharai Valley (LTV) Sub-Divisional Hospital Building [ Ground Floor + Part of First Floor ] by 20 (twenty) beds at Chailengta under Dhalai District, Tripura under Special Central Assistance to Tribal Sub-Plan (SCA to TSP) |
CASP |
808.00 |
808.00 |
698.62 |
28-09-2019. |
399.00 |
150.00 |
0.00 |
409.00 |
20% |
Feb.22 |
18 |
Medical College |
Construction of Linac block in cancer Hospital Premises, Agartala |
CASP(SPA) |
1275.00 |
1275.00 |
1210.00 |
Oct-17 |
1195.75 |
1195.79 |
0.00 |
236.05 |
99% |
Jun.21 |
|
|
|
TOTAL |
|
12656.33 |
|
|
|
4166.53 |
3650.96 |
4506.29 |
1626.05 |
|
Home Department (Police)
Published: April 11, 2021
Sl. No. |
Department |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund Released |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Santirbazar |
Construction of 9th BN TSR HQ at Hichacherra, Santirbazar, South Tripura. |
TFC |
1500.00 |
1500.00 |
1793.26 |
06-12-2007 |
1835.67 |
1835.67 |
75.27 |
0.00 |
90% |
May.21 |
2 |
Mohanpur |
Proposed extension of Forensic Science Laborotory at Narsingarh |
SDS |
229.95 |
229.95 |
145.30 |
28.03.2018 |
130.00 |
90.90 |
35.30 |
80.40 |
Agreement closed due to expire of agency. Tender to be invited for balance work. |
|
3 |
L.T. Valley |
Construction of 8th BN TSR H.Q. at Lalcherra, L.T. Valley, Manu, Dhalai / SH: (i) Construction Of Administrative Building, (ii) 100 Men Barrack [02 nos], (iii) Quarter Guard, (iv) Wireless Station, (v) Officer's Mess, (vi) SO's Mess, (vii) Store Building (viii) MT Office (ix) Magazine Store Building (x) MT Garrage (xi) Watch Tower and (Xii) Boundary Wall. |
TFC |
1500.00 |
1500.00 |
1500.00 |
09-02-2009. |
1473.30 |
1362.42 |
426.70 |
0.00 |
1. Wireless Station, 2. Officer's mess, 3. Store Building & 4. Watch tower work not started |
Jun.21 |
|
|
|
TOTAL |
|
3229.95 |
|
|
|
3438.97 |
3288.99 |
537.27 |
80.40 |
|
Information Cultural Affairs Department
Information Cultural Affairs Department
Published: April 11, 2021
(In Lakhs) |
SL. No. |
Division |
Name of Works |
Sanction Cost |
Scheme |
Year of Sanctioned |
Total Fund Released |
Target date of Completion |
Status of Physical implementation/Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
UNOKOTI DISTRICT |
1 |
Kumarghat Division |
Proposed 1000 seated capacity Town hall at Kumarghat, Unakoti District. |
1180.00 |
-- |
2015-16 |
100 |
December, 2017. |
Work upto plinth level.. |
KHOWAI DISTRICT |
2 |
Khowai Division |
Cultural complex at Khowai Town, West Tripura. |
630.00 |
SPA |
2010-11 |
700 |
Completed |
Work completed and ready for handed over. |
WEST DISTRICT |
3 |
Agartala Division No 1. |
Development of Rabindra Parishar at Children’s Park, Agartala, Tripura.(Open Air Stage) |
200.00 |
I.C.A Deptt. |
2013-14 |
100 |
Sep 2017 |
Work upto lintel level in progress..
|
4 |
Development of Children Park. |
--- |
I.C.A Deptt. |
------ |
---- |
Completed |
Completed. |
5 |
Repair and Renovation of Nazrul Kalakshetra, Agartala. |
154.00 |
I.C.A Deptt. |
2016-17 |
--- |
---- |
Work upto 20% completed. |
6 |
Agartala Division No-III, Agartala |
Renovation of Town Hall at Agartala/ SH.Modification of Green Room, Ceiling, Acoustic works on wall & Ceiling, Flooring, Internal lighting, Audio system and Fire fighting etc.. |
574.00 |
SPA, Tied |
2014-15 |
210.36 |
15-02-2017
|
80% work completed. Work in progress.. |
Health & Family Welfare
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Kumarghat |
Construction of 10 bedded PHC including 10 Nos staff Qtrs at Santirpur under Unakoti District |
RIDF-XX |
540.00 |
540.00 |
358.36 |
18-12-2019 |
237.00 |
237.00 |
150.00 |
0.00 |
65% |
Mar.22 |
2 |
Dharmanagar |
Proposed construction of Office Building (G+ storied) for for Chief Medical Officer (CMO) at Dharmanagar, North Tripura. |
IMR |
438.40 |
438.40 |
253.81 |
05-06-2018 |
150.00 |
0.00 |
0.00 |
0.00 |
|
Site problem. Procesed for cancellation of agreement |
3 |
Dharmanagar |
Construction of double storied District Ware House of Dharmanagar, North Tripura. |
HFWD |
250.10 |
250.10 |
118.78 |
|
250.00 |
0.00 |
0.00 |
0.00 |
|
Site problem. Procesed for cancellation of agreement |
4 |
Dharmanagar |
Construction of Type -V Qtr. for Chief Medical Officer at North Tripura District |
HFWD |
46.10 |
46.10 |
42.07 |
|
46.10 |
|
|
|
|
Site not available |
5 |
Kailashahar |
Construction of New 10 nos. staff quarters (Type-I-4, Type-II-4 & Type-III-2) at Irani under Gournagar block, Kailashahar Sub-Division, Unakoti District, Tripura. |
IMR - 13th FC |
225.00 |
225.00 |
173.53 |
23-3-16 |
201.71 |
186.71 |
10.00 |
0.00 |
95% |
Jun.21 |
6 |
Kailashahar |
Proposed construction of District Training Centre at Kailashahar, Unakoti District, Tripura. |
IMR |
597.40 |
597.40 |
361.61 |
11.11.16 |
130.40 |
130.40 |
369.60 |
0.00 |
75% |
Nov.21 |
7 |
Kanchanpur |
Construction of boundary wall at Dasda P.H.C. Tripura North, during the year 2014-2015/SH:-Boundary wall, gates, C.D., drains and approach road. |
DFWPM |
72.07 |
72.07 |
73.42 |
16-07-2016 |
NIL. |
Nil. |
73.42 |
|
Boundary wall 90% completed. |
Mar.21 |
8 |
Udaipur |
Construction of 10 bedded Primary Health Centre (PHC) including 10(ten) Nos. Staff Quarters at Nityabazar under Killa Block, Gomati District, Tripura. |
RIDF-XX |
540.00 |
540.00 |
404.90 |
23.09.2015 |
300.80 |
267.80 |
156.67 |
0.00 |
52% |
Oct.21 |
9 |
Udaipur |
Proposed construction of 10 (ten) nos. staff quarters at Tulamura Primary Health Centre (PHC) under Kakraban Block, Udaipur Sub-Division, Gomati District, Tripura. |
IMR-13th FC |
225.00 |
225.00 |
209.64 |
31.07.2017 |
50.00 |
0.00 |
0.00 |
0.00 |
- |
Tender is in progress |
10 |
Udaipur |
Construction of Adipur PHC |
IMR-13th Finance |
385.00 |
385.00 |
324.35 |
26.08.2016 |
385.00 |
89.52 |
295.50 |
|
95% |
Mar.21 |
11 |
Udaipur |
Up-gradation of Kakraban PHC to CHC SH: Building portion including Internal water supply, Sanitary Installation, Sewage & Drainage works ( Phase-I ). |
IMR-13th Finance |
420.00 |
420.00 |
352.46 |
03.03.2017 |
300.00 |
209.44 |
213.46 |
0.00 |
90% |
Mar.21 |
12 |
Santirbazar |
Construciton of boundary wall of Kowaifung P.H.C. under Santirbazar Sub-Division during the year 2016-17. |
Plan |
68.51 |
68.51 |
57.83 |
15-09-2017 |
18.70 |
0.00 |
28.83 |
0.00 |
50% |
Mar.21 |
13 |
Santirbazar |
Construction of boundary wall of Ramraibari P.H.C. under Santirbazar Sub-Division during the year 2017-18. |
Plan |
68.31 |
68.31 |
57.66 |
25-10-2017 |
29.00 |
0.00 |
28.66 |
0.00 |
50% |
Mar.21 |
14 |
Santirbazar |
Proposed construction of 10 (ten) nos. staff quarters [ Type -I quarter - 04 units (one block - twin double storey ), Type-II quarter - 04 units (one block - twin double storey ) and Type-III quarter - 02 units (one block - twin single storey ) ] at Kwaifang Primary Health Centre (PHC), Santirbazar, South Tripura District, Tripura. |
SPA |
213.74 |
213.74 |
170.89 |
10-08-2014 |
176.90 |
176.90 |
36.84 |
0.00 |
80% |
Apl.21 |
15 |
Santirbazar |
Proposed Construction of 20 (twenty) bedded Primary Health Centre (PHC) building [ double storied ] including Kitchen, Morgue and Garage & Generator with Driver room building at existing Muhuripur PHC Complex under Jolaibari Block, Santirbazar, South Tripura. |
IMR - 13th FC |
416.00 |
416.00 |
352.95 |
16-11-2017 |
59.92 |
59.92 |
293.00 |
47.00 |
50% |
Agency expired. Balance work tender will be called. |
16 |
Santirbazar |
Construction of 10 bedded PHC at Durpabari with 10 nos. quarters under Santirbazar Sub-Division, Bagafa Block, South Tripura including Staff quarters. |
RIDF-XX |
540.00 |
540.00 |
407.22 |
26-12-2015 |
208.90 |
57.07 |
0.00 |
0.00 |
|
Work rescined. 5th call tender is in progress. |
17 |
Belonia |
Proposed construction of 10 (ten) nos. staff quarters [ Type -I quarter - 04 units (one block - twin double storey ), Type-II quarter - 04 units (one block - twin double storey ) and Type-III quarter - 02 units (one block - twin single storey ) ] at Chottakhola Primary Health Centre (PHC), Rajnagar, Belonia, South Tripura District, Tripura . |
IMR Incentive Grants - 13th F.C. |
221.00 |
221.00 |
178.12 |
25.11.2014 |
211.37 |
211.37 |
10.00 |
0.00 |
75% Type-III Quarter completed & handed over. Brick work for Type-I & II is in progress |
Sep.21 |
18 |
Belonia |
Proposed construction of Type - I Quarter - 04 unit (one block-twin G+1 storied) at Barpathari PHC, Belonia, South Tripura under Rajnagar Block during the year-2016-17. |
IMR |
80.00 |
80.00 |
80.37 |
17.11.2017 |
0.00 |
0.00 |
88.41 |
0.00 |
80% |
Jun.21 |
19 |
Belonia |
Construction of RCC boundary wall around the Hrishyamukh CHC and Staff quarter, Hrishyamukh, South Tripura during the year-2017-18. |
IMR |
49.82 |
49.82 |
49.00 |
25.01.2018 |
0.00 |
0.00 |
49.00 |
0.00 |
80% |
Apl.21 |
20 |
Belonia |
Construction of RCC boundary wall around the Nalua PHC and staff quarter, Nalua, South Tripura during the year-2017-18. |
IMR |
40.84 |
40.84 |
40.52 |
25.01.2018 |
0.00 |
0.00 |
40.52 |
0.00 |
90% |
Apl.21 |
21 |
Belonia |
Construction of RCC boundary wall around the Ratanpur PHC and staff quarter, Belonia, South Tripura during the year-2017-18. |
IMR |
28.34 |
28.34 |
27.88 |
25.01.2018 |
0.00 |
0.00 |
27.88 |
0.00 |
50% |
Balance portion land dispute |
22 |
Ambassa |
Construction of New 10 nos. staff quarters (Type-I-4, Type-II-4 & Type-III-2) at Ambassa under Ambassa block, Ambassa Sub-Division, Dhalai District, Tripura. |
IMR - 13th FC |
225.00 |
225.00 |
170.81 |
18-01-17 |
121.44 |
121.44 |
103.56 |
0.00 |
90% |
May.21 |
23 |
L.T. Valley |
Construction of 10(ten) nos. staff quarters building [Type-I quarter-04 units (one block-twin double storey), [Type-II quarter-04 units (One block-twin single storey] and [Type-III quarter-02 units (one block-twin single storey] for 23-km Primary Health Centre (PHC) under Dhalai District, Tripura under IMR Incentive Grant. |
IMR |
207.61 |
207.61 |
213.61 |
19-12-2017. |
0.00 |
0.00 |
280.00 |
0.00 |
85% |
Balance work not yet started. |
|
|
|
TOTAL |
|
5898.24 |
|
|
87073.00 |
2877.24 |
1747.57 |
2255.35 |
47.00 |
|
National Health Mission (NHM)
National Health Mission (NHM)
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Kumarghat |
Constn. Of 10(ten) bedded PHC building in/c 10(ten) nos. Staff quarters(Type-I qtr. 04 units,Type -II qtr. 04 units and Type-III qtrs.02 units in/c kitchen, Morgue, Garage and generator with driver room building at Fatikroy under Kumarghat Sub-division under NHM. |
NHM |
458.00 |
458.00 |
437.80 |
02-03-2020 |
75.00 |
0.00 |
220.00 |
163.00 |
50% |
Dec.21 |
2 |
Kumarghat |
Constn. Of 10(ten) bedded PHC building in/c 10(ten) nos. Staff quarters(Type-I qtr. 04 units,Type -II qtr. 04 units and Type-III qtrs.02 units building portion in/c Water supply and Sanitary installation at Kanchanbari under Kumarghat Sub-division under NHM. |
NHM |
458.00 |
458.00 |
446.84 |
03-02-2020 |
75.00 |
Nil |
100.00 |
283.00 |
5% |
Nov.22 |
3 |
Kumarghat |
Construction of 10 Nos Staff Qtrs. At Pecharthal PHC ( Type-I=4 Nos, Type II=4 Nos & Type -III= 2 Nos.) |
NHM |
225.00 |
225.00 |
194.74 |
12th Mar-18 |
175.00 |
175.00 |
20.00 |
30.00 |
90% |
Apl.21 |
4 |
Kumarghat |
Construction of 10 Bedded PHC at Pecharthal, Kumarghat |
NHM |
210.00 |
210.00 |
183.06 |
9th Mar-17 |
150.00 |
Nil |
0.00 |
60.00 |
|
Nov.22 |
5 |
Dharmanagar |
"Proposed Construction of 10 (ten) nos. staff quarters building [type-I quarter -04 units, ( on block-twin double story), type-II quarter -04 units (one block -twin double story) and type-III quarter -02 units (one block-twin single story)] for Jalebassa Primary Health Centre (PHC) under Panisgar Sub-Division, North Tripura. |
NHM |
225.00 |
225.00 |
191.00 |
18-07-2017 |
225.00 |
185.00 |
Nil |
NIl |
95% |
Feb.21 |
6 |
Dharmanagar |
Up-gradation of Panisagar Community Health Centre (CHC) to 50 (fifty) bedded Sub-Divisional Hospital / SH: Construction of (i) 50 (fifty) bedded Sub-Divisional Hospital building [ double storied ] (ii) 16 (sixteen) Nos. Staff Quarters building { Type -I- staff quarters - 04 units [ 1(one) Block - twin (G+1) storied], Type -II- staff quarters - 04 units [ 1(one) Block - twin (G+1) storied], Type -III- staff quarters - 04 units [ 1(one) Block - twin (G+1) storied] and Type -IV- staff quarters - 04 units [ 1(one) Block – twin (G+1) storied]} (iii) Isolation Ward (iv) Kitchen (v) Morgue and (vi) Garage & Generator with Driver room building at Panisagar under North Tripura District under NHM Scheme during the year 2016-17. |
NHM |
1417.00 |
1417.00 |
1003.37 |
07-01-2018 |
1000.00 |
425.00 |
400.00 |
17.00 |
90% |
Apl.21 |
7 |
Dharmanagar |
Construction of New 10 bedded PHC building along with 10 nos. staff quarters at existing Brajendranagar PHC. |
NHM |
486.00 |
486.00 |
420.38 |
10/04/20 |
150.00 |
50.00 |
100.00 |
236.00 |
39% |
Apl.22 |
8 |
Kanchanpur |
Proposed construction of single storied 10(ten) bedded Primary Health Centre (PHC) building including 10(ten) Nos. Staff Quarters [ Type -I quarter - 04 units (one block - twin double storey ), Type-II quarter - 04 units (one block - twin double storey ) and Type-III quarter - 02 units (one block - twin single storey ) ], Kitchen, Morgue, Garage & Generator with Driver Room Building at existing Damcherra PHC under Kanchanpur Sub-division, North Tripura under NHM |
NHM |
486.00 |
486.00 |
434.57 |
11-02-2019 |
100.00 |
0.00 |
50.00 |
328.13 |
Site development work in progress |
Feb.22 |
9 |
Teliamura |
Proposed construction of (i) New 30 (thirty) bedded Community Health Centre (CHC) building including Ramp [ GF + Part of FF ] (ii) Kitchen (iii) Morgue and (iv) Garage & Generator with Driver room building at existing Kalyanpur CHC under Teliamura Sub-Division, Khowai District, Tripura under NHM Scheme during the year 2017-18. |
NHM |
670.00 |
670.00 |
519.64 |
15/01/18 |
200.00 |
200.00 |
470.00 |
0.00 |
75% |
Aug.21 |
10 |
Teliamura |
Proposed construction of 12(twelve) Nos. Staff Quarters building [ Type -I quarter - 04 units (one block - twin double storey ), Type-II quarter - 04 units (one block - twin double storey ) and Type-III quarter - 04 units (one block - twin double storey ) ] at Kalyanpur Community Health Centre (CHC) under Teliamura Sub-division, Khowai District, Tripura under NHM scheme. |
NHM |
295.00 |
295.00 |
245.44 |
24/09/2019 |
50.00 |
0.00 |
100.00 |
145.00 |
45% |
Aug.21 |
11 |
Udaipur |
Proposed construction of single storied 10(ten) bedded Primary Health Centre (PHC) building including 10(ten) Nos. Staff Quarters Morgue, Garage & Generator with Driver Room Building at Mirza under Kakraban Block, Udaipur Sub-Division, Gomati District, Tripura during the year 2016-17. |
NHM |
385.00 |
385.00 |
347.00 |
16.02.2017 |
399.00 |
399.00 |
0.00 |
0.00 |
90% |
Feb.21 |
12 |
Udaipur |
Proposed construction of 12(twelve) Nos. Staff Quarters building at Kakraban Community Health Centre (CHC) under Udaipur Sub-division, Gomati District, Tripura under NHM scheme. |
NHM |
295.00 |
295.00 |
252.19 |
11-08-19 |
50.00 |
50.00 |
245.00 |
0.00 |
15% |
Mar.22 |
13 |
Udaipur |
Proposed construction of 50 ( fifty) bedded MCH Wing [ G+3 Storied ] building at Gomati District Hospital, Tepania, Udaipur, Gomati District, Tripura (2nd Call). |
NHM |
797.00 |
797.00 |
0.00 |
0 |
225.00 |
Nil |
225.00 |
0.00 |
Tender in process |
Jan.23 |
14 |
Udaipur |
Construction of 10(ten) Nos. (type.I- 04 Nos, Type.II - 4 Nos. & Type.III - 2 Nos,) staff quarter at Maharani PHC. |
NHM |
225.00 |
225.00 |
0.00 |
|
0.00 |
0.00 |
0.00 |
0.00 |
1st call cancelled, 2nd call tender in process |
|
15 |
Amarpur |
Proposed construction of 30 (thirty) bedded Nutanbazar Community Health Centre (CHC) Building [ GF + Part of FF] at Nutanbazar, Amarpur Sub-Division, Gomati District, Tripura under NHM during the year 2016-17. |
NHM |
536.00 |
536.00 |
418.26 |
12-07-2017 |
461.00 |
461.00 |
75.00 |
0.00 |
90% |
May.21 |
16 |
Amarpur |
Up-Gradation of Karbook Community health Centre (CHC) to 50(Fifty) bedded Sub-Divisional Hospital including 16(Sixteen) Nos. Staff quarters at Karbook under Gomati District, Tripura. |
NHM |
1227.00 |
1227.00 |
823.42 |
12-01-2018 |
300.00 |
300.00 |
350.00 |
300.00 |
70% |
Mar.22 |
17 |
Amarpur |
Proposed construction of single storied 10(ten) bedded Primary Health Centre (PHC) building including 10(ten) Nos. Staff Quarters [ Type -I quarter - 04 units (one block - twin double storey ), Type-II quarter - 04 units (one block - twin double storey ) and Type-III quarter - 02 units (one block - twin single storey ) ], Kitchen, Morgue, Garage & Generator with Driver Room Building and Boundary wall at Silachari, Karbook Sub-division, Gomati District, Tripura under NHM during the year 2017-18 |
NHM |
486.00 |
486.00 |
400.18 |
12-01-2018 |
150.00 |
0.00 |
25.00 |
300.00 |
15% |
Dec.22 |
18 |
Amarpur |
Proposed construction of single storied 30(Thirty) bedded Primary Health Centre (PHC) building including 10(ten) Nos. Staff Quarters [ Type -I quarter - 04 units (one block - twin double storey ), Type-II quarter - 04 units (one block - twin double storey ) and Type-III quarter - 02 units (one block - twin single storey ) ], Kitchen, Morgue, Garage & Generator with Driver Room Building and Boundary wall at Ompi, Amarpur Sub-division, Gomati District, Tripura under NHM during the year 2017-18 |
NHM |
894.00 |
894.00 |
691.71 |
18-07-2018 |
150.00 |
150.00 |
250.00 |
425.00 |
50% |
Mar.22 |
19 |
Belonia |
Construction of 10 bedded PHC with quarters at Tripura Bazar under Hrishyamukh block, Belonia Sub-Division, South Tripura District. |
NHM |
385.00 |
385.00 |
306.22 |
05.01.2017 |
449.00 |
330.43 |
0.00 |
0.00 |
75% |
Dec.21 |
20 |
Belonia |
Proposed construction of new single storied 10(ten) bedded Primary Health Centre (PHC) building at existing Niharnagar PHC Complex, Niharnagar under Rajnagar Block, Belonia, South Tripura. |
NHM/IMR |
173.00 |
173.00 |
144.06 |
02.06.2016 |
221.65 |
190.36 |
0.00 |
0.00 |
80% |
Sep.21 |
21 |
Belonia |
Construction of MCH wing at Belonia Sub-Divisional Hospital, South Tripura |
NHM |
797.00 |
797.00 |
479.84 |
31.01.2018 |
325.00 |
250.00 |
211.10 |
0.00 |
75% |
Dec.21 |
22 |
Sabroom |
Proposed constn. Of single storied 10 (ten) bedded Primary Health Centre (PHC) in/c 10 (ten) nos staff quarters ,Type - I qtr. 04 units (one block twin double storey), Type - II, qtr.-04 units (one block twin double storey) and Type - III qtr. - 02 units (one block twing single storey) at Kalacherra under Sabroom Sub-Division, South Tripura. |
NHM |
385.00 |
385.00 |
326.66 |
31-03-2017 |
335.00 |
335.00 |
50.00 |
0.00 |
95% |
May.21 |
23 |
Mohanpur |
Construction of 10 nos staff qtrs at Katlamara PHC. |
NHM |
233.00 |
233.00 |
188.99 |
27.01.2018 |
Nil |
Nil |
150.00 |
83.00 |
30% |
Mar.22 |
24 |
Mohanpur |
Construction of 10 nos bedded PHC at Katlamara including Kitchen, Morgue & Garrage.. |
NHM |
239.00 |
239.00 |
176.89 |
21.01.2018 |
175.00 |
50.00 |
14.00 |
50.00 |
40% |
Mar.22 |
25 |
Mohanpur |
Construction of 10 nos staff qtrs at Bamutia PHC. |
NHM |
233.00 |
233.00 |
183.01 |
04.04.2018 |
50.00 |
50.00 |
150.00 |
33.00 |
70% |
Dec.21 |
26 |
Bishalgarh |
Proposed construction of (i) 20 (twenty) bedded Primary Health Centre (PHC) building [ double storied ], (ii) 15 (fifteen) seated Boy's Hostel, (iii) 15 (fifteen) seated Girl's Hostel, (iv) Kitchen, (v) Morgue and (vi) Garage & Generator with Driver room building at existing Madhupur PHC Complex under Bishalgarh Sub-division, Sepahijala District, Tripura |
NHM/IMR |
808.00 |
808.00 |
586.00 |
14.07.2018 |
275.00 |
275.00 |
342.00 |
NIL |
60% |
Jan.22 |
27 |
Bishramganj |
Proposed construction of (i) New 30 (thirty) bedded Community Health Centre (CHC) building including Ramp [ GF + Part of FF ] (ii) Kitchen (iii) Morgue and (iv) Garage & Generator with Driver room building at existing Takarjala CHC under Jampuijala Sub-Division, Sepahijala District, Tripura under NHM Scheme during the year 2017-18. |
RIDF |
670.00 |
670.00 |
586.71 |
03-02-2018 |
200.00 |
75.00 |
300.00 |
215.00 |
50% |
May.22 |
28 |
Sonamura |
Construction of 10 bedded PHC building at existing Taibandal PHC, Sonamura. |
NHM |
210.00 |
210.00 |
175.39 |
12-01-2018 |
260.00 |
117.00 |
0.00 |
0.00 |
95% |
Jun.21 |
29 |
Ambassa |
Proposed construction of staff quarter 09 nos. [Type-I=04 nos. Type-II=04 nos. and Type-III = 01 nos.] for Raishyabari PHC, Gandacherra. |
NHM |
198.00 |
198.00 |
179.44 |
19-09-17 |
175.00 |
165.58 |
47.00 |
0.00 |
65% |
Sep.21 |
30 |
Ambassa |
Proposed construction of staff quarter [8 nos.] (Type-I=04 nos. & Type-II=04 nos.) for Ganganagar PHC, Jawharnagar Sub-division, Dhalai District, Tripura. |
NHM |
170.00 |
170.00 |
153.78 |
15-11-17 |
125.00 |
87.05 |
66.00 |
0.00 |
70% |
Feb.22 |
31 |
L.T. Valley |
Proposed construction of 12(twelve) Nos. Staff Quarters building [ Type -I quarter - 04 units (one block - twin double storey ), Type-II quarter - 04 units (one block - twin double storey ) and Type-III quarter - 04 units (one block - twin double storey ) ] at Chawmanu Community Health Centre (CHC), L.T. Valley Sub-division under Dhalai District, Tripura under NHM scheme. |
NHM |
295.00 |
295.00 |
255.87 |
21-08-2019. |
50.00 |
50.00 |
245.00 |
0.00 |
75% |
Aug.21 |
32 |
L.T. Valley |
Construction of 10 beded PHC with 10 (ten) Nos. staff quarters (Type-I-04 Units, Type-II-04 Units and Type-III-02 Units] in the existing Primary Health Centres (PHCs) at 82 Miles PHC, L.T. Valley Sub-Division, Dhalai District, Tripura. |
NHM |
486.00 |
486.00 |
436.37 |
17-03-2020. |
100.00 |
0.00 |
100.00 |
286.00 |
Foundation work in progress |
Mar.22 |
33 |
L.T. Valley |
Proposed construction of 12(twelve) Nos. Staff Quarters building [ Type -I quarter - 04 units (one block - twin double storey ), Type-II quarter - 04 units (one block - twin double storey ) and Type-III quarter - 04 units (one block - twin double storey ) ] at Manu Community Health Centre (CHC), L.T. Valley Sub-division under Dhalai District, Tripura. |
NHM |
295.00 |
295.00 |
254.33 |
30-04-2020. |
50.00 |
50.00 |
150.00 |
95.00 |
20% |
Apl.22 |
34 |
Kamalpur |
Construction of 10 nos. staff quarters at Salema PHC [ Type-I = 04 nos., Type-II = 04 nos., Type-III = 02 nos. ] |
NHM |
225.00 |
225.00 |
151.09 |
17-04-2017 |
50.00 |
0.48 |
- |
- |
- |
Dispute, land not available. |
|
|
|
TOTAL |
|
15577.00 |
|
|
|
6775.65 |
4420.90 |
4455.10 |
3049.13 |
|
SC WELFARE
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Agartala Div. No.III |
Construction of quarters (Phase-II) for Safai Karmachari at Harijan Colony, IGM Hospital, Agartala, Tripura (W). |
SDS |
293.00 |
293.00 |
217.54 |
31/05/2016 |
293.00 |
146.50 |
0.00 |
0.00 |
97% |
Mar.21 |
2 |
Agartala Div. no.III |
Proposed Construction of 100 (One Hundred) seated SC Girl's Hostel [G+2 Storied] at B.R. Ambedkar Hostel Complex, JagannathBari Road, Agartala, Tripura under the scheme of BJRCY under Centrally Sponsored Scheme (CSS) during the year 2017-18. |
CSS |
376.00 |
376.00 |
376.00 |
19/05/2018 |
233.00 |
100.00 |
80.00 |
87.00 |
60% |
Oct.21 |
3 |
Udaipur |
Proposed construction of G+1 storied market and open shed at Kakraban market complex, Kakraban Udaipur Gomati District Tripura / SH: Building portion only. |
SC Welfare |
200.00 |
200.00 |
150.39 |
22.12.2017 |
200.00 |
132.42 |
0.00 |
0.00 |
85% |
Balance work tender invited. |
|
|
|
TOTAL |
|
869.00 |
|
|
|
726.00 |
378.92 |
80.00 |
87.00 |
|
FISHERIES
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Dharmanagar |
Construction of Fish Farmers Training Centre (G+2) with accommodation facilities for faculty members at Superintendent of Fisheries Office Complex, Dharmanagar, North Tripura/ Ground Floor portion except entrance lobby (phase-I)/ SH: Building portion including internal water supply and sanitary installations. |
Fisheries |
100.00 |
100.00 |
81.60 |
09-08-2017 |
100.00 |
70.00 |
20.00 |
Nil |
80% |
Mar.21 |
|
|
|
TOTAL |
|
100.00 |
|
|
|
100.00 |
70.00 |
20.00 |
0.00 |
|
Jail & Sub-Jails
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Bishalgarh |
Construction of 56 Nos Type-II & 24 Nos Type-III residential quarters at Kendriya Sansodhanagar Complex at Bishalgarh (Balance work - Phase-II) / SH: Building portion including internal water supply and sanitary installation. |
SPA |
695.63 |
695.63 |
546.36 |
07.08.2015 |
549.53 |
549.53 |
146.00 |
NIL |
90% |
Work suspended. |
2 |
Kailashahar |
Construction of Kailashahar Sub-Jail |
SPA |
1597.69 |
1597.69 |
1171.04 |
20/06/14 |
1166.74 |
1166.74 |
0.00 |
0.00 |
|
Work has been rescind. Balance work tender will be called |
|
|
|
TOTAL |
|
2293.32 |
|
|
|
1716.27 |
1716.27 |
146.00 |
0.00 |
|
Labour Department
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Agartala Div. No.III |
Construction of G+3 (4 storied) building for Labour & Employment and other Departments, Agartala, West Tripura/(Phase-I) Part Piling & Allied Foundation |
SPA'-Tied |
1576.72 |
1814.00 |
1178.67 |
13-11-2014 |
1400.00 |
1350.00 |
150.00 |
264.00 |
97% |
Apl.21 |
|
|
|
TOTAL |
|
1576.72 |
|
|
|
1400.00 |
1350.00 |
150.00 |
264.00 |
|
Minority Welfare Department
Minority Welfare Department
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Dharmanagar |
Proposed construction of 50 seated Girl's Hostel building (G+1) Storied) including boundary wall atached to Fulbari Class XII school under Kadamtala R.D block, Dharmanagar, North Tripura under multi sector development programe (MsDP) scheme during the year 2016-17(boundary wall). |
MSDP |
293.12 |
293.12 |
215.78 |
01-12-2016 |
109.75 |
109.75 |
183.37 |
Nil |
77% |
May.21 |
2 |
Agartala Div. No.III |
Construction of New building for Nazrul Chatrabas of 150 nos. capacity at Agartala, West Tripura/ Construction of Front Block (Phase-II). |
CASP (SPA-untied) |
329.55 |
329.55 |
369.00 |
03-03-2015 |
302.00 |
302.00 |
140.00 |
10.00 |
|
Work closed. Balance work tender will be called. |
|
|
|
TOTAL |
|
622.67 |
|
|
|
411.75 |
411.75 |
323.37 |
10.00 |
|
Law Department
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction with reference |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Dharmanagar |
Construction of residential quarters for Grade-II Judicial Officers at Dharmanagar, North tripura. |
State Plan |
277.00 |
277.00 |
|
|
Nil |
0.00 |
|
|
|
Tender under evaluation |
2 |
Dharmanagar |
Construction of residential quarters for Grade-III Judicial Officers at Dharmanagar, North tripura. |
State Plan |
237.00 |
237.00 |
|
|
237.00 |
0.00 |
237.00 |
|
|
Tender under evaluation. |
3 |
Amarpur |
Proposed construction of Court Building at Amarpur, Gomati District, Tripura /SH: Building portion including internal water supply and sanitary installation |
CSS |
694.00 |
694.00 |
403.03 |
05-12-2017 |
301.34 |
229.40 |
153.66 |
0.00 |
95% |
May.21 |
4 |
Ambassa |
Construction of 7 (seven) Nos. Judicial Quarter at Ambassa. |
CSS |
570.00 |
570.00 |
545.46 |
31-08-18 |
274.40 |
259.90 |
271.00 |
0.00 |
75% |
Jul.21 |
5 |
Ambassa |
Construction of Canteen with kitchen and Dining in the 1st floor of the District court at Ambassa, under Dhalai Judicial District , Tripura. |
CASP |
69.49 |
69.49 |
69.49 |
3/19/2020 |
0.00 |
0.00 |
0.00 |
69.49 |
70% |
May.21 |
6 |
Kamalpur |
Construction of proposed Court building at Kamalpur, Dhalai District, Tripura. |
CSS |
683.00 |
683.00 |
475.53 |
05-01-2018 |
400.00 |
400.00 |
130.00 |
260.00 |
65% |
Now suspended |
7 |
Mohanpur |
Construction of Tripura Judicial Academy at Narsingarh. |
State Plan |
2330 |
2330 |
189.33 |
01-03-2022 |
0.00 |
0.00 |
500.00 |
1830.00 |
10% |
Mar.22 |
|
|
|
TOTAL |
|
4860.49 |
|
|
|
1212.74 |
889.30 |
1291.66 |
2159.49 |
|
Panchayet Department
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction with reference |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Agartala Div. no.V |
Construction of Auditorium at Panchayati Raj Training Institute at A. D. Nagar, Agartala, West Tripura / SH. Civil Works, Plumbing Works, Stage Works including Stage Lighting, Internal Electrification, Sound System & HVAC Work. |
SPA/SDS |
1001.00 |
1001.00 |
686.00 |
08.03.2016 |
590.00 |
590.00 |
410.00 |
Nil |
85% |
Jul.21 |
|
|
|
TOTAL |
|
1001.00 |
|
|
|
590.00 |
590.00 |
410.00 |
0.00 |
|
Public Works Department (R&B)
Public Works Department (R&B)
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Dharmanagar |
Construction of Double storied building for Kadamtala (R&B) sub division, Kadamtala , North Tripura/Sh Building works in/c water supply arrangement ( 2nd call) |
State Plan |
85.42 |
85.42 |
67.34 |
14-03-2017 |
15.00 |
15.00 |
70.42 |
Nil |
100% |
Completed |
2 |
Kailashahar |
Construction of building for Kailashahar Division Office for PWD(R&B) at Kailashahar /Phase-II. |
CASP |
308.00 |
308.00 |
232.00 |
11-9-17. |
50.00 |
5.70 |
100.00 |
158.00 |
Ground improvement work completed. |
31-3-2022 |
3 |
Agartala Div. no.III |
Proposed construction of Chief Minister Bungalow including Frisking & Barrack, Type-II Quarters (One Unit) and Boundary wall at Agartala, West Tripura. |
SDS |
467.31 |
467.31 |
357.61 |
21-01-2016 |
514.24 |
312.24 |
157.76 |
0.00 |
98% |
Sep.21 |
4 |
Agartala Div. no.III |
Construction of 8(eight) Nos. Type -I quarter [1(one) Block - twin (G+3) storied ] and 8 (eight) Nos. Type -II quarter [1(one) Block - twin (G+3) storied ] at Melarmath, Agartala, West Tripura. |
(Housing) Civil works |
416.00 |
416.00 |
329.22 |
04-06-2015 |
339.52 |
269.52 |
20.48 |
0.00 |
95% |
Mar.21 |
5 |
Jirania |
Construction of Double Storied Office Building for PWD Mandai Sub-division at Mandai West Tripura) |
State Plan |
48.23 |
48.23 |
51.03 |
14/08/14 |
53.43 |
0.00 |
0.00 |
0.00 |
100% |
Completed |
6 |
Ambassa |
Infrastructural Development of Gandacherra Sub-Division, Dhalai District / Construction of Revenue Dak Bungalow |
SDS |
3235.00 |
No. F.01(10)/PCD/ PF/SEC(UNTIED)/2015-16/2830-40,Dated- 27-03-2015, Of the principle. Secretary (planning-P & C) Govt. of Tripura. |
307.48 |
31-07-16 |
1096.93 |
797.00 |
70.00 |
2456.07 |
55% |
|
7 |
Ambassa |
Infrastructural Development of Gandacherra Sub-Division, Dhalai District / 1000 seated capacity Auditorium |
No. F.01(10)/PCD/ PF/SEC(UNTIED)/2015-16/2830-40,Dated- 27-03-2015, Of the principle. Secretary (planning-P & C)Govt. of Tripura. |
893.29 |
04-11-16 |
70% |
Jun'2020 |
8 |
Ambassa |
Infrastructural Development of Gandacherra Sub-Division, Dhalai District / Construction of Staff Quarters 36 nos. [Type-I G+2: 348 sqm (6 nos.), Type-II-g+2: 840 sqm (12 nos.), type-III-G+2: 1008 sqm (12 nos.), T-IV-G+2: 558.60 sqm (6 nos.)] |
No. F.01(10)/PCD/ PF/SEC(UNTIED)/2015-16/2830-40,Dated- 27-03-2015, Of the principle. Secretary (planning-P & C)Govt. of Tripura. |
590.32 |
16-03-16 |
80% |
July' 2020 |
9 |
Ambassa |
Infrastructural Development of Gandacherra Sub-Division, Dhalai District /Construction of Police Station |
No. F.01(10)/PCD/ PF/SEC(UNTIED)/2015-16/2830-40,Dated- 27-03-2015, Of the principle. Secretary (planning-P & C) Govt. of Tripura. |
224.48 |
19-04-18 |
Work cancelled |
Nil |
10 |
Capital Complex |
Construction of a composite building for Accommodation of different offices of PWD at Capital Complex, Khejurbagan, Agartala/ Construction of Lower Ground Floor and Upper Ground Floor only. |
|
1406.00 |
|
|
|
|
|
560.00 |
|
85% of structural part of two floor completed. Tender called for remaining work. |
Sep.2021 |
11 |
Capital Complex |
construction of Proposed MLA Hostel, Capital Complex at Agartala , West Tripura/SH:Building portion including internal water supply, sanitary installation, mechanical installation (HVAC and LIFT) and concealed conduting for internal electrical works. (1st Phase) |
|
5215.00 |
5215.00 |
2961.45 |
06-02-2016 |
2766.83 |
2369.93 |
194.62 |
|
97% |
Phase-I= Completed Phase-II= Aug.21 |
12 |
Santirbazar |
Construction of building for Santirbazar PWD(R&B) Division and Sub-Division office at Santirbazar, South Tripura /SH: Building portion including Internal water supply, sanitary installation, Sewage & Drainage work. |
|
255.00 |
255.00 |
185.40 |
04-09-2017 |
167.52 |
167.52 |
20.00 |
- |
100% |
Completed |
13 |
Dharmanagar |
Proposed Extension of Circuit House at Dharmanagar, North Tripura/SH: Building portion including internal water supply, sanitary installation and concealed conduiting for internal electrification works. |
SPA |
542.39 |
542.39 |
409.87 |
42423.00 |
455.00 |
345.00 |
87.39 |
- |
80% |
Apl.21 |
14 |
THCB |
Construction of 08(eight) nos. Type-IV quarters (1 no. twin-4 storied) at Kunjaban Township, Govt. residential Complex, Agartala. |
|
285.00 |
285.00 |
|
|
127.00 |
127.00 |
158.00 |
0.00 |
80% |
May.21 |
15 |
Jirania |
Construction of boundary wall around the newly constructed R&B Sub-Division office building at Mandai during the year 2016-17(L-26.00 mtr) Agreement No.T/EE/JRN/B&R/PWD/13/2018-19 |
State Plan |
6.23 |
6.23 |
6.23 |
|
|
4.65 |
|
|
90% |
Completed |
16 |
Kailashahar |
Construction of building for Kailashahar Division Office for PWD(R&B) at Kailashahar /Phase-II. |
CASP |
308.00 |
308.00 |
232.00 |
11-9-17. |
50.00 |
5.70 |
44.30 |
100.00 |
158.00 |
Work suspended |
17 |
Capital Complex |
Construction of New Raj Bhawan at capital complex, agartala/SH: construction of Boundary wall I between Type-II and Type-IV qtr. With gate, passages for Type-1 with wall at D-Block four Nos. garage, guard base with shed for CRPF personals, peripheral drain alongwith protection wall aluminium partition etc. |
|
60.50 |
60.50 |
56.26 |
22-08-2018 |
Nil |
Nil |
Nil |
10.00 |
Nil |
work in progress |
18 |
Ambassa |
Infrastructural Development of Gandacherra Sub-Division, Dhalai District / Construction of Revenue Dak Bungalow |
SDS |
3235.00 |
3235.00 |
307.48 |
31-07-16 |
1296.93 |
957.00 |
|
1439.07 |
55% |
Work suspended |
19 |
Ambassa |
Infrastructural Development of Gandacherra Sub-Division, Dhalai District / 1000 seated capacity Auditorium |
SDS |
3235.00 |
3235.00 |
893.29 |
04-11-16 |
|
|
|
|
72% |
Oct.21 |
20 |
Ambassa |
Infrastructural Development of Gandacherra Sub-Division, Dhalai District / Construction of Staff Quarters 36 nos. [Type-I G+2: 348 sqm (6 nos.), Type-II-g+2: 840 sqm (12 nos.), type-III-G+2: 1008 sqm (12 nos.), T-IV-G+2: 558.60 sqm (6 nos.)] |
|
590.32 |
16-03-16 |
|
|
|
|
97% |
Apl.21 |
21 |
Ambassa |
Infrastructural Development of Gandacherra Sub-Division, Dhalai District /Construction of Police Station |
|
224.48 |
19-04-18 |
|
|
|
|
|
Finance deptt. has excluded this project from the list |
|
|
TOTAL |
|
19108.08 |
|
|
|
6932.40 |
5376.26 |
1482.97 |
4163.14 |
|
|
School Education Department
School Education Department
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Kailashahar |
Up-gradation of infrastructure of Srirampur Surjyamani H.S. School at Kailashahar. |
SPA |
300.00 |
300.00 |
262.25 |
04-12-2016 |
250.00 |
173.59 |
48.00 |
0.00 |
90% |
Jun.21 |
2 |
Kailashahar |
Construction of Academic and Administrative Block for DIET at Kailashahar, Unakoti District, Tripura. |
CASP |
940.00 |
940.00 |
759.34 |
23-3-16 |
401.54 |
401.54 |
500.00 |
0.00 |
55% |
Feb.22 |
3 |
Kanchanpur |
Constn. Of Anandabazar H.S. School Building at Dasda Block, Kanchanpur, under North Tripura District. |
SPA-Tied |
720.00 |
720.00 |
531.60 |
18-02-2017 |
359.00 |
359.00 |
100.00 |
121.00 |
50% |
Mar.22 |
4 |
Kanchanpur |
Constn. Of Laljuri H.S. School Building at Kanchanpur under North Tripura District. |
CASP(SPA) |
872.00 |
872.00 |
590.70 |
11-02-2016 |
539.00 |
539.00 |
101.00 |
0.00 |
95% |
Jul.21 |
5 |
Kanchanpur |
Constn. Of Jampui Hill H.S. School Building at Jampui Hill Block, Kanchanpur, under North Tripura District. |
SPA-Tied |
635.00 |
635.00 |
509.55 |
11-06-2016 |
389.00 |
389.00 |
171.00 |
0.00 |
95% |
Jul.21 |
6 |
Kanchanpur |
Constn. Of Gachirampara H.S. School Building at Dasda Block, Kanchanpur, under North Tripura District. |
SPA-Tied |
455.00 |
455.00 |
403.77 |
18-02-2017 |
142.65 |
142.65 |
100.00 |
212.00 |
60% |
Feb.22 |
7 |
Khowai |
Up-gradation of infrastructure of Tulasikhar Rajnagar H.S. School, Khowai. (SDS) |
SDS |
300.00 |
300.00 |
221.04 |
08-12-2016 |
88.76 |
88.76 |
155.28 |
0.00 |
Civil work completed |
Mar.21 |
8 |
Teliamura |
Up-gradation of infrastructure of Teliamura H.S. School at Teliamura, Khowai District, Tripura (Phase-I). |
CASP |
600.00 |
600.00 |
422.06 |
01/01/16 |
271.52 |
191.52 |
100.00 |
0.00 |
85% |
Dec.21 |
9 |
Amarpur |
Proposed construction of Punjiham H.S. School at Karbook, District Gomati, Tripura. |
SPA/ NABARD |
742.00 |
742.00 |
463.00 |
31-12-2015 |
295.00 |
227.91 |
100.00 |
295.00 |
60% |
Jan.22 |
10 |
Amarpur |
Proposed construction of Silachari H.S. School at Silachari , District Gomati, Tripura. |
SPA/ NABARD |
927.00 |
927.00 |
508.98 |
10-04-2016 |
255.00 |
253.98 |
100.00 |
340.00 |
40% |
Mar.22 |
11 |
Santirbazar |
Construction of Baikhora H.S. School at Santirbazar, South Tripura. |
CASP(SPA) |
609.00 |
609.00 |
435.22 |
04-05-2016 |
256.20 |
131.20 |
20.00 |
223.00 |
45% |
Feb.22 |
12 |
Belonia |
Proposed construction of Extension for Arya Colony H.S. School at Belonia, South Tripura. |
CASP (SCA Untied) |
655.38 |
100.00 |
360.03 |
15.01.2013 |
552.42 |
549.40 |
102.96 |
0.00 |
95% |
Aug.21 |
13 |
Belonia |
Up-gradation of infrastructure of Barpathari H.S. School, Belonia, South Tripura under Special Devlopment Scheme (SDS) under State Plan during the year 2015-16 (Phase-I). |
SDS |
600.00 |
600.00 |
390.35 |
02.06.2016 |
527.37 |
477.37 |
0.00 |
0.00 |
95% |
Nov.21 |
14 |
Sonamura |
Proposed Construction of Boxanagar H.S. School at Boxanagar, Sonamura, Sepahijala District, Tripura undern SCA (un-tied) during the year 2012-13. |
SCA (un-tied) |
777.00 |
777.00 |
527.72 |
07-03-2014 |
629.04 |
200.00 |
54.15 |
0.00 |
85% |
Nov.21 |
15 |
Sonamura |
Construction of School building for Nabakumar CP High School under Manaipathar ADC village, Kathalia. |
Rurban |
160.00 |
160.00 |
113.00 |
22-12-2017 |
160.00 |
160.00 |
0.00 |
0.00 |
85% |
Nov.21 |
16 |
Ambassa |
Up-gradation of Infrastructure of Chandraipara H. S. School, Ambassa, Dhalai, Tripura under ACA (SPA Tied) during the year 2011-12 (1st Phase). |
SPA' Tied |
500.00 |
500.00 |
396.80 |
22-06-14 |
449.57 |
449.57 |
50.43 |
Nil |
80% |
Jan.22 |
|
|
|
TOTAL |
|
9792.38 |
|
|
|
5566.07 |
4734.49 |
1702.82 |
1191.00 |
|
Science & Technology Department
Science & Technology Department
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Agartala Div. No.III |
Proposed Vigyan gram at Agartala(Phase -I) Agency : Reacon Engineers (I) Ltd |
ACA/SPA/NLCPR |
3179.00 |
3179.00 |
2519.59 |
08.08.2013 |
2265.87 |
2098.08 |
253.72 |
Nil |
83% |
Aug.21 |
|
|
|
TOTAL |
|
3179.00 |
|
|
|
2265.87 |
2098.08 |
253.72 |
0.00 |
|
Transport Department
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Jirania |
Construction of Terminus building for Interstate Truck Terminus (ISTT) at Madhabbari, Jirania, West Tripura/SH: Construction of 1st floor of Terminus building (Vertical extension). |
NEC |
303.40 |
303.40 |
|
|
|
|
|
|
|
Jun.22 |
|
|
|
TOTAL |
|
303.40 |
|
|
|
|
|
|
|
|
Tribal Welfare Department
Tribal Welfare Department
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Khowai |
Construction of 150 seated Girls hostel building at EMR Rajnagar, Khowai. |
TW |
481.51 |
481.51 |
413.90 |
13-08-2019 |
300.00 |
287.51 |
157.40 |
0.00 |
90% |
Apl.21 |
2 |
Agartala Div. No.V |
Construction of Type-III Residential Quarter for Hostel Superintendent for ST &SC Hostels in Tripura at Arundhutinagar H.S. School , Agartala , West Tripura under NEC Plan Scheme during the year 2014-15 . |
NEC |
20.18 |
20.18 |
20.49 |
04.01.2019 |
15.31 |
0.00 |
6.00 |
0.00 |
70% |
Mar.21 |
3 |
Santirbazar |
Const. of Sports Complex for Eklavya Model Residential School at Birchandra Manu under Santirbazar Sub-Division, South Tripura/SH:- Development of Playground |
Plan |
106.50 |
106.50 |
84.42 |
21-01-20 |
68.60 |
54.00 |
37.90 |
0.00 |
80% |
Apl.21 |
4 |
Kanchanpur |
Proposed construction of 24 (twenty-four) Nos. Staff Quarters building at Ratan Moni Memorial Ashram School, Kanchanpur, North Tripura / SH: Construction of (i) 12(twelve) nos. of Type-I- quarters [one Block - four unit at each floor - G+2 storied] & (ii) 12(twelve) nos. of Type-III-quarters [one Block - four units at each floor- G+2 storied] / Building portion including internal water supply, sanitary installation, Sewage & Drainage works. |
MINISTRY OF TRIBAL AFFAIRS |
567.00 |
567.00 |
429.81 |
27-10-2017 |
283.00 |
185.57 |
0.00 |
0.00 |
45% |
Jun.22 |
|
|
|
TOTAL |
|
1175.19 |
|
|
86725.00 |
666.91 |
527.08 |
201.30 |
0.00 |
|
Urban Development Department
Urban Development Department
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Kumarghat |
Proposed 1000 seated capacity Town Hall at Kumarghat, Unakoti District |
Deposite (SPA Tide) |
1180.00 |
1180.00 |
586.55 |
30 th Sep2016 |
400.00 |
400.00 |
780.00 |
Nil |
75% |
Fund not available. |
2 |
Agartala Div. No.V |
1. Construction of Bus Terminal at Nagerjala, Agartala under NLCPR ruction of Terminal building, (ii) Construction of Rehabilitated Shops/SH: Building portion including internal water supply and sanitary installation. Sri Arun Kr. Dey |
NLCPR |
1688.90 |
1688.90 |
627.50 |
13.12.2014 |
988.18 |
988.18 |
700.72 |
Nil |
73% |
Jul.21 (if fund is available) |
3 |
Agartala Div. No.V |
Construction of Bus Terminal at Nagerjala, Agartala under NLCPR : Construction of internal road and road side drain , waiting shed and parking area for different types of Vehicle . Sri Arun Kr. Dey |
NLCPR |
607.74 |
16.03.2017 |
30% |
Jul.21 (if fund is available) |
4 |
Santirbazar |
Construction of Fish Market at Santirbazar under Santirbazar Municipal Council under Special Central Assistance (SCA- Untied) during the year 2015-2016 (Ground Floor only - Phase – I). |
SCA- united |
100.00 |
100.00 |
108.60 |
28-11-2017 |
0.00 |
0.00 |
120.00 |
0.00 |
20% |
May.22 |
5 |
Santirbazar |
Construction of Santirbazar Municipal Council at Santirbazar, South Tripura. |
Urban |
317.42 |
125.00 |
252.71 |
07-03-2017 |
175.00 |
107.77 |
95.00 |
0.00 |
80% |
Mar.21 |
6 |
Agartala Div-I |
Construction of Stalls at Mantribari Road,PWD Complex, Netaji Chowmuhani, Agartala /SH.Building portion (GF & FF only) in/c internal water supply,sanitary installation |
Deposit |
182.40 |
182.40 |
147.73 |
23-7-17 |
182.40 |
98.40 |
0.00 |
0.00 |
90% |
Apl.21 |
|
|
|
TOTAL |
|
3468.72 |
|
|
|
1745.58 |
1594.35 |
1695.72 |
|
|
Border Area Development Programme (BADP)
Border Area Development Programme (BADP)
Published: January 19, 2021
(In Lakhs) |
SL. No. |
Division |
Name of Works |
Sanction Cost |
Scheme/ Head |
Year of Sanctioned |
Total Fund Released |
Target Date of Completion |
Status of Physical implementation/Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
DHALAI DISTRICT |
1 |
Ambassa Division |
(i) Road from Ratan Nagar Market to IBB Road via S K Para BOP under Gandacherra Sub-division (L=6.00 KM). (ii) Road from Ratan Nagar Market to IBB Road via S K Para BOP under Gandacherra Sub-division (L=4.00 KM). |
1097.00 |
BRDP |
---- |
1097.00 |
March, 2016. |
Formation =10.56 km, GSB=8.56 km, Retaining wall=279.10 Mtr, CD=13 nos completed. Target date of completion: March'16 |
2 |
Additional link Road from Boalkhali to Maharaja-I (L=7.35 km) |
810.00 |
BRDP |
---- |
810.00 |
March, 2016. |
Formation =7.35 km, GSB=5.00 km, Metalling=4.50 km, Retaining wall=88.00 Mtr, Box Cell=2 No completed.
Target date of completion: March-16
|
Clinical Research Finance-Sponsored Projects Administration(CRF-SPA )
Clinical Research Finance-Sponsored Projects Administration(CRF-SPA )
Published: January 19, 2021
(In Lakhs) |
SL. No. |
Division |
Name of Works |
Sanction Cost |
Scheme/ Head |
Year of Sanctioned |
Total Fund Released |
Target Date of Completion |
Status of Physical implementation/Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
WEST DISTRICT |
1 |
--- |
Improvement and upgradation of road from Chandrapur to Chaturdash Devta Temple via Baldakhal(L=3.831 km) |
646.50 |
--- |
--- |
--- |
--- |
Work yet to be started. |
GOMOTI DISTRICT |
2 |
Amarpur Division |
Improvement of road leading to newly constructed Sub divisional H.Q. Karbok/ portion from Amarpur to Karbook/ Silachari (l=25.50 km) (beyond the protion upgrade from (PMGSY) under SPA-tide |
2415.00 |
-- |
-- |
-- |
March, 2016. |
Work completed for 18 km. Work in progress for balance work. |
Centrally Sponsored Scheme(CSS)
Centrally Sponsored Scheme(CSS)
Published: January 19, 2021
(In Lakhs) |
SL. No. |
Division |
Name of Works |
Sanction Cost |
Scheme/ Head |
Year of Sanctioned |
Total Fund Released |
Target Date of Completion |
Status of Physical implementation/Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
WEST DISTRICT |
1 |
Agartala Division No-I, Agartala |
Construction of RCC covered drain from ICP main gate upto Zero Point at Indo-Bangladesh Border over Akhaura Khal (L=130.00 mtr.) |
200.89 |
CSS |
---- |
---- |
March, 2017. |
Tender just received |
2 |
Imp. upgradation of the approach road from Fire Bridge Chowmuhani to Agartala Land Custom station by providing RCC covered drain/covering of existing drain to the RCC Box cell along Akhaura road. |
387.43 |
CSS |
---- |
500.00 |
March, 2017. |
Foundation work of drain in progress. Formation work is in progress.10% completed. |
3 |
Development of road in front of ICP, Agartala upto Zero Point at Indo-Bangladesh Border at Akhaura (L=324.85 mtr) |
144.31 |
CSS |
---- |
--- |
March, 2017. |
Tender invited |
Economic & Importance (E & I PROJECT)
Economic & Importance (E & I PROJECT)
Published: January 19, 2021
(In Lakhs) |
SL. No. |
Division |
Name of Works |
Sanction Cost |
Scheme/ Head |
Year of Sanctioned |
Total Fund Released |
Target Date of Completion |
Status of Physical implementation/Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
SOUTH DISTRICT |
1 |
--- |
Improvement of road from NH-44 junction at Udaipur (District Head Quarter) to Amarpur Sub-divisional Head Quarter (24.96 km)/ Portion from Maharai to Amarpur, Length- 16.080 km (Ch: 8.80 km to 24.960 km) (Job No.-EI-TR-2011-12-03) |
2122.26 |
E & I Project. |
--- |
---- |
---- |
Road work completed Bridge: completed CD: completed R/W: 153.00 M Road side drain: 8682 M. Maintenance work for the defect portion has been completed by the agency(M/s GPT Infrastructure Pvt. Ltd.). |
Fisharies Department
Published: January 19, 2021
(In Lakhs) |
SL. No. |
Division |
Name of Works |
Sanction Cost |
Scheme/ Head |
Year of Sanctioned |
Total Fund Released |
Target Date of Completion |
Status of Physical implementation/Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
NORTH DISTRICT |
1 |
Dharmanagar Division |
Construction of Fish Farmers Training Centre (G+2) with accommodation facilities for faculty members at Superintendent of Fisheries Office Complex, Dharmanagar, North Tripura/SH: Building portion including internal water supply and sanitary installations. |
263.61 |
--- |
2015-16 |
--- |
--- |
Preliminary cost estimate issued for according A/A & E/S.Draft NIT for GF on Rs.100.00 lakhs only.
. |
SOUTH DISTRICT |
2 |
Santirbazar Division |
Construction of Fish Market at Santirbazar under Santirbazar Municipal Council under Special Central Assistance (SCA- Untied) during the year 2015-2016 (Ground Floor only - Phase – I). |
126.00 |
--- |
2015-16 |
--- |
--- |
DNIT issued for calling tender.A/A & E/S awaited.
|
GA (Print & Stationery)
Published: January 19, 2021
(In Lakhs) |
SL. No. |
Division |
Name of Works |
Sanction Cost |
Scheme/ Head |
Year of Sanctioned |
Total Fund Released |
Target Date of Completion |
Status of Physical implementation/Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
WEST DISTRICT |
1 |
Agartala Division No-V, Agartala |
Proposed renovation and re-orientation of Machine room in existing Government Press building, Bordowali, Agartala / SH: Construction of a three storied building with provision of one more storey foundation by dismantaling of existing old structure. |
832.00 |
-- |
2015-16 |
--- |
--- |
DPR sent to the concerned Department for according A/A & E/S in Apl.2015.
Sanction yet to be accorded.
|
Education Department
Published: January 19, 2021
(In Lakhs) |
SL. No. |
Division |
Name of Works |
Sanction Cost |
Scheme |
Year of Sanctioned |
Total Fund Released |
Target date of Completion |
Status of Physical implementation/Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
WEST DISTRICT :- |
1 |
Agartala Division No-V, Agartala |
Construction of 1000 seated Auditorium for Ramthakur College, Agartala, West Tripura. |
445.20 |
NLCPR |
2012-13 |
425.00 |
Dec 2017. |
All RCC roof completed . Brick work completed. Finishing work 90% completed . Truss work completed. |
2 |
Construction of Women Polytechnic College, Amtali, Agartala. |
500 |
---- |
2015-16 |
---- |
----- |
DNIT under preparation. |
3 |
Jirania Division |
Construction of General Degree College at Khumulwng (TTAADC) at Belbari, West Tripura/ Proposed Vertical Expansion of another one floor over existing Ground Floors of Academic Building and Administrative Building / SH : Building portion including internal water supply and sanitary installation. |
350.00 |
SPA-tied |
2015-16 |
--- |
Oct., 2017. |
Work Order Issued. |
4 |
Construction of Academic Block for Khumluwng Govt. Degree College, Jirania, West Tripura under Special Plan Assistant (SPA-tied) during the year 2012-13(Phase-II). |
305.00 |
SPA-tied |
2012-13 |
470.40 |
Dec 2017. |
1st floor roof is ready for casting. |
5 |
Agartala Division No.I |
Special repair & Retrofitting of MBB College, Agartala, Tripura West. |
824.00 |
---- |
2015-16 |
100 |
Mar 2018. |
Work Order Issued.Rs.52.00 lakhs to be revalidated. |
6 |
Proposed construction of English Medium Degree College at Old Central Jail Premises, Agartala. |
5671.00 |
Deposit |
2012-13 |
2000 |
Dec 2017. |
Foundation work in progress. 50% pile cap completed. |
7 |
Agartala Division No-III, Agartala |
Development of Infrastructure of MBB College, Agartala, West Tripura:-
a) Construction of composite Auditorium having students Common room, Council room & Canteen etc.
|
900.00 |
TFC |
2012-13 |
2700.00 |
Dec 2017. |
Structure above lintel level. Ground floor 70% completed. Retaining wall completed.
|
8 |
b) Construction of new building for Commerce & Management etc. |
1000.00 |
TFC |
2012-13 |
Completed |
Work completed.
Combined LOC was placed for different TFC project.
|
9 |
Construction of (G+4) storied Office Building at Office Lane, Agartala, Tripura (W)/SH: Building portion including internal water supply and sanitary installations. |
1113.00 |
SPA |
2012-13 |
1614.00 |
Completed |
Completed and handed over. |
10 |
Proposed Construction of Annexe Block of Birchandra State Central Library at Agartala, West Tripura/ Phase-I: Western Block/Building portion including internal water supply and sanitary installation. |
1647.00 |
NLCPR |
2013-14 |
569.90 |
March, 2018. |
Finishing work in progress.
Whole site not ready.
Revalidation required for Rs.217.38 lakhs
|
11 |
Proposed construction of English Medium Degree College at Old Central Jail Premises, Agartala. |
5171.00 |
Deposit |
2015-16 |
200.00 |
--- |
First phase tender value Rs.2888.00 lakhs.
Work order issued. Test pile done.
First phase: Administrative, Academic & Library building.
|
12 |
Development of MBB College/Proposed construction of new Library building, Computer Centre Bank, Post Office & Co-operative Building, Guest House and Health Centre at MBB College Complex, Agartala, West Tripura. |
1341.70 |
|
2015-16 |
--- |
Dec 2018 |
Yet to be clear site not found. |
13 |
Development of MBB College/Proposed construction of Guest House at MBB College Complex, Agartala, West Tripura. |
325.00 |
|
2015-16 |
--- |
--- |
Preliminary estimate processed to concerned Deptt. in the month of April, 2016 for A/A & E/S. |
14 |
Special repair & Renovation of MBB College Complex Govt. Residential quarters / Type-IV quarters 24 nos. |
109.13 |
|
2015-16 |
--- |
--- |
Preliminary estimate processed to concerned Deptt. in the month of Feb. 2016 for A/A & E/S. |
GOMATI DISTRICT :- |
15 |
Udaipur Division |
Construction of Polytechnic Institute at Fulkumari, Udaipur, Gomati District, Tripura / SH: Construction of i) 100 Seated Boy's Hostel iii) 50 Seated Girl's Hostel and iii) Staff Quarters -15 Units [ Type -I quarter 1(one) Block - twin double storied 4(four) units , Type -II quarter 1(one) Block - twin double storied 4(four) units, Type -III quarter 1(one) Block - twin three storied 6(six) units and Type -IV quarter - single storied 1(one) unit ] , under SPA-tied for the year 2012-13 (Phase-II). |
500.00 |
SPA-Tied |
2013-14 |
920.00 |
Dec 2017 |
All structure part completed, finishing work is in progress. |
16 |
Proposed construction of Administrative Block at Netaji Subhas Mahavidyalaya at Udaipur, Gomati District. |
610.00 |
SDS |
2016-17 |
----- |
---- |
Preliminary cost estimate processed to concerned Department for according A/A & E/S. |
17 |
Construction of 3 (three) nos. Workshops for Gomati Tripura District Polytechnic at Fulkumari, Udaipur. |
201.71 |
SPA |
2015-16 |
---- |
Aug 2018 |
Work started. |
18 |
Amarpur Division |
Construction of Amarpur Govt. Degree College at Amarpur, Gomati District, Tripura / SH: Vertical extension of 1st floor of Academic Block during the year 2016-17 (Phase-II). |
234.12 |
--- |
2016-17 |
|
---- |
Work order issued.. |
UNAKOTI DISTRICT :- |
19 |
Kailashahar Division |
R.K. Mahavidyalaya, Kailashahar
Administrative Building- (Three storied building. Only Ground floor is to be constructed in 1st Phase. Each floor is to measure 500 Sqm (Approx). (2007-08)/ Ph-1.
|
138.04 |
NLCPR |
2012-13 |
--- |
June, 2016. |
i) 1 No. work shop completed upto plinth level. ii) Another 2 Nos. workshop foundation work in progress for one no. & Layout given to agency 1 no. respectively. |
20 |
Construction of New Science Block at R.K. Mahavidyalaya, Kailashahar (Phase-II). |
500.00 |
--- |
2015-16 |
--- |
--- |
Tender received for Ground floor as per earlier sanction of Rs.500.00 lakhs with addl. sanction full building (G+2) may be taken up on cancellation of the tender for GF for completion of the building in one go for total UC of Rs.(5+10)=Rs.15.00 crores. |
21 |
Proposed constrcution of Science Building (G+2) at Kailashahar College, Unakoti District, Tripura/Ground floor only under Phase-I. |
1000.00 |
--- |
2015-16 |
--- |
Sep 2018 |
Piling work in progress. |
22 |
Kumarghat Division |
Proposed Vertical expansion of one story over existing Double Storied Adacemic and Administrative building of Ambedkar College at Fatikroy, Unakoti District, Tripura. |
216.00 |
NLCPR |
2015-16 |
150.00 |
Dec 2017 |
Work completed. |
NORTH DISTRICT :- |
23 |
Dharmanagar Division |
GDC, Dharmanagar Administrative Building [G+2] - (Three storied building. each floor is to measure 500 Sqm (Approx) (2007-08). |
1349.45 |
NLCPR |
2012-13 |
--- |
--- |
Preliminary estimate processed to concerned Deptt. for A/A & E/S. |
24 |
100 seated Boys hostel and quarters for faculties of Dharmanagar Degree College. |
445.20 |
NLCPR |
2012-13 |
425.00 |
Completed.
|
Building completed and handed over. |
25 |
Dharmanagar General Degree college Academic Wing. |
1341.70 |
ACA |
2012-13 |
--- |
Completed. |
Building completed and handed over. |
26 |
Construction of 3 (three) nos. Workshops for North Tripura District Polytechnic at Bagbassa, Dharmanagar, North Tripura. |
201.71 |
CSS/TFC |
2016-17 |
--- |
Dec 2017. |
Plastering and CC flooring completed. Roof truss work in progress. |
27 |
Kanchanpur Division |
Construction of Model Degree College at GDC Kanchanpur under RUSA / (i) Vertical expansion of Academic building (1st floor) and (ii) Construction of 500 seated Auditorium. |
540.00 |
RUSA |
2015-16 |
300.00 |
Mar 2018 |
Finishing work in progress.
|
DHALAI DISTRICT :- |
28 |
L.T. Valley Division |
Construction of Model Degree College at L.T. Valley under RUSA / (i) Vertical expansion of Academic building (1st floor) and (ii) Construction of 500 seated Auditorium. |
540.00 |
RUSA |
2015-16 |
300.00 |
Mar 2018 |
70% roof casted and 30% ready for casting..
|
29 |
Kamalpur Division |
Construction of Kamalpur Govt. Degree College at Kamalpur, Dhalai Tripura / SH: Vertical extension of 1st floor of Academic Block during the year 2016-17 (Phase-II). |
234.12 |
---- |
2016-17 |
|
---- |
Tender Accepted. |
SOUTH DISTRICT :- |
30 |
Santirbazar Division |
Construction of Model Degree College at Santirbazar under RUSA. |
422.00 |
RUSA |
2015-16 |
300.00 |
Dec 2018 |
Work in progress.
|
KHOWAI DISTRICT :- |
31 |
Khowai Division |
Up-gradation of Dasarath Deb Memorial (DDM) College at Khowai, Tripura / Vertical extension of Administrative building (1st & 2nd floor) and Academic building (2nd floor) under SPA(tied) during the year 2015-16 (Phase-II)/SH: Building portion including internal water supply and sanitary installation. |
500.00 |
SPA-Tied |
2015-16 |
200.00 |
Mar 2018 |
1st floor roof casted 01 Block and for rest ground floor roof casted.. |
Nagar Panchayet Department
Nagar Panchayet Department
Published: January 19, 2021
(In Lakhs) |
SL. No. |
Division |
Name of Works |
Sanction Cost |
Scheme/ Head |
Year of Sanctioned |
Total Fund Released |
Target Date of Completion |
Status of Physical implementation/Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
DHALAI DISTRICT |
1 |
Ambassa Division |
Construction of Nagar Panchayat Office Building at Ambassa, Dhalai, Tripura/SH: Building portion including internal water supply & Sanitary installation. |
317.21 |
---- |
---- |
---- |
---- |
A/A & E/S awaited. |
SEPAHIJALA DISTRICT |
2 |
Bishalgarh Division |
Construction of Nagar Panchayat Office Building at Bishalgarh, Sepahijala, Tripura/SH: Building portion including internal water supply & Sanitary installation. |
317.21 |
-- |
2014-15 |
-- |
-- |
Related drawing has been sent to the Director of Urban Development for approval |
KHOWAI DISTRICT |
3 |
Khowai Division |
Construction of Nagar Panchayet at Khowai, West Tripura/SH: Building portion including internal water supply and sanitary installations. |
244.39 |
Deposit |
2014-15 |
130.00 |
December, 2015. |
Work in finishing Stage. |
SOUTH DISTRICT |
4 |
Sabroom Division |
Construction of Nagar Panchayet at Sabroom, South Tripura/SH: Building portion including internal water supply and sanitary installations. |
239.54 |
Deposit |
2014-15 |
170.00 |
Completed |
Work completed and handed over |
5 |
Santirbazar Division |
Construction of Nagar Panchayat Office Building at Santirbazar, South Tripura/SH: Building portion including internal water supply & Sanitary installation. |
317.21 |
--- |
2014-15 |
---- |
---- |
A/A & E/S awaited. |
UNAKOTI DISTRICT |
6 |
Kailashahar Division |
Construction of Nagar Panchayet at Kailashahar North Tripura /SH: Building portion including internal water supply and sanitary installations. |
150.54 |
---- |
--- |
213.46 |
Dec., 2015 |
Work completed and handed over. |
7 |
Kumarghat Division |
Construction of Nagar Panchayet at Kumarghat, North Tripura /SH: Building portion including internal water supply and sanitary installations. |
242.49 |
Deposit |
---- |
164.00 |
Deceber, 2015 |
Work Completed. |
North Eastern Council (NEC)
North Eastern Council (NEC)
Published: January 19, 2021
(In Lakhs) |
SL. No. |
Division |
Name of Works |
Sanction Cost |
Scheme/ Head |
Year of Sanctioned |
Total Fund Released |
Target Date of Completion |
Status of Physical implementation/Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
DHALAI DISTRICT |
SHEPAHIJALA DISTRICT |
1 |
Bishalgarh Division |
Bishalgarh - Boxanagar - Sonamura - Barpathari - Belonia Road (Revised estimate for `251.02 crore sent during 2013-14) |
19597.00 |
NEC |
2010-11 |
19483.32 |
March, 2016. |
F : 86.63 Km. GSB : 86.63 Km. WMM: 85.28 Km DBM: 85.07 Km PMC: 60.00 Km RW:Completed Drain: Completed CD: Completed Br :6 Nos. completed 1 No. in progress. |
Revenue Department
Published: January 19, 2021
(In Lakhs) |
SL. No. |
Division |
Name of Works |
Sanction Cost |
Scheme/ Head |
Year of Sanctioned |
Total Fund Released |
Target Date of Completion |
Status of Physical implementation/Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
KHOWAI DISTRICT |
1 |
Khowai Division |
Construction of office building for DM & Collector at Khowai, Khowai District, Tripura (Ground floor and part of First floor only, Phase-I) |
2420.00 |
SPA, Tide |
2015-16 |
|
|
A/A & E/S received. DNIT is being prepared. |
2 |
Construction of composite office building of the DM & Collector, Khowai District. |
1950.73 |
|
|
|
|
Preliminary estimate sent to concerned Deptt. for A/A & E/S. |
SEPAHIJALA DISTRICT |
3 |
Sonamura Division |
SDM office at Sonamura, Sonamura Sub-Division. |
1977.00
|
SPA, Tide |
2015-16 |
|
|
Preliminary cost estimate processed to concerned Department for according A/A & E/S. |
4 |
Bishramganj Division |
Construction of office building for DM & Collector at Bishramganj. |
2420.00 |
---- |
2015-16 |
---- |
----- |
Preliminary cost estimate processed to concerned Department for according A/A & E/S. |
NORTH DISTRICT :- |
5 |
Dharmanagar Division |
Construction of office building for DM & Collector at Dharmanagar. |
2420.00 |
|
2015-16 |
|
|
Preliminary cost estimate processed to concerned Department for according A/A & E/S. |
State Forensic Science Laboratory
State Forensic Science Laboratory
Published: January 19, 2021
(In Lakhs) |
SL. No. |
Division |
Name of Works |
Sanction Cost |
Scheme /Head |
Year of Sanctioned |
Total Fund Released |
Target Date of Completion |
Status of Physical implementation/Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
WEST DISTRICT |
1 |
Mohanpur Division |
Proposed extension of Forensic Science Laboratory building at Narsingarh, West Tripura. |
229.95 |
--- |
2015-16 |
--- |
--- |
Estimate processed to concerned Deptt. for A/A & E/S. Sanction of A/A & E/S awaited. However, DNIT is under preparation for Ground Floor only. |
Tourism Department
Published: April 11, 2021
Sl. No. |
Division |
Name of work |
Scheme |
Project Cost |
Value of Expenditure Sanction |
Tendered Value |
Date of commencement as per work order |
Fund received |
UC submitted |
Further fund required during 2020-21 |
Further fund required during 2021-22 |
Physical progress of work |
Target date of completion |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Sonamura |
Development of works at Melaghar and Neer Mahal (Access point), Sepahijala District under Swadesh Darshan Scheme. |
Swadesh Darshan |
340.00 |
340.00 |
317.09 |
19-03-2019 |
356.00 |
160.00 |
0.00 |
0.00 |
57% |
Agreement closed. Tender for balance work will be called. |
2 |
Divn-III |
Constn of Conf Block, Wayside aminities (Cafeteria) i/c site development at Border Ceremony facility at Akhaura, Agartala. |
Swadesh Darshan |
475.65 |
475.65 |
383.00 |
December, 2016 |
423.65 |
353.00 |
0.00 |
0.00 |
90% |
Oct.21 |
3 |
Divn-I |
Constn of Covered Gallery with Barrack, Toilet block, Gate & Site development & Border Ceremony facility, Akhaura, Agartala. |
Swadesh Darshan |
354.43 |
354.43 |
395.72 |
17/06/2020 |
476.43 |
0.00 |
0.00 |
0.00 |
Work started |
May.22 |
4 |
Udaipur |
Proposed Water Front development of Jagannath Dighi, Udaipur. |
Swadesh Darshan |
300.00 |
300.00 |
264.00 |
|
300.00 |
180.00 |
0.00 |
0.00 |
85% |
Apl.21 |
|
|
|
TOTAL |
|
1470.08 |
|
|
|
1556.08 |
693.00 |
0.00 |
0.00 |
|
YOUTH AFFAIRS AND SPORTS DEPARTMENT
YOUTH AFFAIRS AND SPORTS DEPARTMENT
Published: January 19, 2021
STATUS OF WORK UNDER YOUTH AFFAIRS AND SPORTS DEPARTMENT |
|
(Rupees In lakhs |
Sl. No. |
Division |
Name of work |
Sanction cost |
Scheme |
Year of sanction |
Total fund released |
Target date of completion |
Status of physical implementation / remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
1 |
Agartala Div. no.III |
Construction of Sports Building for different activities like Judo, Weight lifting, Yoga, Table Tennis & Indoor Batminton Court at NSRCC. |
1424.00 |
ACA |
2012-13 |
1242.62 |
Completed |
100% |
2 |
Agartala Div. no.III |
Upgradation of Netaji Subhash Regional Coaching Centre [NSRCC], Agartala, Tripura Construction of Badminton Hall. |
Deposit |
2013-14 |
100% |
|
|
TOTAL |
1424.00 |
|
|
1242.62 |
|
|
Miscellaneous Works
Published: January 19, 2021
(In Lakhs) |
SL. No. |
Division |
Name of Works |
Sanction Cost |
Scheme /Head |
Year of Sanctioned |
Total Fund Released |
Target Date of Completion |
Status of Physical implementation/Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
DHALAI DISTRICT :- |
1 |
Ambassa Division |
Infrastructural Development of Gandacherra Sub-Division, Dhalai District / Construction of Revenue Dak Bungalow. |
3235.00 |
SCA, Un-tied |
2015-16 |
---- |
May,2017. |
No tender received in 1st call. 2nd call of tender is under process. |
2 |
Infrastructural Development of Gandacherra Sub-Division, Dhalai District / 1000 seated capacity Auditorium. |
--- |
Tender accepted. |
3 |
Infrastructural Development of Gandacherra Sub-Division, Dhalai District / Construction of Staff Quarters 36 nos. [Type-I G+2: 348 sqm (6 nos.), Type-II-g+2: 840 sqm (12 nos.), type-III-G+2: 1008 sqm (12 nos.), T-IV-G+2: 558.60 sqm (6 nos.)]. |
---- |
Tender accepted. |
4 |
Infrastructural Development of Gandacherra Sub-Division, Dhalai District /Construction of Police Station. |
---- |
Site finalised. Tender will be called soon. |
WEST DISTRICT :- |
5 |
Mohanpur Division |
Modernization of State Poultry Farm with Automated layer unit at Gandhigram, West Tripura under NEC scheme during the year 2015-16. |
489.00 |
--- |
2015-16 |
--- |
---- |
Preliminary estimate processed to concerned Department on 20-05-2017 for according A/A & E/S.. |
6 |
Proposed construction of double storied School building for Mohanpur H.S. School at Mohanpur, West Tripura. |
812.00 |
--- |
2017-18 |
--- |
--- |
Preliminary estimate processed to concerned Department on 03-05-2017 for according A/A & E/S. |
7 |
Development of Playground at Mohanpur School, West Tripura. |
----- |
--- |
2017-18 |
--- |
--- |
Preliminary drawing is under process by Sr. Architect. |
Admistrative department
Published: September 09, 2020
(In Lakhs) |
SL. No. |
Division |
Name of Works |
Sanction Cost |
Scheme |
Year of Sanctioned |
Total Fund Released |
Target date of Completion |
Status of Physical implementation/Remarks |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
NORTH DISTRICT |
1 |
Dharmanagar Division |
Extension of Circuit House at Dharmanagar, North Tripura during the year 2013-2014." |
759.05 |
SPA |
2014-15 |
100.00 |
Jan, 2018. |
Finishing work is in progress. |
DHALAI DISTRICT |
2 |
Ambassa Division |
Construction of New Forest Rest House adjacent to Ambassa – Kamalpur Road under Ambassa Forest Division, Ambassa, Dhalai, Tripura/SH: Building portion including internal water supply and sanitary installation. |
519.08 |
State Plan |
2012-13 |
464.00 |
Completed |
Work completed and ready for handed over. |
|