Projects

Administrative Department

(In Lakhs)
SL. No.DivisionName of WorksSanction CostSchemeYear of SanctionedTotal Fund ReleasedTarget date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
SOUTH DISTRICT:-
1 Santirbazar Division Proposed Construction of Community Hall at Birchandra Manu Sahid Smriti Complex at Birchandra Manu, Santirbazar, South Tripura under MPLADS (Rajya Sabha)/SH: Construction of Lower Ground Floor only (Phase-I) /Building portion including internal water supply and sanitary installation. 173.00 MPLADS (Rajya Sabha) 2015-16   ---- Foundation work started.
NORTH DISTRICT
1 Dharmanagar Division Extension of Circuit House at Dharmanagar, North Tripura during the year 2013-2014." 759.05 SPA 2014-15 100.00 Jan, 2018. Finishing work is in progress.
DHALAI DISTRICT
1 Ambassa Division Construction of New Forest Rest House adjacent to Ambassa – Kamalpur Road under Ambassa Forest Division, Ambassa, Dhalai, Tripura/SH: Building portion including internal water supply and sanitary installation. 519.08 State Plan 2012-13 464.00 Completed Work Completed
KHOWAI DISTRICT
1 Khowai Division Proposed construction of Circuit House (G+2) storied at Khowai. 530.00 --- 2016-17 --- --- Preliminary estimate amount to Rs.530.00 lakhs sent to the concerned deptt. for according A/A & E/S on 03-06-2016.

Animal Resource Development Department (ARDD)

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme /HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
WEST DISTRICT
1 Jirania Division College of Veterinary Sciences and Animal Husbandry at R.K.Nagar, West Tripura /SH. Construction of 2(Two) Nos Hostel Building for Boys & Girls (1st Phase- G+1)/Building Portion including internal water supply and sanitary installation. 827.05 ARDD 2012-13 250.00 August, 2017 Work almost completed to make it handed over..
2 College of Veterinary Sciences and Animal Husbandry at R.K.Nagar, West Tripura [3rd Phase]/SH. Vertical Extension of Academic Block (Remaining portion-3rd & part of 4th floor). 710.00 ARDD 2015-16 --- ---- Preliminary estimate sent to concerned Deptt. for A/A & E/S.

Border Area Development Programme (BADP)

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme/ HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
DHALAI DISTRICT
1 Ambassa Division (i) Road from Ratan Nagar Market to IBB Road via S K Para BOP under Gandacherra Sub-division (L=6.00 KM).
(ii) Road from Ratan Nagar Market to IBB Road via S K Para BOP under Gandacherra Sub-division (L=4.00 KM).
1097.00 BRDP ---- 1097.00 March, 2016. Formation =10.56 km, GSB=8.56 km, Retaining wall=279.10 Mtr, CD=13 nos completed.
Target date of completion: March'16
2 Additional link Road from Boalkhali to Maharaja-I (L=7.35 km) 810.00 BRDP ---- 810.00 March, 2016.

Formation =7.35 km, GSB=5.00 km, Metalling=4.50 km, Retaining wall=88.00 Mtr, Box Cell=2 No completed.

Target date of completion: March-16

Clinical Research Finance-Sponsored Projects Administration(CRF-SPA )

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme/ HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
WEST DISTRICT
1 --- Improvement and upgradation of road from Chandrapur to Chaturdash Devta Temple via Baldakhal(L=3.831 km) 646.50 --- --- --- --- Work yet to be started.
GOMOTI DISTRICT
1 Amarpur Division Improvement of road leading to newly constructed Sub divisional H.Q. Karbok/ portion from Amarpur to Karbook/ Silachari (l=25.50 km) (beyond the protion upgrade from (PMGSY) under SPA-tide 2415.00 -- -- -- March, 2016. Work completed for 18 km. Work in progress for balance work.

Centrally Sponsored Scheme(CSS)

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme/ HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
WEST DISTRICT
1 Agartala Division No-I, Agartala Construction of RCC covered drain from ICP main gate upto Zero Point at Indo-Bangladesh Border over Akhaura Khal (L=130.00 mtr.) 200.89 CSS ---- ---- March, 2017. Tender just received
2 Imp. upgradation of the approach road from Fire Bridge Chowmuhani to Agartala Land Custom station by providing RCC covered drain/covering of existing drain to the RCC Box cell along Akhaura road. 387.43 CSS ---- 500.00 March, 2017. Foundation work of drain in progress. Formation work is in progress.10% completed.
3 Development of road in front of ICP, Agartala upto Zero Point at Indo-Bangladesh Border at Akhaura (L=324.85 mtr) 144.31 CSS ---- --- March, 2017. Tender invited

Economic & Importance (E & I PROJECT)

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme/ HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
SOUTH DISTRICT
1 --- Improvement of road from NH-44 junction at Udaipur (District Head Quarter) to Amarpur Sub-divisional Head Quarter (24.96 km)/ Portion from Maharai to Amarpur, Length- 16.080 km (Ch: 8.80 km to 24.960 km) (Job No.-EI-TR-2011-12-03) 2122.26 E & I Project. --- ---- ---- Road work completed
Bridge: completed
CD: completed
R/W: 153.00 M
Road side drain: 8682 M.
Maintenance work for the defect portion has been completed by the agency(M/s GPT Infrastructure Pvt. Ltd.).

 

Fire Service Department

 

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme /HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
DHALAI DISTRICT
1 Kamalpur Division Construction of Permanent building for Kamalpur Fire Station, Kamalpur, Dhalai, Tripura /SH: Building portion including internal water supply and sanitary installations. 152.18 State Plan 2014-15 50.00 Completed Completed and ready for handed over.
Inauguration date fixed on 23-05-2016.
2 Ambassa Division Construction of Ambassa Fire Service Station, Dhalai, Tripura/SH: Building portion including internal water supply and sanitary installations. 134.84 State Plan 2014-15 78.01 ---

Finishing work in progress..

3 Proposed permanent functional building for Raishyabari Fire Station at Dhalai District, Tripura. 176.97 State Plan 2015-16 --- --- Detailed Preliminary Estimate processed for according A/A & E/S.
SEPAHIJALA DISTRICT
1 Sonamura Division Construction of Permanent functional building of Kathalia Fire Station under Sonamura Sub-division /SH: Building portion including internal water supply and sanitary installations. 169.16 NEC 2013-14 ---- Completed Work completed and handed over.
2 Permanent functional building for Melaghar Fire Station at Melaghar, Sonamura, Sepahijala District, Tripura. 102.53 SCA (un-tied) 2014-15 131.46 Dec., 2016. Work completed .
3 Proposed construction of 6 nos. Type-II staff quarters including boundary wall at Kathalia Fire Service station. 145.00 State Plan 2015-16. ---- --- Preliminary estimate processed to concerned Deptt. for A/A & E/S.
4 Bishramganj Division Construction of Permanent functional building of Bishramganj Fire Station, Bishramganj, Sepahijala District, Tripura /SH: Building portion including internal water supply and sanitary installations. 153.90 Deposit 2014-15 142.94 August, 2016 Work completed and handed over.
WEST DISTRICT
1 Mohanpur Division Proposed Permanent Functional Building for Mohanpur Fire Station/SH: Building portion including an under ground Tank, internal water supply and sanitary installation. 154.26 State Plan 2014-15 100.00 Sep, 2017 Finishing work in progress
SOUTH DISTRICT
1 Belonia Division Construction of Permanent functional building of Belonia Fire Station, Belonia, South Tripura /SH: Building portion including internal water supply and sanitary installations. 191.51 --- 2015-16 --- --- Preliminary estimate processed to concerned Department for according A/A & E/S.
2 Proposed permanent functional building for Hrishyamukh Fire Station at Belonia, South Tripura District. 176.97 --- 2015-16 --- --- Detailed Preliminary Estimate processed for according A/A & E/S.
3 Sabroom Division Proposed permanent functional building for Manubazar Fire Station at Sabroom, South Tripura District. 176.97 --- 2015-16 --- --- Detailed Preliminary Estimate processed for according A/A & E/S.
NORTH DISTRICT
1 Kanchanpur Division Construction of Permanent functional building of Kanchanpur Fire Station, Kanchanpur, North Tripura /SH: Building portion including internal water supply and sanitary installations. 152.02 State Plan 2013-14 199.58 Completed Completed & Handed Over.
2 Fire Station Station at Damcherra. 191.51   2016-17 --- --- Preliminary estimate processed to concerned Department for according A/A & E/S.
3 Fire Station Station at Jampui Hill. ---   2016-17 --- -- Architectural drawing is under preparation.
UNOKOTI DISTRICT
1 Kumarghat Division Fire Station Station at Petcharthal. ---   2016-17 --- --- Architectural drawing is under preparation.

Food & Consumer Affairs Department

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme/ HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
WEST DISTRICT
1 Jirania Division Construction of 2(two) nos. 5000 MT capacity Food Godown internal road at Inter State Truck Terminus, Madhavbari, Jirania, West. 1007.00 CSS 2012-13 1008.59 August, 2017.

Work completed and handed over.Road carpeting work is in progress.

2 Agartala Division No-V, Agartala Construction of double storied Office Building at Central Stores (Food, Civil Supplies & Consumer Affairs Deptt.) at A.D. Nagar, West Tripura/SH: Building portion including internal water supply and sanitary installation. 224.51 NLCPR 2014-15 25.00 March, 2017. Upto 1st floor completed.
3 Agartala Division No-III, Agartala Proposed Vertical extension at 4th floor of Khadya-O-Bhokta Bhavan at Gurkhabasti, Agartala, Tripura excluding lift for permanent accommodation of State Consumer Disputes Redressal Commission (State Commission) & West Tripura, District Consumer Disputes Redressal Forum /SH: Building portion including internal water supply and sanitary installation. 479.00 "Strenthing of Consumer Forum" 2015-16 369.00 August, 2017. Structural work 50% completed.
NORTH DISTRICT
1 Dharmanagar Division Construction of double storied Office Building for Dy. Director of Food at Dharmanagar, North Tripura /SH: Building portion including internal water supply and sanitary installation. 224.51 State Plan 2014-15 90.00 Jan 2018 Finishing work in progress.
GOMOTI DISTRICT
1 Amarpur Division Constn. of 1000 MT capacity go-down at Jatanbari (Now at Karbook) 96.00 CSS 2013-14 73.66 Completed

Main go-down completed and handed over / innaugarated.

Boundary wall will be started after obtaining necessary sanction.

Fisharies Department

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme/ HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
NORTH DISTRICT
1 Dharmanagar Division Construction of Fish Farmers Training Centre (G+2) with accommodation facilities for faculty members at Superintendent of Fisheries Office Complex, Dharmanagar, North Tripura/SH: Building portion including internal water supply and sanitary installations. 263.61 --- 2015-16 --- ---

Preliminary cost estimate issued for according A/A & E/S.Draft NIT for GF on Rs.100.00 lakhs only.

.
SOUTH DISTRICT
1 Dharmanagar Division Construction of Fish Market at Santirbazar under Santirbazar Municipal Council under Special Central Assistance (SCA- Untied) during the year 2015-2016 (Ground Floor only - Phase – I). 126.00 --- 2015-16 --- ---

DNIT issued for calling tender.

Handloom Department

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme/ HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
WEST DISTRICT
1 Agartala Division No-III, Agartala Proposed construction of Godown, Office & Dormitory (Second Phase Development) at THHDC Complex, Purbasha, Agartala, West Tripura.. 1048.00 -- 2015-16 135.00 --- Test pile in progress..

Health Department

.
(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme /HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
Primary Health Centres
NORTH DISTRICT :-
1 Kanchanpur Divison Construction of 10 bedded PHC (single storey) at Gachirampara, Kanchanpur, North Tripura including quarters. 630.00 RIDF 2012-13 586.00 August, 2016. Work Completed
2 Construction of 10 nos quarters (Type-III: 2 nos, Type -II: 4 nos, Type-I: 4 nos) at Laljuiri PHC, Kanchanpur, North Tripura under RIDF-XVIII during the year 2012-2013/ SH: Building portion including internal water supply and sanitary installation. 221.46 IMR(13th FC) 2012-13 141.65 December, 2017.

Type-I, II & III Qtr:- Finishing work in progress.

3 Construction of Kanchanpur Sub-Divisional Hospital, North Tripura. 1924.34 ACA/SPA 2012-13 1818.97 August, 2016.

Work completed and handed over Inaugurated.

.
4 Construction of 16 nos. staff quarters for 100 bedded Sub-Divisional Hospital at Kanchanpur [ Type-I = 04 nos.,  Type-II = 04 nos.,  Type-III = 04 nos. &  Type-IV = 04 nos. ] 406.00 Infant Mortality Grant 2012-13 1818.97 Apl.2019

Foundation work in progress.

5 Dharmanagar Division Construction of 20 bedded PHC at Tilthai under Dharmanagar Sub-Division, North Tripura. 405.00 NHM 2015-16 385.00 Dec2018

Renovation works for shifting the existing PHC is in progress.

6 Construction of 10 bedded PHC with quarters at Rajnagar under Juvarajnagar, Block, Dharmanagar Sub-Division, North District. 399.00 NHM 2016-17 100 --- Work upto plinth level.
7 Construction of 10 nos. staff quarters at Jalebassa PHC [ Type-I = 04 nos.,  Type-II = 04 nos.,  Type-III = 02 nos. ] 225.00 NHM 2016-17 100 Nov2018 Foundation work started for Type-II & III Quarter.
8 Up-gradation of Panisagar CHC to 50 bedded Sub-Divisional Hospital including staff quarters. 1517.00 NHM 2014-15 50 --- Tender received and under scrutiny.
9 Proposed construction of 12(Twelve) nos. Staff quarters {Type-III -6 nos and Type-IV - 6 nos) } at Dharmangar Sub-Divisional Hospital Complex. 246.39 IMR -
13th FC
2015-16 350 Mar.2018

Type-III= Work completed upto ground floor lintel level.Type-IV=Foundation work in progress

10 Construction of District Warehouse at Dharmanagar, North Tripura. 250 -- 2016-17 --- --- Tender received and under scrutiny.
11 Capacity Building for Developing Trauma Care  Facilities in Government Hospitals in National Highway under 12th Five Year Plan/ SH: Proposed Construction of Single storied Building for Trauma Care Centre (Level-III) in the North District Hospital at Dharmanagar. 390 NHM 2017-18 --- ---

DNIT issued for calling of tender.

UNAKOTI DISTRICT :-
1 Kailashahar Division Construction of Primary Health Centre at Bhaterbazar including Quarter. 630.00 NHM 2012-13 477.50 Completed Work completed and handed over.
2 Construction of 10 bedded PHC at Muraibari, Kailashahar, North Tripura including quarters. 630.00 NHM 2012-13 535.00 Completed Work completed and Hundred Over.
3 Construction of New 10 nos. staff quarters (Type-I-4, Type-II-4 & Type-III-2) at Irani under Gournagar block, Kailashahar Sub-Division, Unakoti District, Tripura. 225.00 IMR -
13th FC
2015-16 225.00 Jul2018. Type-I = Plinth level.
Type-II = Work upto 1st floor slab level.
Type-III= Not yet started
4 Proposed construction of District Training Centre at Kailashahar, Unakoti District, Tripura. 597.40 IMR 2015-16 597.40 Oct 2019

Work order issued. Modified drawing yet to receive.New site selected.

Land levelling completed.

5 Infrastructure Development of North District Hospital at Kailashahar, North Tripura/ Construction of Staff Quarters & Development of Site including Internal Roads. Total 40 (Forty) Quarters [Type-IV-6 Nos., Type-III-12 Nos., Type-II-10 Nos. & Type-I-12 Nos./SH: Construction of Type - IV quarter 1(one) Block [Twin three storied, 6(six) units], Type - III quarter 2(two) Block [Twin three storied, 12(twelve) units] , Type - II quarter 1(one) Block [Twin three storied, 6(six) units], Type - II quarter 1(one) Block [Twin double storied, 4(four) units] & Type - I quarter 2(two) Block [Twin three storied, 12(twelve) units]/Building portion including internal water supply and sanitary installations. 815.97 State Plan(NABARD) 2010-11 728.36 Completed Work completed and handed over.
6 Construction of North District Hospital ( Now Unakoti District Hospital at Bhagabannagar, Kailashahar, Unakoti District ), Phase-II (Hospital Quarters) in Tripura under NLCPR Scheme / SH: Construction of 48 ( forty eight ) Nos. Staff quarters (i) Type -I- quarter - 12 Units [ 02(two) Blocks - Double storied (GF + Part of FF) ], (ii) Type -II- quarter - 12 Units [ 02(two) Blocks - Double storied (GF + Part of FF) ],  (iii) Type -III- quarter - 12 Units [ 02(two) Blocks - Double storied (GF + Part of FF) ] and  (iv) Type -IV- quarter - 12 Units [ 02(two) Blocks - Double storied (GF + Part of FF) ] 1110.05 NLCPR 2017-18 ---- ----- e-Tender called.
6 Kumarghat Division Construction of 10 bedded PHC at Rajkandi, Kumarghat, North Tripura including quarters. 630.00 NHM 2012-13 427.5

Oct,2016.

PHC= Finishing work in progress.

Type-I qtr. = Work completed.

Type-II = Roof slab cated. Type- III qtr= Work upto lintel level

7 Construction of 10 bedded PHC at Santipur, Kumarghat Sub-Division, Kumarghat Block, Unakoti District, Tripura. 540.00 RIDF-XX 2014-15 145.8 April 2019 Foundation work started.
8 Up-gradation of Kumarghat CHC to 50 bedded Sub-Divisional Hospital. 2047.00 RDF 2015-16 --- Sep2019 Work order issued. Dismantaling work started.
9 Construction of 10 bedded PHC at including 10 Nos. quarters at Krishnatilla, Pecharthal Block, Unakoti District, Tripura. 540.00 SPA 2014-15 340.00 Completed Completed and handed over.
10 Construction of 10 bedded PHC building at existing Pecharthal, Kumarghat.. 210 NHM 2017-18 --- --- Tender invited.
11 Construction of 10 nos. staff quarters at Pecharthal PHC [ Type-I = 04 nos.,  Type-II = 04 nos.,  Type-III = 02 nos. ] 225.00 NHM 2017-18 --- ---- Site development is in progress.
12 Proposed construction of new single storied 10 (ten) bedded Primary Health Centre (PHC) building including 10 (ten) Nos. staff quarters (Type-I-04 Units, Type-II-04 Units and Type-III-02 Units], Kitchen, Morgue, Garage & Generator with Driver room building at Fatikroy PHC, Kumarghat Sub-Division, Unakoti District, Tripura under NHM Supplementary Programme Implementation Plan (SPIP) for 2017-18. 458 NHM 2017-18 --- ---- DPR sent to concerned deptt. for A/A & E/S.
DHALAI DISTRICT :-
1 L.T. Valley Divison Construction of Primary Health Centre at Lalchara including Quarter. 630.00 NHM 2012-13 427.50 Completed Work completed and handed over, approach road is in progress. Boundary wall essential
2 Construction of Primary Health Centre at Masli including Quarter. 630.00 NHM 2012-13. 476.37 Completed Work completed and handed over.
3 Proposed construction of Type-I quarter (Twin double storeyed-4 units), Type-II quarter (twin double storeyed-4 units), Type-III quarter (Twin single storeyed-2 units) at Manikpur PHC, Chawmanu Block, Dhalai, Tripura under State Plan (NABARD) during the year 2011-12/SH: Building portion including internal water supply and sanitary installation. 189.41 NHM --- 178.89 Oct, 2016

Finishing work in progress.

4 Construction of 10 nos quarters (Type-III: 2 nos, Type -II: 4 nos, Type-I: 4 nos) at 23-KM PHC, L.T. Valley, Dhalai Tripura under RIDF-XVIII during the year 2012-2013/ SH: Building portion including internal water supply and sanitary installation. 221.46 RIDF-XVIII 2012-13 207.61 ---

Tender invited (4th call)

 

 

5 Ambassa Divison Proposed construction of District Training Centre at Kulai, Dhalai District, Tripura. 597.40 IMR 2015-16 --- April2019 Foundation work started.
6 Infrastructure Development of Dhalai District Hospital at Kulai, Ambassa, Dhalai, Tripura/ Construction of Staff Quarters & Development of Site including Internal Roads. Total 40 (Forty) Quarters [Type-IV-6 Nos., Type-III-12 Nos., Type-II-10 Nos. & Type-I-12 Nos./SH: Construction of Type - IV quarter 1(one) Block [Twin three storied, 6(six) units], Type - III quarter 2(two) Block [Twin three storied, 12(twelve) units] , Type - II quarter 1(one) Block [Twin three storied, 6(six) units], Type - II quarter 1(one) Block [Twin double storied, 4(four) units] & Type - I quarter 2(two) Block [Twin three storied, 12(twelve) units]. 800.43 RDF 2010-11 550.15 ---- Work almost completed and ready for handed over.
7 Construction of New 10 nos. staff quarters (Type-I-4, Type-II-4 & Type-III-2) at Ambassa under Ambassa block, Ambassa Sub-Division, Dhalai District, Tripura. 225.00 IMR -
13th FC
2015-16 --- Dec.2018. Foundation work started.
8 Re-construction of Ganganagar PHC under Ganganagar block, Ambassa Sub-Division, Dhalai District, Tripura. 178.00 NHM/IMR 2015-16 --- ---

Foundation work in progress.

9 Construction of 10 nos. quarter at Hatimatha PHC, Gandacherra, Dhalai, Tripura. 172.80 SPA/ACA 2012-13 540.00 completed Work completed and handed over.
9 Construction of 40 nos. Staff Quarters for Dhalai District Hospital at Kulai, Ambassa, Dhalai, Tripura 631.87 RIDF 2010-11 550.15 completed Work completed and handed over.
9 .Proposed construction of staff quarter 09 nos. [Type-I=04 nos. and Type-III = 01 nos.] for Raishyabari PHC, Gandacherra. 179.44 ---- 2016-17 --- Nov 2018 Work order issued.
9 Proposed construction of staff quarter [8 nos.] (Type-I=04 nos. & Type-II=04 nos.) for Ganganagar PHC, Ambassa Sub-division, Dhalai District, Tripura.  156.87 NHM/IMR 2016-17 42.50 completed Tender accepted.
9 Construction of 10 bedded PHC including 10 nos. staff quarter at Kalajari, Gandacherra, Dhalai Tripura. 486.00 NHM 2017-18 ---- ---- e-Tender invited.
9 Construction of Dhalai District Hospital, Phase-II ( Hospital Quarters ) at  Kulai, Ambassa, Tripura under NLCPR Scheme  / SH: Construction of 48 ( forty eight ) Nos. Staff quarters (i) Type -I- quarter - 12 Units [ 02(two) Blocks - Double storied (GF + Part of FF) ], (ii) Type -II- quarter - 12 Units [ 02(two) Blocks - Double storied (GF + Part of FF) ],  (iii) Type -III- quarter - 12 Units [ 02(two) Blocks - Double storied (GF + Part of FF) ] and  (iv) Type -IV- quarter - 12 Units [ 02(two) Blocks - Double storied (GF + Part of FF) ].. 1131.85 NLCPR 2017-18 ---- ---- Tender received and under scrutiny.
1 Kamalpur Division Proposed construction of new single storied 10 (ten) bedded Primary Health Centre (PHC) building including 10 (ten) Nos. staff quarters (Type-I-04 Units, Type-II-04 Units and Type-III-02 Units], Kitchen, Morgue, Garage & Generator with Driver room building at Nakashipara PHC, Kamalpur Sub- Division, Dhalai District, Tripura under NHM Supplementary Programme Implementation Plan (SPIP) for 2017-18. 458.00 NHM 2017-18 ----- -----. DPR sent to concerned deptt. for A/A & E/S.
WEST DISTRICT :-
1 Mohanpur Divison Construction of 10 bedded PHC at Lefunga. including 10 nos. staff quarters including Morgue, Kitchen, Boundary wall etc. at Lefunga, Mohanpur Sub-Division, West Tripura. 597.63 NHM 2014-15 150.00 Completed. Work upto lintel level in progress.
2 Re-construction of 10(ten) bedded Bamutia PHC under Bamutia block, Mohanpur Sub- Division, West Tripura 173.00 NHM 2015-16 102.50 Dec 2017.

Finishing work in progress

3 Construction of New 10 nos. staff quarters (Type-I-4, Type-II-4 & Type-III-2) at Narshingarh under Bamutia block, Mohanpur Sub-Division, West Tripura. 225.00 IMR -
13th FC
2015-16 --- March2018 Type-I=1st floor completed.
Type-II= 1st floor roof ready for casting.
Type-III= Foundation work in progress.
9 Construction of 10 bedded PHC building at existing Katlamara, Mohanpur. 175.00 NHM 2017-18 ---- ---- e-Tender invited.
9 Construction of 10 nos. staff quarters at existing Katlamara PHC, Mohanpur 225 NHM 2017-18 ---- ---- e-Tender invited.
9 Construction of 10 nos quarters (Type-III: 2 nos, Type -II: 4 nos, Type-I: 4 nos) at Chachubazar PHC, Mohanpur, West Tripura under RIDF-XVIII during the year 2012-2013. 187.88 IMR/SP 2012-13 ---- ---- Work completed and handed over.
9 Proposed construction of 10 (ten) Nos. staff quarters (Type-I-04 Units, Type-II-04 Units and Type-III-02 Units] in the existing Bamutia Primary Health Centre (PHC) at Bamutia PHC under Mohanpur Sub-Division, West Tripura. 233 ----- 2017-18 ---- ---- DNIT issued for calling of tender.
1 Bishalgarh Division Re-construction of 10(ten) bedded Anandanagar PHC  under Dukli block, Sadar Sub- Division, West Tripura. 136.14 NHM/IMR 2015-16 -- Sep, 2018.

Dismantaling work started.20 bedded PHC work will be started soon.

7 Jirania Division Construction of 10 nos quarters (Type-III: 2 nos, Type -II: 4 nos, Type-I: 4 nos) at Champaknagar PHC, Jirania, West Tripura under RIDF-XVIII during the year 2012-2013/ SH: Building portion including internal water supply and sanitary installation. 221.46 RIDF-XVIII/NABARD 2012-13 141.67 NOov,2017. Finishing work in progress for Type-I & II.
8 Community Health Centre (CHC) to a 50 bedded Sub-Divisional Hospital at Jirania, West Tripura (Up-gradation). 2003.00 NEC 2015-16 --- --- Sanction awaited..
9 Medical College Division Construction of Office room and Drug Storage room for Central Medical Store, Shymalibazar, Agartala. 434.78 NHM  2015-16 100 Dec2018 Work started.
8 Construction of District Ware House at different District in Tripura namely, (i) South Tripura (ii) North Tripura (iii) Khowai (iv) Sepahijala (v) West Tripura District. 1250.60 NHM 2015-16 --- ---

Khowai tender accepted.

Others tender called.

8 Construction of District Medical stores for District Hospitals at (i) Santirbazar, (ii) Khowai, (iii) Kulai, (iv) Dharmanagar and (v) Bhagawannagar. 1782.20 IMR 2015-16 --- --- Preliminary estimate processed for according A/A & E/S.
8 Constrcution of 8(eight) nos. Type-V quarters for Chief Medical Officers at different Districts 46.10 for Each NHM 2016-17 --- ---

Bishramganj = Work upto plinth level.
Belonia = Work started.
Khowai = Work order issued.
Dharmanagar = Tender invited.
Dhalai = Land dispute.
West = Tender invited.
Gomati = Work order issued.

KHOWAI DISTRICT :-
1 Khowai Divison Construction of 10 nos quarters (Type-III: 2 nos, Type -II: 4 nos, Type-I: 4 nos) at Ampura PHC, Khowai District under RIDF-XVIII during the year 2012-2013/ SH: Building portion including internal water supply and sanitary installation. 221.46 IMR/SP 2012-13 141.67  

Type-I & II = Work upto lintel level.

2 Construction of 10 bedded Primary Health Centre with 10 nos. quarters (Type-I=4 nos. Type-II=4 nos. & Type-IIII=2 nos.) at Champahour, Khowai District, Tripura. 385.00 IMR -
13th FC
2015-16 385.00 Mar,2018.

Type-I = 1st floor roof casted.
Type-II = Ground floor roof casted.
Type-III = Ready for roof casting.

3 Construction of 10 nos quarters (Type-III: 2 nos, Type -II: 4 nos, Type-I: 4 nos) at Behalabari PHC, Khowai District under RIDF-XVIII during the year 2012-2013/ SH: Building portion including internal water supply and sanitary installation. 221.46 NABARD 2012-13 141.67 Dec, 2016. Type-I: Upto roof level completed.
Type-II : Finishing work in progress.
Type-III : Finishing work in progress.
4 Construction of 12 nos staff quarters (Type-III: 6 nos, Type -IV: 6 nos) at Khowai Sub-Divisional Hospital. 350.00 IMR -
13th FC
2015-16 --- Feb 2018

 Work is progress.

5 Re-construction of H.D. Smriti (Behelabari) PHC under Tukashikar block, Khowai Sub- Division, Khowai District, Tripura. 173.00 NHM 2015-16 42.50 Dec., 2017. Roof casted.
6 Construction of 10 bedded PHC building at existing Baijalbari, Khowai. 210 NHM 2017-18 ----- ------

   e-Tender invited.

7 Construction of 10 bedded PHC building at existing Tulashikar, Khowai. 210 NHM 2017-18 ---- -----

     e-Tender invited.

8 Construction of 10 bedded PHC building at existing Ampura PHC, Khowai. 210 NHM 2017-18 ---- ----

         e-Tender invited.

9 Construction of 10 nos. staff quarters at Baijalbari PHC [ Type-I = 04 nos.,  Type-II = 04 nos.,  Type-III = 02 nos. ] 225 NHM 2016-17 ---- June2018

Foundation work in progress.

10 Construction of District Warehouse at Khowai. 250.12 --- 2016-17 --- ----

Tender under evaluation.

11 Proposed construction of new single storied 10 (ten) bedded Primary Health Centre (PHC) building including 10 (ten) Nos. staff quarters (Type-I-04 Units, Type-II-04 Units and Type-III-02 Units], Kitchen, Morgue, Garage & Generator with Driver room building and Boundary wall at Asharambari, Khowai District, Tripura under NHM Supplementary Programme Implementation Plan (SPIP) for 2017-18. 486 NHM 2017-18 ---- -----

DNIT issued for calling of tender

12 Construction of single storied Eye ward and OT for Khowai Sub-Divisional Hospital. 137   2017-18    

DPR sent to concerned deptt. For according A/A & E/S.

7 Teliamura Divison Construction of 10 bedded PHC at Uttar Maharanipur including 10 nos. quarters under Mungiakami Block, Khowai District, Tripura. 540.00 SPA/SDS 2014-15 415.00 Nov., 2017. Finishing work in progress.
7 Construction of 10 bedded PHC at Durgapur alongwith 10 nos. quarters, Khowai Sub-Division, Kalyanpur Block, Khowai District, Tripura. 540.00 RIDF-XX 2014-15 145.8 Nov., 2017. Finishing work in progress
8 Construction of 10 bedded PHC at Mungiakami alongwith 10 nos. quarters, Teliamura Sub-Division, Khowai District. 540.00 NHM 2014-15 250.00 Nov., 2017. Work almost completed.
9 Proposed construction of  (i) New 30 (thirty) bedded Community Health Centre (CHC) building including Ramp [ GF + Part of FF ]  (ii) Kitchen  (iii) Morgue  and (iv) Garage & Generator with Driver room building at existing Kalyanpur CHC under Teliamura Sub-Division, Khowai District, Tripura under NHM Scheme during the year 2017-18. 872.00 --- 2016-17 --- --- Tender received and under scrutiny.
10 Construction of 24 nos. staff quarters for 100 bedded Sub-Divisional Hospital at Teliamura [ Type-I = 06 nos.,  Type-II = 06 nos.,  Type-III = 06 nos. &  Type-IV = 06 nos. ] 583.00 --- 2016-17 --- Aug 2019 Work order issued.
10 Construction of 10 bedded PHC including 10 nos. staff quarter at Duski, Teliamura. 486.00 NHM 2017-18     .e-Tender invited.
SEPAHIJALA DISTRICT :-
1 Sonamura Divison Proposed construction of 10 bedded PHC including 10 Nos. staff quarters with Morgue & Garrage building at Dhanpur, Sonamura, Sepahijala District, Tripura. 548.00 NHM 2014-15. 50.00 Completed 

Work completed and handed over.

Inaugurated.

2 Up-gradation of Sonamua CHC to 50 bedded Hospital, West Tripura. 1192.10 State Plan (SCA) 2011-12 750.00 Completed 

Work completed and handed over.

Inaugurated.

3 Proposed construction of 06 nos. staff quarters (Type-I=04 nos & Type-III=02 nos) at Kamalnagar PHC, Boxanagar Block, Sepahijala District, Tripura. 119.00 MSDP 2015-16 --- ---

Preliminary estimate processed to concerned Deptt. for A/A & E/S.

Sanction awaited.

4 Up- Gradation of Melaghar Sub- Divisional Hospital as First Referral Units (FRU) / Construction of new OPD Complex  and 10 (ten) Bedded Eye Ward with Eye OT building (G+1 storied) at Melaghar, Sonamura Sub-Division, Sepahijala District, Tripura under SPA (CASP) during the year 2016-17 615.00 SPA (CASP) 2016-17 --- Aug2019 Foundation work started.
5 Construction of 10 nos quarters (Type-III: 2 nos, Type -II: 4 nos, Type-I: 4 nos) at Jumerdhepa PHC, Sonamura, Sepahijala District, Tripura under RIDF-XVIII during the year 2012-2013/ SH: Building portion including internal water supply and sanitary installation. 221.46 RIDF-XVIII 2012-13

 

41.67

 

July2018 TWork completed upto plinth level for Type-I and Type-II quarter.
10 Construction of 10 bedded PHC building at existing Taibandal PHC, Sonamura. 210.00 NHM 2017-18              e-Tender invited.
10 Up-gradation of Boxanagar PHC to 30 bedded CHC at Boxanagar, Sepahijala District, Tripura. 644.00 MSDP 2015-16 159.84 Dec2018

50% of ground floor roof casted. Work in progress.Rs.65.60 lakhs revalidation required.

10 Proposed constrcution of 20 (twenty) nos. staff quarters (Type-II=08 nos, III=06 nos., IV-06 nos.) at Boxanagar CHC, Sonamura Sub-Division, Sepahijala District, Tripura. 686.00 NHM 2016-17     .DNIT under preparation.
10 Construction of 10 bedded PHC including 10 nos. staff quarters at Matinagar, Sonamura, Sepahijala District, Tripura. 394.00 MSDP 2015-16 177.60 Oct 2018

Foundation work started for hospital building.

Rs.177.60 lakhs revalidation required.

10 Construction of 10 nos. staff quarters at Taibandal PHC [ Type-I = 04 nos.,  Type-II = 04 nos.,  Type-III = 02 nos. ] 225.00 NHM 2016-17   Oct2018 Work Started
6 Bishalgarh Divison Construction of 10 bedded PHC including 10 nos. staff quarter at Durganagar, Bishalgarh. 486.00 NHM 2017-18 ---- ---- e-Tender invited.
7 Proposed construction of 06 nos. staff quarters (Type-I=04 nos & Type-III=02 nos) at Kanchanmala PHC, Dukli Block, West Tripura. 127.00 IMR -
13th FC
2015-16 127.00 completed Work completed and handed over.
10 Construction of 10 bedded PHC including Construction of Boys & Girls Hostel (15 seated each) at Madhupur under Sepahijala District, Tripura 808.00 NHM 2016-17 ---- ------      e-Tender invited.
10 Construction of 10 nos. Staff Qtr. PHC at Madhupur under Sepahijala District, Tripura. 235.00 NHM 2016-17 ----- ------ .Tender under evaluation.
10 Proposed construction of new single storied 10 (ten) bedded Primary Health Centre (PHC) building including 10 (ten) Nos. staff quarters (Type-I-04 Units, Type-II-04 Units and Type-III-02 Units], Kitchen, Morgue, Garage & Generator with Driver room building and Boundary wall at Champamura, Bishalgarh Sub-Division, Sepahijala District, Tripura under NHM Supplementary Programme Implementation Plan (SPIP) for 2017-18. 486.00 NHM 2017-18 ------ ------- DNIT issued for calling of tender.
  Bishramganj Division Construction of 10 bedded PHC with quarters at Lalsingmura (Shikhariabari), Bishramganj, West Tripura. 791.31 State Plan (SPA) 2013-14 450.00 Completed

Work completed and handed over.

Inaugurated.

9 Proposed construction of 06 nos. staff quarters (Type-II=04 nos & Type-III=02 nos) at Takarjala CHC, Jampuijala Sub-Division, Sepahijala District, Tripura. 142.00 IMR -
13th FC
2015-16 142.00 Nov 2017 Finishing work in progress.
10 Up-gradation of Briddhibazar PHC (under construction) to a 50 bedded Sub-Divisional Hospital at Jampuijala District, Sepahijala Tripura. 883.00 State Plan
(RIDF)
2015-16 576.00 Completed

Work completed and handed over.

Inaugurated.

11 50 bedded Sepahijala District Hospital at Bishramganj, Sepahijala District, Tripura. --- NLCPR 2015-16 --- --- Preparation of Architectural drawing is in progress. On hold.
12 Construction of 10 nos quarters (Type-III: 2 nos, Type -II: 4 nos, Type-I: 4 nos) at Dayarampara PHC, Sepahijala District, Tripura under RIDF-XVIII during the year 2012-2013/ SH: Building portion including internal water supply and sanitary installation. 221.46 IMR 2012-13 141.67 Completed

Work completed and handed over.

Inaugurated.

10 Proposed construction of (i) New 30 (thirty) bedded Community Health Centre (CHC) building including Ramp [ GF + Part of FF ]  (ii) Kitchen  (iii) Morgue  and (iv) Garage & Generator with Driver room building at existing Takarjala CHC under Jampuijala Sub-Division, Sepahijala District, Tripura under NHM Scheme during the year 2017-18. 670.00 NHM 2016-17 ------ ------ .Tender processed to WAB for acceptance.
10 Construction of District Warehouse at Bishramganj, Sepahijala District, Tripura. 250.00 ------ 2016-17 ------ ------ Work order issued.
10 Up-gradation of Briddhibazar PHC (under construction) to a 50 bedded Sub-Divisional Hospital at Jampuijala District, Sepahijala Tripura. 883.00 ----- 2015-16 ------ ------- Revised DPR sent to Ministry of Culture as considered for lump sum grant.Full sanction accorded.However, DNIT under preparation.
GOMATI DISTRICT :-
1 Udaipur Divison Re-construction of Maharani PHC under Matabari block, Udaipur Sub- Division, Gomati District, Tripura. 173.00 NHM 2015-16 42.50 July2018.

Foundation work completed. Work in progress.

2 Construction of 10 bedded PHC at Nityabazar under Udaipur Sub-Division, Killa Block, Gomati District, Tripura. 540.00 RIDF-XX 2014-15 1.030 August 2018 Foundation and column upto lintel level of PHC completed. Work in progress.
3 Construction of 10 bedded Primary Health Centre with 10 nos. quarters (Type-I=4 nos. Type-II=4 nos. & Type-IIII=2 nos.) at Adipur, Udaipur, Gomati District, Tripura. 385.00 IMR -
13th FC
2015-16 --- Sep 2018 Work suspended  long days but now it is to be started shortly.
4 Up-gradation of Kakraban PHC to CHC at Kakraban, Udaipur, Gomati District.Tripura. 420.00 Revenue Dep. 2015-16 120 August 2018

Foundation work is in progress.

5 Construction of New 10 nos. staff quarters (Type-I-4, Type-II-4 & Type-III-2) at Tulamura under Kakraban block, Udaipur Sub-Division, Gomati District, Tripura. 225.00 IMR -
13th FC
2015-16 --- Feb2019.

1Tender accepted. Work order issued.

6 Construction of 10 bedded PHC with quarters at Mirza under Kakraban Block Udaipur Sub-Division, Gomati District. 385 NHM 2016-17 --- Jan 2019 Foundation work is in progress
7 Proposed construction of District Training Centre at Udaipur, Gomati District, Tripura. 597.40 IMR 2015-16 ------ Sep, 2018. Top slab (middle part) completed of District Training Centre and foundation work completed of 50 seated hostel bld. Work is in progress
8 Construction of 10 nos quarters (Type-III: 2 nos, Type -II: 4 nos, Type-I: 4 nos) at Garjee PHC, Udaipur, Gomati District, Tripura under RIDF-XVIII during the year 2012-2013/ SH: Building portion including internal water supply and sanitary installation. 221.46 RIDF-XVIII 2012-13 141.00 Completed Work completed and handed over.
9 Construction of MCH wing at Gomati District Hospital, Tepania, Udaipur 797 NHM 2016-17 ---- --- e-Tender called.
10 Proposed construction of  48 ( forty eight ) Nos. Staff quarters in the Gomati District Hospital, Udaipur, Tripura under NLCPR / SH: Construction of  (i) Type -I- quarter - 12 Units [ 02(two) Blocks - Double storied (GF + Part of FF) ], (ii) Type -II- quarter - 12 Units [ 02(two) Blocks - Double storied (GF + Part of FF) ],  (iii) Type -III- quarter - 12 Units [ 02(two) Blocks - Double storied (GF + Part of FF) ] and  (iv) Type -IV- quarter - 12 Units [ 02(two) Blocks - Double storied (GF + Part of FF) ]  / ( Phase - II ). 968.00 NLCPR 2016-17 ----- Jul 2018 Foundation work started.
10 Constrcution of 6(six) nos. Type-V quarters for Medical Superintentent of District Hospital at Gomati, South, Khowai, Unakoti, Dhalai & North. 46.10 Each IMR 2016-17 --- ---- Dharmangar=Not required.
Khowai=Not required.
Dhalai=Not required.
Gomati=Not required.
10 Constrcution of Chief Medical Officer office at different location inTripura.
(i) South Tripura (Belonia) (ii) North Tripura (DMR) (iii) Sepahijala (BRG), (iv) Khowai & (v) Dhalai
438.40 IMR 2016-17 ---- ----- Dharmanagar = Tender invited.
Khowai = Sanction awaited.
Dhalai = Sanction awaited.
West = Sanction awaited.
Bishramganj = Work order issued.
Gomati = Sanction awaited.
Belonia = Work order issued.
10 Proposed construction of 10 (ten) Nos. staff quarters (Type-I-04 Units, Type-II-04 Units and Type-III-02 Units] in the existing Primary Health Centres (PHCs) at Maharani PHC, Udaipur Sub-Division, Gomati District, Tripura. 233.00 NHM 2017-18 ---- ---- DPR sent to concerned deptt. for A/A & E/S.
10 Capacity Building for Developing Trauma Care  Facilities in Government Hospitals in National Highway under 12th Five Year Plan/ SH: Proposed Construction of Single storied Building for Trauma Care Centre (Level-III) in the Gomati District Hospital at Tepania, Gomati District, Tripura. 390.00 NHM 2017-18 ---- ----- DNIT issued for calling of tender.
11 Amarpur Divison Proposed construction of 30 bedded CHC at Natunbazar, Amarpur Sub-Division, Gomati District, Tripura. 536.00 NHM 2015-16 --- June 2018

Foundation work is in progress.

12 Proposed construction of 10 bedded PHC building including 1o nos. staff quarters at Ghorakappa, Karbook, Gomati District, Tripura. 554-00 RIDF 2014-15 118.00 November, 2017 Finishing work completed  of main Hospital building . Work completed upto lintle level for  Constn. of 10 unit quarters
Type-III = structural part completed Type-II =  work is in progress upto top roof level.
Type-I=  work is in progress upto top roof level.    
13 Proposed construction of 10 bedded PHC at Taido. 597.17 ACA/SPA 2010-11 537.71 Completed  Work completed and handed over.

To be Inaugurated.

14 Up-gradation of Karbook CHC to 50 bedded Sub-Divisional Hospital Karbook. 1327.00 RIDF 2015-16 --- --- 2nd call e-Tender received and under scrutiny.
15 Construction of Primary Health Centre including 10 nos. staff quarters at Tirthamukh under Amarpur Sub-Division, Gomati District. 548.00 NHM 2014-15 ---- August 2018

Foundation work in progress..

16 Construction of New 10 nos. staff quarters (Type-I-4, Type-II-4 & Type-III-2) at Chelagang under Karbook block, Karbook Sub-Division, Gomati District, Tripura. 225.00 MSDP 2015-16 81.92 March 2018. Foundation work is in progress.
17 Construction of Amarpur Sub-Divisional Hospital, Dhalai, Tripura. 942.26 SPA 2012-13 579.50 Dec.,2016

Work completed and handed over.Inaugurated.

10 Construction of 30 bedded CHC building with 10 nos. staff quarters at existing Ompi CHC, Amarpur. 894.00 NHM 2017-18 ----- ---- DNIT under preparation.
10 Construction of 10 bedded PHC including 10 nos. staff quarter at Kasco, Amarpur, Gomati. 786.00 NHM 2017-18 ----- ------    e-Tender invited.
10 Construction of 16 nos. staff quarters for 100 bedded Sub-Divisional Hospital at Amarpur [ Type-I = 04 nos.,  Type-II = 04 nos.,  Type-III = 04 nos. &  Type-IV = 04 nos. ] 406.00 ----- 2016-17 ------ Jul 2019 Dismantaling work in progress.
10 Proposed construction of new single storied 10(ten) bedded Primary Health Centre (PHC) building including Morgue  and Garage & Generator with Driver room building at Chellagang  under Karbook Block, Gomati District, Tripura under MsDP Scheme. 167-00 MSDP 2017-18 ------ ----- Tender invited.
10 Proposed construction of single storied 10(ten) bedded PHC including 10(ten) Nos. Staff Quarters [ Type -I quarter - 04 units , Type-II quarter - 04 units and Type-III quarter - 02 units ], Kitchen, Morgue, Garage & Generator with Driver Room Building and Boundary wall at Silachari, Amarpur Sub-division, Gomati District, Tripura under NHM during the year 2017-18  486.00 NHM 2017-18 ----- ----- Tender invited.
SOUTH DISTRICT:-
1 Sabroom Divison Construction of 10 bedded PHC at Kalacherra with 10 nos. quarters Sabroom, South Tripura including Staff quarters. 385.00 NHM 2014-15 125.00 March 2019

Foundation work in progress.

2 Construction of 100 bedded Sub-Divisional Hospital at Sabroom, South Tripura. 2475.00 RIDF-XX 2015-16 --- Sep 2019 Work in progress.
3 Construction of 30 bedded CHC with quarters at Srinagar, Sabroom, South Tripura under State Plan (SCA) for the year 2012-13. 900.00 SCA 2012-13 690.00 Completed Work completed and handed over.Inaugurated.
4 Constrcution of 10 bedded PHC with quarters at Manughat under Satchand Block, Sabroom Sub-Division, South Tripura District. 385.00 NHM 2012-13 50.00 April 2019 Foundation work in progress.
10 Proposed construction of Type-II staff quarters (G+2) storied 06 units for Manubazar CHC, Sabroom, South Tripura. 138.00 ------- 2016-17 ----- Dec 2018 Foundation work in progress.
10 Construction of 10 nos. staff quarters at existing Manubazar CHC. 225 NHM 2017-18 ---- ----- DNIT under preparation.
5 Santirbazar Divison Construction of Primary Health Centre at Ramraibari including Quarter. 630.00 RIDF 2012-13 567.00 Completed

Work completed and handed over.

Inaugurated.

6 Construction of 10 bedded PHC at Durpabari under Santirbazar Sub-Division, Bagafa Block, South Tripura including Staff quarters. 540.00 RIDF-XX 2014-15 1023.73 October 2018. FSite handed over. Work started.
7 Proposed Construction of 20 (twenty) bedded Primary Health Centre (PHC) building [ double storied ]  including Kitchen, Morgue  and Garage & Generator with Driver room building at existing Muhuripur PHC Complex  under Jolaibari Block, Santirbazar, South Tripura. 173.00 IMR -
13th FC
2015-16 --- ---

Tender accepted.

8 Construction of 10 bedded Primary Health Centre with 10 nos. quarters (Type-I=4 nos. Type-II=4 nos. & Type-IIII=2 nos.) at Debdaru, Santirbazar, South Tripura. 385.00 IMR -
13th FC
2015-16 --- July 2018

Structure work upto lintel level is completed.

9 Proposed construction of 10 (ten) nos. staff quarters [ Type -I quarter - 04 units (one block - twin double storey ), Type-II quarter - 04 units (one block - twin double storey ) and Type-III quarter - 02 units (one block - twin single storey ) ] at Kwaifang Primary Health Centre (PHC), Santirbazar, South Tripura District, Tripura / SH: Building portion including internal water supply and sanitary installation. 221.00 IMR Incentive Grants 2014-15 153.46 feb 2018. Type-I &Type-II = Finishing work in progress.
Type-III = Structure completed.
10 Construction of 10 nos quarters (Type-III: 2 nos, Type -II: 4 nos, Type-I: 4 nos) at Birchandramanu PHC, South Tripura under RIDF-XVIII during the year 2012-2013/ SH: Building portion including internal water supply and sanitary installation. 221.46 IMR 2112-13 141.67 Completed. Completed and handed over.
11 Construction of 24 nos. staff quarters for 100 bedded District Hospital at Santirbazar [ Type-I = 06 nos.,  Type-II = 06 nos.,  Type-III = 06 nos. &  Type-IV = 06 nos. ] 583.00 ---- 2116-17 --- ---

2nd call tender rejected.

E-Tender called for 3rd call.

12 Belonia Divison Construction of Primary Health Centre at Maichara including Quarter. 630.00 SPA/RIDF 2012-13 566.99 completed Work completed and ready for handed over.
13 Construction of 10 bedded PHC at Radhanagar under Belonia Sub-Division, Rajnagar Block, South Tripura including Staff quarters. 540.00 RIDF-XX 2014-15 386.75 Nov 2017. Finishing work is in progress.
14

Re-construction of Niharnagar PHC under Rajnagar block, Belonia Sub-Division, South Tripura.

173.00 NHM 2015-16 94.15 Feb 2018

Work upto lintel level.

15 Proposed up-gradation of Rajnagar PHC to 30 bedded CHC at Rajnagar, Belonia, South Tripura.. 478.00 NHM 2015-16 100.00 Feb,2018.

Work for roof slab is in progress.

16 Proposed construction of 10 (ten) nos. staff quarters [ Type -I quarter - 04 units (one block - twin double storey ), Type-II quarter - 04 units (one block - twin double storey ) and Type-III quarter - 02 units (one block - twin single storey ) ] at Ratanpur Primary Health Centre (PHC), South Sonaicherri, South Tripura District, Tripura / SH: Building portion including internal water supply and sanitary installation. 221.00 IMR Incentive Grants - 13th F.C. 2013-14. 153.46

Type-I
Mar.2018

Type-II & III
Nov.2017

Type-I= Work to be started soon.

Type-II & Type-III= Completed.

17 Construction of 10 nos quarters (Type-III: 2 nos, Type -II: 4 nos, Type-I: 4 nos) at Matai PHC, Belonia, South Tripura under RIDF-XVIII during the year 2012-2013/ SH: Building portion including internal water supply and sanitary installation. 221.46 IMR 2012-13 141.67 Dec 2017

Type-I & III : Work completed and handed over.

Type-II: Roof casting completed for Ground floor.

18 Proposed construction of 10 (ten) nos. staff quarters [ Type -I quarter - 04 units (one block - twin double storey ), Type-II quarter - 04 units (one block - twin double storey ) and Type-III quarter - 02 units (one block - twin single storey ) ] at Chottakhola Primary Health Centre (PHC), Rajnagar, Belonia, South Tripura District, Tripura / SH: Building portion including internal water supply and sanitary installation. 221.00 IMR Incentive Grants - 13th F.C. 2013-14 211.37 Dec, 2016. Finishing work in Type-III quarters in progress. Roof slab of the ground floor of Type-I & II completed. Balance work is in progress.
16 Construction of 10 bedded PHC with quarters at Tripura Bazar under Hrishyamukh block, Belonia Sub-Division, South Tripura District. 399 NHM 2016-17 100 Oct 2018 Upto plinth level completed.
10 onstruction of 10 bedded PHC including 10 nos. staff quarter at Jasmura, Belonia, South Tripura. 486.00 NHM 2017-18 ---- ----- e-Tender invited.
10 Construction of MCH wing at Belonia Sub-Divisional Hospital, South Tripura 468.13 NHM 2016-17 ---- ----- e-Tender invited.
10 Construction of District Ware House at Belonia, South Tripura. 250.00         Workorder Issued 
10 Proposed construction of new single storied 10 (ten) bedded Primary Health Centre (PHC) building including 10 (ten) Nos. staff quarters (Type-I-04 Units, Type-II-04 Units and Type-III-02 Units], Kitchen, Morgue, Garage & Generator with Driver room building and Boundary wall at NBC Nagar, Belonia, South Tripura under NHM Supplementary Programme Implementation Plan (SPIP) for 2017-18. 486.00 NHM 2017-18 --- ----- e-Tender invited.
10 Capacity Building for Developing Trauma Care  Facilities in Government Hospitals in National Highway under 12th Five Year Plan/ SH: Proposed Construction of Single storied Building for Trauma Care Centre (Level-III) in the South District Hospital at Belonia. 390.00 NHM 2017-18 ----- ----- DNIT issued for calling of tender.
VARIOUS DISTRICT WORKS:-
1 ---- Construction of District Medical Stores for District Hospitals at (i) Santirbazar, ii) Khowai (iii) Kulai (iv) Dharmanagar and (v) Bhagawannagar. 1782.20 IMR 2015-16 ---- --- Preliminary estimate sent to concerned Deptt. for A/A & E/S.
2 ---- Construction of District Ware House at different District in Tripura namely, (i) South Tripura (ii) North Tripura (iii) Khowai (iv) Sepahijala (v) West Tripura District. 1250.60 NHM 2015-16 --- --- Preliminary estimate sent to concerned Deptt. for A/A & E/S.
2 ---- District Vaccine store at Different district head quarter.. 85.00 Each ----- 2017-18 --- --- Model DPR sent to concerned Department for according A/A & E/S

 

Education Department

(In Lakhs)
SL. No.DivisionName of WorksSanction CostSchemeYear of SanctionedTotal Fund ReleasedTarget date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
WEST DISTRICT :-
1 Agartala Division No-V, Agartala Construction of 1000 seated Auditorium for Ramthakur College, Agartala, West Tripura. 445.20 NLCPR 2012-13 425.00 Dec 2017. All RCC  roof completed . Brick work  completed. Finishing work 90% completed . Truss work  completed. 
10 Construction of Women Polytechnic College, Amtali, Agartala. 500 ---- 2015-16 ---- ----- DNIT under preparation.
2 Jirania Division Construction of General Degree College at Khumulwng (TTAADC) at Belbari, West Tripura/ Proposed Vertical Expansion of another one floor over existing Ground Floors of Academic Building and Administrative Building / SH : Building portion including internal water supply and sanitary installation. 350.00 SPA-tied 2015-16 --- Oct., 2017. Work Order Issued.
3 Construction of Academic Block for Khumluwng Govt. Degree College, Jirania, West Tripura under Special Plan Assistant (SPA-tied) during the year 2012-13(Phase-II). 305.00 SPA-tied 2012-13 470.40 Dec 2017. 1st floor roof is ready for casting.
2 Agartala Division No.I Special repair & Retrofitting of MBB College, Agartala, Tripura West. 824.00 ---- 2015-16 100 Mar 2018. Work Order Issued.Rs.52.00 lakhs to be revalidated.
3 Proposed construction of English Medium Degree College at Old Central Jail Premises, Agartala. 5671.00 Deposit 2012-13 2000 Dec 2017. Foundation work in progress. 50% pile cap completed.
4 Agartala Division No-III, Agartala

Development of Infrastructure of MBB College, Agartala, West Tripura:-

 

a) Construction of composite Auditorium having students Common room, Council room & Canteen etc.

900.00 TFC 2012-13 2700.00 Dec 2017.

Structure above lintel level.
Ground floor 70% completed.
Retaining wall completed.

5 b) Construction of new building for Commerce & Management etc. 1000.00 TFC 2012-13 Completed

Work completed.

Combined LOC was placed for different TFC project.

5 Construction of (G+4) storied Office Building at Office Lane, Agartala, Tripura (W)/SH: Building portion including internal water supply and sanitary installations. 1113.00 SPA 2012-13 1614.00 Completed Completed and handed over.
6 Proposed Construction of Annexe Block of Birchandra State Central Library at Agartala, West Tripura/ Phase-I: Western Block/Building portion including internal water supply and sanitary installation. 1647.00 NLCPR 2013-14 569.90 March, 2018.

Finishing work in progress.

Whole site not ready.

Revalidation required for Rs.217.38 lakhs

7 Proposed construction of English Medium Degree College at Old Central Jail Premises, Agartala. 5171.00 Deposit 2015-16 200.00 ---

First phase tender value Rs.2888.00 lakhs.

Work order issued. Test pile done.

First phase: Administrative, Academic & Library building.

8 Development of MBB College/Proposed construction of new Library building, Computer Centre Bank, Post Office & Co-operative Building, Guest House and Health Centre at MBB College Complex, Agartala, West Tripura. 1341.70   2015-16 --- Dec 2018 Yet to be clear site not found.
8 Development of MBB College/Proposed construction of Guest House at MBB College Complex, Agartala, West Tripura. 325.00   2015-16 --- --- Preliminary estimate processed to concerned Deptt. in the month of April, 2016 for A/A & E/S.
8 Special repair & Renovation of MBB College Complex Govt. Residential quarters / Type-IV quarters 24 nos. 109.13   2015-16 --- --- Preliminary estimate processed to concerned Deptt. in the month of Feb. 2016 for A/A & E/S.
GOMATI DISTRICT :-
1 Udaipur Division Construction of Polytechnic Institute at Fulkumari, Udaipur, Gomati District,  Tripura / SH:  Construction of  i) 100 Seated Boy's Hostel  iii) 50 Seated Girl's Hostel  and  iii) Staff Quarters -15 Units  [ Type -I quarter 1(one) Block - twin double storied 4(four) units , Type -II quarter 1(one) Block - twin double storied 4(four) units, Type -III quarter 1(one) Block - twin three storied 6(six) units  and Type -IV quarter - single storied 1(one) unit ] , under SPA-tied for the year 2012-13 (Phase-II). 500.00 SPA-Tied 2013-14 920.00 Dec 2017 All structure part completed, finishing work is in progress.
2 Proposed construction of Administrative Block at Netaji Subhas Mahavidyalaya at Udaipur, Gomati District. 610.00 SDS 2016-17 ----- ---- Preliminary cost estimate processed to concerned Department for according A/A & E/S.
3 Construction of 3 (three) nos. Workshops for Gomati Tripura District Polytechnic at Fulkumari, Udaipur. 201.71 SPA 2015-16 ---- Aug 2018 Work started.
1 Amarpur Division Construction of Amarpur Govt. Degree College at Amarpur, Gomati District, Tripura / SH: Vertical extension of 1st floor of  Academic Block during the year 2016-17 (Phase-II). 234.12 --- 2016-17   ---- Work order issued..
UNAKOTI DISTRICT :-
1 Kailashahar Division

R.K. Mahavidyalaya, Kailashahar

Administrative Building- (Three storied building. Only Ground floor is to be constructed in 1st Phase. Each floor is to measure 500 Sqm (Approx). (2007-08)/ Ph-1.

138.04 NLCPR 2012-13 --- June, 2016. i) 1 No. work shop completed upto plinth level. ii) Another 2 Nos. workshop foundation work in progress for one no. & Layout given to agency 1 no. respectively.
2 Construction of New Science Block at R.K. Mahavidyalaya, Kailashahar (Phase-II). 500.00 --- 2015-16 --- --- Tender received for Ground floor as per earlier sanction of Rs.500.00 lakhs with addl. sanction full building (G+2) may be taken up on cancellation of the tender for GF for completion of the building in one go for total UC of Rs.(5+10)=Rs.15.00 crores.
3 Proposed constrcution of Science Building (G+2) at Kailashahar College, Unakoti District, Tripura/Ground floor only under Phase-I. 1000.00 --- 2015-16 --- Sep 2018 Piling work in progress.
1 Kumarghat Division Proposed Vertical expansion of one story over existing Double Storied Adacemic and Administrative building of Ambedkar College at Fatikroy, Unakoti District, Tripura. 216.00 NLCPR 2015-16 150.00 Dec 2017 Work completed.
NORTH DISTRICT :-
1 Dharmanagar Division GDC, Dharmanagar Administrative Building [G+2] - (Three storied building. each floor is to measure 500 Sqm (Approx) (2007-08). 1349.45 NLCPR 2012-13 --- --- Preliminary estimate processed to concerned Deptt. for A/A & E/S.
2 100 seated Boys hostel and quarters for faculties of Dharmanagar Degree College. 445.20 NLCPR 2012-13 425.00

Completed.

 

Building completed and handed over.
3 Dharmanagar General Degree college Academic Wing. 1341.70 ACA 2012-13 --- Completed. Building completed and handed over.
4 Construction of 3 (three) nos. Workshops for North Tripura District Polytechnic at Bagbassa, Dharmanagar, North Tripura. 201.71 CSS/TFC 2016-17 --- Dec 2017. Plastering and CC flooring completed.
Roof truss work in progress.
5 Kanchanpur Division Construction of Model Degree College at GDC Kanchanpur under RUSA / (i) Vertical expansion of Academic building (1st floor) and (ii) Construction of 500 seated Auditorium. 540.00 RUSA 2015-16 300.00 Mar 2018

Finishing work in progress.

DHALAI DISTRICT :-
1 L.T. Valley Division Construction of Model Degree College at L.T. Valley under RUSA / (i) Vertical expansion of Academic building (1st floor) and (ii) Construction of 500 seated Auditorium. 540.00 RUSA 2015-16 300.00 Mar 2018

70% roof casted and 30% ready for casting..

1 Kamalpur
Division
Construction of Kamalpur Govt. Degree College at Kamalpur, Dhalai Tripura / SH: Vertical extension of 1st floor of  Academic Block during the year 2016-17 (Phase-II). 234.12 ---- 2016-17   ---- Tender Accepted.
SOUTH DISTRICT :-
1 Santirbazar Division Construction of Model Degree College at Santirbazar under RUSA. 422.00 RUSA 2015-16 300.00 Dec 2018

Work in progress.

KHOWAI DISTRICT :-
1 Khowai Division Up-gradation of Dasarath Deb Memorial (DDM) College at Khowai, Tripura / Vertical extension of Administrative building (1st & 2nd floor) and Academic building (2nd floor) under SPA(tied) during the year 2015-16 (Phase-II)/SH: Building portion including internal water supply and sanitary installation. 500.00 SPA-Tied 2015-16 200.00 Mar 2018 1st floor roof casted 01 Block and for rest ground floor roof casted..

 

Home Department (Police)

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme /HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
SEPAHIJALA DISTRICT :-
1 Bishramganj Division Construction of 7th BN TSR HQ at Jampuijala under Jampuijala Block Under 13th Finance Commission Award/SH: (i) Construction Of Administrative Building, (ii) 100 Men Barrack, (iii) Quarter Guard, (iv) Wireless Station, (v) Officer's Mess, (vi) SO's Mess, (vii) Store Building (viii) MT Office (ix) Magazine Store Building (x) MT Garrage (xi) Watch Tower and (Xii) Boundary Wall/Civil works including Internal water supply and Sanitary installation of building portions. 1500.00 TFC 2009-10 1495.00 Completed

Work completed and handed over.

Type-V = Work completed and ready for handed over.

2 Construction of 11th BN. TSR Head Quarter at Pathaliaghat, Bishramganj, West Tripura under 13th Finance Commission award / Earth work for Play Ground. 1500.00 TFC 2009-10 1590.56 Dec 2017. Work completed and handed over.
3 Construction of 11th BN. TSR Head Quarter at Pathaliaghat, West Tripura under 13th Finance Commission Award.

MT office, Magzine store building, MT garage, 100 men barrack-2 nos. Admn. Bld, Officers Mess, Quarter guard, SOS mess, TSR Store Wireless and communication bldg, Watch Tower these all component will be completed by Nov.2017 and Boundary wall completed except gate. 

Type-V quarter foundation work in progress will be handed over by Dec.2017.

4 Construction of New building for District SP Office at Bishramganj, Sepahijala District, Tripura. 776.00 MOPF --- ---- ---- Preliminary cost estimate sent to concerned deptt. on 24-07-2016  for according A/A & E/S.
4 Bishalgarh Division Construction of New PS building at Madhupur, Sepahijala District, Tripura. 168.00 MOPF --- --- --- Preliminary cost estimate sent to concerned deptt.  for according A/A & E/S.
Sanction awaited.
5 Construction of  6(six) Nos.  Type -III quarter [ 1(one) Block - twin (G+2) storied] at 1st TSR Hqts. Gakulnagar, Sepahijala District, Tripura under MoPF Scheme -2013-14/SH: Building portion including internal water supply and sanitary installation. 145.00 MOPF 2014-15 --- Completed Work completed and ready for handed over.
6 Construction of Administrative Building and 50 Men Barrack at 1st BN TSR HQ Complex at Gakulnagar, Sepahijala District, Tripura. 619.00 MOPF 2014-15 135.00 April 2018

(i) Administrative Building = Upto floor-II level

(ii) 50 Men Barrack = Ground floor roof casted.

UNAKOTI DISTRICT:-
1 Kailashahar Division Kailasahar Women Police Station at Kailasahar, North Tripura. 78.45 MOPF --- 75.00 Completed Work completed and handed over.
NORTH DISTRICT:-
1 Dharmanagar Division Construction of New building for District SP Office at Dharmanagar, North Tripura. 776.00 MOPF --- --- ---- Preliminary cost estimate sent to concerned deptt. on 24-07-2016  for according A/A & E/S.
DHALAI DISTRICT :-
1 L T Valley Division Construction of 8th BN TSR H.Q. at Lalcherra, L.T. Valley, Manu, Dhalai / SH: (i) Construction Of Administrative Building, (ii) 100 Men Barrack [02 nos], (iii) Quarter Guard, (iv) Wireless Station, (v) Officer's Mess, (vi) SO's Mess,  (vii) Store Building (viii) MT Office (ix) Magazine Store Building (x) MT Garrage (xi) Watch Tower and (Xii) Boundary Wall.
incl.  Boundary wall.
1500.00 TFC 2009-10 1323.00 Dec 2017 (i) Administrative Building = GF roof level.
 (ii) 100 Men Barrack ( 02 nos) = Barrack-I= Finishing work in progress. Barack-II= Roof casting ready.
(iii) Quarter Guard = Finishing stage. 
(iv) Wireless Station = Not started.
 (v) Officer's Mess = Not started.
(vi) SO's Mess = Plustering stage.
  (vii) Store Building = Not started.
 (viii) MT Office = I.E. completed.
(ix) Magazine Store Building = Not started.
(x) MT Garrage=I.E. completed.
 (xi) Watch Tower = Not started.
(xii ) Boundary wall:- Completed except gate. 
2 Construction of 2(two) nos. Type-II quarter  at Dhumacherra Police Station, L.T. Valley, Dhalai. 48.99 MOPF 2014-15 50.45 Completed Clear site recently handed over. Foundation work completed. Work is in progress.
3 Ambassa Division Construction of 6(six) Nos. Type -III quarter [ 1(one) Block - twin (G+2) storied] at Police Line Ambassa, Dhalai District, Tripura under MoPF Scheme -2013-14/SH: Building portion including internal water supply and sanitary installation. 145.00 MOPF 2014-15 145.48 O Work almost completed.
4 Infrastructural Development of Gandacherra Sub-Division, Dhalai District /Construction of Police Station 3235.00 SCA
(un-tied)
---- --- May,2017. Architectural drawings under preparation.
5 Kamalpur Division Construction of 6(six) Nos. Type-II Quarters [ 1(one) Block - twin (G+2) storied ] at Kachucherra P.S. Complex, Dhalai District, Tripura under MoPF Scheme, 2014-15/SH: Building portion including internal water supply and sanitary installation. 128.94 MOPF 2014-15 128.94 Feb., 2016. Work completed and ready for handed over.
WEST DISTRICT :-
1 Agartala Division No-V Construction of 36(thirty six) Nos. Type -II quarters [ 6(six) Block - twin (G+2) storied ] at A.D. Nagar Police Line, Agartala, West Tripura under MoPF Scheme -2013-14/SH: Building portion including internal water supply and sanitary installation. 773.82 MOPF 2014-15 117.74 Mar 2018 2 block= Structure completed.
2 block= Work upto lintel level
2 block= Site dispute.
2 Mohanpur Division Establishment of Police Academy at Narsingarh, West Tripura under 13th Finance Commission Award/SH: (i) Construction of 100 Persons Men's Barrack, (ii) Vertical extension of Women's Barrack, (iii) Training Institute, (iv) SI Cadet Hostel, and (v) Front compound wall (425m.)/Civil works Including Internal Water Supply and Sanitary Installations of Building Portions. 1000.00 TFC --- 900.00 Completed (i) Finishing work completed, (ii) Womens barrack completed and handed over, (iii) Finishing completed, (iv) Finishing completed, (v) 850.00 mtr. Completed. Work completed in all respect and ready for handing over.
3 Construction of 6(six) Nos. Type -III quarter [ 1(one) Block - twin (G+2) storied ] at KTDS, PTA, Narsingarh, West Tripura under MoPF Scheme -2013-14/SH: Building portion including internal water supply and sanitary installation. 145.00 MOPF 2014-15 --- Feb, 2016. Work nearing completion.
4 Jirania Division Construction of 6(six) Nos. Type-II Quarters [ 1(one) Block - twin (G+2) storied ] at Radhapur P.S. Complex, Jirania Sub-Division, West District, Tripura under MoPF Scheme, 2014-15/SH: Building portion including internal water supply and sanitary instal 129.00 MOPF 2014-15 128.92 Completed Work completed and handed over.
SOUTH TRIPURA DISTRICT :-
1 Santirbazar Division Development of Infrastructure of 9th BN TSR HQ at Hichacherra, Santirbazar 1500.00 TFC 2009-10 1527.00 Dec 2017 (i) 100 men Barrack = In Aug.2017  will be handed over.
(ii) Officers mess = In Aug.17 will be handed over. 
(iii) Boundary wall = In Mar.2017 will be handed over. 
(iv) MT Garrage, Watch Tower, MT Office:- Work not yet started.
(v) Remaining all components are already handed over.
(vi) Repair / Rectification have already been done.
2 Construction of New PS building at Baikhora, South Tripura. 168.00 MOPF 2014-15 --- ---

Preliminary cost estimate sent to concerned deptt.  for according A/A & E/S.
Sanction awaited.

3 Belonia Division Construction of New building for District SP Office at Belonia, South Tripura. 817.00 MOPF 2014-15 --- ---

Work processed to the WAB for approval. Which deferred by the WAB.

4 Construction of New PS building at Belonia, South Tripura. 635.00 MOPF --- --- --- Preliminary cost estimate sent to concerned deptt.  for according A/A & E/S.
Sanction awaited..
5 Construction of NGO Mess and development of a Parade ground with drill shed at Police Line under South Tripura District. 385 MOPF --- 60.00 Fer.,2016.

Consolidated DPR amounting to Rs.385.00 lakh sent to the AIG, Police on 03-03-2016 for according full amount of A/A & E/S.

NGO Mess & Drill shed = Works to be taken up after obtaining full A/A & E/S.

GOMATI DISTRICT :-
1 Amarpur Division. Construction of 6(six) Nos. Type-II Quarters [ 1(one) Block - twin (G+2) storied ] at Karbook P.S. Complex, Gomati District, Tripura under MoPF Scheme, 2014-15/SH: Building portion including internal water supply and sanitary installation. 129.00 MOPF 2014-15 --- Nov 2017. I.E. work going on. Work at finishing stage.
KHOWAI DISTRICT :-
1 Teliamura Division Construction of 6(six) Nos. Type-II Quarters [ 1(one) Block - twin (G+2) storied ] at Mungiakami P.S. Complex, Teliamura Sub-Division, Khowai District, Tripura under MoPF Scheme, 2014-15/SH: Building portion including internal water supply and sanitary 129.00 MOPF 2014-15 129.00 Completed Work completed and handed over.
2 Khowai Division Construction of New building for District SP Office at Khowai, Khowai District, Tripura. 776.00 MOPF 2014-15 --- ---

Preliminary cost estimate sent to concerned deptt. on 24-07-2016  for according A/A & E/S..

 

Information Cultural Affairs Department

(In Lakhs)
SL. No.DivisionName of WorksSanction CostSchemeYear of SanctionedTotal Fund ReleasedTarget date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
UNOKOTI DISTRICT
1 Kumarghat Division Proposed 1000 seated capacity Town hall at Kumarghat, Unakoti District. 1180.00 -- 2015-16 100 December, 2017. Work upto plinth level..
KHOWAI DISTRICT
1 Khowai Division Cultural complex at Khowai Town, West Tripura. 630.00 SPA 2010-11 700 Completed Work completed and ready for  handed over.
WEST DISTRICT
1 Agartala Division No 1.  Development of Rabindra Parishar at Children’s Park, Agartala, Tripura.(Open Air Stage) 200.00 I.C.A Deptt. 2013-14 100 Sep 2017

Work upto lintel level in progress..

2 Development of Children Park. --- I.C.A Deptt. ------ ---- Completed Completed.
3 Repair and Renovation of Nazrul Kalakshetra, Agartala. 154.00 I.C.A Deptt. 2016-17 --- ---- Work upto 20% completed.
1 Agartala Division No-III, Agartala Renovation of Town Hall at Agartala/ SH.Modification of Green Room, Ceiling, Acoustic works on wall & Ceiling, Flooring, Internal lighting, Audio system and Fire fighting etc.. 574.00 SPA, Tied 2014-15 210.36

February. 2016

50% work completed. Work in progress..

 

Jail & Sub-Jails

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme /HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
SEPAHIJALA DISTRICT:
1 Bishalgarh Division Construction of 56 Nos Type-II & 24 Nos Type-III residential quarters at Kendriya Sansodhanagar Complex at Bishalgarh (Balance work - Phase-II)/ SH: Building portion including internal water supply and sanitary installation. 695.63 MOPF 2015-16 --- Dec, 2017

(i) 24 nos. Type-III = Work completed and handed over.

(ii) 56 nos. Type-II = 50 nos. completed. 6 nos. plastering in progress.

2 Sonamura Division Proposed Construction of new Sub Jail at Sonamura, Sepahijala, Tripura (Phase-I) / SH: Construction of i] 100 Seated Prisoners Ward ( Male) ii] 25 Seated Prisoners Ward (Female) iii] 10 Seated Prisoners Cell iv] Administrative Block v] Watch Tower /Building portion including internal water supply and sanitary installation. 736.99 SPA 2011-12 1285.23 Feb. 2016 Finishing work in progress.
UNAKOTI DISTRICT:
1 Kailashahar Division Construction of Kailasahar District Jail at Kailasahar, Unakoti District, Tripura / SH: Construction of i] 100 Seated Prisoners Ward (Male) ii] 25 Seated Prisoners Ward (Female) iii] 10 Seated Prisoners Cell iv] Administrative Block v] Office & Visitor room vi] Guard room vii] Kitchen Room viii] Dining Hall ix] Barrack for 15 person x] Internal boundary wall xi] Internal boundary wall surrounding female ward xii] Perimeter Wall xiii] Watch Tower and xiv] Staff Quarters {Type-I - 8 Units - (02 Block twin-double storied), Type-II - 8 Units -(02 Block twin-double storied) & Type-III- 8 Units-(02 Block twin-double storied)}/Building portion including internal water supply and sanitary installation. 1597.69 SPA 2013-14 856.74 Dec 2017

1. Perimeter completed.

2. 100 seated capacity prisoners ward= Structural work completed. Finishing work in progress.

3. All other components are nearing completion stage.
4. Female word= Foundation work in progress.
5. Tower=5 tower in progress.

NORTH DISTRICT:
1 Dharmanagar Division Construction of Sub-Jail at Dharmanagar, North Tripura / SH: Construction of i] 100 Seated Prisoners Ward (Male) ii] 25 Seated Prisoners Ward (Female) iii] 10 Seated Prisoners Cell iv] Administrative Block v] Office & Visitor room vi] Guard room vii] Kitchen Room viii] Dining Hall ix] Barrack for 15 person x] Internal boundary wall xi] Internal boundary wall surrounding female ward xii] Jail Perimeter Wall xiii] Watch Towers xiv] Staff Quarters { Type-I - 04 units (01 Block twin-double storied), Type-II-12 units - (02 Block twin- three storied) & Type-III - 08 units - (02 Block twin - double storied)} and xv] Medical Unit / Building portion including internal water supply and sanitary installation. 1597.69 SPA 2013-14 1075.00 Dec, 2017. Finishing work in progress.
DHALAI DISTRICT:
1 Ambassa Division Construction of District Jail at Ambassa, Dhalai District, Tripura / SH: Construction of i] 100 Seated Prisoners Ward (Male) ii] 25 Seated Prisoners Ward (Female) iii] 10 Seated Prisoners Cell iv] Administrative Block v] Office & Visitor room vi] Guard room vii] Kitchen Room viii] Dining Hall ix] Barrack for 15 person x] Internal boundary wall xi] Internal boundary wall surrounding female ward xii] Perimeter Wall xiii] Watch Tower and xiv] Staff Quarters {Type-I - 8 Units - (02 Block twin-double storied), Type-II - 8 Units -(02 Block twin-double storied) & Type-III- 8 Units-(02 Block twin-double storied)}/Building portion including internal water supply and sanitary installation. 1621.23 --- --- --- ---

1st call tender rejected.

A/A & E/S received in Aug.2015 for Rs.10.84 Crores [ DNIT Amount exceeds this amount ] 

However, DPR sent for Rs.16.21 crores.

DNIT is on hold now.

Full sanction yet to be accorded.

SOUTH DISTRICT:
1 Santirbazar Division Construction of Sub-Jail at Santirbazar, South Tripura / SH: Construction of i] 100 Seated Prisoners Ward (Male) ii] 25 Seated Prisoners Ward (Female) iii] 10 Seated Prisoners Cell iv] Administrative Block v] Office & Visitor room vi] Guard room vii] Kitchen Room viii] Dining Hall ix] Barrack for 15 person x] Internal boundary wall xi] Internal boundary wall surrounding female ward xii] Jail Perimeter Wall xiii] Watch Towers xiv] Staff Quarters { Type-I - 04 units (01 Block twin-double storied), Type-II-12 units - (02 Block twin- three storied) & Type-III - 08 units - (02 Block twin - double storied)} and xv] Medical Unit / Building portion including internal water supply and sanitary installation. 1570.00 --- --- --- ---

Full sanction accorded.

DNIT is ready to be issued soon.

UPCOMING:
1   Construction of 1(one) room for the Female prisoners having children with them in 9 (nine) Jaills / Sub-Jails at different places of Tripura. --- SCA, Limited 2015-16 --- --- Model preliminary cost estimate is under preparation. However, A/A & E/S accorded for Rs.120.00 lakhs.

 

Labour Department

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme/ HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
WEST DISTRICT:
1 Agartala Division No-III, Agartala Construction of G+3 (4 storied) building for Labour & Employment and other Departments, Agartala, West Tripura/(Phase-I) Part Piling & Allied Foundation 1576.72 SPA, Tide 2014-15 700.00 March,2018 70% structural work completed.

Minority Welfare Department 

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme /HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
NORTH DISTRICT
1 Dharmanagar Division Construction of 50 seated Girls Hostel attached to Fhulbari Class-XII School at Kadamtala, Dharmanagar, North Tripura. 293.12 MSDP 2015-16 -- Jun 2018

Site handed over to the agency.

Revalidation needed for Rs.109.75 lakhs.

1 Kanchanpur Division Construction of 50 seated Boys Hostel attached to Anandabazar H.S. School at Kanchanpur, North Tripura. 270.00 MSDP 2014-15 125.00 -----

DPR sent to the Minority Welfare Deptt. on 09-05-2016 for according A/A & E/S.

A/A & E/S is still awaited. Fund not received by the EE, Kanchanpur Division.

SEPAHIJALA  DISTRICT
1 Sonamura 
 Division
Proposed construction of 06 nos. staff quarters (Type-I=04 nos & Type-III=02 nos) at Kamalnagar PHC, Boxanagar block, Sepahijala District, Tripura. 199.00 MSDP 2015-16 ----- ------

Preliminary estimate processed to concerned Deptt. for A/A & E/S on 13-08-2015.

Sanction awaited.
Fund not received by the EE, Sonamura Division.

2 Construction of 100 seated Girls Hostel attached to Madhya Boxanagar High Madrassa at Boxanagar, Sepahijala District, Tripura. 586.56 MSDP 2014-15 ---- -----

Work order issued.

Revalidation needed for Rs.290.00 lakhs.

3 Construction of School Building for South Paharpur H.S. School under South Paharpur GP, Sepahijala District, Tripura. 300.00 MSDP 2015-16 135.00 April 2018

Ground floor roof casted.

Revalidation required for Rs.75.00 lakhs.

4 Construction of School Building for South Nirvoypur H.S. School under Nirvoypur GP, Sepahijala District, Tripura. 237.00 MSDP 2015-16 100.00 Jul 2018

Work upto ground floor roof level.

Revalidation required for Rs.100.00

5 Construction of Double storied School Building for Govt. High Madrassa Building under Madhya Baxanagar GP, Sonamura, Sepahijala District. 148.82 MSDP 2015-16      
6 Construction of Double storied School Building for Govt. High Madrassa Building under Madhya Baxanagar GP, Sonamura, Sepahijala District. 237.00 MSDP 2015-16   Aug 2015

Work order issued.

Revalidation needed for Rs.100.00 lakhs.

7 Construction of Double storied School Building for Rahimpur H.S. School under Rahimpur GP, Sonamura, Sepahijala District. 237.0 MSDP 2015-16 90.00 March 2018

1st floor roof casted.

Revalidation needed for Rs.100.00 lakhs.

8 Construction of Double storied School Building for Kamalnagar H.S. School under Kamalnagar GP, Sonamura, Sepahijala District. 237.00 MSDP 2015-16 90.00 Nov 2017

Finishing work is in progress.

Revalidation needed for Rs.45.00 lakhs.

9 Construction of Double storied School Building for Veluarchar H.S. School under Veluarchar GP, Sonamura, Sepahijala District. 237.00 MSDP 2015-16 90.00 Jan 2018

1st floor roof casted.

Revalidation needed for Rs.45.00 lakhs.

10 Construction of Double storied School Building for Durgapur H.S. School under Durgapur GP, Sonamura, Sepahijala District. 237.00 MSDP 2015-16 ---- Mar 2018

Foundation work is in progress.

Revalidation needed for Rs.100.00 lakhs.

11 Construction of Double storied School Building for Nagar High School under Kalshimura GP, Sonamura, Sepahijala District. 237.00 MSDP 2015-16 90.00 Mar 2018

Ground floor roof casted.

Revalidation needed for Rs.45.00 lakhs.

12 Construction of Double storied School Building for Kulubari H.S. School under Kulubari GP, Sonamura, Sepahijala District. 237.00 MSDP 2015-16 90.00 Oct 2017 Finishing work is in progress.
Work in progress.
Revalidation needed for Rs.45.00 lakhs.
10 Construction of Double storied School Building for Rabindranagar H.S. School under Rabindranagar GP, Sonamura Sepahijala District, Tripura. 237.00 MSDP 2015-16 90.00 Jan 2018

Foundation work is in progress.

Revalidation needed for Rs.100.00 lakhs.

Gomati DISTRICT:
1 Amarpur
Division
Construction of 10 bedded PHC at Chellagang, Karbook, Gomati District, Tripura. 355.00 MSDP 2015-16 177.50 ---- Tender invited.
Fund received by the EE, Amarpur Division Rs.85.40 lakhs and returned to DM for revalidation. In addition, EE, RD refunded Rs.81.92 lakhs to DM for placement to EE, Amarpur Division, PWD which is not received by EE, Amarpur Division till now. Additionaly EE, RD spent Rs.10.18 lakhs.
SOUTH DISTRICT:
1 Belonia Division Construction of Double storied School Building for Amzad Nagar High School under Baspadua GP, Hrishyamukh R.D. Block, Belonia, South Tripura. 237.00 MSDP 2015-16 100.00 Jul;y 2018 Work order issued.

Law Department 

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme /HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
WEST DISTRICT:
1 Capital Complex Division Construction of (i) 1 No. Bungalow for Hon'ble Chief Justice of High Court of Tripura and (ii) 3 Nos. Bungalow for Hon'ble Judges of High Court of Tripura at Capital Complex, Agartala, Including Care Takers' Room, Barrack & Sentry Box 334.52 --- 2013-14 ---

(i) Mar.2018


(ii) -------

(i) Work is in good progress for Hon'ble Chief Justice Bungalow.

(ii) DNIT issued for calling of tender for 3 nos. judges bungalow.

2 Construction of a Multistoried (G+4) Building in the High Court premises at Agartala, West Tripura / SH: Building portion including internal water supply, sanitary installation, Retaining wall & Internal Electrification work(Concealed Conduiting only). 1917.00 ---- 2015-16 ----- June  2019 Work order issued.
3 Proposed construction of Digitization room over roof near Record room of High Court, Tripura. 77.03 ------ 2017-18 ----- --- Tender received.
2 Agartala Divn. No.III Division Construction of Multi-storied Court Building (G+5) in the Court Complex of District & Sessions Judge, Agartala ,West Tripura/SH. Building portion including Internal water supply, Sanitary installation, Internal Electrification i/c Fire Detection, Alarm System and Public Address System. 1303.00 State (Non Plan) 2013-14 1303.00 March 2018 3rd floor in progress.
3 Proposed Construction of 8(eight) Nos.  Type -II- Staff Quarters [ 1(one) Block - twin (G+3) storied ] for the Class-III (Group-C) and Class-IV (Group-D) Employees of High Court in the High Court Staff Quarter complex at Ramnagar Road No-3, Agartala, Tripura 197.00 --- 2015-16 --- March 2018 Work upto lintel level.
GOMATI DISTRICT:
1 Udaipur Division Construction of 2[two] Nos. of Grade-I Officers Quarters and 4[four] Nos. of Grade-III Officers Quarters at Udaipur District & Session Judge's Court Complex/SH: Building portion including internal water supply and sanitary installation. 412.82 CSS 2013-14 412.83 March 2018

Grade-I Officers: RCC pilar completed upto 1st floor.

Grade-III Officers: Roof casting completed upto 2nd floor.

3 Amarpur Division Construction of proposed Court building at Amarpur, Gomati District, Tripura/ SH: Building portion including internal water supply and sanitary installation. 694.00 --- --- --- --- Work order issued.
SOUTH DISTRICT:
1 Sabroom Division Construction of proposed Court building at Sabroom, South District, Tripura/ SH: Building portion including internal water supply and sanitary installation. 680.00 CASP 2014-15 --- Mar 2019

Work order issued.

Dismentaling work completed.

KHOWAI DISTRICT:
1 Khowai Division Construction of proposed Court building at Khowai, Khowai District, Tripura/ SH: Building portion including internal water supply and sanitary installation. 1586.00 CASP 2014-15 75.00 Mar 2018 1st floor roof ready for casting.
DHALAI DISTRICT:
1 Kamalpur Division Construction of proposed Court building at Kamalpur, Dhalai District, Tripura. ----- ------ 2016-17 ---- ------ DNIT under preparation. Tender will be invited in 3rd week of Sep.2017.

 

Nagar Panchayet Department 

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme/ HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
DHALAI DISTRICT
1 Ambassa Division Construction of Nagar Panchayat Office Building at Ambassa, Dhalai, Tripura/SH: Building portion including internal water supply & Sanitary installation. 317.21 ---- ---- ---- ---- A/A & E/S awaited.
SEPAHIJALA DISTRICT
1 Bishalgarh Division Construction of Nagar Panchayat Office Building at Bishalgarh, Sepahijala, Tripura/SH: Building portion including internal water supply & Sanitary installation. 317.21 -- 2014-15 -- -- Related drawing has been sent to the Director of Urban Development for approval
KHOWAI DISTRICT
1 Khowai Division Construction of Nagar Panchayet at Khowai, West Tripura/SH: Building portion including internal water supply and sanitary installations. 244.39 Deposit 2014-15 130.00 December, 2015. Work in finishing Stage.
SOUTH DISTRICT
1 Sabroom Division Construction of Nagar Panchayet at Sabroom, South Tripura/SH: Building portion including internal water supply and sanitary installations. 239.54 Deposit 2014-15 170.00 Completed Work completed and handed over
2 Santirbazar Division Construction of Nagar Panchayat Office Building at Santirbazar, South Tripura/SH: Building portion including internal water supply & Sanitary installation. 317.21 --- 2014-15 ---- ---- A/A & E/S awaited.
UNAKOTI DISTRICT
1 Kailashahar Division Construction of Nagar Panchayet at Kailashahar North Tripura /SH: Building portion including internal water supply and sanitary installations. 150.54 ---- --- 213.46 Dec., 2015 Work completed and handed over.
2 Kumarghat Division Construction of Nagar Panchayet at Kumarghat, North Tripura /SH: Building portion including internal water supply and sanitary installations. 242.49 Deposit ---- 164.00 Deceber, 2015 Work Completed.

North Eastern Council (NEC)

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme/ HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
DHALAI DISTRICT
1 Ambassa Division Manu - Chamanu - Gobindabari road
(Project revised in
2012-13 to ` 1488.00 lakh. Earlier cost was
` 956.00 lakh) 
1488.00 NEC 2004-05 1388.89 March, 2016.   F :15.30 Km.
Widening: 9.50 km
GSB : 8.00 Km.
WBM-II : 8.00 Km
WBM-III: 6.00 km
RW : 812.00 Mtr.
CD : 36  Nos.  completed &
2 Nos. in progress.
Road side drain: 6300 m.
NORTH DISTRICT
1 Dharmanagar Division Dharmanagar - Tilthai - Damcherra road.
(Project revised in
2012-13 to ` 8167.00 lakh. Earlier cost was
 ` 6625.00 lakh.) 
8167.00 NEC 2006-07 8077.78 April, 2016. F : 53.526 Km.
GSB : 53.526 Km.
WBM (1st layer) : 53.526 Km.
WBM (2nd layer) :53.526 Km.
DBM :53.526Km.
C: 53.526 Km.
CD : 59 Nos.
Side drain : 15.90 Km.
R/W: 881.00 Mtr.
B : 9 Nos. completed and
2 Nos. in progress.
SHEPAHIJALA DISTRICT
1 Bishalgarh Division Bishalgarh - Boxanagar - Sonamura - Barpathari - Belonia Road
(Revised estimate for `251.02 crore sent during 2013-14)
19597.00 NEC 2010-11 19483.32 March, 2016. F : 86.63 Km.
GSB :  86.63 Km.
WMM: 85.28 Km
DBM: 85.07 Km
PMC: 60.00 Km
RW:Completed
Drain: Completed
CD: Completed
Br :6 Nos. completed
1 No. in progress.

NON LAPSABLE CENTRAL POOL OF RESOURCES (NLCPR)

(In Lakhs)
SL. No.DivisionName of WorksSanction CostReleased Under Central ShareReleased Under State ShareTotal Fund ReleasedExpenditureStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
WEST DISTRICT
1 Jirania Division "Construction of RCC bridge over river Howrah at Ch.0.10 Km on Champaknagar to Udaipur Road." 301.67 212.94 23.66 236.60 236.60 Bridge completed. Work of approach will be started shortly. //
Target date of completion: July,2016.
Reply of clarification submitted on 12.1.16.Requisition for balance fund submitted.
2 Road of Connecting Railway Station to N.H/ SH 4(Four) Nos. in Tripura 1620.28 1437.38 127.77 1565.15 1277.67 Jirania ,Teliamura, Mungiakami & Ambassa  Rly station- completed.  // Fund released on 24.11.15.
Target date of completion:
March, 2016
3 Mohanpur Division "Construction of RCC bridge over river Dhanai at Ch: 6.60 Km on Champaknagar - Mandai Road." 321.34 198.65 22.07 220.72 211.53 Bridge completed. Carpeting of Approach road yet to be done. //  UC  submitted on 13.1.2016
Target date of completion: February,2016.Requisition for balance fund submitted.
4 Jogendranagar to Takarjala road (24.32 K.M) in Tripura 3679.60 2649.30 147.18 2796.48 1471.83 Formation: 17.70 Km, GSB: 16.62 Km,
 WBM-II: 16.62 Km   & WBM-III: 16.62 Km, BM & PMC 8.5 km
CD: 44 nos. & Widening of existing CD: 28 nos completed.  //
Fund released on 24.11.15.
Target date of completion:
March, 2017
NORTH DISTRICT
1 Kanchanpur Division "Construction of RCC bridge over Ujan Machmaracherra at Ch.9.00 Km on Kanchanpur to Jalbassa Road." 307.01 221.04 24.56 245.60 245.60 Bridge completed.
Work of approach yet to be started. // Target date of completion: March 2016. Requisition for balance fund submitted.
2 Improvement & Upgradation of the road connecting Sub Divisional H.Q. with NH-44/ Perchartal (NH-44) to Kanchanpur road (26.50 Km)/ Phase-I portion from pechartal to Machmara (8.50 Km). 2488.56 895.88 99.54 995.42 ---  Widening work almost completed. Preiminary work of 2 nos bridge and 17 nos CD started. //
Work awarded on 12.06.2015.
Stipulated date of completion 11.06.2017.
3 Construction of RCC bridge over Baradupatacherra at Ch: 2.80 Km on Kanchanpur to Jalbassa Road. 387.62 272.61 30.29 302.90 302.90  Fabrication and placing  of Superstructure completed. Casting of deck slab will be started shortly. // Target date of completion:
March, 2016.
Reply of clarification submitted on 8.1.16.Requisition for balance fund submitted.
DHALAI DISTRICT
1 Ambassa Division "Halahali- Ambassa- Dangabari- Amarpur- Bagasa-Belonia Road (173 K.M) Implementing by BRO/BRTF." 18909.00 16285.00 963.00 17248.00 14797.00 BRO is implimenting the work Road work completed. Works suspended by BRO before completion of 4 nos. of bridges. // Prposal for taking/ handing over by PWD(R&B) from BRO  sent to DoNER.

Panchayet Department 

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme /HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
WEST DISTRICT
1   Construction of Auditorium at Panchayati Raj Training Institute at A.D. Nagar, Agartala, West Tripura/SH: Civil Works, Plumbing Works, Stage Works including Stage Lighting, Internal Electrification, Sound system & HVAC Work. 1001.00 SPA 2015-16 490.00 Sep 2018 Work upto plinth level.

Public Works Department (R&B)

 

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme /HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
WEST DISTRICT :-
1 Capital Complex Division Construction of a composite building for Accommodation of different offices of PWD at Capital Complex, Khejurbagan, Agartala / Construction of Lower Ground Floor and Upper Ground Floor only / SH: Building portion including internal water supply and sanitary installation. 1406.3 PWD Plan 2013-14 2185.00

Mar.2017 for main Raj Bhavan

&

Staff qtrs. by Aug.2017

A) Building Part :-
1. Finishing works in progress inside the building.
2. Flooring completed.
3. Painting in progress (in side).
4. Electrical fitting, fixtures to be fitted.
5. False ceiling works at House-hold portion to be taken up soon.
6. Sanitary & Plumbing fittings & Fixtures will start soon.
(B) External Development:-
1. Land leveling almost completed. Hortibed done. External drainage being completed.
2. Internal road formation is in progress.
3. Parking area work is in progress.
 4. Boundary wall 80% completed.
5. New 10 nos. staff qtrs. work in progress.
2 Construction of New Rajbhavan at Khejurbagan, Agartala, West Tripura. 3000.00 TFC --- 2185.00 March, 2016. Work in progress.
3 Construction of MLA Hostel at Capital Complex,Agartala, West Tripura. 4000.00 SPA, Tied. 2014-15 --- Feb 2019

1. Foundation work in good progress (80% of foundation completed).

2. Already executed value for Rs.200.00 lakhs

4 Agartala Division No.III, Agartala Construction of 8(eight) Nos. Type -I quarter [1(one) Block - twin (G+3) storied ] and 8 (eight) Nos. Type -II quarter [1(one) Block - twin (G+3) storied ] at Melarmath, Agartala, West Tripura /SH: Building Portion including internal water supply and sanitary installation. 416.00 Housing ( Civil Works) 2014-15. --- March 2018

Type-II :  70% structure completed.

Type-III: Finishing work in progress.

5 Construction of Minister's Bungalow [3 (three) Nos] including Boundary wall at Agartala, West Tripura/SH: Building Portion including internal water supply and sanitary installation. 555.09 --- 2015-16 --- March 2018 60% structural work completed.
6 Proposed construction of Chief Ministers Bungalow including Frisking & Barrack, Type-II Quarters (One Unit) and Boundary wall at Agartala, West Tripura. 467.31 --- 2015-16 --- March 2018 Structure completed. Finishing work in progress.
NORTH DISTRICT :-
1 Dharmanagar Division Construction of 6(six) nos. Type-II Qtr. [1(one) Block-twin G+2] storied at Dharmanagar PWD Complex, North Tripura during the year 2014-15. 133.92 --- 2014-15 --- --- Tender received and under evaluation.
6 Construction of 6(six) nos. Type-III Qtr. [1(one) Block-twin G+2] storied at Dharmanagar PWD Complex, North Tripura during the year 2014-15. 147.64 --- 2015-16 --- --- Preliminary cost estimate processed to concerned Department for according A/A & E/S.
GOMATI DISTRICT :-
1 Udaipur Division Proposed construction of the SE (D.W.S) and SE (W.R) including Conference Hall of PWD office Complex at Udaipur, Gomati District, Tripura. 1105.00 --- 2014-15 --- --- Preliminary cost estimate processed to concerned Department for according A/A & E/S.

 

Revenue Department

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme/ HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
KHOWAI DISTRICT
1 Khowai Division Construction of office building for DM & Collector at Khowai, Khowai District, Tripura (Ground floor and part of First floor only, Phase-I) 2420.00 SPA, Tide 2015-16     A/A & E/S received. DNIT is being prepared.
2 Construction of composite office building of the DM & Collector, Khowai District. 1950.73         Preliminary estimate sent to concerned Deptt. for A/A & E/S.
SEPAHIJALA DISTRICT
1 Sonamura
Division
SDM office at Sonamura, Sonamura Sub-Division.

1977.00

SPA, Tide 2015-16     Preliminary cost estimate processed to concerned Department for according A/A & E/S.
2 Bishramganj
Division
Construction of office building for DM & Collector at Bishramganj. 2420.00 ---- 2015-16 ---- ----- Preliminary cost estimate processed to concerned Department for according A/A & E/S.
NORTH DISTRICT :-
1 Dharmanagar
Division
Construction of office building for DM & Collector at Dharmanagar. 2420.00   2015-16     Preliminary cost estimate processed to concerned Department for according A/A & E/S.

 

School Education Department

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme /HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7
WEST DISTRICT :
1 Agartala Divn. No-III, Agartala. Construction of Tripple storied  New Block at Northern side of Netaji Subhash Vidyaniketan H.S. School, Agartala. 840.00 SPA/Tied 2014-15 300.00 May 2018 Pile work completed..
2 Up-gradation of infrastructure of Netaji Subhash Vidyaniketan H.S. School under ACA/Phase-II. 263.76 SCS(un-tied) 2012-13 200.00 Completed

Work completed and handed over.

Revalidation of Rs.100.00 lakh for the year 2012-13 is still required.

3 Earth filling at the back side water bodies at Netaji Subhas Vidyaniketan and Construction of boundary wall 50.00 SCS(un-tied) 2015-16 25.00 Completed Work alomost completed. Work in progress.
4 Up-gradation of infrastructure etc. of Netaji Subhash Vidyaniketan, Agartala (i) Dev. Of playground with drainage facilities and installation of one befitting entrance gate at the middle section (ii) Construction of storm water drainage. 247.22 SDS 2015-16 233.00 Aug 2017

Earth filling & Boundary wall 30% completed.

Land demarcation problem.

5 Proposed construction of a New Block for Bijoy Kumar Girl's H.S. School including Campus Hall at Agartala, West Tripura and Boundary wall (Sishu bihar)/MTB Girls/Netaji School (Back side water body) SCA untied. 874.00 SPA 2013-14 340.00 Dec 2017 Finishing work in progress.
6 Proposed extension of Umakanta Academy, Agartala, Tripura. 651.90 SPA' Tied 2014-15 200.00 June 2018 Work upto 50% lintel level and 50% pile cap completed..
7 Construction of Academic and Administrative Block for DIET in Agartala, West Tripura. 940.00 State Plan 2014-15 253.00 Oct 2018

Foundation work  completed.
Ground floor work upto 70% completed.

Revalidation required Rs.421.94 lakhs.

8 Mohanpur
Division
Construction of Mohanpur H.S. School at Mohanpur, West Tripura. 812.00 SDS 2017-18 ---- -----

DPR sent to the concerned Department for according A/A & E/S in Sep.2017.

Sanction yet to be accorded.

9 Jirania Division Up-gradation of infrastructure development of Choudhury Bari Girl’s H.S. School at Jirania, West Tripura  --- ---- 2016-17 ----- ----- Survey site plan is under preparation.
10 Agartala 
Divn. No-V
Up-gradation of infrastructure development of Vivekananda High School at West Pratapgarh, Agartala. 612.00 ---- 2016-17 ---- ---- Preliminary estimate sent to SED for A/A & E/S.
GOMATI DISTRICT :
1 Udaipur Division Up-gradation of Infrastructure of Administrative and Academic Block for DIET, Kakraban Udaipur, South Tripura under SPA during the year 2011-12/SH: Building portion including internal water supply and sanitary installation. 1000.00 SPA 2011-12 700.00 Completed Work completed and ready for handing over.
2 Proposed Construction of building (two storeyed) for Matabari High School at Matabari, Udaipur, Tripura (South)/SH: Building portion including internal water supply and sanitary installation. 400.00 SPA 2011-12 201.50 March, 2016. Finishing work, Painting & flooring work is in progress.
3 Construction of English Medium School Building at Udaipur, Gomati District. 538.00 --- 2015-16 --- ---

Preliminary cost estimate sent to SED for approval.

4 Up-gradation of Infrastructure of Udaipur Girls H.S.School, Udaipur, South Tripura under ACA (SPA Tied) during the year 2011-12 (2nd Phase). 500.00 SCA (SPA) 2011-12 700.00 Completed Completed and handed over.s.
5 Construction of South Bagma Samatalpara H.S. School at Bagma, Udaipur. 585.00 --- 2015-16 -- ---

Preliminary cost estimate sent to SED on 03-08-2016.
Sanction awaited.

6 Up-gradation of infrastructure for Ramesh H.S. School at Udaipur, Gomati (Phase-II)/Vertical extension. 577.80 SCA (un-tied) 2015-16 100.00 ----

Sanction of Rs.500.00 accorded.

E-tender invited.

7 Amarpur Division Up-gradation of Infrastructure of Karbook Panjiham H.S. School under Gomati District, Amarpur Division. (2013-2014) 787.00 SPA 2014-15 45.00 March 2018

Ground floor roof level work is in progress..

8 Construction of Silachari H.S. School at Silachari under Gomati District, Tripura (2013-14) 972.00 SPA 2013-14 45.00 Nov 2018 Upto lintel level work is in progress
10 Up-gradation of infrastructure development of Ampinagar Higher Secondary School at Amarpur. ----- ----- 2016-17 ----- ----- Architectural drawings sent to SED for approval. Drawing approval awaited
10 Up-gradation of infrastructure development of Dakshin Amarpur Town H.S. School, Amarpur. ----- ----- 2017-18 ----- ----- Preliminary estimate is under preparation.
SOUTH DISTRICT :
1 Sabroom Division Up-gradation of Infrastructure of Manu H.S School, Sabroom, South Tripura under State Plan (SPA) during the year 2010-2011/SH: Building portion including internal water supply and sanitary installations. 400.00 SPA 2014-15 180.00 Dec 2017 Finishing work in progress.
2 Belonia Division Proposed construction Extension for Arya Colony H.S. School at Belonia, South Tripura. 655.38 SPA 2012-13 250.39
(Rest from other
 fund)
Dec 2017 School building work completed.  For staff room roof casting work completed. Brick work is in progress. After completion of staff room campus hall will be started.
4 Proposed construction of Hrishyamukh H.S. School at Hrishyamukh, Belonia, South Tripura. 723.00 SPA-tied 2012-13 357.50 Dec 2017 80% clear site found & in this portion work completed. Balance portion -   demolishing of semi-permanent structures completed & work to be taken up immediately.
5 Construction of Ghosh Khamar High School, Belonia, South Tripura. 908.00 --- 2015-16 --- ---

Preliminary cost estimate sent to SED on 22-02-2016.
Sanction awaited.

6 Up-gradation of infrastructure of Barpathari H.S. School, Belonia, South Tripura under Special Devlopment Scheme (SDS) under State Plan during the year 2015-16 (Phase-I). 600.00 SDS 2015-16 300.00 March 2018

Roof casting of ground floor completed. Work is in progress for 1st floor.

7 Up-gradation of infrastructure of Matai Class-XII School at Belonia, South Tripura. 150.00 SDS 2015-16 150.00 Feb 2018

Foundation work in progress.

8 Up-gradation of infrastructure of Asgar Rahamanpur High School at North Rajnagar, Belonia. 662.00 --- 2015-16 --- --- Work entrusted to the R.D. Department.
9 Construction of Niharnagar H.S. School at Belonia, South Tripura. 612.00 --- 2015-16 --- -- Preliminary estimate processed to concerned Deptt. for according A/A & E/S on 30-07-2014.
10 Santirbazar Division Construction of Baikhora H.S. School at Santirbazar, South Tripura. 609.00 SPA 2014-15 100.00 May 2018 Slab casting of 50% building is completed. Work in progress.
10 Up-gradation of infrastructure development of Takma Patichari High School, Santirbaza ----- ----- 2017-18 ----- ----- Preliminary estimate is under preparation.
11 Up-gradation of infrastructure of Twikormo H.S. School, Manipathar, Santirbazar, South Tripura. --- --- 2015-16 --- --- Survey site plan is under preparation.
12 Up-gradation of infrastructure of Chandrapur Chowdhury Para High School, West Manu, Santirbazar, South Tripura. --- --- 2015-16 --- --- Survey site plan is under preparation.
NORTH DISTRICT :
1 Kanchanpur Division Construction of Jampui H.S. School at Jampui Block, Kanchanpur, North Tripura (2013-14) 635.00 SPA 2014-15 45.00 Dec 2018

 

01 Block Ground floor slab casted.
01 Block 50% top roof casted.

2 Construction of Laljuri H.S. School at Kanchanpur, North Tripura (2013-14) 917.00 SPA-Tide 2015-16 145.00 March 2018

3rd block top roof casted.

3 Up-gradation of infrastructure of Kanchanpur H.S. school North Tripura under state paln (ACA) during the year 12-13/SH: Building portion including internal water supply and sanitary installation/ (balance work) phase-(I+II) 400.00 ACA 2012-13 360.00

Completed

Completed and handed over.

4 Construction of Anandabazar H.S. School at Anandabazar, Kanchanpur, North Tripura (2013-14) 720.00 SPA 2014-15 190.00 Oct 2018

Foundation work in progress.

5 Construction of Gachirampara H.S. School, Dasda, North Tripura (2013-14) 455.00 SPA 2013-14 900 Oct 2018

Work upto plinth level.

6 Up-gradation of infrastructure development of Durgaram Reang Para H.S. School, Dasda, Kanchanpur. --- --- 2015-16 --- --- Approved Architectural drawing received.
Preliminary cost estimate under preparation..
8 Dharnamagar Division Up-gradation of infrastructure of Dharmanagar Girl’s H.S. School under ACA/ Phase-II. 450.00 ACA 2012-13 288.21 March, 2016.

Finishing work in progress.

9 Up-gradation of infrastructure of Bagan H.S. School, Kadamtalla, North Tripura. 500.00 CASP (SPA) 2015-16 100.00 --- Tender accepted.
10 Construction of 50 seated Hostel for Manipuri boys at Rajbari in Dharmanagar. 210.00 SPA Un-Tied 2012-13 100.00 ---

Work suspended as per discussion held in at District level meeting at DMR chaired by Hon'ble Minister HED.

Existing agreement closed.

UNAKOTI DISTRICT :
1 Kailashahar Division Construction of Kailashahar Girl’s H.S. School, Kailashahar, Tripura North/Ground Floor (except Auditorium) & 1st Floor (Fr. Block only)/SH: Building portion including internal water supply and sanitary installations (Phase-I). 900.00 NLCPR 2011-12 338.35 Completed. Work completed and handed over.
2 Up-gradation of Infrastructure of Radha Kishore Institute (R.K.I.) Kailashahar, North Tripura (2nd Phase) under State Plan during the year 2010-2011/SH. Building portion including internal water supply and sanitary installation. 500.00 SPA 2011-12 450.00 Dec 2017 South east part = Work completed and handed over. North east pat = Finishing work in progress.
3 Up-gradation of Infrastructure of Kaulikura Class-XII School at Kailashahar, North Tripura under ACA during the year 2011-12/SH: Building portion including internal water supply and sanitary installations. 500.00 SPA 2011-12 250.00 Completed Work completed and handed over.
4 Construction of 100 capacity Boys Hostel for Tilla Bazar Fazil H.S. Madrassa, Kailashahar, Unakoti District, Tripura/SH: Building portion including internal water supply and sanitary installation. 457.00 SPA-Tide 2012-13 149.50 Completed Work completed and handed over.
5 Construction of Academic and Administrative Block for DIET at Kailashahar, Unakoti District, Tripura. 940.00 State Plan 2014-15 293.39 Mar 2018 Initial test pilling work completed. Clear site could not be handed over due to existing ST/LT line over the proposed site. TSECL already called tender to remover the said line.
6 Construction of Belkunbari H.S. School under Gournagar RD Block, Kailashahar, Unakoti District (2013-2014) 575.00 SPA 2014-15 45.00

 

 

Already preliminary cost estimate prepared and under evaluation.
7 Construction of Dulugaon H.S. School under Gournagar Block, Unakoti District, Tripura. 300.00 SPA, Tide 2014-15 --- --- Tender received and under scrutiny.
8 Up-gradation of infrastructure of Srirampur Surjyamani H.S. School at Kailashahar. 438.00 SDS 2015-16 200.00 Mar 2018 Work upto plinth level..
9 Kumarghat Division Up-gradation of infrastructure of Pabiacherra Class-XII School, Kumarghat. --- --- 2015-16 --- --- Architectural drawings yet to be received for preparation of Preliminary cost estimate.
10 Up-gradation of infrastructure of Fatikroy Class-XII School, Kumarghat. --- --- 2015-16 --- --- Architectural drawings yet to be received for preparation of Preliminary cost estimate.
11 Up-gradation of infrastructure of BTC Darchawi Christian G.S. School, Kumarghat. 813.00 --- 2015-16 --- --- Drawing received.
Preliminary estimate is under preparation.
SEPAHIJALA DISTRICT :
2

Bishalgarh 

Division

Construction of 100 capacity Boys Hostel for Bishalgarh Madrassa, Bishalgarh, Sepahijala District, Tripura/SH: Building portion including internal water supply and sanitary installation. 457.00 SPA-tied 2012-13 155.00 Completed. Work completed and handed over..
10 Up-gradation of infrastructure development of Matinagar Higher Secondary School at Matinagar under Dukli RD Block. ----- ---- 2016-17 ------ ------ Requisition received from SED Deptt. subsequently the same forwarded to the Sr. Architect, PWD on 08-08-2016 for preparation of site plan and working Architectural drawing.
2 Sonamura Division Proposed Construction of Boxanagar H.S. School at Boxanagar, Sonamura, Sepahijala District, Tripura undern SCA (un-tied) during the year 2012-13. 777.00 SCA (un-tied) 2013-14 100 Feb 2018 1st floor roof cast in the northside & 50% of the East & West side, 1st floor roof cast completed. For the balance portion basement floor work in progress.
3 Proposed construction of Kathalia H.S. School at Kathalia, Sonamura, Sepahijala District, Tripura under SCA (un-tied) during the year 2012-13. 553.00 SCA (un-tied) 2013-14 400 Completed Building completed and handed over
4 Construction of 100 capacity Boys Hostel for Daodarani Fazil H.S. Madrassa, Sonamura, Sepahijala District, Tripura/SH: Building portion including internal water supply and sanitary installation. 457.00 ACA 2012-13 109.50 Completed Building completed and handed over
5 Up-gradation of infrastructure development of Manaipathar High School under Kathalia Block, Sonamura. 287.00 --- 2015-16 --- --- Preliminary cost estimate sent to concerned department on 18-03-2016 for according A/A &E/S.
6 Construction of Sonamura Girls' H.S. School Building (2nd floor), at Sonamura under Sepahijala District, Tripura/ Phase-II. 252.00 SCA (Un-Tied) 2014-15 126.00 Completed Building completed and handed over
7 Proposed construction of building for Kalikrishna Nagar H.S. School at Sonamura, Sepahijala District, Tripura. 793.04 SCA (Un-Tied) 2014-15 390.0 Completed. Building completed and handed over
8 Proposed construction of building for Taibandal H.S. School at Sonamura, Sepahijala District, Tripura. 853.00 SPA 2014-15 500.00 Dec 2017 Finishing work is in progress.
9 Construction of Mohanbog H.S. School at Melaghar, Sonamura Sub-Division, Sepahijala District, Tripura. 512.20 SPA 2014-15 300.00 Feb 2018. Finishing work is in progress. 
10 Construction of School building for Nabakumar CP High School under Manaipathar ADC village, Kathalia. 160.00 Rurban 2017-18 ----- ------- DPR sent to the concerned Department for according A/A & E/S in Sep.2017..
10 Proposed construction of additional class rooms (double storied School building) for Santinagar H.S. School at Dhanpur, Sonamura Sub-Division, Sepahijala District, Tripura under Special Development Scheme (SDS). 228.00 SDS 2017-18 ----- ----- Tender called..
10 Proposed Extension of School Building (G+1 storied) for South Paharpur H.S. School at Dhanpur, Sonamura Sub-Division, Sepahijala District, Tripura during the year 2017-18. 220.00 SDS 2017-18 ------ ------ Tender received and under scrutiny..
11 Bishramganj Division Construction of Sudhanwa DebBarma Memorial H.S. School at Jampuijala, Sepahijala District. 584.00 SPA, Tied 2014-15 --- June 2018 Ground floor roof ready for casted. Rest structure upto roof level.
DHALAI DISTRICT :
1 Ambassa Division Up-gradation of Infrastructure of Chandraipara H. S. School, Ambassa, Dhalai, Tripura under ACA (SPA Tied) during the year 2011-12 (1st Phase). 500.00 SPA, Tied 2013-14 469.31 Nov 2017. Finishing work in progress. Vertical extension will be started soon.
2 Construction of Academic and Administrative Block including 150 seated Auditorium for BITE at Gandacherra, Dhalai, Tripura. 940.00 State Plan 2014-15 255.00 Jan 2018. Finishing work in progress.
3 Up-gradation of infrastructure of Raishyabari H.S. School under Dhalai District.(2013-14) 500.00 SPA 2014-15 100.00 Oct 2018

1st block =  Roof level.

Others block = Upto lintel level

4 Up-gradation of infrastructure of Ganganagar High School, Ambassa, Dhalai Tripura. 350.00 SDS 2015-16 350.00 ---

Tender received and under scrutiny.

5 L.T. Valley Division Up-gradation of infrastructure of Chawmanu H.S. School under Dhalai District.(2013-14) 222.35 SPA 2014-15 129.50 March 2018

1st floor slab 50% completed and rest ready for casting.

6 Kamalpur Division .Up-gradation of infrastructure of K.C. Girl's H.S. School , Kamalpur, under Dhalai District. 554.00 SPA 2014-15 200.00 Nov 2018 Foundation work completed. Brick wall upto 60% completed. 70% roof casted.
7 Construction of Double storied Harachandra H.S. School at Kamalpur. 852.00 SCA (un-Tied) 2014-15 100.00 --- Preliminary cost estimate sent to the SED for according A/A & E/S.
10 Construction of Kamalpur Boys H.S. School at Kamalpur, Dhalai Tripura/Ground floor only -Phase-I. 540.00 SDS 2017-18 ---- -----

DPR sent to the concerned Department for according A/A & E/S in Sep.2017.

Sanction yet to be accorded.

KHOWAI DISTRICT
1 Teliamura Division Up-gradation of infrastructure of Foundation work in progress. 600.00 SDS 2015-16 300.00 Aug 2018

Foundation work in progress.

10 Up-gradation of infrastructure development of Ghilatali Higher Secondary School at Teliamura. ---- ----- 2016-17 ------ ----- Architectural drawing under preparation.
2 Khowai Division Up-gradation of infrastructure of Tulasikhar Rajnagar H.S. School, Khowai. 300.00 SDS 2015-16 --- June 2018

Work order issued. Site dispute.

However, A/A & E/S accorded for an amount of Rs.300.00 lakhs.

3 Up-gradation of infrastructure of Bharat Sardar Class-XII School, Champahour, Khowai. 300.00 SDS 2015-16 --- March 2018

Site handed over for school building.

 

Science and Technology Department

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme /HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
WEST DISTRICT
1 Agartala Division No-V, Agartala

Proposed Vigyan Gram at Agartala (Phase-I)

31798.00 ACA/SPA/
NLCPR
2013-14 2030.00 'Dec.2017

Slab at 1st floor level for   Seminar Hall-1, Seminar Hall-2, 3D Hall , VIP Room including toilet block and adjacent corridoor casted .

Work for Gr. floor slab Hall -I casted.

Ground floor slabof hall -II & Hall III casted . For Planatorium RCC completed. Foyer slab including entrance lobby completed .

Outer Boundary wall is in progress.

Hall-6 ready for casting. Hall-7 & 8 ready for construction.

Work in progress for all units.

 

State Forensic Science Laboratory

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme /HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
WEST DISTRICT
  Mohanpur Division Proposed extension of Forensic Science Laboratory building at Narsingarh, West Tripura. 229.95 --- 2015-16 --- --- Estimate processed to concerned Deptt. for A/A & E/S. Sanction of A/A & E/S awaited. However, DNIT is under preparation for Ground Floor only.

 

Tourism Department

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme /HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
WEST DISTRICT
1 Agartala Division No. V Construction of Gallery, Barrack and covered drain at Border ceremony facility, Akhaura, Agartala, West Tripura under Swadesh Darshan Scheme. 810.00 Swadesh Darshan 2016-17 ----- ------

Work yet to be started.

2 Agartala Division No.III Construction of Conference Block, Wayside Amenities (Cafeteria) including Site Development at Border Ceremony Facility, Akhaura, Agartala, West Tripura under Swadesh Darshan Scheme. 475.00 Swadesh Darshan 2016-17 ----- Sep 2018

Land not available..

NORTH DISTRICT
3 Kanchanpur Division Construction of Tourist Lodge at Phuldangsei, Jampui Hill, North Tripura. 245.00 Tourisum 2014-15. 117.03 Aug, 2017. Finishing work in progress.
SEPAHIJALA DISTRICT
4 Sonamura Division Development of works at Melaghar and Neer Mahal (Access point), Sepahijala District under Swadesh Darshan Scheme. 340.00 Tourisum 2016-17 ----- ?------ Work started.
GOMATI  DISTRICT
5 Amarpur
Division
Development works at Tirthamukh, Amarpur, Gomati District, Tripura under Swadesh Darshan Scheme. 248.00 Tourisum 2016-17 ----- -----

Work started.

6 Udaipur
Division
Construction shed over the Haritage building of old Royal Palace at Rajnagar, Udaipur. 75.00 ----- ----- ----- -----

DPR sent to concerned deptt. For A/A & E/S...

DHALAI DISTRICT
7 Ambassa Division Development of Infrastructure (Day visitor section & Overnight stay section) at Narkelkunja, Gandacherra, Dhalai District, Tripura under Swadesh Dharshan Scheme. 606.00 Swadesh Darshan 2016-17 606.00 June 2019 ?Work order issued.

 

Transport Department

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme/ HeadYear of SanctionedTotal Fund ReleasedTarget date of completionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
GOMATI DISTRICT
3 Udaipur
Division
Construction of Motorstand at Rajarbag, Udaipur.  1000.00 ---- 2017-18 ----- ----- DPR under preparation..

 

Tribal Welfare  Department

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme /HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
WEST DISTRICT
1 Mohanpur Division Re-construction of 50 seated ST Boys Hostel, Ishanpur H.S. School. 303.00 Umbrella Scheme
(MoTA)
2015-16 -- --- Model Preliminary estimate sent to concerned deptt. on 27-01-2015 for A/A & E/S.
2 Construction of 100 seated ST Girls Hostel at Lembucherra for College Students. 608.00 Umbrella Scheme
(MoTA)
2015-16 --- -- Model Preliminary estimate sent to concerned deptt. on 02-02-2015 for A/A & E/S.
DHALAI DISTRICT
1 L.T. Valley Division Construction of 50 seated ST Boy's/Girl's Hostel attached to different Govt. High/Higher Secondary Schools in Tripura during 2011-12/SH: Construction of Boys' Hostel [50 seated] & Chowkidar's Room including boundary wall of length 300 m at 82 Mile H.S. School, Manu Block, Longtharari Valley Sub-Division, Dhalai/Building portion including internal water supply and sanitary installations. 197.05 CSS Fund
(Tribal Affairs)
2011-12 48.52 Oct 2017 Work at finishing stage.
2 Proposed Construction of 50 (fifty) seated ST Girl's Hostel Building   attached to Kathalcharra TMC H.S. School, L.T. Valley, Dhalai District, Tripura/SH: Building portion including internal water supply, sanitary installation and Boundary wall. 293.12 CSS Fund
(Tribal Affairs)
 
2014-15 73.245 Dec 2017

Finishing work in progress.

1 Kamalpur
Division
Re-construction of 100 seated ST Boys Hostel, Harachandra H.S. School. 608.00 Umbrella Scheme
(MoTA)
2015-16 --- --- Model Preliminary estimate sent to concerned deptt. on 02-02-2015 for A/A & E/S.
  Ambassa Division Re-construction of 100 seated ST Boys Hostel, Ganganagar H.S. School. 608.00 Umbrella Scheme
(MoTA)
2015-16 --- --- Model Preliminary estimate sent to concerned deptt. on 02-02-2015 for A/A & E/S.
GOMATI DISTRICT
1 Udaipur Division Construction of 50 seated ST Girls Hostel attached to Jalemabari High School, Killa Block under Udaipur Sub-Division, Gomati District, Tripura. 293.12 CSS
 (Umbrella)
2014-15 124.28 Oct., 2016 70% work completed, rest work in progress.
10 Re-construction of 100 seated ST Girls Hostel, Udaipur Girls H.S. School. 608.00 Umbrella Scheme 2015-16 ----- ----- Model Preliminary estimate sent to concerned deptt. on 02-02-2015 for A/A & E/S.
1 Amarpur Division Construction of 24 nos. staff quarters (Type-I=12 nos. & Type-III=12 nos.) at Ashram School, Karbook. 567.00 ------ 2016-17 ------ ------ Sanction yet to be accorded.
10 Re-construction of 50 seated ST Girls Hostel, Silachari Girls H.S. School. 303.00 Umbrella Scheme 2015-16 ----- ----- Model Preliminary estimate sent to concerned deptt. on 02-02-2015 for A/A & E/S.
KHOWAI DISTRICT
1 Khowai Division Construction of 480 seated Eklavya Model Residential School (EMR) at Rajnagar under Khowai District, Tripura / SH: Vertical Extension of (i) School Building (1st floor only) and (ii) 240 seated Boys Hostel building (1st & 2nd floor) 567.00 ------ 2016-17 ------ ?------- Work order issued
10 Construction of 24 nos. staff quarters (Type-I=12 nos. & Type-III=12 nos.) at Eklavya Model Residential (EMR) school, Rajnagar, Tulasikhar, Khowai. 567.00 ------ 2016-17 ------ ------ Sanction yet to be accorded.
10 Construction of 150 seated Girls hostel building at EMR Rajnagar, Khowai. 481.51 ------ 2016-17 ------ ------

Sanction accorded.e-Tender invited.

NORTH DISTRICT
1 Kanchanpur Division Re-construction of 50 seated ST Boys Hostel, Purnajoy C.P. H.S. School, Kanchanpur.. 303.00 CSS
 (Umbrella)
2014-15 420.070 May, 2017 Model Preliminary estimate sent to concerned deptt. on 27-01-2015 for A/A & E/S..
1 Re-construction of 100 seated ST Boys Hostel, Kanchanpur H.S. School. 608.00 Umbrella Scheme
(MoTA)
2015-16 --- --- Model Preliminary estimate sent to concerned deptt. on 02-02-2015 for A/A & E/S.
2 Re-construction of 50 seated ST Boys Hostel, Purnajoy C.P. H.S. School, Kanchanpur 303.00 Umbrella Scheme
 
2015-16 --- --- Model Preliminary estimate sent to concerned deptt. on 27-01-2015 for A/A & E/S..
2 Construction of 24 nos. staff quarters (Type-I=12 nos. & Type-III=12 nos.) at Ratanmani Memorial Ashram School. 603.00 Umbrella Scheme
(MoTA)
2015-16 --- Jul 2019 Work order issued.
SEPAHIJALA DISTRICT
1 Bishramganj Division Construction of 50 seated ST Boys Hostel attached to Sepahijala H.S. School, Jumpuijala Sub-Division, Sepahijala District. 293.12 CSS
(Tribal Welfare)
2011-12 187.200 Completed Work completed and handed over.
10 Re-construction of 100 seated ST Boys Hostel, Bishramganj H.S. School. 608.00 Umbrella Scheme 2015-16 ------ ------ Model Preliminary estimate sent to concerned deptt. on 02-02-2015 for A/A & E/S.
2 Sonamura Division Re-construction of 50 seated ST Boys Hostel, NCI, Sonamura. 303.00 Umbrella Scheme 2015-16 ---- ----- Model Preliminary estimate sent to concerned deptt. on 27-01-2015 for A/A & E/S.
10 Re-construction of 50 seated ST Boys Hostel, Melaghar H.S. School. 303.00 Umbrella Scheme 2015-16 ---- ---- Model Preliminary estimate sent to concerned deptt. on 27-01-2015 for A/A & E/S.
SOUTH DISTRICT
1 Belonia Division Construction of 100 seated ST Boys Hostel attached to BKI H.S. School at Belonia, South Tripura District. 586.57 CSS
 (Umbrella)
2014-15 382.011 Nov,2017. Finishing work is in progress.
2 Construction of 100 seated ST Girls Hostel attached to Belonia Girls H.S. School under Belonia Sub-Division, South Tripura. 586.57 CSS
 (Umbrella)
2014-15 385.030 Nov,2017. Finishing work is in progress.
3 Sabroom Division Construction of 100 seated ST Girls Hostel attached to Residental School run by TTWREIS at Bhuratali, Sabroom Sub-Division, South Tripura. 586.565 CSS Fund
(Tribal Affairs)
2015-16 199.480 Dec, 2017 Floor slab of 1st floor casted and column casting of 2nd floor is in progress.
UNAKOTI DISTRICT
3 Kumarghat Division Re-construction of 50 seated ST Boys Hostel, Ledrai Dewan H.S. School, Machmara, Pecharthal. 303.00 Umbrella Scheme 2015-16 ------ ------ Model Preliminary estimate sent to concerned deptt. on 27-01-2015 for A/A & E/S.
10 Re-construction of 100 seated ST Girls Hostel, Pabiacherra H.S. School. 608.0 Umbrella Scheme 2015-16 ------ ------ Model Preliminary estimate sent to concerned deptt. on 02-02-2015 for A/A & E/S.
10 Re-construction of 100 seated ST Boys Hostel, Fatikroy H.S. School. 608.00 Umbrella Scheme 2015-16 ------ ------ Model Preliminary estimate sent to concerned deptt. on 02-02-2015 for A/A & E/S.
10 Construction of 24 nos. staff quarters (Type-I=12 nos. & Type-III=12 nos.) at Eklavya Model Residential (EMR) school, Darchawi, Kumarghat.  567.00 ------ 2016-17 ------ ------ Sanction yet to be accorded.

Urban Development Department

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme /HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
WEST DISTRICT :-
1 Agt. Division No.I, Agartala Construction of covered drain including two-storied Building over Covered Drain from Orient Chowmuhani to Jackson Gate for relocation of shops in the Western and Southern side of Children’s Park. 1097.00 SPA 2013-14 522.66 Completed

Work completed and handed over..

2 Agt. Division No III Proposed construction of Guest house cum Dormetory with open dinning space (B+G+III) building at Back side of Town Hall, Agartala. 778.00 SDS 2016-17 ----- ----- Test pile completed.
10 Construction of Stalls at Mantri Bari Road, Netaji Chowmuhani, Agartala. 182.00 SDS ----- ----- ----- Piling work will be started soon.
DHALAI DISTRICT :-
1 Ambassa Division Construction of Nagar Panchayat Office Building at Ambassa, Dhalai, Tripura. 317.21 ----- 2014-15 ?----- -----. DPR sent to concerned deptt. For according A/A & E/S. Sanction still awaited.

 

Welfare of SC's, OBC & Minority Department

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme /HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
WEST DISTRICT :-
1 Agartala Division No-III,Agartala Proposed Construction of Haj Bhavan (G+3) storied at Melarmath near Nazrul Chatrabash, Agartala during the year 2013-14/SH: Building portion including internal water supply and sanitary installation. 664.85 Deposit 2013-14 286.50 March, 2016. Foundation work completed. Ground floor 60%, Second floor 50% work completed.
2 Construction of Type-I Quarters (Twin Four Storied-8 units)-32 Units [Four Block] at Harijan Colony attached to IGM Hospital, Agartala/SH: Building portion including internal water supply and sanitary installation. 351.82 SPA (Tied) 2014-15 316.80 Completed Work completed and handed over.
3 Construction of quarters (Phase-II) for Safai Karmachari at Harijan Colony, IGM Hospital, Agartala, Tripura (W). 293.00 --- 2015-16 --- --- Tender will be called soon.
4 Construction of New building for Nazrul Chatrabas of 150 nos. capacity at Agartala, West Tripura/ Construction of Front Block (Phase-II). 329.55 SPA 2014-15 775.23 --- Phase-I completed and handed over. Test pile completed.
5 --- Construction of 100 seated SC Girls Hostel attached to Anandanagar English Medium Model School, West Tripura. 590.00 Babu Jagjiban Ram Chhatrawas Yojana Scheme under CSS 2015-16 --- --- Preliminary cost estimate sent to concerned deptt. on 09-04-2015 for according A/A & E/S.
6 --- Construction of 100 seated SC Girls Hostel attached to Women's College, Agartala, West Tripura. 590.00 Babu Jagjiban Ram Chhatrawas Yojana Scheme under CSS ---- --- --- Preliminary cost estimate sent to concerned deptt. on 24-04-2015 for according A/A & E/S.
7 --- Construction of 100 seated SC Girls Hostel attached to Dr. B.R. Ambedkar Chatraniwas, Agartala, West Tripura. 590.00 Babu Jagjiban Ram Chhatrawas Yojana Scheme under CSS ---- --- --- Preliminary cost estimate sent to concerned deptt. on 24-04-2015 for according A/A & E/S.
SEPAHIJALA DISTRICT :-
1 Sonamura Division Construction of 50 seated SC Girls Hostel attached to Sonamura Girl's H.S. School, Sonamura, Sepahijala District, Tripura. 293.00 Babu Jagjiban Ram Chhatrawas Yojana Scheme under CSS -- -- ---. Preliminary cost estimate sent to concerned deptt. on 09-04-2015 for according A/A & E/S.
NORTH DISTRICT :-
1 Kumarghat Division Construction of 50 seated SC Girls Hostel attached to Pabiacherra Girl's H.S. School, Kumarghat, Unakoti District, Tripura. 293.00 ~~Babu Jagjiban Ram Chhatrawas Yojana Scheme under CSS --- -- --- ~~Preliminary cost estimate sent to concerned deptt. on 09-04-2015 for according A/A & E/S.

YOUTH AFFAIRS AND SPORTS DEPARTMENT

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme/ HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
WEST DISTRICT
1 Agartala Division No-III, Agartala. Up-gradation of Netaji Subhash Regional Coaching Centre /Construction of Indoor Gymnasium Hall at Agartala, West Tripura. 3200.00 SPA 2011-12 3378.00 Dec.2017 Finishing work in progress.
2 Construction of Sports Building for different activities like Judo, Weight lifting, Yoga, Table Tennis & Indoor Batminton Court at NSRCC completed 1424.00 SPA 2012-13 200 Dec.2017 Top roof in progress.
3 Upgradation of Netaji Subhash Regional Coaching Centre [NSRCC], Agartala, Tripura/Construction of Badminton Hall/SH. Building portion including Internal water supply & Sanitary installation. 323.00 Deposit 2013-14 470 Dec.2017 70% Truss completed.
4 Development of Playfield opposite to Bholagiri Ashram, Agartala, Tripura/ Construction of Gallery with Retaining wall and Storm water drain. 240.00 --- 2015-16 --- --- Site handed over to the agency.
5 Agartala Division No-V, Agartala. Proposed construction of Office room with dresing room and mini Gymnasium for Lawn Tennis Court at Dasaratdeb Sports Complex, Badharghat, Agartala, West Tripura. 280.10 --- 2015-16 --- Dec.2017 50% building work roof casted.

Tennis court also in progress.
6 Construction of Gymnasium with Foam Pit Gallery and Dressing room at Dasarat Dev Sports Complex, Agartala, West Tripura. 388.00 --- 2016-17 --- --- DPR sent to concerned deptt. for according A/A & E/S.
7 Construction of stadium at Dasarat Deb State Sports complex (DDSSC) Badharghat, Agartala. 17845.00 --- 2017-18 --- --- DPR sent to concerned deptt. for according A/A & E/S.
8   Construction of 7(seven) nos. Sub-divisional office of the Directorate of Youth Affairs & Sports.
(i) Kumarghat    (ii) Teliamura    (iii) Jampuijala    (iv) Mohanpur     (v) Jirania     (vi) Santirbazar & (vii) Karbook.
467.28 --- 2015-16 --- --- DPR sent to concerned deptt. for according A/A & E/S in Aug. 2015.
9  Santirbazar Division Construction of New Sub-Divisional Youth Affairs & Sports (YAS) office at Santirbazar, South Tripura. 84.27 --- 2016-17 --- --- DPR sent to concerned deptt. for according A/A & E/S.
10  Jirania
Division
Construction of Gymnasium with Foam Pit Gallery and Dressing room at West District Sports Complex, Khumulung, West Tripura. 199.50 --- 2016-17 --- -- DPR sent to concerned deptt. for according A/A & E/S.
11  Dharnamagar Division Construction of 240 bedded (G+2), District Yuba Awas (Youth Hostel) at Dharmanagar, North Tripura District under Tehshil Kachani and Muja Borua Kandi. 1485.00 --- 2015-16 --- --- DPR sent to concerned deptt. for according A/A & E/S in Sep.2015.

Miscellaneous Works

(In Lakhs)
SL. No.DivisionName of WorksSanction CostScheme /HeadYear of SanctionedTotal Fund ReleasedTarget Date of CompletionStatus of Physical implementation/Remarks
1 2 3 4 5 6 7 8 9
DHALAI DISTRICT :-
1 Ambassa Division Infrastructural Development of Gandacherra Sub-Division, Dhalai District / Construction of Revenue Dak Bungalow. 3235.00 SCA, Un-tied 2015-16 ---- May,2017. No tender received in 1st call. 2nd call of tender is under process.
2 Infrastructural Development of Gandacherra Sub-Division, Dhalai District / 1000 seated capacity Auditorium. --- Tender accepted.
3 Infrastructural Development of Gandacherra Sub-Division, Dhalai District / Construction of Staff Quarters 36 nos. [Type-I G+2: 348 sqm (6 nos.), Type-II-g+2: 840 sqm (12 nos.), type-III-G+2: 1008 sqm (12 nos.), T-IV-G+2: 558.60 sqm (6 nos.)]. ---- Tender accepted.
4 Infrastructural Development of Gandacherra Sub-Division, Dhalai District /Construction of Police Station. ---- Site finalised. Tender will be called soon.

 

end faq

 
 
 
 
   
This site is the official website of Public Works Department(R & B),Government of Tripura.

Disclaimer  |  Legal Policy   |   All Rights Reserved.  Designed & Developed By  C-DAC  ,Pune.
          Last Modified on : Thursday 14 December 2017, 11:52:49           This site is best viewed in 1280 x 1024 pixel screen resolution with Firefox 16+,IE 7+,Chrome20+.          You are visitor no. - 3